Bi-Tech North Inc v. Lockheed Martin Corp ( 2005 )


Menu:
  •                                                Filed:   April 12, 2005
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 04-1391
    (CA-01-254-AW)
    BI-TECH NORTH, INCORPORATED, a New Hampshire
    Corporation,
    Plaintiff - Appellant,
    and
    WILLIAM SHERLOCK; BI-TECH, INCORPORATED, a
    New Jersey Corporation,
    Plaintiffs,
    versus
    LOCKHEED MARTIN    CORPORATION,  a     Maryland
    Corporation   acting   through  its     Sanders
    Business Unit,
    Defendant - Appellee.
    O R D E R
    The court amends its opinion filed March 10, 2005, as follows:
    On the cover sheet, section 8, line 5 -- the names of Juanita
    A. Crowley, Paul R. Q. Wolfson, Edward N. Siskel, WILMER, CUTLER,
    PICKERING, HALE AND DORR, L.L.P., Washington, D.C., are added as
    counsel for Appellee.
    For the Court - By Direction
    /s/ Patricia S. Connor
    Clerk
    UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 04-1391
    BI-TECH NORTH, INCORPORATED, a New Hampshire
    Corporation,
    Plaintiff - Appellant,
    and
    WILLIAM SHERLOCK; BI-TECH, INCORPORATED, a
    New Jersey Corporation,
    Plaintiffs,
    versus
    LOCKHEED   MARTIN  CORPORATION,  a     Maryland
    Corporation   acting   through  its     Sanders
    Business Unit,
    Defendant - Appellee.
    Appeal from the United States District Court for the District of
    Maryland, at Greenbelt. Alexander Williams, Jr., District Judge.
    (CA-01-254-AW)
    Argued:   November 30, 2004                 Decided:   March 10, 2005
    Before WIDENER, MICHAEL, and MOTZ, Circuit Judges.
    Affirmed by unpublished per curiam opinion.
    ARGUED: Peter David Goldberger, Ardmore, Pennsylvania, for
    Appellant. Francis Joseph Gorman, GORMAN & WILLIAMS, Baltimore,
    Maryland, for Appellee.     ON BRIEF: Neil E. Jokelson, David
    Jokelson, Derek Jokelson, NEIL E. JOKELSON & ASSOCIATES,
    Philadelphia, Pennsylvania, for Appellant.  Juanita A. Crowley,
    Paul R. Q. Wolfson, Edward N. Siskel, WILMER, CUTLER, PICKERING,
    HALE AND DORR, L.L.P., Washington, D.C. for Appellee.
    Unpublished opinions are not binding precedent in this circuit.
    See Local Rule 36(c).
    2
    PER CURIAM
    In this diversity contract and tort action, we affirm the
    district court’s grant of summary judgment to Lockheed Martin Corp.
    and denial of partial summary judgment to Bi-Tech North, Inc.
    (“BTN”).
    I.
    In March 1998, William Sherlock, the principal in Bi-Tech,
    Inc. (“BTI”), a machine shop, began negotiations with a unit of
    Lockheed      to   buy   from    Lockheed       the   Manchester    Machine   Center
    (“MMC”).
    In late December 1999 and early January 2000, the parties
    executed documents that provided, inter alia, that BTN, a New
    Hampshire corporation created for the purpose of the purchase,
    would buy MMC from Lockheed for $500,000--a $100,000 down payment,
    with    the    remaining        $400,000    to    be    paid   in   equal     monthly
    installments for one year, pursuant to the terms of a promissory
    note (the “Note”).         BTN would pay $310,000 to lease the building
    housing MMC for one year, with options to renew at a lower rate or
    to purchase for $2.1 million.                    BTN would continue to employ
    designated MMC employees at (at least) the same pay and with (at
    least) the same benefits.            Also, Lockheed would have a priority
    security interest in the assets transferred to BTN, which BTN could
    not further encumber; and BTI would guarantee BTN’s payment of the
    3
    Note and performance of all obligations under the agreement. While
    the agreement became effective December 23, 1999, the deal was not
    to close until January 3, 2000.
    A few provisions of the agreement are important here:
    1.   Article IX lists “Conditions to Closing.”                     Section 9.03(a)
    conditions    Lockheed’s          obligations      on     BTI’s   and     BTN’s
    performance      of    its     obligations   under      the    agreement    and
    conditioned      Lockheed’s        performance       on    the    truth     and
    correctness (in all material respects) of BTI’s and BTN’s
    representations and warranties contained in the transaction
    documents.        Section        9.03(c)(iii)      conditions      Lockheed’s
    obligations on BTN having provided to Lockheed “reasonable
    assurances”      that    BTN    had   in   place   “sufficient      financial
    resources to satisfy the Promissory Note and to satisfy and
    perform    its        other    obligations      under      the    Transaction
    Documents.”
    2.   Article IV lists the “Representations and Warranties” of BTN
    and BTI.     Section 4.01(e) represents and warrants that each
    was “capable of performing, in all material respects, each
    agreement, covenant and obligation required by the Transaction
    Documents” and that at the time of the transactions, BTN would
    have “the resources and assets necessary and sufficient to
    conduct the [business of MMC] and to perform its obligations
    and Contracts that constitute Transferred Assets.”                      Section
    4
    4.01(h) represents and warrants that BTN had “available to it
    cash, marketable securities or other investments, or presently
    available sources of credit, to enable it to consummate the
    Contemplated Transactions and to pay the Purchase Price.”
    3.   Article XI governs termination.      Section 11.01(b) controls
    termination if the deal has not closed by January 15, 2000,
    and allows immediate termination by either Lockheed or BTN at
    any time prior to closing.         The sole exception to this
    prerogative is if the closing is not consummated by January 15
    because of the terminating party’s breach of any of the
    representations or warranties or its failure to perform the
    covenants    or   agreements   contained   in   the   Transaction
    Documents.    Section 11.01(d) is an alternative termination
    provision, not dependent on the failure of the deal to close
    by January 15.    It allows termination because of a breach of
    any representation, warranty, covenant, or agreement under the
    Transaction Documents, if the effect of the breach “would
    cause the closing conditions of the terminating party not to
    be capable of being satisfied,” and if the breach is not cured
    by the breaching party within 15 days of receiving written
    notice of the breach from the terminating party.
    The parties agree that Maryland law governs the contract.
    BTN began to install new phones and signs at MMC, obtained
    insurance coverage, and secured signed acceptances of employment
    5
    from the designated MMC employees.        Sherlock also contacted Joseph
    Franchetti about a possible loan of $200,000 or more for working
    capital.    The terms of the proposed loan were, however, onerous:
    the interest rate on the loan would be 20%; Franchetti would be
    entitled to 10% of net profit after taxes and would become a board
    member with a monthly retainer.
    The Lockheed/BTN deal did not close on January 3, 2000, and on
    January 5, Lockheed’s in-house counsel sent a handwritten note to
    Sherlock    listing   open   action   items,    including    “evidence   of
    financial    capability.”     On   January     7,   2000,   BTN’s   attorney
    forwarded to Lockheed’s outside counsel materials addressing some
    of the open action items.     Included was a letter from GE Capital to
    Sherlock stating that it was “in the process of completing [the]
    review of [Sherlock’s] request for a $750,000 working capital
    line.”     GE Capital asked for a copy of the executed purchase
    agreement, and “[v]erification from Lockheed management as to the
    invoicing and payment terms.”         It further proposed a January 10
    meeting.    The meeting did not occur.
    On January 12, Sherlock’s consultant calculated that BTN would
    require $218,000 in working capital to operate MMC for the first
    month.     At a meeting with Sherlock on January 12, Lockheed said
    that a $600,000 letter of credit would satisfy BTN’s obligations
    under § 9.03(c)(iii) of the contract.        Sherlock indicated that he
    would look into the issue and intended to talk to his attorney
    6
    about whether he needed to post additional funds.
    By January 14, Sherlock had tendered $50,000 of the $100,000
    down payment.        On January 14, Lockheed sent Sherlock a letter
    informing     him    that,   pursuant     to    the   terms    of   the   agreement,
    Lockheed would exercise its termination rights unless Sherlock had
    provided, by January 15, the remaining $50,000 of the down payment
    and “written evidence that [BTN] has access to a minimum of
    $600,000” via a signed letter of credit.                      Sherlock’s attorney
    replied     that    the   requirement     of    proof   of    access    to   $600,000
    “appears to be a breach of the transaction agreements,” but that
    Sherlock was ready, willing, and able to forward by wire transfer
    the remaining balance of the downpayment.               On January 15, Sherlock
    wrote to Lockheed offering to contact banks to get financing and
    offering as collateral his vacation home, which he valued at $1.6
    million.1      Lockheed      terminated       the   agreement    by    letter   dated
    January 18, 2000.
    Lockheed later sold MMC to another purchaser, PGM. BTN points
    to evidence of phone calls between Lockheed and PGM during early
    January 2000 as suggesting that Lockheed was negotiating a deal
    with PGM before the termination of the BTN deal.
    1
    Sherlock’s actual equity in the house appears to have been
    significantly less than that.    In his April 2000 Petition for
    Bankruptcy, Sherlock valued the property at $900,000, and noted a
    $750,000 mortgage on the property.
    7
    II.
    In January 2001, BTN, BTI, and Sherlock filed suit against
    Lockheed in the United States District Court for the District of
    Maryland, asserting breach of contract and various tort claims.
    Lockheed filed counterclaims against BTN, BTI, and Sherlock.                  In
    May 2001, Sherlock filed a Suggestion of Bankruptcy, and, in August
    2001, the district court ordered the case to go forward except as
    to the counterclaim against Sherlock.2
    By February 2004, BTN’s remaining claims against Lockheed were
    for     breach      of   contract,    detrimental    reliance,      breach    of
    confidential duty, fraud, conspiracy to defraud, and tortious
    interference with prospective business relations.             On February 25,
    2004, the district court granted Lockheed’s motion for summary
    judgment on these claims, and denied BTN’s motion for partial
    summary judgment on its breach of contract claim.                In an order
    dated May 5, 2004, the district court dismissed with prejudice
    Sherlock’s and BTI’s claims against Lockheed; dismissed without
    prejudice     Lockheed’s     counterclaims    against   BTI   and    Sherlock;
    designated the February 25, 2004 Order as the final judgment as to
    BTN’s     claims;    and   stayed    Lockheed’s   counterclaim   against     BTN
    pending BTN’s appeal to this court.           Only BTN appeals; it appeals
    the grant of summary judgment on the breach of contract and tort
    2
    Sherlock’s Petition for Bankruptcy in the District of New
    Jersey has since been voluntarily dismissed.
    8
    claims, and the denial of its own motion for partial summary
    judgment on its breach of contract claim.            BTN does not appeal the
    grant     of    summary    judgment   on     the   quasi-contract   claim    of
    detrimental reliance.
    III.
    We review the district court’s grant of summary judgment de
    novo, viewing the facts in the light most favorable to the non-
    moving party.        Blaustein & Reich v. Buckles, 
    365 F.3d 281
    , 286 (4th
    Cir. 2004).
    A.
    As the district court correctly noted, Maryland law holds that
    no duty arises under a contract if a condition precedent is
    unfulfilled.         See Laurel Race Course, Inc. v. Regal Constr. Co.,
    
    333 A.2d 319
    , 327 (Md. 1975).          Thus, if BTN did not satisfy the
    conditions precedent of §§ 9.03(a) and 9.03(c)(iii), and its
    nonperformance is not excused, it cannot recover for breach of
    contract, and the district court properly granted summary judgment
    to Lockheed.      See     Hubler Rentals, Inc. v. Roadway Express, Inc.,
    
    637 F.2d 257
    , 260-61 (4th Cir. 1981).
    (1)
    The record reveals that BTI and BTN did not satisfy § 9.03(a)
    or § 9.03(c)(iii).
    As    to    §    9.03(a),   contrary     to   the   representations    and
    9
    warranties    in §§ 4.01(e) & (h), neither BTN nor BTI had sufficient
    resources and assets at the time of the transactions to conduct
    MMC’s business or to consummate the contemplated transactions.
    Indeed, BTN had no assets at all when the Transaction Agreement
    became effective on December 23, 1999, and would not have had any
    until the transfer of MMC’s assets to BTN’s control, which was
    supposed to occur on January 6, 2000.               Moreover, there was an
    outstanding judgment of foreclosure of more than $1 million against
    BTI, and BTI’s bank account had a negative balance.
    Nor did BTN or BTI satisfy § 9.03(c)(iii).               That section of
    the contract requires BTN to provide Lockheed with “reasonable
    assurances” that BTN had sufficient financial resources available
    to satisfy the Note and perform its obligations under the contract.
    BTN argues that there are material factual issues as to whether it
    satisfied    this    condition   precedent,      because   (1)   the   Security
    Agreement     in    and   of   itself    could   constitute      the   required
    “reasonable assurances;” or (2) “Sherlock was prepared to complete
    the down payment, . . . BTN had already taken major steps toward
    assuming the business, . . . Lockheed had discussed the short-term
    working capital needs of BTN with Franchetti, who was willing to
    meet them . . . , and . . . the MMC deal was otherwise self-
    financing.”
    But it is a fundamental principle of contract law that a
    contract should be construed so that each provision has meaning,
    10
    and no provision is mere surplusage.           See, e.g., JMP Assocs. v. St.
    Paul Fire & Marine Ins. Co., 
    693 A.2d 832
    , 834-35 (Md. 1997).                   If
    we should construe the Security Agreement (or any other obligation
    in the Transaction Documents) to have satisfied the “reasonable
    assurances” requirement, then that would render § 9.03(c)(iii)
    superfluous. Section 9.03(c)(iii) requires “reasonable assurances”
    in addition to the other requirements of the contract.
    Moreover, BTN’s signage and potential contracts did not assure
    “sufficient      financial    resources”      to   meet    BTN’s   obligations,
    especially in the short-term.          Similarly, the understanding that
    the deal would become self-financing did not assure that BTN had
    the working capital to run the shop for the first month or two.
    And   Sherlock     never   offered    the    potential     Franchetti   loan    to
    Lockheed as a “reasonable assurance.”              Thus, these factors could
    not constitute “reasonable assurances.”
    The only counterproposal that Sherlock made to Lockheed’s
    request for a $600,000 letter of credit was to offer his vacation
    home as collateral.        According to Sherlock’s bankruptcy petition,
    this house was worth $900,000 and was encumbered by a $750,000
    mortgage.   Even if the bare offer of this house as collateral could
    be    considered    an   assurance,    the    value   of   that    property    was
    significantly less than the $218,000 that Sherlock’s own consultant
    stated would be needed to run the shop for the first month.               Thus,
    it could not have been a “reasonable assurance” that BTN had
    11
    sufficient resources to satisfy the $400,000 Note and the other
    obligations under the agreement.
    Because BTI and BTN did not satisfy the conditions precedent
    of §§ 9.03(a) and § 9.03(c)(iii), Lockheed did not have a duty to
    perform under the contract.
    (2)
    Alternatively,     BTN     argues     that   Lockheed   repudiated   the
    contract in its January 14, 2000 letter, thus excusing BTI’s and
    BTN’s failure to fulfill the conditions precedent, and consequently
    allowing   BTN   to   recover   for   Lockheed’s     asserted   anticipatory
    breach.3   The January 14 letter stated that “per terms of [the]
    agreement,” if, by close of business January 15, 2000, Sherlock did
    not tender the remainder of the down payment and submit “written
    evidence that [BTN] has access to a minimum of $600,000 via a
    3
    BTN also argues that Lockheed fraudulently concealed material
    information and did not negotiate in good faith, because, inter
    alia, Lockheed was allegedly simultaneously negotiating with PGM.
    BTN asserts that this excused it from performing the conditions
    precedent. However, there is no authority for BTN’s suggestion
    that there is a generalized fraud exception to the rule that the
    failure of a party to perform conditions precedent excuses the
    other party from its performance under the contract. Of course, if
    a party’s fraud or bad faith causes the other party to be unable to
    perform a condition of the contract, then the nonperformance of the
    condition is excused. See Williston on Contracts § 39.10 (4th ed.)
    (“Although it is not necessary that there be a specific malevolent
    intent, the weight of authority holds that in order for prevention
    to constitute an excuse for nonperformance of a condition or a
    promise, the preventing party must have deliberately taken steps to
    impede performance or have arbitrarily impaired the other party's
    ability to perform.”). However, BTN fails to show that Lockheed’s
    alleged fraud or bad faith caused BTN’s failure to provide
    reasonable assurances as required under § 9.03(c)(iii).
    12
    signed Letter of Credit” from a bank, Lockheed would “have no
    alternative but to terminate the deal.”
    “Ordinarily, in order to constitute anticipatory repudiation,
    there must be a definite, specific, positive, and unconditional
    repudiation of the contract by one of the parties to the contract.”
    C.W. Blomquist & Co. v. Capital Area Realty Investors Corp., 
    311 A.2d 787
    , 791 (Md. 1973).               A party repudiates a contract if it
    demands   performance    to    which       it    is    not   entitled,      and   states
    unequivocally    that   it    will       not    perform      unless   the    demand   is
    satisfied.     WBZE, Inc. v. Arab Network of America, 
    220 B.R. 568
    ,
    572 (D. Md. 1998) (citing Corbin on Contracts § 973 at 910 (1951)).
    Section    11.01(b)      of    the        contract      entitled    Lockheed     to
    “reasonable     assurances”        by    January       15,    2000;     without     such
    assurances     either   party       could       unilaterally      and       immediately
    terminate.     Lockheed’s request that BTN establish a $600,000 line
    of credit did not amount to a repudiation of the contract if that
    request plausibly constituted a request for “reasonable assurances”
    under the contract.     See LAK, Inc. v. Deer Creek Enters., 
    976 F.2d 328
    , 332-34 (7th Cir. 1992) (holding that, in determining whether
    there was an anticipatory breach, the court must look to the
    provision of the contract under which the dispute arises and
    determine whether the allegedly breaching party was “offering to
    perform   in   accordance     with       its     own    interpretation”        of   that
    provision and if “that interpretation was plausible”).
    13
    In this case, Lockheed’s determination that a $600,000 line of
    credit would satisfy § 9.03(c)(iii) was neither implausible, nor
    even unreasonable.      The contract required “reasonable assurances”
    that    BTN   could   pay   the    $400,000   Note    and    satisfy    the    other
    obligations of the contract, which included the running of the
    machine shop.      As explained above, the Security Agreement, which
    secured the Note, could not in itself satisfy the “reasonable
    assurances” requirement.          Lockheed requested a line of credit that
    equaled the amount of the Note, plus $200,000, an approximation of
    the amount necessary to run the shop for one month--and it is
    undisputed that it would be at least one month before the shop
    could realize a profit.           Moreover, as evidence of ability to meet
    BTN’s    financial    obligations,      Sherlock     had    proffered   a     letter
    indicating that he had requested a $750,000 line of credit from GE
    Capital.      Thus, Sherlock himself seems to have contemplated that a
    line of credit for $150,000 more than Lockheed eventually demanded
    might be necessary to provide “reasonable assurances.”
    Finally, Lockheed can only have repudiated the contract if BTN
    was ready and willing to provide “reasonable assurances” by the
    January 15 deadline.        See Wischhusen v. Am. Med. Spirits Co., 
    163 A.2d 685
    , 687 (Md. 1933).           To provide these assurances, Sherlock
    would, at least, have had to accept Franchetti’s loan.                   However,
    not only was Sherlock unwilling to accept the loan, but also both
    he and his attorney repeatedly expressed a belief that Sherlock was
    14
    obligated to do no more under the contract than tender the down
    payment.     BTN’s contention that Sherlock would ultimately have
    accepted the Franchetti loan is belied by the fact that he did not
    do so before the close of business on January 15, 2000, although
    Lockheed    had    informed   him   that    it   would   likely   exercise   its
    termination rights if the deal had not closed by that deadline.
    Because Lockheed did not repudiate the contract, repudiation
    does not excuse BTN’s failure to satisfy the conditions precedent,
    and BTN cannot maintain a suit for breach of contract.4
    B.
    BTN    also    appeals   the   district     court’s   grant   of   summary
    judgment to Lockheed on BTN’s tort claims.               We have reviewed the
    record, briefs, and applicable case law, and we have heard oral
    argument.     We are convinced that the district court properly
    resolved these claims.         See Sherlock v. Lockheed Martin Corp.,
    Civil Action No. AW-01-254 (D. Md. Feb. 25, 2004).
    IV.
    For these reasons, the judgment of the district court is
    AFFIRMED.
    4
    Our resolution of this issue also disposes of BTN’s appeal of
    the district court’s denial of its motion for partial summary
    judgment on the breach of contract claim.
    15