Parkway 1046, LLC v. U. S. Home Corporation ( 2020 )


Menu:
  •                                      PUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 18-1556
    PARKWAY 1046, LLC,
    Plaintiff - Appellee,
    v.
    U. S. HOME CORPORATION,
    Defendant - Appellant.
    Appeal from the United States District Court for the Eastern District of Virginia, at
    Norfolk. Henry Coke Morgan, Jr., Senior District Judge. (2:17-cv-00292-HCM-LRL)
    Submitted: June 1, 2020                                            Decided: June 3, 2020
    Before GREGORY, Chief Judge, and WYNN and HARRIS, Circuit Judges.
    Affirmed in part, reversed in part, and vacated and remanded in part by published opinion.
    Judge Wynn wrote the opinion, in which Chief Judge Gregory and Judge Harris joined.
    David Marroso, Jeffrey Gurrola, John B. Sprangers, O’MELVENY & MYERS LLP, Los
    Angeles, California; Adam M. Carroll, Carl A. Eason, WOLCOTT RIVERS GATES,
    Virginia Beach, Virginia, for Appellant. Robert W. McFarland, E. Rebecca Gantt, Norfolk,
    Virginia, Ashley P. Peterson, MCGUIREWOODS LLP, Richmond, Virginia, for Appellee.
    WYNN, Circuit Judge:
    In this appeal, Defendant U.S. Home Corporation (“U.S. Home”) challenges orders
    granting judgment, prejudgment interest, and attorneys’ fees to Plaintiff Parkway 1046,
    LLC (“Parkway”).
    Years ago, U.S. Home entered land purchase and development contracts with others
    not party to this suit. Under one contract governed by Maryland law, U.S. Home was to
    reimburse Parkway for certain expenses when the land purchase was finalized, which was
    expected to happen around 2008. But the matter became ensnared in litigation, and the
    purchase did not take place until 2017.
    Once the purchase was finalized, Parkway sought the reimbursement required by
    the contract. U.S. Home did not pay, and Parkway filed this action. U.S. Home argues that
    Parkway’s lawsuit is untimely under Maryland’s three-year statute of limitations.
    The district court held that Parkway’s cause of action did not accrue until 2017, and
    thus this lawsuit—filed that same year—is timely. We agree. However, we conclude that
    the district court erred in ordering U.S. Home to pay prejudgment interest dating from May
    27, 2008 and attorneys’ fees. Under Maryland law, Parkway is entitled to prejudgment
    interest only from the date of the purchase in 2017. And under the contract, Parkway may
    not be awarded attorneys’ fees. Accordingly, we reverse the award of attorneys’ fees and
    vacate and remand with instructions to award prejudgment interest from April 21, 2017.
    I.
    In 2005, U.S. Home entered a contract to purchase 1,250 acres of land in Maryland
    (“Purchase Agreement”) from a limited liability company solely owned by two brothers
    2
    (the “Sellers”). The same day, U.S. Home also executed a contract (“Development
    Contract”) with Bevard Development Company (“Bevard Development”), which was to
    take some steps in developing the land. The Sellers were the majority owners of Bevard
    Development.
    Although not a party to either contract, Parkway—another limited liability company
    solely owned by the Sellers—classified itself as “a third-party beneficiary” of the
    Development Contract. J.A. 4. 1 Specifically, under the Development Contract, U.S. Home
    agreed to pay Parkway approximately $2.25 million “at the time of Settlement under the
    [Purchase] Agreement” as reimbursement for Parkway’s acquisition of certain nearby
    properties “for right of way purposes” (“Reimbursement”). J.A. 11, 55. The Purchase
    Agreement defined “Settlement” as “[t]he consummation of the purchase and sale” of the
    land. J.A. 279; see also J.A. 330 (same definition in an amendment to the Purchase
    Agreement). 2
    The original date of Settlement was to be in June 2006, or September 2006 at the
    latest. After an amendment in May 2007, the Settlement date was changed to December
    2007, or March 2009 at the latest.
    In April 2008, the Sellers “called for settlement to occur” the next month. U.S. Home
    Corp. v. Settlers Crossing, LLC, 
    33 F. Supp. 3d 596
    , 609 (D. Md. 2014). Instead of
    1
    Citations to “J.A. __” refer to the Joint Appendix filed by the parties in this appeal.
    2
    The definition provided by the Purchase Agreement governs. The Development Contract
    specifies that “[a]ny capitalized terms not defined herein shall have the meaning ascribed
    to them in the [Purchase] Agreement.” J.A. 14.
    3
    agreeing, U.S. Home filed a breach-of-contract lawsuit in Maryland federal court. 
    Id. at 610
    . The Sellers, their lender, and Bevard Development counterclaimed. 
    Id.
     at 611–12.
    The Maryland litigation took years to resolve, during which time the Sellers lost
    their interest in the property to their lender. 
    Id.
     at 612 & n.11. Finally, after a two-week
    bench trial in 2014, the Maryland federal district court found in favor of the Sellers’ lender.
    
    Id. at 599, 629
    . The court remarked that “[t]he evidence demonstrated that, by at least
    October 1, 2007, [U.S. Home] viewed the . . . transaction as a financial albatross and
    actively sought to relieve itself of this burden” by “retain[ing] a team of high priced lawyers
    and consultants to search for an escape clause in the Purchase Agreement.” 
    Id. at 628
    (citation and internal quotation marks omitted); see also 
    id. at 629
     (finding that U.S. Home
    had undertaken various tactics “to delay closing while it settled on a strategy to avoid its
    obligations” under the contracts—and that the maneuvers were “not made in good faith”).
    The Maryland district court concluded that U.S. Home “was required to [proceed to
    Settlement] on May 27, 2008” and that its failure to do so was “wrongful[]” within the
    meaning of a contract amendment entitling the Sellers to interest “from the Settlement Date
    [of May 27, 2008] until [U.S. Home] proceeds to Settlement” if U.S. Home “wrongfully
    fail[ed] to make Settlement hereunder for any reason.” J.A. 329, 427, 444; see J.A. 447.
    The court entered judgment in favor of the Sellers’ lender for the purchase price and
    development fee plus interest from May 27, 2008 until Settlement, which the court ordered
    to take place within 30 days.
    4
    This Court affirmed. U.S. Home Corp. v. Settlers Crossing, L.L.C., 685 F. App’x
    173, 174 (4th Cir. 2017) (per curiam). Shortly thereafter, on April 21, 2017, U.S. Home
    paid the purchase price plus interest dating back to 2008.
    With the sale at last concluded, Parkway sought the Reimbursement (which, as
    noted above, was a sum of approximately $2.25 million to be paid “at the time of Settlement
    under the [Purchase] Agreement” as compensation for Parkway’s acquisition of certain
    properties). J.A. 11. When U.S. Home did not pay, Parkway commenced this action in the
    Eastern District of Virginia, alleging breach of the Development Contract. U.S. Home
    responded that Parkway’s 2017 lawsuit was untimely because its claim accrued no later
    than 2009 and was subject to a three-year statute of limitations.
    The district court held a bench trial in April 2018. Like the Maryland district court,
    the Virginia district court found U.S. Home’s conduct throughout the parties’ dealings to
    have been inappropriate, noting its “highly inequitable” behavior and agreeing with the
    Maryland district court that U.S. Home’s failure to complete the purchase in 2008 was
    likely “simply a market decision.” J.A. 240, 242. The court reprimanded U.S. Home for its
    litigation tactics, finding many of its arguments to be “pretextual,” “bordering on
    unconscionable,” “red herring,” “immaterial,” “absurd,” or examples of “grasping at
    straws” or “swimming upstream.” J.A. 55, 57, 62, 86, 213–16, 221, 241.
    The district court concluded that Parkway’s claim did not accrue until Settlement
    occurred in April 2017, and thus the lawsuit was timely. Parkway 1046, LLC v. U.S. Home
    Corp., No. 2:17-cv-292, 
    2018 WL 1960774
    , at *5 (E.D. Va. Apr. 26, 2018). And the court
    5
    noted that even if Parkway’s claim was untimely, given U.S. Home’s behavior, the court
    “would exercise its equitable tolling power” to allow Parkway to pursue its claim. 
    Id.
    Next, the district court concluded that though the breach occurred in April 2017,
    “given the particular circumstances of this case,” the court would award prejudgment
    interest to Parkway beginning on May 27, 2008. J.A. 256. The court reasoned that, in light
    of the Maryland district court’s finding that U.S. Home should have settled with the Sellers
    on that date, Parkway also should have received payment at that time.
    Finally, the district court awarded attorneys’ fees to Parkway based on a provision
    in the Development Contract allotting attorneys’ fees to the prevailing party in “any
    litigation aris[ing] between the parties regarding th[e] Contract.” J.A. 13. Parkway and U.S.
    Home disputed whether Parkway was a “party” for purposes of that provision. The court
    concluded that, “[t]hough the language may reasonably be subject to either interpretation,”
    Parkway’s argument was more persuasive, particularly in light of “U.S. Home’s
    inequitable conduct in this matter.” J.A. 259.
    U.S. Home timely appealed.
    II.
    “Because this appeal invokes our diversity jurisdiction” to resolve a contract
    dispute, we apply state law. Universal Concrete Prods. v. Turner Constr. Co., 
    595 F.3d 527
    , 529 (4th Cir. 2010). Both agreements—the Purchase Agreement and the Development
    Contract—are, by their terms, governed by the laws of Maryland.
    “[I]n determining state law a federal court must look first and foremost to the law
    of the state’s highest court”—here, the Court of Appeals of Maryland—and, if that court
    6
    “has not directly addressed the issue, a federal court ‘must anticipate how it would rule.’”
    Stahle v. CTS Corp., 
    817 F.3d 96
    , 100 (4th Cir. 2016) (first quoting Assicurazioni Generali,
    S.p.A. v. Neil, 
    160 F.3d 997
    , 1002 (4th Cir. 1998); and then quoting Liberty Univ., Inc. v.
    Citizens Ins. Co. of Am., 
    792 F.3d 520
    , 528 (4th Cir. 2015)).
    Maryland applies “the law of objective interpretation of contracts.” Weichert Co. of
    Md. v. Faust, 
    19 A.3d 393
    , 404 (Md. 2011). This means courts “will give effect to the plain
    meaning of an unambiguous term, and will evaluate a specific provision in light of the
    language of the entire contract.” 
    Id.
     We “must first determine from the language of the
    agreement itself what a reasonable person in the position of the parties would have meant
    at the time it was effectuated.” 
    Id.
     (quoting Myers v. Kayhoe, 
    892 A.2d 520
    , 526 (Md.
    2006)). And “absent ‘fraud, duress, mistake, or some countervailing public policy, courts
    should enforce the terms of unambiguous written contracts without regard to the
    consequences of that enforcement.’” 
    Id.
     (quoting Calomiris v. Woods, 
    727 A.2d 358
    , 368
    (Md. 1999)). Put differently, “it is ‘improper for the court to rewrite the terms of a contract,
    or draw a new contract for the parties, when the terms thereof are clear and unambiguous,
    simply to avoid hardships.’” Calomiris, 727 A.2d at 368 (quoting Canaras v. Lift Truck
    Servs., Inc., 
    322 A.2d 866
    , 873 (Md. 1974)).
    The issues before us on appeal are, first, whether the statute of limitations precludes
    Parkway’s claim; and, if not, whether (and to what extent) Parkway may receive
    prejudgment interest and attorneys’ fees. We consider each question in turn.
    7
    III.
    U.S. Home’s principal argument is that Parkway’s claim accrued in 2008 or 2009,
    and therefore its lawsuit was untimely. We agree with the district court that Parkway’s
    claim accrued in 2017, rendering its suit timely.
    “We review the district court’s statute-of-limitations decision de novo.” Gen. Ins.
    Co. of Am. v. U.S. Fire Ins. Co., 
    886 F.3d 346
    , 359 (4th Cir.), as amended (Mar. 28, 2018).
    In Maryland, an action for breach of contract must “be filed within three years from the
    date it accrues.” 
    Md. Code Ann., Cts. & Jud. Proc. § 5-101
    ; see Kumar v. Dhanda, 
    43 A.3d 1029
    , 1033–34 (Md. 2012).
    Although the length of the limitations period is provided by state law, “federal law
    determines . . . when the cause of action ‘accrues.’” Thorn v. Jefferson-Pilot Life Ins. Co.,
    
    445 F.3d 311
    , 320 (4th Cir. 2006). “[A] cause of action accrues under a borrowed statute
    of limitations” when the plaintiff has actual or constructive knowledge of his or her claim.
    
    Id.
     For a “claim” to exist for purposes of accrual, “all of [the] claim’s elements [must] have
    occurred.” Mikels v. City of Durham, 
    183 F.3d 323
    , 329 n.3 (4th Cir. 1999). In a Maryland
    breach of contract case, those elements are “contractual obligation, breach, and damages.”
    Kumar v. Dhanda, 
    17 A.3d 744
    , 749 (Md. Ct. Spec. App. 2011), aff’d, 
    43 A.3d 1029
    .
    The plain language of the contract supports the district court’s finding that there was
    no breach—and thus Parkway’s claim did not accrue—until 2017. We first review the
    contractual language before turning to U.S. Home’s arguments against this straightforward
    interpretation.
    8
    A.
    The Development Contract provides that the “Reimbursement shall be paid” by U.S.
    Home to Parkway “at the time of Settlement under the [Purchase] Agreement.” J.A. 11.
    The Purchase Agreement defines “Settlement” as “[t]he consummation of the purchase and
    sale hereunder.” J.A. 279. Thus, the Development Contract required U.S. Home to pay
    Parkway the Reimbursement “at the time of” the “consummation of the purchase and sale,”
    which occurred on April 21, 2017. J.A. 11, 279. There was no contractual obligation, and
    no breach, until that time.
    Put in “legalese” terms, finalizing the sale was a condition precedent to U.S. Home’s
    obligation to pay Parkway. “A condition precedent has been defined as ‘a fact, other than
    mere lapse of time, which, unless excused, must exist or occur before a duty of immediate
    performance of a promise arises.’” Chirichella v. Erwin, 
    310 A.2d 555
    , 557 (Md. 1973)
    (quoting 17 Am. Jur. 2d Contracts § 320 (1964)). And a defendant “cannot fail to perform
    the condition precedent and [then] successfully interpose the defense of limitations because
    the Statute of Limitations would not commence to run until the condition precedent had
    been satisfied.” Garner v. Garner, 
    358 A.2d 583
    , 589 (Md. Ct. Spec. App. 1976).
    This interpretation is “what a reasonable person in the position of the parties would
    have meant at the time [the contract] was effectuated.” Weichert, 19 A.3d at 404 (quoting
    Myers, 892 A.2d at 526). When the contracts were signed, “the time of Settlement” could
    not have meant a specific calendar date, because the Purchase Agreement provided
    alternative potential dates and the Development Contract planned for the possibility that
    Settlement might “not occur.” J.A. 8. Specifically, the Development Contract contemplated
    9
    that “[i]f the [Purchase] Agreement terminates prior to Settlement . . . , then th[e]
    [Development] Contract shall also automatically terminate”—including the provision
    requiring payment of the Reimbursement to Parkway. J.A. 14. In other words, if the sale
    did not occur, the Reimbursement would not be paid; and before the Reimbursement would
    be owed, U.S. Home and the Sellers needed to proceed to Settlement.
    We are confident that Maryland courts would come to the same conclusion. In
    Prince George’s Country Club, Inc. v. Edward R. Carr, Inc., the Court of Appeals of
    Maryland held that a broker was not entitled to a commission for an unconsummated sale
    where “the broker’s right to a commission was subject to the condition precedent that the
    sale be consummated”—a fact supported, in part, by the contract’s condition that the
    “commission was to be paid ‘at the time of settlement of this contract.’” 
    202 A.2d 354
    ,
    360–61 (Md. 1964); cf. Myers, 892 A.2d at 529 (holding a real estate purchase contract
    “void for failure of a condition precedent” where a party’s obligation to finalize the
    purchase was contingent on that party “entering into a contract for the sale of their then-
    current home” by a date certain).
    The district court properly concluded that “Settlement under the [Purchase]
    Agreement occurred on April 21, 2017,” the “clear language of the Development Contract”
    required payment at the time Settlement actually occurred, and therefore Parkway’s “cause
    of action accrued on April 21, 2017.” J.A. 55, 57. 3
    3
    Because we agree with the district court’s conclusion that Parkway’s cause of action
    accrued in April 2017, we do not reach U.S. Home’s objections to the court’s alternative
    justification based on equitable tolling.
    10
    B.
    U.S. Home raises a litany of arguments to resist this conclusion, but to no avail.
    Each argument boils down to one central theme: that Parkway’s cause of action accrued
    when U.S. Home should have proceeded to Settlement, and thus Parkway’s claim is
    untimely. None of U.S. Home’s arguments account for the fatal flaw in this logic—that the
    plain language of the contract provides that there could be no breach as to Parkway until
    the “consummation of the purchase and sale,” which occurred in 2017. J.A. 279.
    In part, U.S. Home’s arguments are self-defeating. U.S. Home argues that the breach
    occurred on May 27, 2008, or no later than March 30, 2009. Yet the inability of U.S. Home
    to point to a specific date on which Parkway’s claim supposedly accrued highlights a key
    problem with its position: the contracts did not provide for a specific, unalterable date for
    Settlement (and thus for payment of the Reimbursement). Rather, the contracts had flexible
    provisions, including those contemplating a situation in which Settlement never
    occurred—in which case Reimbursement would never be owed. 4
    In U.S. Home’s view, the possible outcomes contemplated by the contracts are
    irrelevant in light of the Maryland district court’s conclusion that U.S. Home should have
    proceeded to Settlement on May 27, 2008. That is, because U.S. Home’s breach of contract
    4
    U.S. Home argues for the first time in a footnote in its Reply Brief that this renders the
    contract illusory. U.S. Home waived this argument both “by raising it for the first time in
    its reply brief,” Metro. Reg’l Info. Sys., Inc. v. Am. Home Realty Network, Inc., 
    722 F.3d 591
    , 602 n.13 (4th Cir. 2013) (citing McBurney v. Young, 
    667 F.3d 454
    , 470 (4th Cir.
    2012), aff’d, 
    569 U.S. 221
     (2013)), and by taking only a “passing shot at the issue” in a
    footnote, Grayson O Co. v. Agadir Int’l LLC, 
    856 F.3d 307
    , 316 (4th Cir. 2017) (quoting
    Brown v. Nucor Corp., 
    785 F.3d 895
    , 919 (4th Cir. 2015)). We decline to consider it.
    11
    in failing to proceed to Settlement has been reduced to a specific date, that date governs
    the Reimbursement provision as well. Thus, the thinking goes, Parkway should have sued
    back in 2008 or 2009—or counterclaimed alongside the Sellers and Bevard Development
    in the Maryland litigation (though U.S. Home has not suggested that Parkway was required
    to raise a compulsory counterclaim). See J.A. 198 (U.S. Home agreeing that Parkway did
    not “ha[ve] to make a mandatory counterclaim”). Along the same lines, U.S. Home argues
    that third-party beneficiaries must abide by the statute of limitations governing the
    principal contract, citing Jones v. Hyatt Insurance Agency, Inc., 
    741 A.2d 1099
     (Md. 1999),
    and that collateral estoppel prevents Parkway from relitigating the Settlement date here.
    These arguments fail to grapple with the fundamentally different position of
    Parkway as compared to the Sellers, Bevard Development, and third-party beneficiaries in
    the typical case. The Sellers and Bevard Development sued to enforce their rights as parties
    to the principal contracts.
    Similarly, the third-party beneficiaries in Jones were held to the limitations period
    applicable to the principal contract because they were suing to enforce that contract. Id. at
    1103. The Court of Appeals of Maryland reasoned that a third-party beneficiary does not
    have greater rights to enforce the principal contract than do the original parties, so a third-
    party beneficiary “takes subject to the same defenses against the enforcement of the
    contract, as such, as exist between the original promisor and promisee.” Id. (emphasis
    added) (quoting Shillman v. Hobstetter, 
    241 A.2d 570
    , 577 (Md. 1968)); see also, e.g.,
    Bragunier Masonry Contractors, Inc. v. Catholic Univ. of Am., 
    796 A.2d 744
    , 756, 758
    (Md. 2002) (holding that the petitioner’s rights to collect funds owed by the respondent to
    12
    the petitioner’s judgment debtor could not “exceed those of” the debtor, since the
    “[p]etitioner stood in the shoes of its debtor,” and thus the petitioner was subject to the
    same statute of limitations as the debtor would have been).
    But Parkway’s suit is not based on the principal contracts, which concerned if and
    when Settlement would occur. Parkway does not attempt to “stand in the shoes” of the
    Sellers or Bevard Development. Rather, Parkway’s claim is grounded in the limited
    language benefitting itself, under which it did not have a claim until the sale was
    “consummat[ed].” J.A. 279; see Prince George’s Country Club, 202 A.2d at 360–61.
    For the same reason, collateral estoppel is inapplicable. The issue in the Maryland
    case was whether U.S. Home wrongfully failed to proceed to Settlement with the Sellers
    in 2008. The question in the instant litigation is when the “consummation of the purchase
    and sale” took place, triggering payment of the Reimbursement to Parkway. J.A. 279. The
    issues in the two cases are not “identical,” as required to invoke collateral estoppel. Garrity
    v. Md. State Bd. of Plumbing, 
    135 A.3d 452
    , 459 (Md. 2016).
    In another maneuver to suggest that Parkway could have sued in 2008 or 2009 and
    thus that its present claim is untimely, U.S. Home invokes Maryland’s prevention
    doctrine. 5 Under that doctrine, “if one party to a contract ‘hinders, prevents or makes
    impossible performance by the other party, the latter’s failure to perform will be excused.’
    In other words, the prevention doctrine applies when one party prevents another party from
    5
    U.S. Home may have waived this argument by not raising it before the district court. See
    Pornomo v. United States, 
    814 F.3d 681
    , 686 (4th Cir. 2016). In any event, it is without
    merit.
    13
    performing under the contract.” WSC/2005 LLC v. Trio Ventures Assocs., 
    190 A.3d 255
    ,
    268 (Md. 2018) (citation omitted) (quoting 13 Richard A. Lord, Williston on Contracts §
    39:3 (4th ed. 2013)). U.S. Home’s theory appears to be that Parkway could have sued long
    ago and invoked the prevention doctrine to show that U.S. Home’s wrongful conduct was
    preventing a condition precedent (Settlement) from occurring.
    But the prevention doctrine is a mechanism to excuse the nonperformance of one
    party when the other fails to perform. Here, there is no dispute that Parkway has performed.
    U.S. Home “cannot use the prevention doctrine to justify its own breach.” Id. at 268.
    As a final variation on the same theme, U.S. Home invokes a Maryland appellate
    decision involving the formation of a partnership, Garner v. Garner—even though, as
    noted, Garner held that a defendant could not “fail to perform the condition precedent” and
    then raise a statute-of-limitations defense (which is precisely what U.S. Home seeks to do
    here). 
    358 A.2d at 589
    . Nevertheless, U.S. Home argues that Garner supports its position
    because the Garner court held that the limitations period had not commenced when “it had
    not yet become clear to [the plaintiff] that no partnership would be formed.” 
    Id.
     According
    to U.S. Home, this means that the statute of limitations starts to run once a promisee
    becomes aware that the promisor has prevented or failed to perform a condition precedent.
    We do not agree with U.S. Home’s interpretation of Garner. 6 But even if we did,
    such a holding would be inapposite. Parkway was not the promisee to U.S. Home’s
    6
    A key issue in Garner was the existence (or not) of a partnership. Garner held that a
    partnership “cannot exist against the consent and intention of the parties, and their intention
    must be gleaned from proof in the case.” 
    358 A.2d at 588
    . Where the intention of the parties
    14
    obligation to proceed to Settlement. Rather, its interest was limited to receiving the
    Reimbursement if Settlement occurred. Until the Maryland litigation resolved, it was not
    clear that U.S. Home was required to proceed to Settlement, and so until that date, Parkway
    could not have been aware that the condition precedent would not be satisfied.
    In sum, we agree with the district court’s straightforward reading of the contract
    language: Parkway was owed the Reimbursement at the time of Settlement, which occurred
    in April 2017. It filed suit two months later. Its claim was timely.
    IV.
    U.S. Home next challenges the district court’s award of prejudgment interest to
    Parkway accruing from May 27, 2008. We conclude that Maryland law requires that
    Parkway receive prejudgment interest, but only from April 21, 2017.
    We review a district court’s rulings on questions of damages, including prejudgment
    interest, for abuse of discretion. Dotson v. Pfizer, Inc., 
    558 F.3d 284
    , 299 (4th Cir. 2009).
    The court “abuses its discretion only if its conclusions are based on mistaken legal
    principles or clearly erroneous factual findings.” 
    Id.
     (quoting People for the Ethical
    Treatment of Animals v. Doughney, 
    263 F.3d 359
    , 370 (4th Cir. 2001)).
    to form a partnership was at issue—and the condition precedent was that the parties “would
    work together for a while before finalizing the partnership,” 
    id.
     at 585—it is logical that
    the plaintiff’s awareness of the defendant’s intent not to enter a partnership would be
    required before the statute of limitations would begin to run. See, e.g., MAS Assocs. v.
    Korotki, 
    214 A.3d 1076
    , 1087 (Md. 2019) (citing Garner for the proposition that the
    intention of the parties is essential to the formation of a partnership). There is nothing in
    Garner to suggest that this knowledge requirement is more broadly applicable. Nor has
    any court cited Garner for such a proposition.
    15
    State law “governs the award of prejudgment interest in a diversity case.” Hitachi
    Credit Am. Corp. v. Signet Bank, 
    166 F.3d 614
    , 633 (4th Cir. 1999). In Maryland, there are
    “three basic rules governing the allowance of pre-judgment interest.” Harford Cty. v. Saks
    Fifth Ave. Distribution Co., 
    923 A.2d 1
    , 13 (Md. 2007) (quoting Buxton v. Buxton, 
    770 A.2d 152
    , 165 (Md. 2001)). They are as follows:
    1. Prejudgment interest must be granted where “the obligation to pay and the
    amount due” were “certain, definite, and liquidated by a specific date prior
    to judgment.” Buxton, 770 A.2d at 165 (quoting First Va. Bank v. Settles,
    
    588 A.2d 803
    , 807 (Md. 1991)). Interest accrues from when “payment was
    due.” I. W. Berman Props. v. Porter Bros., 
    344 A.2d 65
    , 75–76 (Md. 1975)
    (quoting Affiliated Distillers Brands Corp. v. R. W. L. Wine & Liquor Co.,
    
    132 A.2d 582
    , 586 (Md. 1957)). 7
    2. Prejudgment interest may not be granted “in tort cases where the recovery is
    for bodily harm, emotional distress, or similar intangible elements of damage
    not easily susceptible of precise measurement.” Buxton, 770 A.2d at 165.
    3. Prejudgment interest may be granted, but is not required, in the remaining
    “broad category of contract cases.” Id. In this catchall category, which is the
    default for contract cases, Harford Cty., 923 A.2d at 13–14 (citing Ver
    Brycke v. Ver Brycke, 
    843 A.2d 758
    , 777 (Md. 2004)), whether to order
    prejudgment interest “is within the discretion of the trier of fact,” Buxton,
    770 A.2d at 165.
    Courts must determine whether a contract case falls under the first or third category
    based on their level of certainty as to the existence, amount, and due date of an obligation
    to pay. 8 The rationale is that, where such certainty exists, “the effect of the debtor’s
    7
    Maryland’s rule in such cases is endorsed by the Restatement (Second) of Contracts. See
    Crystal v. West & Callahan, Inc., 
    614 A.2d 560
    , 572–73 (Md. 1992) (citing Restatement
    (Second) of Contracts § 354(1) (Am. Law Inst. 1981)).
    8
    Compare Harford Cty., 923 A.2d at 14 (prejudgment interest mandatory because a
    specific amount was owed on a specific date), and E. Park Ltd. P’ship v. Larkin, 
    893 A.2d 1219
    , 1235 (Md. 2006) (prejudgment interest mandatory on portion of judgment that was
    16
    withholding payment [is] to deprive the creditor of the use of a fixed amount as of a known
    date,” and mandatory prejudgment interest is meant to rectify the situation. Buxton, 770
    A.2d at 165 (quoting Settles, 588 A.2d at 807). Where the impact of withholding payment
    is less certain, the trier of fact has discretion to award prejudgment interest as appropriate
    to the unique circumstances of the case. E.g., Crystal, 614 A.2d at 573.
    Here, “the obligation to pay and the amount due” were “certain, definite, and
    liquidated by a specific date prior to judgment.” Settles, 588 A.2d at 807 (quoting David
    Sloane, Inc. v. Stanley G. House & Assocs., 
    532 A.2d 694
    , 702 (Md. 1987)). So this case
    falls under the first category, and prejudgment interest is mandatory. The district court
    apparently agreed. See J.A. 255 & n.1 (finding Parkway to be “entitled” to prejudgment
    interest, and citing a case involving “a liquidated sum of money [owed] at a certain time”).
    But the district court erred as a matter of law in concluding, based on equitable
    principles, that Parkway was entitled to interest accruing from May 2008. In cases within
    the first category, prejudgment interest accrues from the date where “the obligation to pay
    and the amount due” were both “certain.” Settles, 588 A.2d at 807 (emphasis added); see
    Gordon v. Posner, 
    790 A.2d 675
    , 698 (Md. Ct. Spec. App. 2002) (“[A] right to pre-
    judgment interest only exists when liability and damages are certain . . . .”).
    “‘certain, definite, and liquidated’ from the time the case was remanded by the Court of
    Appeals”), with Ver Brycke, 843 A.2d at 761–62, 777–78 (prejudgment interest
    discretionary in complex family dispute involving whether monetary gift was conditional
    or absolute), Crystal, 614 A.2d at 562, 573 (prejudgment interest discretionary in dispute
    between contractor and homeowner regarding work on home), and I. W. Berman Props.,
    344 A.2d at 77 (prejudgment interest discretionary in construction contract dispute).
    17
    Here, as noted, the contract did not create any obligation for U.S. Home to pay
    Parkway the Reimbursement until the time of Settlement. However, as of the date of
    Settlement, the Reimbursement was a specific amount that was definitively owed. This
    case falls within the first, mandatory category, and Parkway is entitled to prejudgment
    interest as of right—but only from the date the Reimbursement came due, that is, the date
    of Settlement in 2017. We therefore vacate the district court’s order and remand with
    directions to order prejudgment interest as of right accruing from April 21, 2017.
    V.
    Finally, U.S. Home contends that the district court erred when it awarded attorneys’
    fees to Parkway. Considering the plain language of the Development Contract, we agree.
    The proper interpretation of a contract “is a question of law and subject to de novo
    review.” Sky Angel U.S., LLC v. Discovery Commc’ns, LLC, 
    885 F.3d 271
    , 278 (4th Cir.
    2018) (quoting Diamond Point Plaza Ltd. P’ship v. Wells Fargo Bank, 
    929 A.2d 932
    , 951
    (Md. 2007)). “Contract provisions providing for awards of attorney’s fees to the prevailing
    party in litigation under the contract generally are valid and enforceable in Maryland.”
    Myers, 892 A.2d at 532. There is no reason to suppose this general rule would not apply to
    a third-party beneficiary suing under the contract if the beneficiary was covered by the
    relevant contract provision.
    However, “Maryland follows the common law ‘American Rule,’ which states that,
    generally, a prevailing party is not awarded attorney’s fees ‘unless . . . the parties to a
    contract have an agreement to that effect,’” or unless other exceptions not relevant here
    apply. Nova Research, Inc. v. Penske Truck Leasing Co., 
    952 A.2d 275
    , 281 (Md. 2008)
    18
    (quoting Thomas v. Gladstone, 
    874 A.2d 434
    , 437 (Md. 2005)). Thus, “attorney’s fees
    provisions must be strictly construed to avoid inferring duties that the parties did not intend
    to create.” Bainbridge St. Elmo Bethesda Apartments, LLC v. White Flint Express Realty
    Grp. Ltd. P’ship, 
    164 A.3d 978
    , 985 (Md. 2017) (internal quotation marks omitted).
    The Development Contract provides that “[i]n the event that any litigation arises
    between the parties regarding this Contract, the substantially prevailing party shall be
    entitled to recover its reasonable attorneys fees . . . from the other party.” J.A. 13 (emphasis
    added). Despite labeling itself a “third-party beneficiary” of the Development Contract,
    Parkway argues that it is entitled to attorneys’ fees under the fee-shifting provision. J.A. 4.
    The plain meaning of “party,” when interpreting a contract, is a signatory. See
    Signatory, Black’s Law Dictionary (11th ed. 2019) (defining “signatory” as “[a] person or
    entity that signs a document . . . and thereby becomes a party to an agreement”); cf.
    Montana v. Wyoming, 
    563 U.S. 368
    , 375 n.4 (2011) (“As with all contracts, we interpret
    the Compact according to the intent of the parties, here the signatory States.”); Dickerson
    v. Longoria, 
    995 A.2d 721
    , 742 (Md. 2010) (noting that “a third-party beneficiary is not a
    party to the contract”). Thus, litigation “between the parties” naturally suggests litigation
    between the signatories—which does not include Parkway.
    That understanding of the term “party” permeates the Development Contract. The
    contract is made “by and between” U.S. Home and Bevard Development. J.A. 7. Regarding
    any litigation involving escrow, “[t]he party (i.e., U.S. Home and Bevard Development, as
    applicable), which is the non-prevailing party,” is to be held responsible for related costs.
    19
    J.A. 8. Required notices must be sent to Bevard Development and U.S. Home 9—not
    Parkway—and “[e]ither party may at any time change its addresses . . . by written notice
    to the other.” J.A. 13 (emphases added). The Development Contract concludes by stating
    that “the parties have executed this Contract”—followed by signature lines only for U.S.
    Home and Bevard Development. J.A. 15 (emphasis added).
    An amendment to the Development Contract continues in the same vein. The
    amendment, which is made “by and between” U.S. Home and Bevard Development, notes
    that “the parties desire to amend the Contract” and that “the parties acknowledge and agree”
    to certain terms. J.A. 321, 325. The amendment states that it is executed by “the parties,”
    again providing signature lines only for U.S. Home and Bevard Development. J.A. 327.
    Further, the amendment binds Lennar Corporation, “the sole stockholder of U.S.
    Home,” to some provisions—and explicitly addresses attorneys’ fees in litigation between
    Lennar and Bevard Development. J.A. 325. Lennar is not described as a party; its signature
    acknowledges only the provisions relevant to it.
    Significant textual evidence thus supports interpreting “party” to mean a signatory
    to the Development Contract and to the full text of the amendment (so, U.S. Home or
    Bevard Development), and not to include others like Lennar and Parkway. And where
    attorneys’ fees were to be permitted for a non-party (like Lennar), the contract so specified.
    9
    A copy of notices is also to be sent to the minority owner of Bevard Development.
    20
    Nevertheless, the district court found Parkway to be a “party” for purposes of fee-
    shifting. The court focused primarily on the “i.e.” parenthetical in the escrow provisions:
    “[t]he party (i.e., U.S. Home and Bevard Development, as applicable).” J.A. 8.
    Parkway claimed below that the parenthetical suggested that “where the parties to
    the Development Contract intended to limit the term ‘party’ to the signatories,” they did
    so. J.A. 259. By contrast, U.S. Home argued that the parenthetical defined the term “party.”
    The district court concluded that, “[t]hough the language may reasonably be subject to
    either interpretation,” Parkway’s interpretation was “more persuasive.” J.A. 259.
    We disagree. Because “i.e.” means “that is,” “a reasonable person in the position of
    the parties . . . at the time [the contract] was effectuated” would have understood the
    parenthetical to be serving a defining function. Weichert, 19 A.3d at 404 (quoting Myers,
    892 A.2d at 526). And, more importantly, substantial other textual evidence in the
    Development Contract and related amendment supports the same conclusion.
    The district court also noted that it was “inclined to find for [Parkway] due to U.S.
    Home’s inequitable conduct.” J.A. 259. But the default presumption under Maryland law
    is against fee-shifting, and the contract does not provide otherwise with regard to Parkway.
    Accordingly, we reverse the district court’s order awarding attorneys’ fees to Parkway.
    VI.
    We have no reason to doubt the conclusions of not one, but two district court judges
    who chided U.S. Home for its behavior in this and a related case. But our role is limited to
    enforcing the plain language of the contracts. In addition to providing certainty, this
    approach encourages parties to negotiate contracts carefully.
    21
    The plain language of the contracts supports the district court’s conclusion that
    Parkway’s lawsuit is timely. But we cannot agree that Parkway is entitled to attorneys’
    fees. And, in accordance with Maryland law, Parkway is entitled to prejudgment interest
    as a matter of right, but only dating from Settlement on April 21, 2017.
    AFFIRMED IN PART, REVERSED IN PART,
    VACATED IN PART, AND REMANDED
    WITH INSTRUCTIONS
    22