Costello Construction of Maryland, Inc. v. J.D. Long Masonry, Inc. , 236 F. App'x 877 ( 2007 )


Menu:
  •                              UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 06-1704
    COSTELLO     CONSTRUCTION    OF       MARYLAND,
    INCORPORATED;    LIBERTY  MUTUAL      INSURANCE
    COMPANY,
    Plaintiffs - Appellees,
    versus
    J.D. LONG MASONRY, INCORPORATED,
    Defendant - Appellant.
    Appeal from the United States District Court for the Eastern
    District of Virginia, at Alexandria. Gerald Bruce Lee, District
    Judge. (1:05-cv-00742-GBL)
    Argued:   March 13, 2007                    Decided:   June 26, 2007
    Before NIEMEYER, MICHAEL, and TRAXLER, Circuit Judges.
    Affirmed in part, vacated in part, and remanded with instructions
    by unpublished per curiam opinion.
    ARGUED: Stephen Murray Seeger, QUAGLIANO & SEEGER, Washington,
    D.C., for Appellant. David Hilton Wise, WATERS & WISE, P.L.L.C.,
    Fairfax, Virginia, for Appellees.    ON BRIEF: Leonard A. Sacks,
    Rockville, Maryland, for Appellant. Paul V. Waters, WATERS & WISE,
    P.L.L.C., Fairfax, Virginia, for Appellees.
    Unpublished opinions are not binding precedent in this circuit.
    PER CURIAM:
    Costello Construction (Costello) received a substantial
    contract to build a new administration building for Loudoun County
    Public Schools (Loudoun County or County).     Costello subcontracted
    the masonry work to J.D. Long Masonry, Inc. (J.D. Long).            Four
    months after J.D. Long commenced its work on the building, Costello
    terminated the subcontract and hired another masonry company to
    complete the work.      Costello sued J.D. Long in federal district
    court, seeking indemnification and damages for breach of contract.
    J.D. Long counterclaimed for wrongful termination and damages
    caused by Costello’s delays to the construction schedule.           The
    district court granted summary judgment to Costello on J.D. Long’s
    counterclaims. Following a bench trial, the district court awarded
    $777,138.41 in damages to Costello.      J.D. Long appeals.   We affirm
    the order of partial summary judgment for Costello but reduce its
    damages award to $489,224.69.
    I.
    On September 15, 2003, Loudoun County awarded Costello a
    contract     to   construct   a   new   administration   building    for
    $21,435,200.      The contract provided a substantial completion date
    of January 10, 2005, and a final completion date of February 10,
    2005.      The contract said that “time was of the essence” and
    provided that Costello would pay $2,500 per day in liquidated
    2
    damages for delays to substantial completion and $1,000 per day in
    delays to final completion.   J.A. 1339.
    Costello subcontracted with J.D. Long to do the masonry
    work for a fixed sum of $1,435,000.   The subcontract stated that
    J.D. Long had 50 days to complete the exterior masonry work, which
    entailed installing “Arriscraft masonry units at the first level,
    cast stone above the Arriscraft, and above the cast stone brick
    masonry with cast stone bands.”   Appellant’s Br. at 4.    J.D. Long
    was originally scheduled to start work in April 2004, but the start
    date was delayed by several months due to problems beyond J.D.
    Long’s control.   On August 11, 2004, Costello informed J.D. Long
    that the new completion date for the exterior masonry work was
    September 26, 2004. J.D. Long contested the end date, stating that
    it had 50 working days to complete the work.    J.D. Long said that
    it would be unable to finish the work until the end of October.
    Costello expressed concerns about the quality of the
    masonry work soon after J.D. Long started.   Among other problems,
    Costello complained that the brickwork did not comply with the job
    specifications, the cast stones were damaged, and the first-floor
    Arriscraft wall was improperly installed.      (J.D. Long’s on-site
    foreman, Michael Boyd, admitted at trial that he was unaware of the
    masonry specifications or the 50-day timetable.)     On October 29,
    2004, Costello told J.D. Long that its “performance on the Project
    has been and continues to be seriously deficient.”        J.A. 1446.
    3
    Costello then sent a notice-to-cure letter on November 1, 2004,
    stating that Costello would terminate the subcontract if J.D. Long
    did not take immediate corrective action.        J.D. Long assured
    Costello that it would correct the problems, but said that it could
    not finish the work until the end of November.    Costello decided
    not to take any action under the subcontract until that time.   J.D.
    Long failed, however, to correct the deficiencies or complete the
    work by the promised date.    On December 9, 2004, Costello hired
    another company, Bragunier Masonry, to take over the work on the
    building’s exterior.   J.D. Long continued to work on the interior
    of the building.
    In January 2005 Loudoun County threatened to terminate
    its contract with Costello, due in part to defects in the masonry
    work. Loudoun County then hired a masonry consultant, Wiss Janney,
    Elstner Associates, Inc. (Wiss Janney), to review J.D. Long’s work
    and identify the corrective action needed.     On March 10, 2005,
    Costello notified J.D. Long of the County’s concerns with the
    masonry work. Costello stated that it would give J.D. Long another
    opportunity to cure its breach of the subcontract.       J.D. Long
    denied that it was the cause of the County’s complaints.    On May
    20, 2005, after receiving the report prepared by Wiss Janney,
    Costello sent another notice-to-cure letter, which instructed J.D.
    Long to correct the deficiencies listed in the report.   J.D. Long
    4
    failed to remedy Costello’s and Loudoun County’s concerns, and
    Costello terminated the subcontract on June 22, 2005.
    Costello sued J.D. Long in the district court for breach
    of   contract,   seeking   $1,767,702   in   damages.     J.D.   Long
    counterclaimed for wrongful termination, requesting $677,832 in
    damages for delays caused by Costello and quantum meruit relief for
    work already performed. The district court granted partial summary
    judgment to Costello on J.D. Long’s counterclaims.      After a bench
    trial the district court awarded Costello $777,138.41 in damages.
    J.D. Long appeals the district court’s order granting
    partial summary judgment to Costello and the award for damages. We
    review the summary judgment decision de novo, and, with respect to
    the bench trial, we review the district court’s factual findings
    for clear error and its legal determinations de novo. See Williams
    v. Sandman, 
    187 F.3d 379
    , 381 (4th Cir. 1999).
    II.
    A.
    J.D. Long contends that the district court erred in
    granting summary judgment to Costello on J.D. Long’s counterclaim
    for damages caused by Costello’s delays. J.D. Long says that these
    delays cost it $370,951 for additional scaffolding and $306,881 for
    additional labor.   The district court determined that J.D. Long’s
    5
    counterclaim for damages was precluded by Articles 4.1.1.1 and
    4.1.1.3 of the subcontract.
    Article   4.1.1.1      (“Time   is    of   the   essence”)   of   the
    subcontract states:
    The Contractor has the right to direct the manner in
    which the Subcontractor performs its work. Subcontractor
    shall proceed with the performance of the work at such
    time and in such sequence as the Contractor may direct
    and/or as required by the Schedule of Progress, which may
    be updated and revised from time to time by the
    Contractor as working conditions require, including
    overtime or shift work performance as necessary.
    Subcontractor shall perform overtime work and/or provide
    additional shifts and/or increase crews and equipment to
    assure timely completion of the project at not [sic] cost
    to Contractor, unless and only if the costs therefore are
    paid by the Owner for the Subcontractor’s behalf.
    J.A. 1391 (emphasis added).       Article 4.1.1.3 (“Damages for Delay”)
    states that “[a] time extension shall be the sole and exclusive
    remedy of the Subcontractor for delays or suspensions caused by
    Contractor.”   J.A. 1391.
    These two provisions unambiguously prevent J.D. Long from
    recovering monetary damages from Costello, even for delays that
    Costello caused, unless Loudoun County agrees to pay the costs.
    Under   Maryland   law,   which    governs      our   interpretation    of   the
    contract, “[w]here a contract is plain and unambiguous, there is no
    room for construction, and it must be presumed that the parties
    meant what they expressed.”         Feick v. Thrutchlev, 
    586 A.2d 3
    , 4
    (Md. 1991).    We therefore affirm the district court’s grant of
    6
    summary judgment to Costello on J.D. Long’s counterclaim for
    damages.
    B.
    J.D. Long also claims that the district court erred in
    determining that Costello terminated the subcontract for default.
    J.D. Long says that the termination was wrongful, and therefore a
    breach, because Costello did not provide it proper notice or
    sufficient opportunity to cure the defects in the masonry work. In
    addition, J.D. Long argues that it could not cure the defects in
    the exterior masonry because Costello had prohibited J.D. Long’s
    crew from returning to work on the building’s facade.
    J.D. Long’s claims are without merit.    Beginning in
    August 2004 Costello repeatedly advised J.D. Long, orally and in
    writing, that its work was deficient.    Costello told J.D. Long on
    October 29, 2004, that it was in default of the subcontract, and it
    sent J.D. Long a 14-page notice-to-cure letter on November 1, 2004.
    The letter informed J.D. Long of the corrective action that it
    needed to take and stated that it had three days, pursuant to
    Article 6.1 of the subcontract, to cure the default.       Although
    Costello could have terminated the subcontract on November 4, it
    provided J.D. Long over a month to address the deficiencies.
    J.D. Long’s claim that it could not cure the default
    because it was not permitted on the construction site is also
    meritless.     Costello did not bar J.D. Long from working on the
    7
    exterior of the building until December 9, 2004.               J.D. Long had
    substantial opportunity to cure its default by this date, and
    Costello reasonably concluded that extending more time to J.D. Long
    would result in additional damages.              Thus, the district court
    correctly determined that Costello was entitled to terminate J.D.
    Long’s subcontract on grounds of default.
    III.
    J.D. Long challenges the $777,138.41 in damages awarded
    to Costello at trial.           In calculating this award, the district
    court first determined that J.D. Long’s breach caused $1,028,151.40
    in damages: $210,000 for liquidated damages, $249,084.29 to repair
    J.D. Long’s deficient work, $126,396 to complete the exterior
    masonry work, $42,151.89 to heat the building until the masonry
    work was finished, $37,074 to replace cracked masonry stones,
    $147,341.23 for administration and overhead costs, $72,000 for
    litigation costs, and $144,104 for attorneys’ fees. The court then
    subtracted the unpaid balance on the subcontract, $251,013, which
    is the amount that Costello saved by terminating it.
    J.D. Long says that the damage award should be vacated
    for two reasons.          First, it says that it is not liable for
    liquidated damages because Loudoun County has not withheld from
    Costello   any    money   for    the   158-day   delay   in   the   building’s
    completion.      Second, it argues that the court erred in calculating
    8
    the 20 percent in administration and overhead costs that Costello
    could recover under the subcontract.1              We review the factual
    underpinnings of the district court’s damages calculations for
    clear error, “but to the extent those calculations were influenced
    by legal error, review is de novo.”           United States ex rel. Maddux
    Supply Co. v. St. Paul Fire & Marine Ins. Co., 
    86 F.3d 332
    , 334
    (4th Cir. 1996).
    A.
    J.D. Long disputes the award for liquidated damages. The
    district court determined that J.D. Long delayed the project’s
    completion by 60 days, and was therefore liable for $210,000 in
    liquidated damages ($2,500 for each day to substantial completion
    and $1,000 for each day to final completion).          J.D. Long says that
    the district court erred in awarding a sum for liquidated damages
    because Loudoun County has not attempted to recover such damages
    from Costello.
    We agree that J.D. Long is not liable for liquidated
    damages.     Article   3.3.1   of       the    subcontract   states,   “The
    1
    J.D. Long also claims that Costello owed $339,478 under the
    subcontract, not $251,013. J.D. Long says that the two exhibits
    that the court used to determine the balance of the subcontract
    were unreliable.    J.D. Long, however, did not object to the
    admission of these exhibits, nor did it cross-examine Costello
    about their contents or authenticity. J.D. Long thus waived any
    objection to the admission of the two exhibits, see, e.g., Clausen
    v. SEA-3, Inc., 
    21 F.3d 1181
    , 1190 (1st Cir. 1994), and the
    district court did not clearly err in using them to calculate the
    balance on the subcontract.
    9
    Subcontractor shall be responsible for its proportionate share of
    liquidated damages . . . including all or a portion of any
    liquidated damages assessed by the Owner against the Contractor.”
    J.A. 1391.   The subcontract clearly provides that Costello can
    recover liquidated damages from J.D. Long only if it is required to
    pay liquidated damages to Loudoun County. The County, however, has
    not claimed any liquidated damages against Costello.   Indeed, the
    district court explicitly found that “Loudoun County did not
    withhold [liquidated damages] from the contract balance.”     J.A.
    2622. Although the County has withheld $750,000 “to insure all the
    punch list items are done,” its representative, Tom Sullivan, made
    clear at trial that this sum does not include money for liquidated
    damages. J.A. 691-92. Sullivan also affirmed that the County does
    not intend to assert its right to seek liquidated damages.
    The $210,000 award for liquidated damages against J.D.
    Long is also improper under contract law principles.   The purpose
    of breach of contract damages “is to place the non-breaching party
    in the same position it would have been in but for the breach.”
    Air Caledonie Int’l v. AAR Parts Trading, Inc., 
    315 F. Supp. 2d 1319
    , 1337 (S.D. Fla. 2004).   In this case, the district court’s
    award places Costello in a better position than it would be in but
    for the breach because the $210,000 would become a windfall when
    the County pays Costello the $750,000 that it withheld to ensure
    completion of the punch list items.   Of course, Costello could be
    10
    injured   if   Loudoun    County    decides    at   a    later    date    to    seek
    liquidated damages, but this injury is speculative.                  Damages for
    breach    of   contract     are    inappropriate        when   the     injury     is
    “speculative, possible, or imaginary.”           Schonfeld v. Hillard, 
    218 F.3d 164
    , 172 (2d Cir. 2000); see also Willard Packaging Co. v.
    Javier, 
    899 A.2d 940
    , 945 (Md. App. 2006) (stating that liquidated
    damage provision is not enforceable when it is not a reasonable
    estimate of the damages suffered).           For these reasons, we conclude
    that the district court erred as a matter of law in awarding
    liquidated damages to Costello.2
    B.
    The   district       court   also   committed       clear     error   in
    calculating the damages that Costello could recover for overhead
    and administration costs.         Article 6.1 of the subcontract provides
    that the “contractor may immediately take all steps necessary to
    supplement the work activities of Subcontractor and charge all
    resulting cost therefrom plus 10% overhead and 10% profit to
    Subcontractor.”    J.A. 1393.        The district court awarded Costello
    $147,341.23    under     this   provision,     finding     that   Costello       was
    entitled to 20 percent of the following costs:                       the cost to
    complete the exterior masonry work ($126,396); the cost to repair
    2
    J.D. Long also argues that the district court abused its
    discretion in admitting Costello’s expert witness testimony
    regarding the delay attributable to J.D. Long. Because we conclude
    that the liquidated damages are improper, we do not reach this
    evidentiary issue.
    11
    J.D. Long’s deficient work ($249,084.29); the expert consultant
    fees ($18,827.39); the cost to enclose and heat the building
    ($42,151.89); the cost to replace cracked masonry stones ($37,074);
    liquidated damages ($210,000); and Costello’s expert witness fees
    ($53,172.61).
    The court committed three errors in calculating the
    administration and overhead costs. First, the 20 percent markup on
    liquidated   damages    is   error   in   light   of   our   conclusion   that
    Costello cannot recover liquidated damages from J.D. Long.                 See
    supra part II.A.       Second, the markup on expert witness fees is
    inappropriate because the subcontract does not permit Costello to
    recover 20 percent of litigation costs as part of overhead and
    administration. Third, the court’s figure for the cost to complete
    the masonry work ($126,396) already included the 20 percent markup
    because Costello paid only $105,830 to finish the exterior masonry
    work.    These errors require Costello’s recovery under Article 6.1
    of the subcontract to be reduced from $147,341.23 to $90,593.513
    and its overall damage award to be reduced by an additional $21,166
    to account for the cost-to-complete figure that was inflated by 20
    percent.
    3
    The $90,593.51 sum is 20 percent of the following costs: the
    cost to complete the masonry work ($105,830), the cost to repair
    the deficient work ($249,084.29), expert consultant fees not
    related to litigation ($18,827.39), the cost to enclose and heat
    the building ($42,151.89), and the cost to replace the cracked
    masonry stones ($37,074).
    12
    IV.
    In sum, we affirm the district court’s order of partial
    summary judgment for Costello.        We conclude, however, that the
    damage award to Costello must be reduced by $287,913.72 ($210,000
    for liquidated damages, $56,747.72 for administration and overhead
    costs, and $21,166 for the cost to complete the masonry work).     We
    therefore vacate the judgment entered in favor of Costello with
    respect to damages and instruct the district court on remand to
    enter judgment in favor of Costello for $489,224.69.
    AFFIRMED IN PART,
    VACATED IN PART,
    AND REMANDED WITH INSTRUCTIONS
    13