Pennsylvania Electric Coil, Ltd v. City of Danville , 329 F. App'x 399 ( 2009 )


Menu:
  •                              UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 08-1746
    PENNSYLVANIA ELECTRIC COIL, LIMITED,
    Plaintiff - Appellant,
    v.
    CITY OF DANVILLE,
    Defendant - Appellee.
    Appeal from the United States District Court for the Western
    District of Virginia, at Danville.    Jackson L. Kiser, Senior
    District Judge. (4:06-cv-00080-jlk-mfu)
    Argued:   March 27, 2009                      Decided:   May 11, 2009
    Before NIEMEYER, KING, and DUNCAN, Circuit Judges.
    Affirmed by unpublished per curiam opinion.
    ARGUED: Chauncey Reynolds Keller, Jr., ULMER & BERNE, Cleveland,
    Ohio, for Appellant. Jeremy E. Carroll, GLENN, FELDMANN, DARBY
    & GOODLATTE, Roanoke, Virginia, for Appellee. ON BRIEF: Neil W.
    Gurney, ULMER & BERNE, Cleveland, Ohio; Glenn W. Pulley, Amanda
    M.   Morgan,  CLEMENT  &   WHEATLEY,  Danville,   Virginia,  for
    Appellant.
    Unpublished opinions are not binding precedent in this circuit.
    PER CURIAM:
    This appeal arises out of a dispute over the responsibility
    for costs exceeding the contract price for work done on three
    hydroelectric generating units, which supply power to the City
    of Danville, Virginia (“the City”).          Pennsylvania Electric Coil,
    Ltd. (“PEC”) and the City entered into a contract under which
    PEC   would   disassemble,   rewind,     refurbish,   and       reassemble   the
    units.    PEC incurred extra costs to complete the work, which the
    City ultimately refused to pay.            PEC sought recovery, alleging
    claims for breach of contract and quantum meruit.                 The district
    court granted summary judgment in favor of the City, and PEC now
    appeals on its quantum meruit claim.           Because the parties have
    an    express,   valid   contract   that    prescribes      a    change   order
    procedure to obtain approval and payment for extra work, PEC’s
    quantum meruit claim fails under Virginia law.                    We therefore
    affirm the judgment of the district court.
    I.
    In March 2003, the City of Danville issued an Invitation
    for Bids (“IFB”) on a project to disassemble, rewind, refurbish,
    and reassemble three hydroelectric units (“Units 1, 2, and 3”),
    which supply power to the City as part of the Pinnacles Hydro
    Dam on the Dan River.        The City hosted a prebid meeting at the
    2
    dam in April 2003 and allowed six potential bidders to tour and
    inspect the facility, ask questions, and seek modifications to
    the proposed contract.         PEC submitted a bid in May 2003 in which
    it affirmed that it had “visited the site and become familiar
    with and [was] satisfied as to the general location and site
    conditions that may affect cost, progress, and performance or
    furnishing of the Work.”         J.A. 282.
    The   City     ultimately       awarded    the       contract    to     PEC    for
    $882,000    in   August   2003.        The    parties’      fixed-price       contract
    consisted      of,   among     other     things,       a    four-page        agreement
    describing the work to be done, the City’s IFB, and the City of
    Danville    Procurement       Code.      These   documents         outlined    several
    constraints on the contract price and the manner in which the
    parties could agree on any increases to that price.                         Article 7
    of the contract stated:
    Notwithstanding any other provision of this contract
    to the contrary, the total obligation of the City
    shall not exceed $882,000.00 and no increase shall be
    made to this amount except by a written amendment
    executed by officials of the City and [PEC] who are
    authorized by law to execute agreements.
    J.A. 14.     In addition, article 8.e of the contract stated that
    PEC   “shall     bear   all     losses    resulting         from    the     amount   or
    character of the work being different, or because the nature of
    the premises on which the work is done is different from what
    3
    was expected or on account of the weather, or similar causes.”
    Id.    Further, section 15.1 of the IFB stated:
    The   City,   without  invalidating any    construction
    contract, and without notice to any surety, may order
    changes in the work within the general scope of the
    contract consisting of additions, deletions, or other
    revisions,   providing  the   total amount    added  or
    eliminated does not exceed twenty-five   percent (25%)
    of the total contract price, or $10,000, whichever is
    greater.    All such changes in the work shall be
    authorized by change order, and shall be executed
    under the applicable conditions of the contract
    documents.
    J.A.   206.      This    25%   cap    on    price      increases     is   mandated    by
    Virginia state law, Va. Code § 2.2-4309, and is restated in
    section 30-13 the Danville Procurement Code, J.A. 398.
    PEC    began     working      on     the    project      in    October    2003.
    Significantly for purposes of the issue before us, the project
    required      cost    adjustments     for       work   beyond   the   scope     of   the
    contract.       PEC submitted written requests for and was granted
    authorization to conduct such work on several occasions at the
    outset of the project.            For example, on October 14, 2003, PEC
    submitted a written proposal to perform a heat run test on Unit
    1, suggesting that “it would be in the best interest of all
    concerned if a heat run test was performed on one of the units
    at the City of Danville Pinnacles Hydro Station while it was in
    service.”      J.A. 436.       Noting that “[t]his heat run test . . .
    was not specified and, if opted for, would be an extra charge,”
    4
    (emphasis     added),      the   proposal       included       a    suggested      testing
    schedule and stated that the price for such a test would be
    $17,500.      Id. at 436-37.       The City approved the heat run test in
    December 2003 and issued a Purchase Order signed by Gary Via,
    the City’s Director of Purchasing.                Id. at 439–40.
    Also,    after      performing     the     heat    run   test    and    an    uprate
    study required by the parties’ contract, PEC submitted a written
    proposal in March 2004 recommending additional work and design
    changes for all three units.              J.A. 442–43.         The written proposal
    noted   that      these     changes      “will     require         additional      actions
    outside of the existing work scope;” laid out PEC’s “pricing to
    complete    the    [required]      actions;”       and    “request[ed]           that    the
    contract    between       Pennsylvania      Electric      Coil      and    The    City    of
    Danville . . . be revised to include the above workscope and
    associated costs.”             Id. (emphasis added). The City ultimately
    approved two of the recommended changes and issued a Purchase
    Order signed by Gary Via in June 2004.                  J.A. 447.
    PEC subsequently began working on the disassembly of Unit 1
    and   determined     that      certain    parts     required        repairs      that    the
    parties had not originally anticipated.                        In August 2004, PEC
    submitted     a   list    of    prices    for    these    repairs,        which    totaled
    $23,065.      J.A. 449–50, 52.           The City approved these repairs and
    issued a Purchase Order signed by Gary Via in September 2004.
    5
    J.A.       454.       Work   on    Unit     1,    including     the       reassembly   and
    alignment, proceeded into early 2005.                     PEC also began work on
    Units 2 and 3 in March or April 2005.
    This lawsuit primarily arises out of alignment and plumb
    work related to all three units, as well as additional repair
    work performed on Units 2 and 3 (together, “the disputed work”).
    During the course of PEC’s performance, the parties disagreed on
    whether       PEC’s    alignment      work       fell   under    the      scope   of   the
    contract.          Although the contract called for “shaft alignment”
    after the units were reassembled, J.A. 236, it also required
    each unit to “be assembled to the existing alignment and plumb
    condition,” id. at 233 (emphasis added).                        PEC discovered that
    the units were out of alignment at the outset of the project, a
    circumstance that the contract did not anticipate. 1                          The record
    contains          correspondence      and        documentation       of     conversations
    between      the     parties      through    the     spring     of    2005,    discussing
    alignment problems for all three units as well as PEC’s concern
    that the contract failed to address the fact that units were
    already out of alignment.
    1
    PEC also asserts that the contract did not accurately
    describe   the  necessary methods for  the  disassembly  and
    reassembly work, and in some cases required “methods and
    procedures which were contrary to known industry standards.”
    Petr.’s Br. at 12.
    6
    For example, a January 11, 2005 e-mail from Tim Jablonski,
    a     City   engineer,     noted   that        PEC    and    City     employees      had
    “discussed     the   alignment     and    bearings”         and   that    PEC’s     field
    supervisor     had   pointed   out     that     “the    contract      does    not   have
    provisions to correct the plumb if [it is] out of tolerance.”
    J.A. 639.      The e-mail further stated that “Penn Coil would like
    to submit an adder if they have to adjust plumb or make any
    alignment moves.”        Id.   An April 7, 2005 letter from PEC to Phil
    Slate, the Pinnacles Hydro Dam supervisor, quotes a $2,000 price
    for adjusting the alignment for Unit 3’s sole plate, which “is
    out of flat by .033 in[ches].”                   J.A. 477.          The record also
    contains a June 24, 2005 e-mail from David Summers, another City
    engineer,      memorializing       a     phone       conversation        between     PEC
    employees and City engineers.                  J.A. 522-23.         In the e-mail,
    Summers noted that PEC’s field supervisor, Mark Wenckus, “felt
    there was additional work performed on alignment” for all three
    units and that Wenckus had “submitted a spreadsheet on 2/11/05
    to Brad Child [PEC’s General Manager] with his estimate” of the
    extra cost for this additional alignment work.                           Id. at 522.
    Summers further noted that Brad Child had received Wenckus’s
    spreadsheet, “but had never forwarded it to [the Pinnacles Hydro
    Dam    supervisor]    or    requested      a     Change      Order”      or   otherwise
    “provided any written notification that a potential Change Order
    7
    issue existed.”          Id.     Summers indicated that he “encouraged” PEC
    to contact the City “immediately in writing if [PEC] intended to
    request additional compensation regarding field work they felt
    was   out    of    scope.”        Id.    at    523.         Significantly,           he     noted
    stressing     to   Brad       Child    “that       the   City    is     not    obligated      to
    [make]      any    additional         payment       since       no    change        order    was
    requested or approved in advance of the work being completed.”
    Id.
    Notwithstanding PEC’s concerns during the spring of 2005
    about “field work they felt was out of scope,” J.A. 523, and
    reminders from the City about the need for change orders, the
    record contains only three written price increase proposals from
    PEC in 2005: two submitted in April 2005 for concrete repairs to
    Unit 3’s sole plate and for alignment work on Unit 3’s stator
    and sole plate; and one submitted in May 2005 for modifications
    to the Unit 2 turbine housing.                     J.A. 475, 477, 485.                  The City
    did   not    issue       a    Purchase   Order       to     authorize         any    of     these
    proposed changes.             The only change that the City did approve in
    2005,    through     a       letter   written       by    Gary       Via,   was     a    written
    request from Mark Wenckus on May 6, 2005 to extend the contract
    completion deadline for two weeks because Wenckus had discovered
    that Unit 2’s “vertical centerline was out of industry standard
    tolerance for a hydraulic turbine and generator of its type.”
    8
    J.A.       641.         During   the      course    of    the    parties’      discussions
    concerning the alignment work and additional repairs, work on
    all three units steadily progressed.                        All work on Unit 1 was
    completed          by    February      2005,     while    work     on    Units      2   and    3
    continued through June 2005.
    PEC completed work on Units 2 and 3 in June 2005 and the
    units       were     restarted       that    month.        On    July    29,       2005,     PEC
    presented the City with three final invoices for “additional
    work” on the units.              J.A. 498–501.           PEC billed $60,785 for Unit
    1,   $110,387           for   Unit   2,    and   $107,875    for    Unit    3. 2        Of    the
    original invoiced amounts, the City ultimately paid PEC a total
    of $52,902. 3            The City left unpaid a balance of $226,145, which
    included costs relating to the alignment work that totaled at
    least $216,785.
    PEC filed an action against the City, alleging claims for
    breach      of     contract      and      quantum   meruit.        The    district       court
    2
    These invoices represent bills for amounts in addition to
    the contract price.
    3
    The parties dispute whether this amount reflects work that
    a City official had approved in advance under the terms of the
    contract.    PEC asserts that $30,620 of this sum reflects work
    for which the City had never issued a purchase order.     Petr.’s
    Br. at 23.      However, the City asserts that it “made these
    payments because it determined, in good faith, that the amounts
    were outside the scope of the Contract, PEC had provided prices
    in advance of the work, and the work had been approved in
    advance by the proper City official.” Respt.’s Br. at 18.
    9
    granted summary judgment in favor of the City, and this appeal
    of the quantum meruit claim followed.
    II.
    We review de novo the district court’s grant of summary
    judgment.     Jennings v. Univ. of N.C., 
    482 F.3d 686
    , 694 (4th
    Cir. 2007) (en banc) (citing Hill v. Lockheed Martin Logistics
    Mgmt., Inc., 
    354 F.3d 277
    , 283 (4th Cir. 2004) (en banc)).
    III.
    The    district   court   exercised   diversity     jurisdiction    over
    this case under 
    28 U.S.C. § 1332
    , and we now have jurisdiction
    over PEC’s appeal under 
    28 U.S.C. § 1291
    .                 A federal court
    exercising diversity jurisdiction must apply the substantive law
    of the state in which it sits.           See Erie R.R. Co. v. Tompkins,
    
    204 U.S. 64
    , 79 (1938); see also Volvo Const. Equip. N. Am.,
    Inc. v. CLM Equip. Co., Inc., 
    386 F.3d 581
    , 599–600 (4th Cir.
    2004).     Because this appeal is taken from a federal district
    court in Virginia, we apply Virginia state law.
    The    Virginia    Supreme   Court     has   held    that   “when    one
    furnishes labor to another under a contract which, for reasons
    not prejudicial to the former, is void and of no effect, he may
    recover the value of his services on a quantum meruit.”              Marine
    10
    Dev’t Corp. v. Rodak, 
    300 S.E.2d 763
    , 765 (Va. 1983) (quoting
    Hendrickson v. Meredith, 
    170 S.E. 602
    , 604 (1933)).                             “It is a
    general rule of law that he who gains the labor of another must
    make reasonable compensation for the same.”                           
    Id.
     (punctuation
    and citation omitted).               However, the Virginia Supreme Court has
    also    held    that      “where     there   is   an    express       and     enforceable
    contract in existence which governs the rights of the parties,
    the law will not imply a contract in contravention thereof.”
    Royer    v.    Bd.   of    County      Supervisors      of       Albemarle    County,   
    10 S.E.2d 876
    , 881 (Va. 1940).
    PEC bases its quantum meruit claim on the district court’s
    holding that the parties’ contract did not cover the disputed
    work, such that there was no contract to govern the parties’
    rights as to that work.              PEC contends that in aligning the units
    it rendered a benefit to the City that the City accepted, and
    that the City had reasonable notice that PEC expected to be paid
    for the alignment work.               Relying on Main v. Dep’t of Highways,
    
    142 S.E.2d 524
    ,      531   (Va.    1965),    the    City       responds    that    the
    parties’ contract forecloses any recovery under a quantum meruit
    theory    because      the      contract     contains        a    provision    requiring
    written change orders for price increases.
    Main controls the outcome of this case and compels us to
    affirm    the    judgment       of    the    district    court.         In     Main,    the
    11
    Virginia Supreme Court noted that change order provisions “are
    frequently embodied in building and construction contracts and
    are   generally      upheld.”      142    S.E.2d         at    529.     Like      PEC,    the
    plaintiff     in     Main    entered      into       a        construction        contract,
    performed extra work while satisfying its obligations under the
    contract, and sought to recover the cost of that extra work
    under a quantum meruit theory.                 The Main court found that “the
    written contract which the plaintiffs executed clearly provided
    the method by which they could insure the recovery of the cost
    of    such   extra   work,   and   not     having         followed      the    prescribed
    method, they are not entitled to such recovery.”                        Id. at 530–31.
    Under Main, quantum meruit relief is not available to PEC
    because there is a valid, enforceable contract that governs the
    parties’ rights and lays out a change order procedure requiring
    PEC to obtain approval from a designated person with authority
    to execute agreements on behalf of the City.                          PEC’s own actions
    regarding the heat test run on Unit 1 and the ensuing proposed
    design   changes     demonstrate     that       it   knew       of    and   was    able   to
    follow this change order procedure.                  The record shows that City
    employees reminded PEC about the change order procedure, and
    that PEC was aware of the change order procedure, while work
    continued on Units 2 and 3.              See J.A. 522–23, 639.                PEC has not
    disputed the validity of the change order provision.                           Nor has it
    12
    supplied a reason for its failure to continue complying with the
    provision as work on the units progressed.            Like the plaintiffs
    in Main, PEC failed to follow the prescribed method outlined in
    the parties’ contract to obtain approval and payment for extra
    work -- a method with which it was not only familiar, but which
    it had in fact utilized.
    Although   we   are   not   unsympathetic   to   the   fact   that   our
    decision likely allows the City to reap a substantial windfall,
    while sitting in diversity we are constrained to apply Virginia
    law as articulated by the Virginia Supreme Court.             Virginia law
    forecloses PEC’s quantum meruit claim.
    IV.
    For the foregoing reasons, the judgment of the district
    court is
    AFFIRMED.
    13
    

Document Info

Docket Number: 08-1746

Citation Numbers: 329 F. App'x 399

Judges: Duncan, King, Niemeyer, Per Curiam

Filed Date: 5/11/2009

Precedential Status: Non-Precedential

Modified Date: 8/7/2023