Service Pump & Supply v. Sun Industries, LLC ( 2020 )


Menu:
  •                                      UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 19-1891
    SERVICE PUMP & SUPPLY CO., INC.,
    Plaintiff - Appellee,
    v.
    SUN INDUSTRIES, LLC; TOBY BERTHELOT,
    Defendants - Appellants.
    Appeal from the United States District Court for the Southern District of West Virginia, at
    Huntington. Robert C. Chambers, District Judge. (3:18-cv-00976)
    Submitted: March 24, 2020                                         Decided: April 16, 2020
    Before GREGORY, Chief Judge, and KEENAN and WYNN, Circuit Judges.
    Affirmed by unpublished per curiam opinion.
    Gerald M. Titus, III, James E. Simon, SPILMAN, THOMAS & BATTLE, PLLC,
    Charleston, West Virginia, for Appellants. Clayton James Maddox, GREENE,
    KETCHUM, FARRELL, BAILEY & TWEEL, LLP, Huntington, West Virginia, for
    Appellee.
    Unpublished opinions are not binding precedent in this circuit.
    PER CURIAM:
    After being retained to aid disaster relief efforts in the aftermath of Hurricane Irma,
    Sun Industries, LLC (“Sun”), leased two dozen generators from Service Pump & Supply
    (“Service Pump”). Critically, the lease agreement—memorialized only in email exchanges
    between the parties’ representatives—neglected to establish the duration of the lease,
    though it did make reference to a monthly rental rate of approximately $139,000. 1 When
    Sun returned the generators roughly two weeks later, Service Pump advised Sun that the
    contract required, at minimum, payment of a one-month rental fee. Sun disagreed, insisting
    that it owed only for the time it possessed the generators. As a result, Service Pump filed
    the instant breach of contract suit.
    In cross motions for summary judgment, the parties disputed whether the agreement
    contained a one-month minimum lease term. The district court, however, found this issue
    irrelevant because, in the court’s view, the parties had clearly agreed to a total lease price,
    regardless of the length of the lease. Thus, the court determined that, under the terms of
    the agreement, Sun owed Service Pump $139,104. The court further determined that Sun’s
    president, Toby Berthelot, was personally liable for this debt based on a credit application
    he signed on behalf of Sun. Sun and Berthelot (collectively, “Defendants”) timely
    appealed, and for the reasons that follow, we affirm.
    1
    Initially, Service Pump asked for a $10,000, deposit, plus an additional $129,000,
    by the end of the week. In response, Sun agreed to the deposit amount but asked for 30
    days from receipt of the generators to satisfy the remaining balance. Thereafter, Service
    Pump proposed, and Sun accepted, a payment schedule of “$35,000 (25%)” upfront, to be
    followed by weekly invoices.
    2
    “We review de novo a district court’s grant or denial of a motion for summary
    judgment, construing all facts and reasonable inferences therefrom in favor of the
    nonmoving party.” Gen. Ins. Co. of Am. v. U.S. Fire Ins. Co., 
    886 F.3d 346
    , 353 (4th Cir.
    2018). Summary judgment is appropriate “if the movant shows that there is no genuine
    dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
    Fed. R. Civ. P. 56(a).
    Defendants contend that, because the lease term was not included in the agreement,
    the district court should have applied the statute of frauds’ gap-filling provisions, which
    would have led the court to determine both the correct lease term and the related amount
    due. In other words, Defendants seek to marry the lease price to the lease term, suggesting
    that the cost of the lease necessarily depended on its duration. However, we discern
    nothing in the pertinent statute of frauds, W. Va. Code Ann. § 46-2A-201 (LexisNexis
    2007), that supports this argument. 2 Although Defendants understandably seize on the
    agreement’s omission of the lease term, they cannot use this oversight to disturb a separate,
    unambiguous part of the contract. Thus, we conclude that the district court properly
    granted summary judgment to Service Pump on its breach of contract claim.
    Next, Berthelot challenges the district court’s determination that the credit
    application made him personally liable for the balance owed on the lease agreement.
    However, the clear language of the application provided that Berthelot was signing both as
    2
    Indeed, § 46-2A-201 merely describes how to supply a missing lease term; it does
    not indicate that the absence of a lease term necessarily affects the price of the lease.
    3
    an authorized officer of the applicant, Sun, and as a personal guarantor of Sun’s
    indebtedness to Service Pump. Like the district court, we are unpersuaded by Berthelot’s
    attempts to complicate this straightforward provision.
    Accordingly, we affirm the judgment of the district court. We dispense with oral
    argument because the facts and legal contentions are adequately presented in the materials
    before this court and argument would not aid the decisional process.
    AFFIRMED
    4
    

Document Info

Docket Number: 19-1891

Filed Date: 4/16/2020

Precedential Status: Non-Precedential

Modified Date: 4/16/2020