Dennis Stubbs Plumbing, Inc. v. Travelers Casualty & Surety Co. of America , 67 F. App'x 789 ( 2003 )


Menu:
  •                         UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    DENNIS STUBBS PLUMBING,                
    INCORPORATED,
    Plaintiff-Appellant,
    v.                             No. 02-2050
    TRAVELERS CASUALTY AND SURETY
    COMPANY OF AMERICA,
    Defendant-Appellee.
    
    Appeal from the United States District Court
    for the Eastern District of Virginia, at Alexandria.
    Gerald Bruce Lee, District Judge.
    (CA-02-381-A)
    Argued: May 8, 2003
    Decided: June 5, 2003
    Before LUTTIG and MICHAEL, Circuit Judges, and
    Joseph Robert GOODWIN, United States District Judge
    for the Southern District of West Virginia,
    sitting by designation.
    Vacated and remanded by unpublished per curiam opinion.
    COUNSEL
    ARGUED: William H. Moore, ITTIG & ITTIG, P.C., Washington,
    D.C., for Appellant. Tamara Marie McNulty, VENABLE, BAETJER
    & HOWARD, L.L.P., Vienna, Virginia, for Appellee.
    2          DENNIS STUBBS PLUMBING v. TRAVELERS CASUALTY
    Unpublished opinions are not binding precedent in this circuit. See
    Local Rule 36(c).
    OPINION
    PER CURIAM:
    The plaintiff in this matter, Dennis Stubbs Plumbing, Inc.
    ("Stubbs"), appeals from the dismissal of its claim below. The district
    court concluded that Stubbs’ claim did not satisfy the amount-in-
    controversy requirement of 
    28 U.S.C. § 1332
    , and dismissed Stubbs’
    case without prejudice. Because we conclude that Stubbs may in fact
    have claims exceeding the $75,000 amount-in-controversy require-
    ment, we vacate the district court’s decision and remand for further
    proceedings.
    I.
    This action arises out of a failed construction project. MDC Build-
    ers, LLC ("MDC") was the prime contractor for a public construction
    contract with the Northern Virginia Community College System
    ("NVCC"). NVCC contracted with MDC for the construction of a
    new classroom building (the "Project"). In accordance with the
    requirements of Virginia law, MDC, as principal, and Travelers Casu-
    alty and Surety Company of America ("Travelers"), as surety, issued
    a payment bond for the protection of those supplying labor and mate-
    rials on the project.
    MDC subcontracted with Stubbs to furnish all labor, materials,
    equipment, supervision, and services for the plumbing work for the
    subcontract price of $210,000 (the "Subcontract"). The Subcontract
    contained what is generally referred to as a "no damages for delay"
    clause. This clause provided, in relevant part:
    EXTENSIONS OF TIME — If Subcontractor shall be
    materially delayed by the wrongful act or omission of the
    Contractor, the time for completion of the Work shall be
    extended for a period equal to the reasonably estimated
    DENNIS STUBBS PLUMBING v. TRAVELERS CASUALTY               3
    period of delay as determined by Contractor. . . . The exten-
    sion of time herein provided shall be Subcontractor’s sole
    and exclusive remedy for any delay, and Subcontractor shall
    have no claim for damages against Contractor by reason
    thereof.
    J.A. 32. The provision for delay reflected some prescience on the part
    of the contracting parties, for numerous delays ensued in the course
    of construction. Ultimately, MDC’s contract was default terminated
    by Virginia for gross mismanagement of the Project.
    Stubbs brought suit against Travelers in federal district court in an
    effort to recover $153,064.83 in damages incurred in its performance
    of the Subcontract. Stubbs itemized its damages as follows:
    Item #1     Contract Balance & Retainage           $14,910
    Item #2     Additional & Extended Field            $10,799.25
    Supervision
    Item #3     Additional Labor Costs Due to          $88,799.29
    Interferences, Poor Scheduling,
    Acceleration & Disruptions
    Item #4     Extended Home Office Overhead          $38,556.29
    S.J.A. 4-5 (hereinafter "Itemized Damages"). Travelers, Stubbs
    alleged, was liable for these damages because it had failed to make
    payment pursuant to the payment bond. Stubbs also alleged that the
    district court had diversity jurisdiction over the action as the parties
    were diverse and the amount in controversy exceeded $75,000.
    Travelers filed a Motion for Partial Summary Judgment based upon
    the "no damages for delay" clause. In response to that motion, Stubbs
    introduced an affidavit by Dennis Stubbs, the president of Stubbs
    Plumbing, which stated, among other things, that "MDC ordered
    Stubbs to perform work in areas that were not ready for installation
    of plumbing work," and that "Stubbs incurred additional costs and
    damages as a direct result of MDC’s gross mismanagement of the
    Project and its active interference with Stubbs’ work." J.A. 73.
    4          DENNIS STUBBS PLUMBING v. TRAVELERS CASUALTY
    The district court granted Travelers’ motion, holding that the "no
    damages for delay" clause prohibited Stubbs from recovering dam-
    ages due to delays, including those delays caused by MDC. The dis-
    trict court construed Itemized Damages 2-4 as delay damages. Since
    such damages were not recoverable under the contract, and since the
    remaining amount in controversy was only $14,910 for "Contract Bal-
    ance & Retainage," the district court concluded that it lacked subject
    matter jurisdiction over the case and dismissed it without prejudice.
    From that ruling, Stubbs appeals.
    II.
    We review the district court’s grant of summary judgment de novo.
    See Bass v. E.I. DuPont de Nemours & Co., 
    324 F.3d 761
    , 766 (4th
    Cir. 2003). In doing so, we view the facts proffered in the light most
    favorable to the non-moving party — in this case Stubbs — and deter-
    mine whether such proffer is sufficient to create a genuine issue of
    material fact. See Fed. R. Civ. P. 56(c).
    The issue presented is whether the "no damages for delay" clause
    prohibits Stubbs from recovering the types of damages asserted in
    Itemized Damages 2-4. Once again, the relevant language from the
    Subcontract provides that "[t]he extension of time herein provided
    shall be Subcontractor’s sole and exclusive remedy for any delay, and
    Subcontractor shall have no claim for damages against Contractor by
    reason thereof." J.A. 32. By stating that extension of time shall be the
    sole and exclusive remedy "for any delay," the Subcontract makes
    clear that delay damages resulting from a material delay by MDC are
    not recoverable.
    Stubbs claims, however, that the types of damages listed in Item-
    ized Damages 2-4 are not delay damages. The Stubbs affidavit avers
    that "Stubbs incurred additional costs and damages as a direct result
    of MDC’s gross mismanagement of the Project and its active interfer-
    ence with Stubbs’ work." J.A. 73. As stated in Stubbs’ brief, "Stubbs’
    claims for damages include excess labor and material and supervision
    costs relating to the increased difficulty of performing its work and
    the additional time it took to complete." Appellant Br. at 6. The latter
    type of damage — additional time necessary for completion — might
    amount simply to delay damages, but the former type of damage —
    DENNIS STUBBS PLUMBING v. TRAVELERS CASUALTY                5
    increased difficulty in performing its work — is not itself necessarily
    a request for damages resulting from delay. Claims of the former type
    of damage, which can generally be referred to as claims of active
    interference by MDC, seek recompense for increased costs imposed
    by MDC’s wrongful acts. While some such costs may result from
    delay, others may not (e.g., the costs associated with having to redo
    a project because the plans initially provided were incorrect).
    The distinction between delay damages and active interference
    damages has long been recognized in the law. See American Bridge
    Co. v. New York, 
    245 A.D. 535
    , 538-39 (N.Y. App. Div. 1935); 
    id.
    at 540 (citing cases). While there is no authority from Virginia
    directly on point, we think Virginia would recognize an independent
    claim for damages resulting from active interference that were not
    themselves delay damages. Virginia has recognized a difference
    between mere delay and delay caused by active interference. See Al-
    gernon Blair, Inc. v. Norfolk Redevelopment and Housing Authority,
    108 S.E. 2d. 259, 263 (Va. 1959). The types of damages alleged by
    Stubbs are merely another type of damages resulting from active
    interference.
    As damages for active interference or additional and extra work
    caused by the wrongful acts of the contractor are not themselves delay
    damages, they do not fall within the ambit of the "no damages for
    delay" clause, which by its terms precludes only those damages that
    result "from any delay."
    The only remaining question then is whether Stubbs has proffered
    sufficient evidence as to non-delay damages to overcome a motion for
    summary judgment. Though the only evidence Stubbs proffered of
    active interference was a somewhat self-serving and conclusory affi-
    davit by Dennis Stubbs, that affidavit did include Mr. Stubbs’ asser-
    tions that "MDC ordered Stubbs to perform work in areas that were
    not ready for installation of plumbing work." J.A. 73. That allegation
    is sufficiently particular (though barely so) to support an active inter-
    ference claim given that similar circumstances historically have been
    the gravamen of triable active interference claims. See American
    Bridge Co., 245 A.D. at 538-39 (concluding that the state was liable
    for the damages caused by its premature directing of its contractor to
    begin work, despite the parties’ adoption of a general "no damages for
    6          DENNIS STUBBS PLUMBING v. TRAVELERS CASUALTY
    delay" agreement). Additionally, in its itemized list of damages,
    Stubbs claims that it suffered $88,799.29 in damages from "Addi-
    tional Labor Costs Due to Interferences, Poor Scheduling, Accelera-
    tion & Disruptions." S.J.A. 4. While some of these categories might
    encompass delay damages, others, like "Acceleration," clearly do not.
    While Stubbs’ complaint and the affidavit are far from pellucid as
    to the nature of damages incurred, we think it is clear that Stubbs
    could possibly be claiming non-delay damages in excess of $75,000,
    in which case it is entitled to have its case tried in federal court. If,
    upon further proceedings, it becomes clear that Stubbs is not actually
    claiming more than the requisite jurisdictional amount in non-delay
    damages, then dismissal for lack of subject matter jurisdiction would
    be appropriate at that time. But because, based on the record before
    us now, Stubbs may well have claims for non-delay damages in
    excess of $75,000, we vacate the district court’s dismissal and
    remand.
    VACATED AND REMANDED
    

Document Info

Docket Number: 02-2050

Citation Numbers: 67 F. App'x 789

Judges: Goodwin, Luttig, Michael, Per Curiam, Southern

Filed Date: 6/5/2003

Precedential Status: Non-Precedential

Modified Date: 8/6/2023