Mt. Lookout-Mt. Nebo v. FERC , 143 F.3d 165 ( 1998 )


Menu:
  • PUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    MT. LOOKOUT - MT. NEBO PROPERTY
    PROTECTION ASSOCIATION, an
    unincorporated association,
    Petitioner,
    v.
    No. 97-1376
    FEDERAL ENERGY REGULATORY
    COMMISSION,
    Respondent,
    CITY OF SUMMERSVILLE, West
    Virginia,
    Intervenor.
    AMERICAN WHITEWATER AFFILIATION,
    Petitioner,
    v.
    FEDERAL ENERGY REGULATORY
    No. 97-1377
    COMMISSION,
    Respondent,
    CITY OF SUMMERSVILLE, West
    Virginia,
    Intervenor.
    MT. LOOKOUT - MT. NEBO PROPERTY
    PROTECTION ASSOCIATION, an
    unincorporated association,
    Petitioner,
    No. 97-2058
    v.
    FEDERAL ENERGY REGULATORY
    COMMISSION,
    Respondent.
    On Petitions for Review of Orders
    of the Federal Energy Regulatory Commission.
    (FERC 10813)
    Argued: January 26, 1998
    Decided: May 1, 1998
    Before MURNAGHAN, NIEMEYER, and MOTZ, Circuit Judges.
    _________________________________________________________________
    Affirmed by published opinion. Judge Niemeyer wrote the opinion,
    in which Judge Murnaghan and Judge Motz joined.
    _________________________________________________________________
    COUNSEL
    ARGUED: Richard Roos-Collins, NATURAL HERITAGE INSTI-
    TUTE, San Francisco, California; James Wilbur McNeely, Green-
    ville, West Virginia, for Petitioners. Samuel Soopper, FEDERAL
    ENERGY REGULATORY COMMISSION, Washington, D.C., for
    Respondent. Earle Duncan Getchell, Jr., MCGUIRE, WOODS, BAT-
    TLE & BOOTHE, L.L.P., Richmond, Virginia, for Intervenor. ON
    BRIEF: David N. Cook, Acting General Counsel, Jay L. Witkin,
    Solicitor, John H. Conway, Deputy Solicitor, FEDERAL ENERGY
    REGULATORY COMMISSION, Washington, D.C., for Respondent.
    2
    James L. Sanderlin, Stephen H. Watts, II, Patrick T. Horne,
    MCGUIRE, WOODS, BATTLE & BOOTHE, L.L.P., Richmond,
    Virginia, for Intervenor.
    _________________________________________________________________
    OPINION
    NIEMEYER, Circuit Judge:
    In 1992 the Federal Energy Regulatory Commission ("FERC"),
    acting pursuant to the Federal Power Act, 16 U.S.C.§ 791a et seq.,
    granted a 50-year license to the City of Summersville, West Virginia,
    to construct and operate a hydroelectric power generation plant on the
    Gauley River in south central West Virginia. The license included the
    right to transmit power to a Monongahela Power Company substation
    over an eight-mile-long, 138-kilovolt transmission line running north-
    ward from the plant. About three years later, in 1995, the City of
    Summersville sought to amend the license to reduce the size of the
    power plant and to run the transmission line southward from the plant
    for 9.6 miles to an Appalachian Power Company substation. Although
    the Mt. Lookout-Mt. Nebo Property Protection Association ("the
    Association") and the American Whitewater Affiliation ("the AWA")
    challenged the location of the revised transmission line route, FERC
    granted Summersville's application for amendment by order of Octo-
    ber 18, 1996. On appeal, the Association and the AWA raise both
    procedural and substantive objections to FERC's approval of the
    amendment. For the reasons that follow, we affirm.
    I. Statement of the Case
    The City of Summersville is located in Nicholas County, West Vir-
    ginia, near the scenic Gauley River. In connection with a flood-
    control dam constructed on the Gauley by the U.S. Army Corps of
    Engineers, FERC licensed Summersville in September 1992 to con-
    struct and operate a hydroelectric power plant, using the dam's out-
    flow as its source of power. The license, which was granted following
    appropriate environmental review, authorized Summersville to trans-
    mit power to a Monongahela Power Company substation over an
    eight-mile-long, 138-kilovolt transmission line running northward
    from the power plant.
    3
    Because of economic concerns and an inability to reach agreement
    with Monongahela Power Company, Summersville decided to reduce
    the size of the plant and to enter into an agreement to sell electric
    power to Appalachian Power Company at its substation south of Sum-
    mersville in Fayette County. The agreement would require Summers-
    ville to transmit 69 kilovolts of power over a 9.6-mile line running
    southward from the power plant and crossing the Meadow River,
    which runs westward and ultimately feeds into the Gauley River.
    To effect the change in its proposed power plant and relocate the
    transmission line, Summersville filed an application with FERC in
    September 1995 for an amendment to its license. The amendment
    would authorize Summersville to reduce the number of turbines at its
    power plant from four to two and to construct the 9.6-mile transmis-
    sion line to the Appalachian Power Company substation in Fayette
    County. The proposed corridor for the line would have a maximum
    width of 80 feet. In its application, Summersville indicated that it had
    notified three West Virginia state agencies and four federal agencies
    of the proposed amendment, as well as 23 property owners whose
    property would be crossed by the power line. FERC thereafter pub-
    lished notice of Summersville's application in the Federal Register
    and in the Charleston Gazette, the newspaper with the largest circula-
    tion in Nicholas County and the second largest in Fayette County. The
    FERC notices provided that comments and motions to intervene from
    interested parties were to be submitted by December 4, 1995. A few
    months later, FERC completed a draft "Environmental Assessment"
    (or "EA") of the application and published notice of its availability in
    the Federal Register on May 9, 1996, requesting comments within 20
    days.
    The notices produced a number of comments. Comments from the
    National Park Service caused Summersville to move the transmission
    line several times so that it would not compromise the aesthetics of
    the Gauley River National Recreational Area, a public recreational
    area administered by the National Park Service. During the relevant
    time periods for public comment, however, neither the Association
    nor the AWA intervened in the proceedings or responded to the
    requests for comments. Indeed, the Association did not exist at the
    time, having been formed only on June 27, 1996, for the purpose of
    objecting to the location where the transmission line crossed the
    4
    Meadow River. The Association filed its first objections on August
    15, 1996. In response to late comments from the Association and
    from others not party to this appeal, FERC decided to conduct a pub-
    lic meeting in Summersville on September 19, 1996, for the purpose
    of giving the public another opportunity to comment on the amend-
    ment application. Public notice of the meeting was given, and it was
    held as scheduled. The Association participated and presented its
    views.
    The AWA did not object to Summersville's application until Octo-
    ber 8, 1996, when it filed its motion for late intervention. In its
    papers, the AWA expressed concern about the effect of the transmis-
    sion line on whitewater recreation on the Gauley and Meadow Rivers.
    On October 18, 1996, FERC published its order granting Summers-
    ville's application for amendment and its final Environmental Assess-
    ment, which it attached to the order. The order also granted the
    motions of the Association and the AWA for late intervention and
    addressed the substantive issues raised by them.
    With respect to the adequacy of notice complained of by both the
    Association and the AWA, FERC explained that although the initial
    notice given by Summersville in connection with the filing of its
    application had been "far from ideal," any defect in the notice had
    been cured by FERC's giving notice of the application by publication
    in the Federal Register and in the Charleston Gazette and by its giv-
    ing notice of the draft Environmental Assessment. FERC observed
    that public notice was also given in connection with its meeting on
    September 19, 1996. It found that any defect in the notice procedure
    which remained had also been cured by the fact that"interested per-
    sons have had actual notice of this proceeding" and that both the
    Association and the AWA participated.
    On the merits, FERC addressed in some detail the Association's
    and the AWA's challenges based on alleged compromises of the aes-
    thetic integrity of the Meadow River. FERC stated that the transmis-
    sion line would be visible to rafters on the Meadow River
    for only a brief period as they pass beneath the portion of
    the line that crosses the river. The remainder of the line will
    5
    not protrude above existing vegetation, and only 80 feet of
    shoreline (out of a total of five miles) will be cleared by the
    right of way. The licensee will use wooden poles that will
    blend with the existing forest, will plant trees along the
    transmission line corridor, and will keep the width of the
    corridor to the minimum needed. Thus, the transmission line
    will not have significant adverse impact on the aesthetic
    quality of the Meadow River Gorge.
    In comparing the transmission line route proposed by Summersville
    with an alternative route proposed by the Association, FERC stated
    that neither "would significantly impact the environment" and that the
    "impacts associated with the two routes are similar." The order
    explained:
    The 11.2-mile-long route proposed by the Association is 1.3
    miles longer than the 9.9-mile-long route proposed by the
    amendment. Thus, the Association's route would affect an
    approximately 12 percent greater area and cost approxi-
    mately 12 percent more than the route proposed by the
    licensee.
    Given that the two proposed routes have similar overall
    impacts, but that the Association's route would have a
    slightly greater environmental impact due to its greater
    length and higher cost, we adopt the EA's conclusion that
    the route proposed by the licensee is environmentally prefer-
    able.
    While FERC selected Summersville's proposed route, it imposed a
    requirement that Summersville consult with affected landowners in
    "developing a final design plan" for construction of the transmission
    line. Based on its conclusions in the final Environmental Assessment,
    which it attached to its order, that neither of the routes would signifi-
    cantly affect the environment, FERC concluded that it was not neces-
    sary to prepare a formal Environmental Impact Statement ("EIS").
    Subject to the new condition that it imposed requiring Summersville
    to consult with landowners, FERC approved the amendment to Sum-
    mersville's license.
    6
    The Association and the AWA filed petitions for rehearing, which
    FERC denied on January 21, 1997.
    Parallel to its application for amendment, Summersville filed a
    Visual Resource Protection Plan on September 23, 1996. This docu-
    ment was filed pursuant to Article 409 of the original license, which
    required Summersville to minimize the visual impacts of the project
    in the power plant area in consultation with the National Park Service,
    the AWA, the Corps of Engineers, and the West Virginia Professional
    River Outfitters. The Plan proposed gratuitously to apply the require-
    ments of Article 409 to the entire proposed transmission line "to
    reduce the visual impacts of the project by constructing project works
    so that they would blend into the landscape, and by planting a variety
    of shrubs and trees to screen the project from view to a substantial
    degree." FERC approved Summersville's Plan on February 19, 1997,
    and the Association filed a petition for rehearing, complaining that it
    had had no opportunity to comment. FERC denied the petition for
    rehearing on July 1, 1997. Although FERC noted that the Association
    had no right to intervene in the Plan proceeding under Article 409, it
    entertained, sua sponte, its objections that the new route would have
    unacceptable visual impacts, stating:
    The Commission carefully considered these assertions and,
    based on the environmental assessment prepared by our
    staff, concluded that the environmental impacts of the route
    proposed by Summersville, including visual impacts, would
    not be significant. In response to the concerns regarding the
    portion of the new transmission line routing not near the
    dam and therefore not covered by Article 409, the Commis-
    sion added Article 414, requiring that the final design plan
    for the transmission line be developed in consultation with
    affected property owners, the U.S. Fish and Wildlife Ser-
    vice, and West Virginia Resource agencies.
    The Association and the AWA appeal the orders entered by FERC
    approving the license amendment, approving the Visual Resource
    Protection Plan, and denying their petitions for rehearing. They pre-
    sent the following issues: (1) whether sufficient notice and opportu-
    nity to be heard on Summersville's application was given; (2) whether
    FERC's decision not to prepare an Environmental Impact Statement
    7
    was supported by substantial evidence; (3) whether FERC considered
    reasonable alternatives to the transmission line route as required by
    the National Environmental Policy Act of 1969; (4) whether the
    Visual Resource Protection Plan was adequate; and (5) whether the
    Association and the AWA can advance new arguments on appeal. We
    address these issues seriatim.
    II. Adequacy of Notice
    The Association contends first that neither Summersville nor FERC
    provided it with adequate notice of Summersville's application, with
    the result that the Association was unable to participate meaningfully
    in the license amendment proceedings. The Association argues, in
    particular, that the proper documents were not mailed to property
    owners affected by the amendment, as required by 16 U.S.C.
    § 802(b)(1). Section 802(b)(1) provides, "Upon the filing of any
    application for a license . . . the applicant shall make a good faith
    effort to notify [a]ny person who is an owner of record of any interest
    in the property within the bounds of the project."
    Summersville's application asserts that it notified each property
    owner whose property would be crossed by the proposed transmission
    line, as well as state and federal agencies, of its application. More-
    over, FERC found that these notices were in fact provided. At the
    time that Summersville gave these notices, however, the Association
    was not in existence. Indeed, it was formed in June 1996, after the
    time for responding had expired, for the very purpose of opposing the
    proposed route of the transmission line. In order to form an associa-
    tion for that purpose, however, the Association's organizers necessar-
    ily must have known of the proceeding's existence.
    Moreover, because of the Association's late comments, as well as
    late comments by others, FERC left the record open and conducted
    a public meeting in Summersville in September 1996 for the specific
    purpose of receiving all views on the project. The Association
    attended the meeting and testified. It also submitted written materials
    in support of its position.
    Finally, the Association's motion for late intervention was granted
    and all of the points raised by it were considered by FERC and
    8
    addressed in its October 18, 1996 order approving the license amend-
    ment.
    In these circumstances, we fail to understand how the Association
    can claim a lack of notice, and we reject this procedural challenge to
    the amendment.
    In addition, the AWA contends that FERC failed adequately to
    consult with affected governmental agencies as required by the Fed-
    eral Power Act. In particular, it alleges that Summersville failed to
    consult Fayette County and consulted inadequately with the National
    Park Service. Section 802(b)(2) of Title 16 requires that the applicant
    for a license or amendment make a good faith effort to notify "[a]ny
    Federal, State, municipal or other local governmental agency likely to
    be interested in or affected by such application." Moreover,
    § 803(a)(2) mandates that, in approving a project, FERC must con-
    sider "[t]he recommendations of Federal and State agencies exercis-
    ing administration over flood control, navigation, irrigation,
    recreation, cultural and other relevant resources of the State in which
    the project is located."
    Contrary to the AWA's assertion, the record in this case shows that
    FERC did consult with Fayette County. Indeed, Fayette County
    approved of the project and took affirmative steps in support of it.
    Likewise, Summersville consulted the National Park Service and
    acted on its suggestions on various occasions, moving the location of
    the transmission line several times in order to satisfy the Service's
    desire to protect the Gauley River National Recreational Area.
    Although FERC recognized that Summersville's initial notice to
    landowners was "far from ideal," it correctly observed that any defi-
    ciency was cured by FERC's subsequent notice published in the
    Federal Register and in the local newspaper. Any doubt about the
    adequacy of that notice is further dispelled by the fact that the prop-
    erty owners, the Association, and the AWA had actual notice. Not
    only was an adequate opportunity to participate thus provided, but the
    opportunity was in fact taken and numerous private and public groups
    actually participated in the proceedings before FERC. Accordingly,
    we conclude that the notice requirements of the Federal Power Act
    were satisfied.
    9
    III. Environmental Impact Statement
    The Association and the AWA next argue that FERC erred in
    deciding that an Environmental Impact Statement was unnecessary.
    FERC conducted an Environmental Assessment in which it concluded
    that the proposed redesign and relocation of the project powerhouse
    would "decrease the overall impacts of construction at the dam by
    reducing the size of the facility and siting it on the shore instead of
    in the middle of the river." With respect to the alternative transmis-
    sion line routes, FERC concluded:
    The impacts of the licensed [route], the licensee's pro-
    posed transmission line route and the Association's[route]
    are similar. However, since the licensed route is not eco-
    nomically feasible, we will base our conclusion on a review
    of the licensee's and the Association's proposed routes.
    In general, both would have minor adverse impacts on
    soils, vegetation, wildlife, land use and aesthetics and no
    impacts on human health, water quality, fisheries, and cul-
    tural resources. Our review of the routes did not identify any
    resources that would be significantly impacted.
    Based on these conclusions, FERC determined that it was not
    required to prepare an Environmental Impact Statement.
    The parties agree that FERC's review of Summersville's applica-
    tion for amendment must include compliance with the National Envi-
    ronmental Policy Act of 1969 ("NEPA"), as amended, 42 U.S.C.
    § 4321 et seq., which applies to any major federal action which may
    have a significant effect on "the quality of the human environment."
    42 U.S.C. § 4332(2)(C); see also North Carolina v. City of Va. Beach,
    
    951 F.2d 596
    , 603 (4th Cir. 1991). The Council on Environmental
    Quality regulations implementing NEPA require each federal agency
    to prepare an Environmental Assessment, i.e., a document that con-
    tains sufficient evidence and analysis "for determining whether to pre-
    pare an environmental impact statement or a finding of no significant
    impact." 40 C.F.R. § 1508.9(a)(1). Thus, if the environmental assess-
    ment results in a finding of no significant impact, the agency is not
    required to prepare an Environmental Impact Statement.
    10
    An agency's decision to rely on an Environmental Assessment
    instead of preparing an Environmental Impact Statement is entitled to
    deference from the courts. South Carolina v. O'Leary, 
    64 F.3d 892
    ,
    896 (4th Cir. 1995); Providence Rd. Community Ass'n v. EPA, 
    683 F.2d 80
    , 82 (4th Cir. 1982); see also LaFlamme v. FERC, 
    945 F.2d 1124
    , 1128-29 (9th Cir. 1991) ("We review the Commission's deci-
    sion not to prepare an EIS by considering whether it reasonably con-
    cluded that the Project would have no significant adverse
    environmental consequences"). Thus, our review is limited to the
    question of whether FERC reasonably concluded that the license
    amendment would not significantly impact the quality of the human
    environment. See City of Alexandria v. Helms, 
    728 F.2d 643
    , 646 (4th
    Cir. 1984). Only if the environmental assessment leads FERC to con-
    clude that the applicant's proposed major federal action may have a
    significant environmental impact must it require the preparation of a
    formal Environmental Impact Statement. See 18 C.F.R. § 380.6; 40
    C.F.R. § 1501.4.
    In compliance with NEPA, FERC prepared an Environmental
    Assessment in which it evaluated the impact of the proposed revised
    power plant, the proposed transmission line route, and the Associa-
    tion's proposed transmission line route on geology and soils, water
    resources, threatened and endangered species, land use and recreation,
    aesthetics, and cultural resources. Following its lengthy analysis,
    FERC concluded that both of the proposed transmission line routes
    would impact the environment similarly, and neither would impact it
    significantly:
    [B]oth would have minor adverse impacts on soils, vegeta-
    tion, wildlife, land use, and aesthetics and no impacts on
    human health, water quality, fisheries, and cultural
    resources. Our review of the routes did not identify any
    resources that would be significantly impacted.
    It also noted that the specific plans proposed by the licensee "will
    adequately mitigate any [adverse] impacts." Because we find that
    FERC's analysis is supported by the record and is reasonable, we will
    not disturb its conclusion that no Environmental Impact Statement
    was required.
    11
    IV. Reasonable Alternatives
    The Association and the AWA also contend that FERC did not
    consider an adequate range of alternatives in approving the location
    of the transmission line. Under NEPA, federal agencies must "study,
    develop, and describe appropriate alternatives to recommended
    courses of action in any proposal which involves unresolved conflicts
    concerning alternative uses of available resources." 42 U.S.C.
    § 4332(2)(E).
    The rigor with which an agency must consider alternatives is
    greater when the agency determines that an EIS is required for a par-
    ticular federal action. See 40 C.F.R. § 1502.14 (agency must
    "[r]igorously explore and objectively evaluate all reasonable alterna-
    tives" when EIS required). In this case, when FERC determined that
    an EIS was not necessary, it was required only to"include brief
    discussions of the need for the proposal, of alternatives as required by
    section 102(2)(E), of the environmental impacts of the proposed
    action and alternatives, and a listing of agencies and persons con-
    sulted." 40 C.F.R. § 1508.9(b) (emphasis added); see also North Car-
    olina v. FAA, 
    957 F.2d 1125
    , 1134 (4th Cir. 1992) ("In an
    environmental assessment, the range of alternatives an agency must
    consider is smaller than in an environmental impact statement");
    Friends of the Ompompanoosuc v. FERC, 
    968 F.2d 1549
    , 1558 (2d
    Cir. 1992) (same); Olmsted Citizens for a Better Community v. United
    States, 
    793 F.2d 201
    , 208-09 (8th Cir. 1986) (same). We review
    FERC's decision as to the appropriate range of alternatives for abuse
    of discretion. See 
    Ompompanoosuc, 968 F.2d at 1558
    .
    In this case FERC considered three alternative transmission line
    routes: (1) the route proposed by Summersville in its application for
    amendment; (2) the route proposed by the Association which would
    follow U.S. Highway 19 as it crosses the Meadow River; and (3) the
    northward route originally approved in 1992 with the license. FERC
    agreed with Summersville that alternative (3) was not economically
    feasible and that the proposed amendment was necessary to reduce
    the plant's size and cost. As between the remaining two proposals,
    Summersville's route and the Association's route, FERC found that
    the route proposed by Summersville was preferable because it was
    shorter. It explained, "By constructing the licensee's proposed route,
    12
    short-term and long-term impacts of the project's transmission line
    would be reduced by approximately 12 percent. Further, the shorter
    route would be less costly to construct."
    Thus, FERC did consider alternatives as required by NEPA, and
    we cannot say that the range of the alternatives it considered was
    unreasonable, particularly in view of the marginal difference in envi-
    ronmental impact between the two viable alternatives.
    V. Visual Resource Protection Plan
    Finally, the Association contends that the Visual Resource Protec-
    tion Plan filed by Summersville under Article 409 of its original
    license and approved by FERC is inadequate because it does not ade-
    quately address the visual impact of the transmission line as it crosses
    the Meadow River. This argument, however, overlooks the absence
    of any legal requirement to provide a Protection Plan for the Meadow
    River crossing.
    Article 409 of the license as originally approved requires that Sum-
    mersville minimize the visual impacts of the powerhouse and the
    transmission line in the area of the powerhouse. In connection with
    the original application for a license, no one challenged the visual
    impact of the transmission line elsewhere, and FERC did not take
    Article 409 as applying elsewhere. Nonetheless, in considering the
    amendment, FERC decided to mitigate any adverse visual impacts of
    the transmission line away from the dam as a condition of approving
    the amendment. It added Article 414, which requires Summersville to
    adopt a final design plan for the entire transmission line in consulta-
    tion with affected property owners and relevant federal and state
    agencies.
    But FERC's imposition of new Article 414 does not give the Asso-
    ciation a right to challenge Summersville's Plan under Article 409
    based on its inadequacy at the Meadow River crossing. Article 409
    never imposed an obligation on Summersville to address the Meadow
    River crossing.
    VI. New Arguments on Appeal
    The Association and the AWA have advanced a number of other
    arguments on appeal that we will not consider. These arguments
    13
    include allegations that a comprehensive plan was never developed,
    that FERC failed to follow its own regulations, including 18 C.F.R.
    § 2.13, and that this matter should be reviewed under the provisions
    of Executive Order No. 12898 (February 11, 1994) (providing that
    "each Federal agency shall make achieving environmental justice part
    of its mission"). Our review of FERC's order is limited by 16 U.S.C.
    § 825l(b), which provides, "No objection to the order of the Commis-
    sion shall be considered by the court unless such objection shall have
    been urged before the Commission in the application for rehearing
    unless there is reasonable ground for failure to do so." See also
    Escondido Mut. Water Co. v. La Jolla Band of Mission Indians, 
    466 U.S. 765
    , 779 n.23 (1984).
    The petitioners argue that they should be excused from this proce-
    dural limitation because they were not adequately notified of FERC's
    actions and were, in effect, ambushed by the application for amend-
    ment. As we have already discussed, however, we are satisfied that
    the petitioners had adequate notice of the proceedings below. Indeed,
    they participated in them extensively, both through oral testimony and
    in writing. Moreover, FERC addressed each of their claims in some
    detail in its various orders. Accordingly, we find no reason to expand
    our review beyond the limits fixed by Congress.
    For the foregoing reasons, we affirm FERC's various orders grant-
    ing Summersville's application for amendment to its license.
    AFFIRMED
    14