Lone Mountain Processing, Inc. v. Bowser Morner, Inc. , 94 F. App'x 149 ( 2004 )


Menu:
  •                          UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    LONE MOUNTAIN PROCESSING,             
    INCORPORATED,
    Plaintiff-Appellant,
    v.
              No. 02-2392
    BOWSER-MORNER, INCORPORATED;
    BOWSER-MORNER ASSOCIATES,
    INCORPORATED,
    Defendants-Appellees.
    
    Appeal from the United States District Court
    for the Western District of Virginia, at Big Stone Gap.
    Glen M. Williams, Senior District Judge.
    (CA-00-93-2)
    Argued: December 5, 2003
    Decided: April 8, 2004
    Before NIEMEYER and TRAXLER, Circuit Judges, and
    Richard D. BENNETT, United States District Judge for the
    District of Maryland, sitting by designation.
    Affirmed in part, reversed in part, and remanded by unpublished opin-
    ion. District Judge Bennett wrote the opinion, in which Judge Nie-
    meyer joined. Judge Traxler wrote a separate opinion concurring in
    part and dissenting in part.
    COUNSEL
    ARGUED: Frank Kenneth Friedman, WOODS, ROGERS &
    HAZLEGROVE, P.L.C., Roanoke, Virginia, for Appellant. Stephan
    2          LONE MOUNTAIN PROCESSING v. BOWSER-MORNER
    Forrest Andrews, WRIGHT, ROBINSON, OSTHIMER & TATUM,
    Richmond, Virginia, for Appellees. ON BRIEF: Francis H. Casola,
    Daniel C. Summerlin, WOODS, ROGERS & HAZLEGROVE,
    P.L.C., Roanoke, Virginia, for Appellant. Noelle L. Shaw-Bell, David
    M. Brink, WRIGHT, ROBINSON, OSTHIMER & TATUM, Rich-
    mond, Virginia, for Appellees.
    Unpublished opinions are not binding precedent in this circuit. See
    Local Rule 36(c).
    OPINION
    BENNETT, District Judge:
    I.
    Procedural History
    On May 26, 2000, Lone Mountain Processing, Inc. ("Lone Moun-
    tain"), which operates a coal preparation facility in St. Charles, Vir-
    ginia, filed a two-count complaint against Bowser-Morner, Inc.;
    Bowser-Morner Associates, Inc. ("Bowser-Morner"), an engineering
    design firm in Dayton, Ohio, alleging breach of contract and negli-
    gence in connection with a November 1, 1991 contract between the
    parties. Pursuant to that contract, Bowser-Morner was to design a coal
    slurry impoundment for Lone Mountain’s facility. On October 24,
    2000, Lone Mountain filed an amended complaint, adding a third
    count for contractual indemnification. In its answer to the amended
    complaint, Bowser-Morner asserted the affirmative defense of the
    statute of limitations. Subsequently, Bowser-Morner moved to dis-
    miss the amended complaint.
    The District Court subsequently converted Bowser-Morner’s
    motion to dismiss into a motion for summary judgment. Lone Moun-
    tain then filed its own motion for summary judgment. The District
    Court limited discovery to the issue of statute of limitations. The
    LONE MOUNTAIN PROCESSING v. BOWSER-MORNER                   3
    motions, both based upon affidavits, were briefed and argued in
    August of 2001. In February of 2002, the District Judge dismissed
    both motions without prejudice, advising that the motions should be
    re-filed based upon additional discovery that had been taken in the
    interim. In July of 2002, Lone Mountain filed a motion for partial
    summary judgment on the issue of statute of limitations and repose.1
    Bowser-Morner also filed a motion for summary judgment.
    The District Court, in a September 13, 2002 memorandum opinion,
    granted Bowser-Morner’s motion for summary judgment and denied
    Lone Mountain’s partial motion for summary judgment. The court
    found that Lone Mountain was time-barred from bringing this action
    pursuant to a contract statute of limitations, referencing Virginia stat-
    utory law applying a five-year limitations period for a written con-
    tract.
    Pursuant to Rule 59(e) of the Federal Rules of Civil Procedure,
    Lone Mountain moved to alter or amend its judgment, noting that the
    District Court had ruled that all claims were controlled by the contract
    statute of limitations and had not addressed the additional claims of
    negligence, breach of warranty and contractual indemnification. By
    memorandum opinion dated November 1, 2002, the District Court
    denied Lone Mountain’s motion to alter or amend its September 13,
    2002 decision. The District Court reiterated its position on the negli-
    gence and breach of warranty claims as set forth in its earlier order.
    With respect to the contractual indemnification claim, the District
    Judge reiterated his holding that there was "no apparent need to
    address an issue that is, in the minds-eye of this court, constitutionally
    moot." (JA 2059). This appeal follows.
    II.
    Facts
    Lone Mountain operates a coal preparation plant in St. Charles,
    Virginia where it cleans coal in preparation for shipment. On Novem-
    ber 5, 1991, Lone Mountain entered into a contract (the "Contract")
    1
    The District Court subsequently did not address the statute of repose
    issue.
    4          LONE MOUNTAIN PROCESSING v. BOWSER-MORNER
    with Bowser-Morner, an engineering design firm, for engineering and
    design services related to a coal slurry impoundment adjacent to the
    coal preparation plant. Pursuant to the Contract, Bowser-Morner
    agreed to design the structure in accordance with federal regulations
    established by the United States Department of Mine Safety and
    Health Administration ("MSHA"), and state regulations established
    by the Commonwealth of Virginia’s Division of Mined Land Recla-
    mation ("DMLR"). While Bowser-Morner was not responsible for
    securing the necessary permits, it was required to answer questions by
    federal and state regulators during a review of the design.
    The Contract provided that any lack of conformance to regulatory
    standards was to be corrected by Bowser-Morner at no cost to Lone
    Mountain. The record of this case indicates that a representative of
    Bowser-Morner acknowledged that Bowser-Morner had an obligation
    to answer questions raised by federal and state regulators. (JA 1127-
    28).
    After a lengthy period of regulatory review during the permitting
    process and after initial federal and state approval of the design, the
    Bowser-Morner design of the coal slurry was approved on March 20,
    1995. Consequently, on March 24, 1995, Bowser-Morner issued what
    it termed its final payment order to Lone Mountain. Under the Con-
    tract, "upon acceptance and approval of the work," Lone Mountain
    was to retain (10%) and forward the remainder of payment within fif-
    teen days of approval and acceptance. On April 25, 1995, Lone
    Mountain paid Bowser-Morner’s payment order, not exercising any
    right of retainage.2
    The question of the completion of the contract is vigorously con-
    tested by the parties. Following the acceptance and approval of the
    design plan, the parties had interactions in August, October, and
    November of 1995, the legal effect of which are contested by Lone
    Mountain and Bowser-Morner. In August of 1995, at Lone Moun-
    tain’s request, Bowser-Morner provided Lone Mountain with a
    2
    Lone Mountain did not pay for one line-item listed on the invoice,
    charges of $2,850 for "[a]nswers to questions generated by the state of
    Virginia in their 10-29-92 comments," because it deemed the item to be
    "work not authorized." (JA 371, 375).
    LONE MOUNTAIN PROCESSING v. BOWSER-MORNER                 5
    hydraulics analysis with respect to alternative locations for the
    impoundment pipe. In October of 1995, representatives of Bowser-
    Morner visited the impoundment site. In November of 1995, in
    response to Lone Mountain’s request, Bowser-Morner provided a fea-
    sibility study for control of cracking concrete in the area of the pipe.
    While the ramifications of the above three events in the latter part
    of 1995 generate a dispute among the parties, it is undisputed that on
    June 5, 1996, upon filling the impoundment designed by Bowser-
    Morner with coal slurry, a pipe collapsed allowing contaminated
    water to escape and leak. This fracturing and cracking along the west-
    ern wall of the slurry impoundment resulted in the leaking of contam-
    inated water in violation of the National Pollutant Discharge
    Elimination System permit issued to Lone Mountain. See 
    33 U.S.C. §§ 1311
    , 1319.
    Subsequently, on August 9, 1996, water flowed through a collapsed
    wall of the slurry impoundment into an abandoned coal mine. DMLR
    ordered Lone Mountain to suspend operations until repairs could be
    made. After performing those repairs, Lone Mountain was allowed to
    restart its operations on August 16, 1996. One month later, on or
    about September 20, 1996, Lone Mountain discovered another leak in
    the slurry impoundment in the western wall. On or about October 9,
    1996, Lone Mountain discovered yet another leak in the impound-
    ment.
    On or about October 24, 1996, a massive leak resulted in the slurry
    impoundment allowing approximately three thousand gallons of con-
    taminated water per minute to flow into Gin Creek. This contami-
    nated water flowed approximately eleven miles into the Powell River,
    causing the pool elevation in the impoundment to drop by three feet
    and contaminating and destroying an estimated eleven thousand fish.
    As a result of the leaks and release of contaminated water into the
    Powell River, which had been designated by the government as a crit-
    ical habit area, Lone Mountain pled guilty to a two-count information
    charging it with negligent discharge of a pollutant in violation of 
    33 U.S.C. §§ 1311
    , 1319(c)(1)(A) (negligent discharge of a pollutant). In
    addition, Lone Mountain was required to pay the National Fish and
    Wildlife Foundation the sum of $15,000. Pursuant to the plea agree-
    6           LONE MOUNTAIN PROCESSING v. BOWSER-MORNER
    ment with the government, Lone Mountain was fined a total of
    $85,000 and was ordered to pay restitution in the amount $1,510,000.
    III.
    We review a grant of summary judgment de novo. Perini Corp. v.
    Perini Constr., Inc., 
    915 F.2d 121
    , 123 (4th Cir. 1990). Summary
    judgment is appropriate when "the record taken as a whole could not
    lead a rational trier of fact to find for the non-moving party." Mat-
    sushita Elec. Indus. Co. v. Zenith Radio Corp., 
    475 U.S. 574
    , 587
    (1986). "And, in evaluating a motion for summary judgment, the
    court must view the record in the light most favorable to the nonmov-
    ing party." Perini Corp., 
    915 F.2d at 123
    .
    When sitting in diversity, a federal court must apply the choice of
    law rules of the forum state, in this case Virginia. Klaxon Co. v. Sten-
    tor Elec. Mfg. Co., 
    313 U.S. 487
    , 496 (1941). Under Virginia law, the
    parties’ choice of law will be enforced if it is "reasonably related to
    the purpose of the agreement." Hooper v. Musolino, 
    234 Va. 558
    ,
    566, 
    364 S.E.2d 207
    , 211 (1988)(citing Tate v. Hain, 
    181 Va. 402
    ,
    410, 
    25 S.E.2d 321
    , 324 (1943); C.I.T. Corporation v. Guy, 
    170 Va. 16
    , 22, 
    195 S.E. 659
    , 661 (1938)). Section 13 of the instant Contract
    provides that Virginia law governs disputes between the parties aris-
    ing from the agreement. (JA 183). Thus, as the present parties agree,
    Virginia law governs the pending matters.
    IV.
    The District Court found that Lone Mountain’s breach of contract,
    warranty and negligence claims were time-barred under the applicable
    statute of limitations. We agree.
    A.
    Breach of Contract/Warranty Count
    Lone Mountain’s complaint brought one count for breach of con-
    tract, claiming that Bowser-Morner breached its obligations under the
    Contract by providing defective design services. (JA 29). As noted by
    LONE MOUNTAIN PROCESSING v. BOWSER-MORNER                 7
    Lone Mountain, the Contract "contained warranties which are inte-
    grally related to Lone Mountain’s contract claim." (Appellant’s Brief
    at 51). Indeed, the Contract’s "Warranty" provision provided that
    Bowser-Morner would provide services "free from defects." (JA 162).
    Thus, the "warranty" cited by Lone Mountain simply is another provi-
    sion of the Contract, and as such, any breach thereof necessarily
    arises simultaneously with any other design-defect claim asserted
    under the Contract. See, e.g., Federal Reserve Bank v. Wright, 
    392 F. Supp. 1126
    , 1129-31 (E.D. Va. 1975) (applying Virginia’s five-year
    statute of limitations for contract claims to a claim for breach of war-
    ranty involving alleged defective designs by architects, and holding
    that the claim arose on the date upon which the architects delivered
    the defective designs); McCloskey & Co. v. Wright, 
    363 F. Supp. 223
    ,
    225-26 (E.D. Va. 1973) (same).
    Under section 8.01-246(2) of the Virginia Code, the statute of limi-
    tations period applicable to claims on a written contract is five years.
    The statute of limitations for a design-defect claim based upon a con-
    tract commences at the time the defect or condition causing the
    breach occurs, and not when it is discovered, regardless of the diffi-
    culty in ascertaining the existence of the claim. Virginia Military
    Institute v. King, 
    217 Va. 751
    , 759, 
    232 S.E.2d 895
    , 900 (1977) (here-
    inafter VMI)(citing Housing Authority v. Laburnum Corp., 
    195 Va. 827
    , 838, 
    80 S.E.2d 574
    , 580-81 (1954)); see also 
    Va. Code Ann. § 8.01-230
     ("the right of action shall be deemed to accrue and the pre-
    scribed limitation period shall begin to run from . . . when the breach
    of contract occurs in actions ex contractu and not when the resulting
    damage is discovered . . . .").
    The Supreme Court of Virginia established the framework for ana-
    lyzing design-defect claims in VMI and in Nelson v. Commonwealth
    of Virginia, 
    235 Va. 228
    , 
    368 S.E.2d 239
     (1988). In VMI, the plaintiff
    sued defendant-architects for alleged professional negligence and
    improper design work performed pursuant to a divisible contract.
    VMI, 232 S.E.2d at 896. The VMI Court held that the plaintiff’s cause
    of action for design-defects accrued when the allegedly defective
    plans were finally approved. Id. at 900. "At that time, the architects
    had a right to demand and received payment" for their design ser-
    vices, and likewise, at that time, "if defects had been discovered, [the
    plaintiff] could have initiated legal proceedings against the archi-
    8           LONE MOUNTAIN PROCESSING v. BOWSER-MORNER
    tects." Id. In so ruling, the court distinguished a situation in which the
    "continuation of services" exception had been applied to an attorney-
    client relationship, by emphasizing that in the present case, "when the
    plans were approved the undertaking to furnish them ceased." Id.
    Similar to the scenario in VMI, in Nelson, the plaintiff brought,
    inter alia, design-defect claims against architects stemming from pro-
    fessional services rendered pursuant to a divisible contract. Nelson,
    
    368 S.E.2d at 241
    . The Nelson Court found that once the design plans
    were accepted by the plaintiff, the architects’ duty to design the proj-
    ect ended, thereby triggering the limitations period for design-defect
    claims. 
    Id. at 243
    . The court further noted that although a general
    architect-owner relationship continued to exist thereafter, the archi-
    tects’ design services effectively ended upon acceptance of the design
    plans. 
    Id.
    The instant contractual design-defect claims accrued upon payment
    by Lone Mountain, because such payment constituted "approval and
    acceptance" of the designs. Under Section 4 of the Contract, "[u]pon
    approval and acceptance of the work, [Lone Mountain] shall retain
    ten percent (10%) and forward payment of the balance within fifteen
    (15) days thereof." (JA 171). Thus, under the language of the Con-
    tract, payment indicated approval and acceptance of the design plans.
    Bowser-Morner issued its final payment order on March 24, 1995. In
    reply, Lone Mountain tendered payment to Bowser-Morner on April
    25, 1995, thereby indicating approval and acceptance of the work.
    Accordingly, under applicable Virginia law, the District Judge cor-
    rectly concluded that Lone Mountain’s contractual design-related
    claims arose on April 25, 1995. See VMI, 232 S.E.2d at 900; Nelson,
    
    368 S.E.2d at 243
    .
    Relying on County School Board of Fairfax County v. A.A. Beiro
    Construction Co., 
    223 Va. 161
    , 
    286 S.E.2d 232
     (1982) and Suffolk
    City School Board v. Conrad Brothers, Inc., 
    255 Va. 171
    , 
    495 S.E.2d 470
     (1998), Lone Mountain urges the adoption of a "bright line"
    dichotomy for the accrual of design-defect claims depending on
    whether the design work is performed pursuant to a divisible or indi-
    visible contract. We decline to establish such a rigid distinction.
    In Beiro, the parties entered into an indivisible contract for the con-
    struction of, inter alia, a school building roof. Beiro, 286 S.E.2d at
    LONE MOUNTAIN PROCESSING v. BOWSER-MORNER                  9
    233. Defendant Beiro was a contractor who had retained the right to
    correct any construction defects until the completion of the building
    construction. 
    Id.
     The court in Beiro found that the plaintiff’s claim for
    defective construction accrued, "at the earliest," upon issuance of the
    certificate of final payment in August 1973, and not upon the comple-
    tion of construction in August 1972. 
    Id.
    Similar to the situation in Beiro, in Conrad Bros., the defendant-
    contractor installed allegedly defective roofs in school buildings pur-
    suant to an indivisible contract. Conrad Bros., 
    495 S.E.2d at 470
    .
    Looking to the express terms of the construction contract at issue, the
    court found that construction was completed upon the issuance of a
    "final Certificate for Payment" regardless of the date construction was
    completed or when the roofs were known to be defective. 
    Id.
     at 471-
    72. Thus, the submission of the "final Certificate for Payment" trig-
    gered the applicable statute of limitations.
    Both Beiro and Conrad Bros. looked to the acceptance of the con-
    tracted work through the issuance of final certificates of payment as
    triggers for the applicable statute of limitations for the construction
    defect claims in question. Such holdings are consistent with the rul-
    ings of VMI and Nelson, which involved divisible contracts and held
    that design-defect claims arose at the time the corresponding design
    plans were accepted.
    The instant Contract was not divisible into distinct design, con-
    struction or supervision phases because it provided for only one
    "phase"—the design of the coal slurry impoundment structure. Thus,
    the Contract simply provided for the execution and delivery of the
    design plan. Once the completed design plan for the impoundment
    structure was "approved and accepted" by Lone Mountain, the under-
    taking to furnish it ceased to exist, thus triggering the accrual of
    design-defect related claims. VMI, 232 S.E.2d at 900; see also Fed-
    eral Reserve Bank v. Wright, 
    392 F. Supp. 1126
     at 1131 (holding that
    design-defect claims accrued at "the date upon which the architects
    delivered the defective plans" regardless of when the alleged defect
    was ascertainable); McCloskey & Co. v. Wright, 
    363 F. Supp. 223
     at
    226 (holding that a design-defect breach of warranty or contract claim
    arose "at the time the architects tendered allegedly defective plans to
    10          LONE MOUNTAIN PROCESSING v. BOWSER-MORNER
    the government" regardless of when the alleged defect was ascertain-
    able).
    Nonetheless, Lone Mountain also asserts that the parties’ Contract
    consisted of an undertaking requiring a "continuation of services,"
    whereby full performance did not occur upon acceptance of the
    design plan but rather occurred once any post-acceptance services
    were completed.3 According to Lone Mountain, such reasoning is in
    accord with the application of the "continuing services" doctrine in
    Virginia professional negligence cases involving physicians, attor-
    neys, and accountants. See, e.g., Farley v. Goode, 
    219 Va. 969
    , 
    252 S.E.2d 594
     (1979) (physician); McCormick v. Romans, 
    214 Va. 144
    ,
    
    198 S.E.2d 651
     (1973)(attorney); Boone v. C. Arthur Weaver Co., 
    235 Va. 157
    , 
    365 S.E.2d 764
     (1988) (accountant).
    Lone Mountain’s assertion is unpersuasive, however. Unlike the
    patient or client relationships created in the medical, legal, and
    accounting professions, architectural design professionals do not rou-
    tinely create confidential or fiduciary client relationships entailing
    inherent, ongoing duties of care. Moreover, the submission of reme-
    dial measures or advice does not alter the fact that design-defect
    claims generally arise at the date when the design initially is accepted
    by a purchaser, especially when acceptance is pursuant to the terms
    of a written contract. See VMI, 232 S.E.2d at 897, 900 (finding that
    design-defect claims accrued upon acceptance of design plans despite
    defendant-architects subsequent corrective design drawings, advice,
    and site visits). Indeed, to hold otherwise would contravene the pur-
    pose of the statute of limitations, in that any remedial work or advice
    subsequent to design acceptance automatically would re-start the limi-
    tations clock in design-defect cases. See Lavery v. Automation Man-
    agement Consultants, Inc., 
    234 Va. 145
    , 148, 
    360 S.E.2d 336
    , 338
    (1987) (stating that under Virginia law, "a statute of limitations is
    designed to compel the exercise of a right to sue within a reasonable
    time; to suppress fraudulent and stale claims; to prevent surprise; to
    3
    Three interactions following design acceptance specifically are refer-
    enced by Lone Mountain as evincing "continuing services": (1) the
    hydraulics analysis in August, 1995; (2) the site visit by Bowser-Morner
    representatives in October, 1995; and (3) the feasibility study in Novem-
    ber, 1995.
    LONE MOUNTAIN PROCESSING v. BOWSER-MORNER                   11
    guard against lost evidence; to keep facts from becoming obscure; and
    to prevent witnesses from disappearing"). Ultimately, therefore, Lone
    Mountain cannot overcome the fact that under the Contract, payment
    constituted "approval and acceptance" of the design plans, which in
    turn triggered the limitations period for related design-defect claims.
    B.
    Negligence Count
    Under Virginia law, the contract statute of limitations applies to an
    action to recover for professional negligence, regardless of whether a
    claim is framed as a tort. See, e.g., Boone, 
    365 S.E.2d at 766
     (holding
    that the contract statute of limitations applied to an action to recover
    for the professional negligence of an accountant, despite the fact that
    the claim was framed as a tort); VMI, 232 S.E.2d at 899-900 (holding
    that the contract statute of limitations applied to an action to recover
    for the professional negligence of an architect, despite the fact that the
    claim was framed in tort); Oleyar v. Kerr, 
    217 Va. 88
    , 90, 
    225 S.E.2d 398
    , 400 (1976)(holding that the contract statute of limitations applied
    to an action to recover for the professional negligence of an attorney,
    despite the fact that the claim was framed in tort). Such a "result fol-
    lows from the distinction between duties assumed pursuant to an
    agreement and duties imposed by general law." Boone, 
    365 S.E.2d at 766
    . Thus, "[b]ecause there would be no duty from [the professional]
    to the client in the absence of a contract, the contract statute of limita-
    tions applie[s] to the client’s action for negligence." 
    Id.
     (citing Ole-
    yar, 225 S.E.2d at 399; VMI, 232 S.E.2d at 899-900). Therefore, as
    Lone Mountain’s negligence claim stems from its contract with
    Bowser-Morner for professional design services, the applicable period
    of limitations for the negligence claim also is five years from the date
    the design plans were accepted. See, e.g., Nelson, 
    368 S.E.2d at 248
    .
    C.
    Lone Mountain’s design-defect claims stemming from the Contract
    accrued on the date the corresponding design plans were accepted,
    April 25, 1995. Because Lone Mountain filed its complaint on May
    26, 2000, the District Court correctly concluded that its breach of con-
    tract, warranty, and negligence claims were time-barred under Virgin-
    12          LONE MOUNTAIN PROCESSING v. BOWSER-MORNER
    ia’s five-year limitations period. Accordingly, we affirm the grant of
    summary judgment to Bowser-Morner on Lone Mountain’s breach of
    contract, warranty, and negligence claims.
    V.
    The District Court also found that Lone Mountain’s contractual
    indemnification claim was time-barred under the Virginia statute of
    limitations for contract claims. Under the "Indemnity" provision of
    the Contract, Bowser-Morner agreed to "indemnify, hold harmless
    and defend [Lone Mountain] from any and all liability, claims,
    demands, suits, expenses and judgments arising out of" the Purchase
    Order or Bowser-Morner’s contractual work. (JA 162, ¶ 8). We dis-
    agree with the District Court’s conclusion that the indemnity claim
    filed by Lone Mountain under the above provision was time-barred.
    As previously noted, section 8.01-246(2) of the Virginia Code pro-
    vides a five-year statute of limitations for claims on a written contract.
    Virginia Code section 8.01-230 establishes the accrual date of actions
    for which a limitation period is prescribed. In pertinent part, section
    8.01-230 provides:
    In every action for which a limitation period is prescribed,
    the right of action shall be deemed to accrue and the pre-
    scribed limitation period shall begin to run from . . . when
    the breach of contract occurs in actions ex contractu and not
    when the resulting damage is discovered, except . . . where
    otherwise provided under . . . § 8.01-249 . . . . 
    Va. Code Ann. § 8.01-230
    .
    Thus, Virginia Code section 8.01-230 explicitly excludes claims
    under section 8.01-249 from the general statute of limitations accrual
    date for contracts.
    Under section 8.01-249(5) of the Virginia Code, a cause of action
    for "contribution or for indemnification" accrues "when the contrib-
    utee or the indemnitee has paid or discharged the obligation." Accord-
    ingly, by the plain terms of the statutory language, a claim for
    indemnification does not accrue until the indemnitee has suffered a
    LONE MOUNTAIN PROCESSING v. BOWSER-MORNER                 13
    loss. See Indus. Dev. Auth. v. Bd. of Supervisors, 
    263 Va. 349
    , 353,
    
    559 S.E.2d 621
    , 623 (2002)(citing Vaughn, Inc. v. Beck, 
    262 Va. 673
    ,
    677, 
    554 S.E.2d 88
    , 90 (2001)) ("When the language of a statute is
    clear and unambiguous, [appellate courts] are bound by the plain
    meaning of that language.").
    The rule espoused in section 8.01-249(5) reflects the view that the
    "accrual of a cause of action for indemnity . . . is better linked to a
    time at which the indemnitee is injured, not the time at which the
    original plaintiff was injured." In re Fela Asbestos Litig., 
    638 F. Supp. 107
    , 113 (W.D. Va. 1986), rev’d on other grounds sub nom., Wingo
    v. Celotex Corp., 
    834 F.2d 375
     (4th Cir. 1987); see also 41 Am Jur
    2d, Indemnity § 43 (2003)("A cause of action on a contract indemni-
    fying against loss or damage does not arise until the indemnitee has
    actually incurred loss."). This Court adopted identical reasoning in
    Walker Manufacturing Co. v. Dickerson, Inc., 
    619 F.2d 305
     (4th Cir.
    1980), when we held that a claim for indemnity based on a breach of
    implied warranty was not barred even though the direct action of the
    original plaintiff was time-barred. 
    Id. at 308-10
    ; see also Premier
    Corp. v. Economic Research Analysts, Inc., 
    578 F.2d 551
    , 553-54 (4th
    Cir. 1978). Other courts routinely apply similar reasoning regarding
    the accrual of indemnity claims. See, e.g., Burlington N. R.R. v. Hyun-
    dai Merchant Marine Co., 
    63 F.3d 1227
    , 1230 (3rd Cir. 1995) (stating
    the general rule that an indemnity claim does not accrue until the
    indemnitee suffers a loss); Central Wash. Refrigeration, Inc. v. Bar-
    bee, 
    133 Wn.2d 509
    , 517, 
    946 P.2d 760
    , 764 (1997) (stating that
    "[i]ndemnity actions are distinct, separate causes of action from the
    underlying wrong and are governed by separate statutes of limita-
    tions" and citing supporting cases from various jurisdictions in a foot-
    note).
    Faced with the patent impact of the controlling statutory language
    regarding the accrual of indemnification claims and the fact that dam-
    age resulting from the design plan first occurred after the impound-
    ment failure in June of 1996, Bowser-Morner contends that Lone
    Mountain suffered a "loss" triggering an indemnity claim simply by
    incurring the initial contractual expense of paying for the design plan
    in 1995. Bowser-Morner’s reasoning, however, flies in the face of tra-
    ditional notions of indemnity reimbursement and loss. Both this Court
    and the Supreme Court of Virginia have characterized indemnity as
    14          LONE MOUNTAIN PROCESSING v. BOWSER-MORNER
    a promise to reimburse for a loss sustained. See Uptagrafft v. United
    States, 
    315 F.2d 200
    , 203 (4th Cir.), cert. denied, 
    375 U.S. 818
     (1963)
    (stating that indemnity is a right "generally based upon contract,"
    which "means compensation for loss already sustained"); First Vir-
    ginia Bank-Colonial v. Baker, 
    225 Va. 72
    , 77, 
    301 S.E.2d 8
    , 11
    (1983) (stating that "a contract of indemnity is a bilateral agreement
    between an indemnitor and an indemnitee in which the indemnitor
    promises to reimburse his indemnitee for loss suffered or to save him
    harmless from liability"). Logically, the act of originally paying to
    obtain an underlying contractual service does not constitute a loss
    arising out of the contractual work performed for which an indem-
    nitee can be reimbursed. Indeed, under Bowser-Morner’s reasoning,
    Lone Mountain would have been entitled to a full refund of the con-
    tractual costs as an indemnitee even if it did not suffer any harm or
    loss from Bowser-Morner’s contractual performance. Quite simply,
    such a theory is untenable.
    Plainly, therefore, Lone Mountain did not suffer damages sufficient
    to trigger the provisions of Virginia Code section 8.01-249(5) prior
    to the impoundment failure in June of 1996. At that time, Lone Moun-
    tain suffered a loss "arising out of" Bowser-Morner’s design work
    performed under the Contract. Thus, at the time of the impoundment
    failures, Lone Mountain suffered a loss as a contractual indemnitee,
    thereby commencing the five-year statute of limitations period for
    contract claims. Accordingly, by filing a contractual indemnification
    claim in its amended complaint on October 24, 2000, Lone Mountain
    brought its action within five years of any indemnitee loss and, there-
    fore, its indemnification claim was timely.
    VI.
    For the reasons set forth above, we affirm the District Court’s deci-
    sion that Lone Mountain’s breach of contract, warranty and negli-
    gence claims were time-barred under Virginia’s five-year statute of
    limitations, but reverse the District Court’s determination that Lone
    Mountain’s contractual indemnification claim was time-barred.
    Accordingly, we remand the contractual indemnification claim to the
    District Court to permit said claim to proceed on the merits.
    AFFIRMED IN PART, REVERSED
    IN PART, AND REMANDED
    LONE MOUNTAIN PROCESSING v. BOWSER-MORNER                15
    TRAXLER, Circuit Judge, concurring and dissenting:
    I concur in the majority’s determination that Lone Mountain’s
    indemnification claim accrued no earlier than June 1996 and that its
    indemnification claim, therefore, is not barred by the applicable stat-
    ute of limitations. I also believe, however, that Lone Mountain’s
    breach of contract and professional negligence claims were timely
    filed. Accordingly, I respectfully dissent from the majority’s affir-
    mance of the dismissal of those claims.
    As to the breach of contract claim, the majority concludes Lone
    Mountain accepted and approved the plans for the coal slurry
    impoundment in April 1995 when it made the final payment to
    Bowser-Morner and that, under Virginia law, all of Lone Mountain’s
    design-defect claims accrued at that time. I agree that a design-defect
    claim accrues under Virginia law when the plans are approved. See
    Comptroller ex rel. Virginia Military Inst. v. King, 
    232 S.E.2d 895
    ,
    900 (Va. 1977) ("We cannot escape the conclusion that V.M.I. has
    alleged a cause of action for improper design which accrued when the
    plans were finally approved." (emphasis added)); see also Nelson v.
    Commonwealth, 
    368 S.E.2d 239
    , 247 (Va. 1988). In this case, how-
    ever, I do not believe that approval occurred upon payment by Lone
    Mountain.
    The contract between Lone Mountain and Bowser-Morner condi-
    tions Lone Mountain’s obligation to pay upon its "approval and
    acceptance of the work." J.A. 171. If this were the only relevant con-
    tractual provision, then I might agree that, under VMI and Nelson,
    Lone Mountain’s design claims accrued upon payment. The payment
    clause, however, must be considered along with the clauses defining
    Bowser-Morner’s obligations under the contract. See, e.g., Berry v.
    Klinger, 
    300 S.E.2d 792
    , 796 (Va. 1983) ("The court must give effect
    to all of the language of a contract if its parts can be read together
    without conflict. Where possible, meaning must be given to every
    clause. The contract must be read as a single document. Its meaning
    is to be gathered from all its associated parts assembled as the unitary
    expression of the agreement of the parties."). Bowser-Morner was
    obligated under the contract to design the slurry impoundment "in
    accordance with all MSHA requirements and memoranda as well as
    with the Commonwealth of Virginia criteria," J.A. 161 (emphasis
    16          LONE MOUNTAIN PROCESSING v. BOWSER-MORNER
    added), and to answer questions that arose during the federal and state
    permitting processes. Thus, the contract required Bowser-Morner to
    do more than simply deliver plans that satisfied Lone Mountain’s par-
    ticular business needs—the plans also had to comply with significant
    state and federal regulatory requirements.
    In my view, the presence of these complex regulatory permitting
    schemes and Bowser-Morner’s contractual obligation to deliver plans
    that conformed with all regulatory requirements distinguishes this
    case from King and Nelson. In King and Nelson, the defendant’s con-
    tractual obligation was to deliver plans that suited the client’s particu-
    lar business needs, and the client was fully capable of determining the
    suitability of the plans. Thus, the client’s approval of the plans signi-
    fied that the contractual obligation to provide plans had been fulfilled.
    In this case, however, while Lone Mountain was capable of reviewing
    the plans to determine whether they satisfied its specific business
    needs, it did not have the expertise to know whether Bowser-
    Morner’s plans complied with the complex regulatory requirements.
    That determination could be made only upon approval of the plans by
    the appropriate state and federal agencies. Thus, while Lone Moun-
    tain’s payment may have indicated that the plans met its specific busi-
    ness needs, the payment and approval by Lone Mountain cannot be
    viewed as an indication that the plans conformed with state regula-
    tions, as required by the contract.
    Accordingly, I would hold that Lone Mountain’s design-defect
    claims did not accrue until November 17, 1995, when the plans were
    approved by Virginia’s Division of Mined Land Reclamation and
    Bowser-Morner’s final obligation under the contract was fulfilled.*
    Lone Mountain’s complaint, filed in May 2000, was thus timely under
    the applicable five-year statute of limitations. From this conclusion it
    follows that Lone Mountain’s professional negligence claims were
    also timely filed. See, e.g., Oleyar v. Kerr, 
    225 S.E.2d 398
    , 400 (Va.
    1976) (explaining that a professional malpractice claim, "while
    sounding in tort, is an action for breach of contract and thus governed
    *This analysis makes it unnecessary for me to consider the signifi-
    cance of the actions with regard to the impoundment that Bowser-Morner
    took after the April 1995 payment or whether Lone Mountain’s claim
    could be considered timely under the "continuing services" doctrine.
    LONE MOUNTAIN PROCESSING v. BOWSER-MORNER                 17
    by the statute of limitations applicable to contracts"). I therefore dis-
    sent from the conclusion that Lone Mountain’s breach of contract and
    professional negligence claims were not timely filed.
    

Document Info

Docket Number: 02-2392

Citation Numbers: 94 F. App'x 149

Judges: Bennett, Niemeyer, Richard, Traxler

Filed Date: 4/8/2004

Precedential Status: Non-Precedential

Modified Date: 8/6/2023

Authorities (20)

Burlington Northern Railroad Company v. Hyundai Merchant ... , 63 F.3d 1227 ( 1995 )

Premier Corporation v. Economic Research Analysts, Inc. , 578 F.2d 551 ( 1978 )

Vaughn, Inc. v. Beck , 262 Va. 673 ( 2001 )

Klaxon Co. v. Stentor Electric Manufacturing Co. , 61 S. Ct. 1020 ( 1941 )

Perini Corporation v. Perini Construction, Inc. , 915 F.2d 121 ( 1990 )

Matsushita Electric Industrial Co., Ltd. v. Zenith Radio ... , 106 S. Ct. 1348 ( 1986 )

Nelson v. Com. , 235 Va. 228 ( 1988 )

Virginia Military Institute v. King , 217 Va. 751 ( 1977 )

Farley v. Goode , 219 Va. 969 ( 1979 )

Richmond Redevelopment & Housing Authority v. Laburnum ... , 195 Va. 827 ( 1954 )

Oleyar v. Kerr, Trustee , 217 Va. 88 ( 1976 )

First Virginia Bank-Colonial v. Baker , 225 Va. 72 ( 1983 )

Suffolk City School Board v. Conrad Bros. , 255 Va. 171 ( 1998 )

Hooper v. Musolino , 234 Va. 558 ( 1988 )

Central Wash. Refrigeration v. Barbee , 946 P.2d 760 ( 1997 )

Boone v. C. Arthur Weaver Co., Inc. , 235 Va. 157 ( 1988 )

McCormick v. Romans , 214 Va. 144 ( 1973 )

Federal Reserve Bank of Richmond v. Wright , 392 F. Supp. 1126 ( 1975 )

In Re Fela Asbestos Litigation , 638 F. Supp. 107 ( 1986 )

McCloskey & Company, Inc. v. Wright , 363 F. Supp. 223 ( 1973 )

View All Authorities »