Elliot Dickson v. Fidelity and Deposit Company ( 2023 )


Menu:
  • USCA4 Appeal: 21-1160     Doc: 33        Filed: 04/26/2023   Pg: 1 of 34
    PUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 21-1160
    UNITED STATES EX REL. ELLIOT DICKSON, P. E.; ELLIOT H. DICKSON,
    P. E.,
    Plaintiffs - Appellants,
    v.
    FIDELITY AND DEPOSIT COMPANY OF MARYLAND,
    Defendant - Appellee,
    FORNEY ENTERPRISES, INC.; ZURICH AMERICAN INSURANCE
    COMPANY; COLONIAL AMERICAN CASUALTY AND SURETY COMPANY,
    Defendants.
    Appeal from the United States District Court for the Eastern District of Virginia, at
    Alexandria. Claude M. Hilton, Senior District Judge. (1:20-cv-00129-CMH-JFA)
    Argued: March 8, 2022                                         Decided: April 26, 2023
    Before AGEE and RICHARDSON, Circuit Judges, and FLOYD, Senior Circuit Judge.
    Affirmed by published opinion. Judge Richardson wrote the opinion, in which Judge Agee
    joined. Senior Judge Floyd wrote a dissenting opinion.
    ARGUED: C. Thomas Brown, SILVER & BROWN, Fairfax, Virginia, for Appellants.
    Dominick Preston Weinkam, WATT, TIEDER, HOFFAR & FITZGERALD, LLP,
    USCA4 Appeal: 21-1160   Doc: 33     Filed: 04/26/2023   Pg: 2 of 34
    McLean, Virginia, for Appellee. ON BRIEF: Erik B. Lawson, SILVER & BROWN,
    Fairfax, Virginia, for Appellants.
    2
    USCA4 Appeal: 21-1160        Doc: 33        Filed: 04/26/2023      Pg: 3 of 34
    RICHARDSON, Circuit Judge:
    Under the Miller Act, contractors hired to work on government projects are required
    to furnish bonds to pay those who provided labor and were not paid as a result of a dispute.
    But not all work on a government project qualifies as “labor” under the Miller Act, 
    40 U.S.C. §§ 3131
    –34. And even when the work qualifies as labor, to claim his piece of the
    bond, a laborer must sue within one year of completing the labor to recover.
    Elliott Dickson was a subcontractor for Forney Enterprises, a contractor working
    for the Pentagon. Forney Enterprises was bonded through the Fidelity and Deposit
    Company of Maryland. Dickson worked as a project manager for Forney Enterprises,
    supervising others who engaged in manual labor. After Forney Enterprises’ work at the
    Pentagon was terminated, Dickson sued Fidelity to recover the value of the work he had
    not been paid for.
    The district court found that his supervisory work did not qualify as “labor” and
    granted summary judgment for Fidelity. While we find much of Dickson’s work was
    “labor,” the only work he performed within one year of filing suit, a materials inventory,
    was not “labor.” And no circumstances warrant estopping Fidelity from asserting the
    statute of limitations. So we affirm the district court.
    I.     Background
    The Department of Defense hired Forney Enterprises as the prime contractor to
    renovate several staircases at the Pentagon and their accompanying fire suppression
    systems. Forney Enterprises then subcontracted with Elliott Dickson, a professional
    engineer, to work as a project manager on that contract, starting in 2015. The bulk of
    3
    USCA4 Appeal: 21-1160      Doc: 33         Filed: 04/26/2023     Pg: 4 of 34
    Dickson’s work focused on supervising labor on the site. But Dickson performed many
    other tasks, including logistical and clerical duties, taking various field measurements,
    cleaning the worksite, moving tools and materials, and sometimes even watering the
    concrete himself. This work required Dickson to be at the project site almost daily.
    Forney Enterprises’ work at the Pentagon involved 10 separate stair complexes. In
    December 2018, a Defense subagency terminated its contract with Forney Enterprises for
    “failure to prosecute the work with . . . diligence.” J.A. 140. The agency directed Forney
    Enterprises to stop all work, except for the work on staircases 1 and 2, and cleaning up the
    worksite. The agency gave Forney Enterprises a January 31, 2019 deadline to complete
    the work on staircases 1 and 2. The government also ordered Forney Enterprises to submit
    a materials inventory by February 11, 2019, so it could reimburse some of Forney’s costs.
    Dickson conducted this on-site inventory on February 8, 2019, the last day he was on the
    project site.
    Under the Miller Act, Forney Enterprises was required to furnish the government
    with two surety bonds: a performance bond “for the protection of the Government” and a
    payment bond “for the protection of all persons supplying labor and material in carrying
    out the work provided for in the contract.” See 
    40 U.S.C. § 3131
    (b). Forney Enterprises
    secured Fidelity and Deposit Company of Maryland to issue those bonds. On January 10,
    2019, Dickson submitted a claim to Fidelity for about $400,000 for his work on the project.
    On January 14, 2020—more than a full year later—Fidelity denied the claim, largely
    because Dickson failed to provide evidence that he had performed “labor” as required for
    recovery under the Miller Act. J.A. 412. The letter expressed Fidelity’s desire to “work
    4
    USCA4 Appeal: 21-1160       Doc: 33          Filed: 04/26/2023     Pg: 5 of 34
    with [Dickson] in a cooperative manner to reach a practical resolution” to Dickson’s claim.
    J.A. 412. Fidelity then asked Dickson to resubmit his Proof of Claim, asserting that
    Dickson needed to remove from his claim “all hours worked off-site, as well as those
    performed on-site relating to clerical and administrative tasks.” J.A. 412. The letter stated
    that “[o]nce the Surety has received your revised Proof of Claim, it will conduct another
    review to determine any amounts recoverable under the Payment Bond.” J.A. 412. The
    letter made sure to “reserve[ ] all rights.” J.A. 412. 1
    Dickson never submitted a revised Proof of Claim, and instead, on February 5,
    2020—less than a month after Fidelity rejected his claim—sued Fidelity for recovery under
    the Miller Act. He claimed that his work qualified as “labor” and he had a right to recover,
    and that even if he sued outside the statute of limitations period, he did so based on
    reasonable reliance on the letter from Fidelity urging him to refile his claims. The district
    court granted summary judgment for Fidelity, holding that Dickson’s work did not qualify
    as “labor” for Miller Act purposes, on a theory that supervisory work is generally not
    “labor.” The court found that “any de minimis physical work by Plaintiff was merely
    incidental to his contractual duty to supervise.” J.A. 2894. The court also held that even
    if Dickson’s supervisory work qualified as labor, the project concluded on January 31,
    2019, and the later inventory was a “clerical task” that did not fall within the definition of
    1
    A previous communication from Fidelity to Dickson made similar reservations:
    “Our actions are taken for the purposes of investigation only, and the Surety reserves all
    rights and defenses . . . . Nothing stated or unstated in this or any other correspondence is
    intended or should be construed as an acknowledgment of liability . . . or as a waiver of
    any right or defense . . . .” J.A. 389–90.
    5
    USCA4 Appeal: 21-1160       Doc: 33         Filed: 04/26/2023     Pg: 6 of 34
    labor under the Miller Act. J.A. 2896. 2 Finally, the court held that there were no grounds
    for estopping Fidelity from asserting the statute of limitations because the letter sent to
    Dickson was merely a promise to investigate, that a promise to investigate cannot cause
    reasonable reliance, and that, even if it could, the previous communications reserving all
    defenses meant Dickson could not have reasonably relied on the letter to delay litigation.
    Dickson timely appealed.
    II.    Discussion
    The district court granted summary judgment to Fidelity. We review a grant of
    summary judgment de novo, applying the same standard the district court applied and
    viewing the facts in the light most favorable to the nonmoving party. See Sylvia Dev. Corp.
    v. Calvert Cnty., 
    48 F.3d 810
    , 817 (4th Cir. 1995). Summary judgment is appropriate only
    when no genuine disputes of material fact exist, and the movants are “entitled to judgment
    as a matter of law.” Fed. R. Civ. P. 56(a).
    A.     The Miller Act and The Heard Act
    Before turning to what counts as “labor” under the Miller Act, some context will be
    useful. Contractors, subcontractors, and workers often perform work on construction
    projects only to be paid later. This set-up creates a risk that an owner or a contractor won’t
    pay up. At common law, unpaid construction workers had few effective options to recover
    for the value of their labor. See Chas. E. Davidson, The Mechanic’s Lien Law of Illinois
    6–7 (1922). In the late 1700s, the risk of nonpayment caused a shortage of construction
    2
    The district court separately held that the inventory was “a post-project task and
    thus not recoverable under the Miller Act.” J.A. 2896.
    6
    USCA4 Appeal: 21-1160      Doc: 33         Filed: 04/26/2023     Pg: 7 of 34
    workers, resulting in a housing crisis in Washington, D.C. Id. at 6. In 1791, Thomas
    Jefferson proposed a “mechanic’s lien” statute to solve the problem. Id. The mechanic’s
    lien allowed unpaid workers to place something like a common-law lien—but significantly
    harder to avoid—on the property they worked on, thereby insuring them against getting
    stiffed by the owner.
    The mechanic’s lien is a solution in many cases, but not here. A “lien cannot attach
    to Government property,” so a different solution was needed for builders and laborers
    working on government projects. J. W. Bateson Co. v. United States ex rel. Bd. of Trs. of
    The Nat’l Automatic Sprinkler Indus. Pension Fund, 
    434 U.S. 586
    , 589 (1978) (quoting F.
    D. Rich Co. v. U. S. for Use of Indus. Lumber Co., 
    417 U.S. 116
    , 122 (1974)). To protect
    those workers, Congress passed the Heard Act, ch. 280, 
    28 Stat. 278
     (1894), which was
    eventually replaced by the Miller Act, 
    Pub. L. No. 74-321, 49
     Stat. 793 (1935) (codified as
    amended at 
    40 U.S.C. §§ 3131
    –34).
    Under the Miller Act, like the Heard Act before it, a primary contractor working on
    a government project must furnish a bond which can be used later to pay subcontractors,
    laborers, and materials providers. See George Fiedler, The Heard Act and the Miller Act
    After Fifty Years, 12 Ins. Couns. J. 22, 23–24 (1945). Typically, a bond is furnished
    through a surety company, and unpaid subcontractors or workers can sue the surety
    company to collect the money they are owed. But a bond issued under the Miller Act does
    not cover all the money that might be owed for the project. Instead, the Miller Act retained
    the Heard Act’s requirement that a bond need only cover “labor” and “materials.” Dickson
    alleges that his work constituted labor under the Miller Act.
    7
    USCA4 Appeal: 21-1160      Doc: 33          Filed: 04/26/2023     Pg: 8 of 34
    B.     Miller Act “labor”
    The Miller Act requires any contractor working on a government project worth more
    than $100,000 to supply a bond “for the protection of all persons supplying labor.”
    § 3131(b)(2). For any person who “has furnished labor . . . provided for in a contract” and
    who “has not been paid in full within 90 days after the day on which the person did or
    performed the last of the labor,” the Miller Act provides a cause of action to pursue
    reimbursement through the bond. § 3133(b)(1).
    While published caselaw interpreting the word “labor” under the Miller Act is
    sparse, courts have largely agreed that tasks involving “physical toil” are labor and that on-
    site supervision of “physical toil” is also labor. See Luong v. W. Sur. Co., 
    485 P.3d 46
    , 51–
    52 (Alaska 2021) (collecting cases); see also United States ex rel. Barber-Colman Co. v.
    U.S. Fid. & Guar. Co., No. 93-1665, 
    1994 WL 108502
    , at *3 (4th Cir. 1994) (per curiam)
    (unpublished); United States ex rel. Constructors, Inc. v. Gulf Ins. Co., 
    313 F. Supp. 2d 593
    , 597 (E.D. Va. 2004).
    Those two ideas—that “labor” requires physical toil, and that on-site supervision of
    physical toil is itself “labor”—trace to the Miller Act’s predecessor, the Heard Act. The
    federal courts (including our own circuit) interpreted “labor” under the Heard Act to require
    physical toil, or its direct supervision. Because the Miller Act copied this “labor” language
    directly from the Heard Act, we apply our construction of Heard Act “labor” to the same
    language today.
    In a sense, our Court has already answered the question before us. Over a hundred
    years ago, in Bankers’ Surety Co. of Cleveland v. Maxwell, 
    222 F. 797
     (4th Cir. 1915), we
    8
    USCA4 Appeal: 21-1160         Doc: 33         Filed: 04/26/2023     Pg: 9 of 34
    considered what “labor” meant under the Heard Act. We asked whether the act of
    supervising workers, who were themselves engaged in bodily toil and physical exertion,
    qualified as labor. Maxwell, 
    222 F. at
    799–800. And we determined that the supervisor in
    Maxwell did indeed engage in “labor,” since he “was employed as a working foreman,”
    and actually performed physical labor alongside his workers. 
    Id. at 800
    . Thus, the best
    reading of our decision in Maxwell is that “labor” under the Heard Act must be physical.
    Supervisory work is fine, since it often involves a physical component. Yet mental labor
    alone, such as clerical or administrative tasks, does not suffice.
    True, Maxwell does not say all of this explicitly. But its extended focus on physical
    labor would make little sense otherwise. Supervising workers always involves mental
    labor. If the Maxwell court believed that mental labor alone was sufficient, why spend so
    much time discussing whether that specific supervisor’s labor was physical? Courts of
    long ago often dispensed with cases in a few short paragraphs. While that has real benefits,
    one downside is that those courts did not make every premise explicit. We must read
    between the lines. And one clear premise permeates Maxwell: “labor” means “physical
    labor.”
    Maxwell’s reliance on an earlier Supreme Court case, Mining Co. v. Cullins, 
    104 U.S. 176
     (1881), bolsters this reading. Cullins asked what a state mechanic’s lien statute
    meant by “labor.” 
    104 U.S. at
    177–78. And Maxwell’s analysis about what constitutes
    Heard Act “labor” relies heavily upon one long quotation from Cullins. See Maxwell, 
    222 F. at 799
     (quoting Cullins, 
    104 U.S. at
    177–78). In that quoted section, the Supreme Court
    explicitly drew a line between work “of a professional character,” which is not covered as
    9
    USCA4 Appeal: 21-1160      Doc: 33          Filed: 04/26/2023     Pg: 10 of 34
    “work and labor” under the statute, and “manual labor,” which is covered. Cullins, 
    104 U.S. at 177
    ; see 
    id. at 179
     (“It is somewhat difficult to draw the line between the kind of
    work and labor which is entitled to a lien, and that which is mere professional or
    supervisory employment, not fairly to be included in those terms.”). Granted, Cullins
    declined to precisely define where that line fell, since the plaintiff there—a direct
    supervisor of workers—was clearly on the “physical” side of the line. 
    Id. at 178
     (noting
    that because the supervisor’s services “may well be called work and labor” themselves,
    and, “occasionally in an emergency, . . . [he must] assist with his own hands,” that
    supervisor engages in “[b]odily toil,” and thus “labor” that is covered by the statute). But
    drawing that line shows that the Court thought “labor,” as used in the state statute, required
    a physical component.
    This federal interpretation that “labor” requires physical toil was not uniformly
    followed by state courts interpreting that term in their own mechanic’s lien statutes.
    Indeed, whether “labor” could be purely mental bitterly divided states in the late 19th and
    early 20th centuries. Some states held that mental toil qualified as “labor” under their state
    statutes. See, e.g., Stryker v. Cassidy, 76 N.Y. (31 Sickels) 50, 53–54 (1879); Knight v.
    Norris, 
    13 Minn. 473
    , 475–76 (1868); see also Field & Slocomb v. Consol. Min. Water
    Co., 
    55 A. 757
    , 758 (R.I. 1903) (collecting cases). Other states held that mental toil alone
    was not enough. See, e.g., Mitchell v. Packard, 
    47 N.E. 113
    , 114–15 (Mass. 1897); Price
    v. Kirk, 
    90 Pa. 47
    , 48–49 (1879) (per curiam); Brockway v. Innes, 
    39 Mich. 47
    , 48 (1878).
    The Supreme Court, in Cullins, sided with the latter group of states requiring physical toil.
    10
    USCA4 Appeal: 21-1160       Doc: 33         Filed: 04/26/2023      Pg: 11 of 34
    And Cullins is where we turned in Maxwell when deciding what the Heard Act meant by
    “labor.”
    Our Court in Maxwell was not alone in interpreting Heard Act “labor” to require a
    physical component. Indeed, to our knowledge, the only other federal appellate court to
    consider what counts as Heard Act “labor” seemed to take the same position. Like our
    circuit, the Fifth Circuit held that a direct supervisor of workers could furnish “labor” under
    the Act. See Am. Sur. Co. of N.Y. v. United States ex rel. Barrow-Agee Lab’ys, 
    76 F.2d 67
    ,
    68 (5th Cir. 1935). In doing so, it assumed that “the term ‘labor’ in [the Heard Act] . . .
    refers to physical labor rather than technical and professional skill and judgment.” 
    Id.
    Citing both Maxwell and Cullins, the Fifth Circuit noted that direct supervisors often
    engage in “manual labor” themselves. 
    Id.
     So, like our Court, the Fifth Circuit held that
    this “hard physical labor” meant that the supervisor was covered by the Heard Act. 
    Id.
    This view of “labor” was not limited to the Heard Act. During the same period, in
    Church of the Holy Trinity v. United States, 
    143 U.S. 457
     (1892), the Supreme Court also
    considered the meaning of “labor” under our immigration statutes. There, the Court
    explained that “labor”—this time used in the Alien Contract Labor Law—extended “only
    to the work of the manual laborer, as distinguished from that of the professional man.” 3
    3
    Holy Trinity is best known for its role in the broader statutory interpretation debate
    between purposivists and textualists. See Antonin Scalia, A Matter of Interpretation 18
    (1997); compare also Zuni Pub. Sch. Dist. No. 89 v. Dep’t of Educ., 
    550 U.S. 81
    , 107 &
    n.3 (2007) (Stevens, J., concurring) with 
    id. at 108
    , 116–17 (Scalia, J., dissenting). We cite
    it today for a much more limited proposition: that the Supreme Court of the 1890s
    understood the word “labor” to include physical, but not purely mental, toil.
    11
    USCA4 Appeal: 21-1160      Doc: 33          Filed: 04/26/2023     Pg: 12 of 34
    
    143 U.S. at 463
    . Although in a different statutory context, the Supreme Court in Holy
    Trinity used a definition for “labor” that tracked both Cullins and Maxwell, a mere two
    years before Congress passed the Heard Act.
    A clear picture thus emerges from the fog. Although the states were divided about
    whether purely mental toil constituted “labor” under their various mechanic’s lien statutes,
    the Supreme Court held in Cullins that it did not. The only circuits to consider this question
    under the Heard Act adopted Cullins’s logic, reasoning that “labor,” as used in that statute,
    required a physical component. They never suggested that purely mental “labor” was
    enough.
    Dickson, of course, isn’t suing under the Heard Act. He’s suing under the Miller
    Act. And the Miller Act replaced the Heard Act in 1935. So we must consider how “labor”
    in the Miller Act would have been understood in 1935.
    But we do not start on a blank slate. Instead, we must take stock of the Miller Act’s
    context: Congress copied the disputed provision of the Miller Act directly from the Heard
    Act. When a statute’s language is “obviously transported from another legal source,
    whether the common law or other legislation, it brings the old soil with it.” Sekhar v.
    United States, 
    570 U.S. 729
    , 733 (2013) (quoting Felix Frankfurter, Some Reflections on
    the Reading of Statutes, 
    47 Colum. L. Rev. 527
    , 537 (1947)). 4 Here, the “old soil” giving
    legal meaning to the Miller Act is the Heard Act.
    4
    See Taggart v. Lorenzen, 
    139 S. Ct. 1795
    , 1801 (2019); Hall v. Hall, 
    138 S. Ct. 1118
    , 1128 (2018).
    12
    USCA4 Appeal: 21-1160      Doc: 33         Filed: 04/26/2023      Pg: 13 of 34
    What this means is that a reader of the Miller Act in 1935 would have connected it
    to the Heard Act. So a 1935 inquiry about what “labor” meant under the Miller Act would
    be informed by how courts interpreted “labor” under the Heard Act. And, in the Fourth
    Circuit, the reader would have found that Maxwell answers this question: “labor” under
    the Heard Act must be physical. See 
    222 F. at
    799–800. If any lingering doubts remained,
    they would have been assuaged by the fact that the only other federal appellate court to
    consider the question agreed with Maxwell. See Barrow-Agee, 
    76 F.2d at 68
    . Indeed—as
    far as this Court is aware—no published decision existed that interpreted this part of the
    Heard Act differently. 5 Add to this the Supreme Court’s consonant decisions in Cullins
    and Holy Trinity, and a reader of the Miller Act would have understood that “labor”
    requires a physical component.
    Perhaps the result would be different if Congress had infused “labor” with new
    meaning when it passed the Miller Act. Then, it might not make sense to trace “labor”
    back to the Heard Act. But this did not happen.
    To start, while the Miller Act “repealed” the Heard Act, see Miller Act, 49 Stat. at
    794, § 5 (1935), it did so only technically. Congress passed the Miller Act as the direct
    5
    To be clear, there are plenty of cases that discuss related questions under the Heard
    Act. For instance, what counts as a “public work” under the act? See, e.g., Title Guar. &
    Tr. Co. of Scranton v. Crane Co., 
    219 U.S. 24
    , 32–33 (1910). What does the act mean by
    “materials,” and what does it mean for the labor and materials to be supplied “in the
    prosecution of” the public work? See, e.g., Title Guar. & Tr. Co. of Scranton v. Puget
    Sound Engine Works, 
    163 F. 168
    , 179 (9th Cir. 1908) aff’d sub nom. Crane Co., 
    219 U.S. 24
    ; United States ex rel. Watsabaugh & Co. v. Seaboard Sur. Co., 
    26 F. Supp. 681
    , 689–
    92 (D. Mont. 1938) (collecting cases). But these cases do not address our question: must
    “labor” under the Heard Act involve a physical component?
    13
    USCA4 Appeal: 21-1160      Doc: 33         Filed: 04/26/2023      Pg: 14 of 34
    successor to the Heard Act, Bateson, 
    434 U.S. at 589
    , and it “reinstated [the Heard Act’s]
    basic provisions,” Clifford F. MacEvoy Co. v. United States ex rel. Calvin Thompkins Co.,
    
    322 U.S. 102
    , 105 (1944). The new act “was designed primarily to eliminate certain
    procedural limitations on its beneficiaries,” not to expand the scope of those beneficiaries.
    
    Id.
     (emphasis added). The Miller Act’s changes thus focused mostly on the procedures
    that workers had to follow in order to make claims. Yet, like the Heard Act before it, the
    Miller Act continued to limit its coverage to people who supplied “labor” or “materials” in
    the construction of a public work, and the relevant provisions containing those terms
    remained identical between the two acts. There is no sign that Congress broadened the
    Miller Act’s scope beyond that of the Heard Act by mechanically repeating its terms. Quite
    the opposite.
    What’s more, it is far from clear that the meaning of “labor” had changed between
    1894 and 1935. Throughout this period, state courts engaged in a vigorous debate about
    the scope of “labor” in their state mechanic’s lien statutes. Contemporary dictionaries,
    rather than resolving this debate, simply reflected it. Dictionaries at the time of the Heard
    Act were split, some defining labor as limited to physical toil, others including mental toil
    in their definition, and still others acknowledging both the narrower and broader definitions
    as distinct senses of the word. 6 This split continued through the time that the Miller Act
    6
    For an example that limits labor to the physical context, see Labor, Black’s Law
    Dictionary (1st ed. 1891) (“Continued exertion, of the more onerous and inferior kind,
    usually and chiefly consisting in the protracted expenditure of muscular force, adapted to
    the accomplishment of specific useful ends.”). But for examples of definitions including
    both physical and mental labor, see Labor, Bouvier’s Law Dictionary, vol. II (1897)
    (Continued)
    14
    USCA4 Appeal: 21-1160       Doc: 33         Filed: 04/26/2023     Pg: 15 of 34
    was drafted. 7 At bottom, there is no reason to think that—even if we were to ignore the
    meaning “labor” had under the Heard Act—its ordinary meaning in 1935 would have been
    broader than in 1894.
    In any case, dictionaries do not provide a definitive answer here. The point is not
    that labor could theoretically be understood expansively to include mental exertion. It is
    that a reader of the Miller Act would not have understood it that way. And conflict in the
    state courts or dictionaries does not change that fact.
    C.     Dickson’s “labor”
    With this understanding of “labor” in mind, we turn to Dickson’s claims. The
    district court first held that Dickson’s supervisory work did not qualify as “labor.” We
    disagree. The bulk of Dickson’s work involved both direction and supervision of manual
    labor and occasional performance of manual labor and therefore qualifies as “labor.” And
    (“Work requiring exertion or effort, either physical or mental.”); Labor, Universal
    Dictionary of the English Language, vol. III (1897) (including “[t]he act of doing, or
    endeavoring to do, that which involves hard work, toil, or exertion of strength, whether
    physical or mental”). Finally, for examples noting both as distinct definitions, see Labor,
    Webster’s Collegiate Dictionary (1898) (including “[p]hysical toil or bodily exertion” and
    “[i]ntellectual exertion; mental effort”); Labor, The Century Dictionary and Cyclopedia,
    vol. IV (1899) (including “exertion of body or mind, or both, for the accomplishment of an
    end” and “the use of muscular strength for the satisfaction of wants, in distinction from
    purely mental exertion”).
    7
    Compare, e.g., Labor, Black’s Law Dictionary (3d ed. 1933) (retaining its
    narrower definition of labor, which it claimed was the meaning usually used in state
    “statutes giving liens to laborers” and in the federal Immigration Act, but also noting the
    term “is sometimes given a broader meaning as [i]ncluding all bodily or intellectual
    exertion done for a purpose other than pleasure”), and Labor, Law Dictionary with
    Pronunciations (1930) (“Physical toil.”), with Labor, Bouvier’s Law Dictionary (1934)
    (retaining its broad definition), and Labor, Webster’s New International Dictionary (2d ed.
    1934) (“Physical or mental toil.”).
    15
    USCA4 Appeal: 21-1160      Doc: 33         Filed: 04/26/2023      Pg: 16 of 34
    this supervisory work continued until no later than January 31, 2019. See J.A. 143
    (directing Forney Enterprises “to continue work on [staircases] 1 & 2 on the condition the
    work . . . is fully complete . . . no later than 31 Jan 2019”). Thus we hold that Dickson’s
    supervisory work through January 2019 was Miller Act “labor.”
    While the district court erred in finding that Dickson’s supervisory work was not
    “labor” under the Miller Act, the district court alternatively held that the statute of
    limitations barred his claim. And on this point, we agree.
    The statute of limitations runs “one year after the day on which the last of the labor
    was performed.” § 3133(b)(4) (emphasis added). Dickson’s supervision of other workers
    was last performed more than one year before suit was filed. The only on-site work
    Dickson completed within one year of filing suit was taking a final inventory on February
    8, 2019. 8 Dickson’s final inventory did not involve any supervisory work, as he did it
    himself. So our understanding of the meaning of labor under the Miller Act does not apply
    to that work. See Maxwell, 
    222 F. at 799
    . The district court found that the inventory work
    was merely clerical—mostly paperwork with perhaps some manipulation of light pipe—
    which would not qualify as labor under the Miller Act. And we agree with the district
    8
    It is unclear whether the work was “provided for in the contract” because it was
    performed after the contract was terminated. See § 3131(b)(2); see also United States ex
    rel. Magna Masonry, Inc. v. R.T. Woodfield, Inc., 
    709 F.2d 249
    , 251 (4th Cir. 1983)
    (holding that follow-up work “correcting defects, or making repairs following inspection”
    is not work provided for under the contract (quoting United States ex rel. Noland v.
    Andrews, 
    406 F.2d 790
    , 792 (4th Cir.1969)); United States ex rel. T.M.S. Mech.
    Contractors, Inc. v. Millers Mut. Fire Ins. Co. of Tex., 
    942 F.2d 946
    , 953 (5th Cir. 1991)
    (“[A] subcontractor cannot recover on a Miller Act payment bond for the cost of labor and
    materials provided after the termination of work under a government construction
    project.”).
    16
    USCA4 Appeal: 21-1160      Doc: 33         Filed: 04/26/2023      Pg: 17 of 34
    court’s conclusion that, based on this record, taking the final inventory of a job site lacks
    the “physical exertion” and “[b]odily toil” required to qualify as labor. See 
    id.
    True, Dickson’s inventory work may have been “physical” in a broad sense, just as
    any office work—filing papers, typing on a keyboard, or refilling the printer—involves
    “physical” acts. But when a law clerk staples the pages of this opinion together, he has not
    engaged in “physical exertion” or “bodily toil.” Maxwell and Cullins drew a line between
    work “of a professional character” and “manual labor.” See Cullins, 
    104 U.S. at 177
    ;
    Maxwell, 
    222 F. at 799
     (quoting Cullins). For that line to mean anything, it is not enough
    that an act is technically “physical”: it must rise to “exertion” or “toil.” And Dickson’s
    inventory simply did not.
    We thus conclude that Dickson’s supervision of laborers constitutes labor under his
    contract with Forney Enterprises. But that supervision ended no later than January 31,
    2019, which is outside the one-year limitations period for Miller Act claims.            See
    § 3133(b)(4). The only work done within the one-year period was taking an inventory and
    that does not count as labor. So unless Fidelity is estopped from asserting the statute of
    limitations, Dickson’s claim must fail.
    D.     Estoppel
    Estoppel is an equitable defense based on the principle “that where one party has by
    his conduct induced the other party to a transaction to give him an advantage which it
    would be against equity and good conscience for him to assert, he would not in a court of
    justice be permitted to avail himself of that advantage.” United States ex rel. Humble Oil
    & Refin. Co. v. Fid. & Cas. Co. of N.Y., 
    402 F.2d 893
    , 897 n.3 (4th Cir. 1968). In our
    17
    USCA4 Appeal: 21-1160      Doc: 33         Filed: 04/26/2023      Pg: 18 of 34
    Circuit, estoppel does not require unjust or fraudulent conduct by the estopped party, only
    that “the person estopped, by his statements or conduct, misled another to his prejudice.”
    
    Id. at 898
     (quoting United States ex rel. Noland Co. v. Wood, 
    99 F.2d 80
    , 82 (4th Cir.
    1938)). Nonetheless, the reliance must be “unmistakably” foreseeable by the estopped
    party. See Felty v. Graves-Humphreys Co., 
    818 F.2d 1126
    , 1128 (4th Cir. 1987). The
    reliance of the other party must also be objectively reasonable. See 
    id.
     at 1128–29 (“One
    who fails to act diligently cannot invoke equitable principles to excuse that lack of
    diligence.” (quoting Baldwin Cnty. Welcome Ctr. v. Brown, 
    466 U.S. 147
    , 151 (1984))).
    And in Miller Act disputes, estoppel “arises where one party by his words, acts, and
    conduct led the other to believe that it would acknowledge and pay the claim, if, after
    investigation, the claim were found to be just, but when, after the time for suit had passed,
    breaks off negotiations and denies liability and refuses to pay.” Humble Oil, 402 F.2d at
    897 (quoting McWaters & Bartlett v. United States ex rel. Wilson, 
    272 F.2d 291
    , 296 (10th
    Cir. 1959)).
    Here, there was no affirmative indication Fidelity would acknowledge and pay the
    claim. There were no negotiations or promises to pay. Instead, Fidelity only promised to
    investigate the claim. Not only did Fidelity not promise to acknowledge and pay the claim,
    but it repeatedly made clear that its communications were for investigative purposes and
    reserved all rights and defenses. Fidelity’s communications fail to establish equitable
    estoppel. See United States ex rel. E. Coast Contracting, Inc. v. U.S. Fid. & Guar. Co.,
    
    133 F. App’x 58
    , 60 (4th Cir. 2005) (per curiam). So Fidelity can assert its statute-of-
    limitations defense, which bars Dickson’s recovery.
    18
    USCA4 Appeal: 21-1160      Doc: 33         Filed: 04/26/2023     Pg: 19 of 34
    *            *             *
    The Miller Act provides a substitute for mechanics’ liens for subcontractors working
    on federal projects, allowing them to recover for the value of their “labor.” Under our
    precedent, Dickson’s supervisory work through January 2019 qualified as labor, but his
    later work taking a final inventory did not. He filed suit more than the one year after his
    last act of labor, so the Miller Act limitations period barred any claim.         And the
    circumstances that warrant estoppel do not apply here. So Dickson cannot recover.
    Therefore, the district court must be
    AFFIRMED.
    19
    USCA4 Appeal: 21-1160      Doc: 33          Filed: 04/26/2023     Pg: 20 of 34
    FLOYD, Senior Circuit Judge, dissenting:
    The outcome here turns on the meaning of “labor” under the Miller Act, 
    40 U.S.C. § 3133
    (a)–(b). My fine colleagues in the majority conclude that an individual only supplies
    labor under the Miller Act if he or she engages in “bodily toil and physical exertion” or,
    alternatively, supervises the physical work of others, “since [supervision] often involves a
    physical component.” Majority Op. 9. But because a crucial tenet of the Miller Act is that
    its reach must be liberally construed, I do not share the majority’s view.
    As a matter of statutory interpretation, nothing about the term “labor” limits its
    meaning to only “bodily toil and physical exertion,” or some other supervision of physical
    work, as the majority now declares. 
    Id.
     And Bankers’ Surety Co. of Cleveland v. Maxwell,
    
    222 F. 797
     (4th Cir. 1915), on which the majority heavily relies, hardly offers clarity.
    Furthermore, even if we cabin labor to activity with a physical component, the majority
    turns a blind eye to the physical nature of Dickson’s work on February 8, 2019. Implicit
    in the majority’s logic is that some physical exertion is sufficient under the Miller Act,
    while other physical exertion falls short. Where we delineate between these categories on
    a spectrum of physicality is anyone’s guess, and the majority’s exclusion of Dickson’s
    labor as insufficient leaves us at sea with a polestar of arbitrary judgment.
    Unlike the majority, I would first hold that the plain meaning of labor also
    encompasses “mental exertion.” With that conception of labor in mind, I would then hold
    that Dickson’s final inventory, which took place on February 8, 2019, constitutes “labor”
    under the Miller Act, thus rendering his lawsuit timely. Alternatively, I would hold that
    Dickson’s manipulation of pipe during the inventory process involved sufficient
    20
    USCA4 Appeal: 21-1160       Doc: 33          Filed: 04/26/2023      Pg: 21 of 34
    physicality to constitute actionable labor—even under the majority’s conception of the
    term—again, rendering Dickson’s lawsuit timely. At the very least, the degree to which
    he exerted himself physically while manipulating pipe amounts to a factual question
    sufficient to preclude summary judgment below. Thus, I respectfully dissent.
    I.
    A.
    Congress repealed and replaced the Heard Act of 1894 when it passed the Miller
    Act in 1935. N. Pieter M. O’Leary, Bullies in the Sandbox: Federal Construction Projects,
    the Miller Act, and a Material Supplier’s Right to Recover Attorney’s Fees and Other
    “Sums Justly Due” Under a General Contractor’s Payment Bond, 
    38 Transp. L.J. 1
    , 6–7
    (2011). “The Miller Act represents a congressional effort to protect persons supplying
    labor and material for the construction of federal public buildings in lieu of the protection
    [that] they might receive under state statutes with respect to the construction of nonfederal
    buildings.” U.S. ex rel. Sherman v. Carter, 
    353 U.S. 210
    , 216 (1957). Before a contract
    exceeding $100,000.00 is awarded for the “construction, alteration, or repair” of a federal
    building or project, the Miller Act requires contractors to supply the government with both
    a performance bond and payment bond. 
    40 U.S.C. § 3131
    (b)(1)–(2). The payment bond
    is for the “protection of all persons supplying labor and material[s].” 
    Id.
     § 3131(b)(2).
    Individuals providing “labor or material[s]” to a project, including subcontractors, may
    bring a civil action on the payment bond if he or she is not paid in full. Id. § 3133(b)(1)–(2).
    The civil action must be initiated “no later than one year after the day on which the last of
    21
    USCA4 Appeal: 21-1160      Doc: 33         Filed: 04/26/2023     Pg: 22 of 34
    the labor was performed or material was supplied by the person bringing the action.” Id.
    § 3133(b)(4).
    B.
    As relevant here, the Miller Act expressly provides:
    Every person that has furnished labor . . . in carrying out work provided for
    in a contract for which a payment bond is furnished under section 3131 of
    this title and that has not been paid in full within 90 days after the day on
    which the person did or performed the last of the labor . . . for which the
    claim is made may bring a civil action on the payment bond for the amount
    unpaid at the time the civil action is brought . . . .
    Id. § 3133(b)(1) (emphases added). In this case, the parties dispute the meaning of “labor”
    under the Miller Act’s express terms. Is labor restricted to physical or manual work—or
    supervision of such work—as the majority holds? Or does the term contemplate far more?
    This is a question of statutory interpretation, so I start with the text. See United
    States v. Young, 
    989 F.3d 253
    , 259 (4th Cir. 2021). The Miller Act never defines the word
    “labor.” See 
    40 U.S.C. §§ 3131
    –34. Nor do any qualifying adjectives—such as “physical,”
    “manual,” or even “mental”—precede the term. 
    Id.
     Instead, the statute simply references
    undefined and unqualified “labor.” 
    Id.
     But the lack of a definition or limiting descriptor
    is of no moment. “When a term goes undefined in a statute, we give the term its ordinary
    meaning.” Taniguchi v. Kan Pac. Saipan, Ltd., 
    566 U.S. 560
    , 566 (2012) (citing Asgrow
    Seed Co. v. Winterboer, 
    513 U.S. 179
    , 187 (1995)); see also United States v. Ward, 
    972 F.3d 364
    , 369–70 (4th Cir. 2020). So, I give labor its “ordinary meaning,” and that is
    determined by what the term meant “at the time of the statute’s enactment.” United States
    22
    USCA4 Appeal: 21-1160       Doc: 33         Filed: 04/26/2023      Pg: 23 of 34
    v. George, 
    946 F.3d 643
    , 645 (4th Cir. 2020) (quoting United States v. Abdelshafi, 
    592 F.3d 602
    , 607 (4th Cir. 2010)).
    As such, the term’s meaning should begin and end with the sources existing during
    the Miller Act’s passage. In 1910, labor generally meant “physical or mental toil”; “bodily
    or intellectual exertion, esp. when fatiguing, painful, irksome, or unavoidable”; or “work.”
    Webster’s New International Dictionary of the English Language 1200 (1910). 1 By 1933,
    just one year before the Miller Act’s passage, labor still denoted the “[e]xertion of the
    faculties of the body or mind, esp. when painful or compulsory[,]” including “bodily or
    mental toil.” 6 The Oxford English Dictionary 5 (1933). During that same year, Black’s
    Law Dictionary provided a more nuanced definition of labor, first defining it as: “Work;
    toil; service. Continued exertion, of the more onerous and inferior kind, usually and chiefly
    consisting in the protracted expenditure of muscular force, adapted to the accomplishment
    of specific useful ends.” Labor, Black’s Law Dictionary (3d ed. 1933). But it then
    explained that “[t]he term ‘labor’ is sometimes given a broader meaning as [i]ncluding all
    1
    To be sure, this 1910 edition also states that labor can specifically mean “[b]odily
    exertion or effort directed to supplying society with the required material things; the service
    rendered or part played by the laborer, operative, and artisan in the production of wealth,
    as distinguished from the service rendered by capitalists or by those whose exertion is
    primarily and almost entirely mental.” Webster’s New International Dictionary of the
    English Language 1200 (1910). But this definition does not preclude Dickson’s materials
    inventory from qualifying as labor. The materials inventory was part and parcel of
    “supplying” the federal government with a “material[] thing”—the staircases that
    inevitably enhanced its wealth. 
    Id.
     Surely, leaving the staircases in a state of disrepair
    does not leave the federal government financially better off. And Dickson never resembled
    anything of a “capitalist” because his work was not “primarily and almost entirely mental.”
    
    Id.
     Indeed, even under its narrow view of labor, the majority acknowledges that “[t]he
    bulk of Dickson’s work” was labor through January 2019. Majority Op. 15.
    23
    USCA4 Appeal: 21-1160       Doc: 33          Filed: 04/26/2023      Pg: 24 of 34
    bodily or intellectual exertion done for purpose other than pleasure.” 
    Id.
     I have no qualms
    with adopting the term’s broader definition that embraces “intellectual exertion.” In fact,
    the Supreme Court requires us to give the Miller Act a “liberal construction and application
    in order properly to effectuate the Congressional intent to protect those whose labor and
    materials go into public projects.” 2 Clifford F. MacEvoy Co. v. U.S. ex rel. Calvin Tomkins
    Co., 
    322 U.S. 102
    , 107 (1944). The majority’s narrower interpretation of labor fails to give
    the Miller Act the “liberal construction” demanded by the Supreme Court. 
    Id.
    Other sources from the period likewise support labor’s inclusion of mental toil and
    mental exertion. 3 See The Practical Standard Dictionary of the English Language 642
    (1936) (defining labor to include (1) “[p]hysical or mental exertion, particularly for some
    useful or desired end; toil; work”; and (2) “[t]hat which requires exertion or effort; a task”).
    The majority’s narrow definition of labor, which imposes a requirement of “physical work
    or bodily toil,” undermines the term’s plain meaning. Even if Congress intended for labor
    to only include “physical work and bodily toil,” the Supreme Court has declared that “the
    limits of the drafters’ imagination supply no reason to ignore the law’s demands.” Bostock
    2
    In any event, today, no ambiguity remains as to what labor means according to
    Black’s Law Dictionary. Black’s now defines labor as “[w]ork of any type, including
    mental exertion.” Labor, Black’s Law Dictionary (11th ed. 2019) (emphasis added).
    3
    Jurisdictions of the relevant time period viewed “labor” as encompassing mental
    exertion. See Crook v. Commonwealth, 
    136 S.E. 565
    , 567 (Va. 1927) (noting that “labor”
    includes “[p]hysical or mental toil” (cleaned up)); Ex parte Messer, 
    99 So. 330
    , 333 (Fla.
    1924) (“Labor, according to recognized authority, includes mental effort and intellectual
    exertion, as well as physical toil.”).
    24
    USCA4 Appeal: 21-1160       Doc: 33          Filed: 04/26/2023     Pg: 25 of 34
    v. Clayton Cnty., 
    140 S. Ct. 1731
    , 1737 (2020). “Only the written word is the law, and all
    persons are entitled to its benefit.” 
    Id.
    To be clear, I do not entirely fault my colleagues for attempting to read labor as it
    was employed under the Heard Act. I wholly agree that “statutes addressing the same
    subject matter generally should be read ‘as if they were one law.’” See Wachovia Bank v.
    Schmidt, 
    546 U.S. 303
    , 316 (2006) (quoting Erlenbaugh v. United States, 
    409 U.S. 239
    ,
    243 (1972)). But the manner in which the majority employs that principle—and the
    conclusion derived therefrom—contrives its purpose to evade what ought to be forgone
    conclusions: that the Miller Act must be liberally construed, and it must be construed in
    the temporal context of 1935.
    When enacted in 1935, the Miller Act repealed the Heard Act of 1894. See MacEvoy
    Co., 
    322 U.S. at 105
     (observing that, although it “reinstated its basic provisions[,]” the
    Miller Act repealed the Heard Act). Because the Heard Act was technically rendered null,
    we must examine the meaning of labor as it stood in 1935, the year of the Miller Act’s
    passage. See Wis. Cent. Ltd. v. United States, 
    138 S. Ct. 2067
    , 2070 (2018) (“[O]ur job is
    to interpret the words consistent with their ‘ordinary meaning . . . at the time Congress
    enacted the statute.’” (quoting Perrin v. United States, 
    444 U.S. 37
    , 42 (1979))). Nothing
    in the Miller Act provides that Congress intended to incorporate a definition of labor that
    existed over four decades earlier, and yet the majority does just that. 4 Unlike the majority’s
    4
    Again, even pre-Miller Act, some state courts did not subscribe to the majority’s
    restricted meaning of labor. See Crook, 136 S.E. at 567; Ex parte Messer, 99 So. at 333.
    And as I discuss shortly, federal courts never directly addressed the issue. See infra Part
    (Continued)
    25
    USCA4 Appeal: 21-1160       Doc: 33         Filed: 04/26/2023     Pg: 26 of 34
    approach, my reading of the Miller Act ensures that it remains true to its era, as well as
    “highly remedial and . . . construed liberally.” Fleisher Eng’g & Constr. Co. v. U.S. ex rel.
    Hallenbeck, 
    311 U.S. 15
    , 17 (1940) (citations omitted).
    C.
    Not only do my colleagues give short shrift to the plain meaning of labor, but they
    enlarge Maxwell beyond its scope. Maxwell simply has nothing to do with dictating the
    definitive meaning of labor. See 
    222 F. at
    798–800.
    In Maxwell, a contractor “entered into a contract with the United States for the
    construction of a post office building at Clifton Forge, Va.” 
    Id. at 798
    . One of the
    contractor’s employees “superintended the work of building the post office.” 
    Id.
     The
    employee alleged that he never received his full salary for his work on the project, so he
    intervened in an action that was brought against the contractor and its surety to recover
    sums for unpaid accounts that were used to obtain the project’s materials. 
    Id.
     at 798–99.
    The district court issued a decree in favor of the employee for $1,270.27, the entire amount
    of his claim. 
    Id. at 799
    .
    I.C. Because federal and state courts never laid down an established or settled meaning of
    labor, I cannot apply the statutory-construction presumption of “when ‘judicial
    interpretations have settled the meaning of an existing statutory provision, repetition of the
    same language in a new statute indicates, as a general matter, the intent to incorporate
    its . . . judicial interpretations as well.’” Merrill Lynch, Pierce, Fenner & Smith Inc. v.
    Dabit, 
    547 U.S. 71
    , 85–86 (2006) (quoting Bragdon v. Abbott, 
    524 U.S. 624
    , 645 (1988)).
    Despite the fact that there is no settled meaning of labor, the majority effectively applies
    the presumption anyway.
    26
    USCA4 Appeal: 21-1160       Doc: 33        Filed: 04/26/2023     Pg: 27 of 34
    On appeal to this Court, the surety argued that the contractor’s employee “was
    not . . . a laborer within the meaning of the [Heard Act].” 
    Id. at 799
    . Relying in part on
    Mining Co. v. Cullins, 
    104 U.S. 176
     (1881), we held that the employee’s supervisory work,
    which included some physical toil, fell within the “purview of the statute.” Maxwell, 
    222 F. at 800
    . We relied upon the employee’s deposition in which he “state[d] positively that
    he was employed as working foreman, and that as such it was his duty ‘to go among the
    men and actually build the building.’” 
    Id.
    Importantly, neither Maxwell nor Cullins even applied the Miller Act—the more
    recent of the two applied the Heard Act two decades pre-Miller Act in the context of
    woefully dated conceptions of labor. Furthermore, even if we turn a blind eye to these
    obvious concerns, Maxwell does not limit labor to only physical exertion and bodily toil or
    the supervision thereof. Rather, Maxwell makes no attempt to construe labor in its own
    right. See 
    222 F. at
    799–800. It never announced a general rule specifying certain
    categories of exertion, supervision, or toil as the only labor actionable under the Heard
    Act. 5, 6 See 
    id.
     at 799–800.
    5
    Perplexingly, the majority frames Maxwell as having “already answered the
    question” of labor’s definition, while simultaneously acknowledging that the case provides
    no explicit guidance, thus “[w]e must read between the lines.” Majority Op. 9. To my
    mind, the position that precedent illuminates our path forward and the position that said
    precedent is ambiguous—at best—are mutually exclusive.
    6
    The majority also invokes Church of the Holy Trinity v. United States, 
    143 U.S. 457
     (1892), as supporting its position given that “labor” under the Alien Contract Labor
    Law was held to require a manual component, thus tracking with the majority’s readings
    of Cullins and Maxwell. This reliance is hardly persuasive. First, Holy Trinity’s
    interpretation of labor precedes the Miller Act by over four decades and fails to reflect
    (Continued)
    27
    USCA4 Appeal: 21-1160       Doc: 33          Filed: 04/26/2023      Pg: 28 of 34
    Instead, Maxwell turned on an employee’s deposition testimony. See 
    id.
     In addition
    to stating that “it was his duty ‘to go among the men and actually build the building,’” the
    employee testified that “there wasn’t a stone, nor a sash, piece of iron, piece of trim, or a
    part of the heating or electric light plant that I did not actually assist in placing in the
    building.” Id. at 800. Maxwell compels us to inquire as to the circumstances of an
    individual’s work—nothing more and nothing less.
    In this respect, Maxwell faithfully followed Cullins. Cullins, 
    104 U.S. at
    177–79.
    But Cullins likewise never reached what labor does or does not mean under the Miller Act.
    See 
    id.
     First, Cullins interpreted a Utah statute that governed miner’s liens—not the Miller
    Act. 
    Id. at 176
    . Further, like Maxwell, Cullins only decided that a particular individual’s
    work qualified as labor based upon the case’s specific facts. 
    Id.
     I do not fault Maxwell for
    undertaking a similar analysis as Cullins, but neither dictates a particular result here.
    society’s conception of the term at the time of the Miller Act’s promulgation—a
    consideration at the heart of our statutory-interpretation analysis. See George, 946 F.3d at
    645. Furthermore, statutory context matters. It cannot reasonably be said that the
    legislature’s goals in crafting immigration legislation are sufficiently similar to its goals in
    crafting remedies for nonpayment on federal construction projects such that shared terms
    necessarily share implications.
    28
    USCA4 Appeal: 21-1160       Doc: 33         Filed: 04/26/2023      Pg: 29 of 34
    II.
    Employing a definition of labor that includes “mental exertion” and “mental toil,” I
    would hold that Dickson’s materials inventory on February 8, 2019, amounts to actionable
    labor for purposes of the Miller Act’s statute-of-limitations period. 7
    As it concerns the materials inventory, the uncontroverted evidence is that Dickson
    “traveled to the site to conduct the onsite inventory and verification at the direction and
    request of the [Washington Headquarters Services of the United States Department of
    Defense (WHS)].” J.A. 305. The materials inventory required him to “manipulate various
    items of the inventory left on site, then take a physical inventory [of] the items left on site
    which had not been incorporated into the Project yet, and thereafter . . . ascribe values to
    the inventory in a Schedule of Values.” J.A. 305. He provides an example of his labor that
    day: “I had to determine the amount of Schedule 40 pipe which had been incorporated into
    the project which required [me] to physically inspect and take measurement[s] of the work
    completed.” J.A. 305. At WHS’s direction, Dickson clearly engaged in “mental exertion”
    and “mental toil” on February 8, 2019, by conducting the inspection, measuring materials,
    and eventually creating a Schedule of Values in furtherance of the project. He thus
    performed labor in accordance with my conceptualization of the term.
    7
    I readily agree with the majority that Dickson provided labor before February 8,
    2019, which included: taking out the trash, conducting measurements, watering concrete,
    reinforcing steel, physically inspecting materials, and supervising workers. J.A. 302, 908–
    10 (Dickson describing his various duties).
    29
    USCA4 Appeal: 21-1160        Doc: 33          Filed: 04/26/2023      Pg: 30 of 34
    But he also satisfied the majority’s requirement of physical exertion and bodily toil
    when he “manipulate[d] various items” during the inspection and inventory. J.A. 305. The
    majority echoes the district court’s conclusion that Dickson’s manipulation of various
    items was primarily clerical or administrative in nature, and thus not cognizable as labor
    under the Miller Act. This conclusion, however, is irreconcilable with the majority’s
    definition of labor. If all that labor under the Miller Act textually requires is that (1) a
    claimant performed some work, and (2) that work involved physical exertion or bodily
    toil—or the supervision thereof—then the clerical goal of a task is entirely irrelevant. See
    
    40 U.S.C. § 3133
    (b)(1) (also requiring that the labor must be performed in furtherance of
    the contracted-for job).
    Even if the majority’s definition of labor left room for a clerical exception, the sorts
    of non-actionable tasks that I perceive as truly administrative or clerical are, by way of
    example, tasks relating to overhead like payroll or headquarters bills. To be sure, the ability
    to perform work relies on the completion of such background tasks, but they exist wholly
    untethered from a discrete job or contract, and they more directly relate to the profitability
    of the performing entity itself rather than the completion of a contracted-for project.
    Dickson’s work was of an entirely different nature. He physically exerted himself, on the
    jobsite, at the behest of WHS, for a purpose that directly furthered that entity’s project
    goals.
    Furthermore, it cannot reasonably be said that manipulating pipe or other items with
    one’s own two hands does not involve at least some amount of physical exertion. And
    nothing in the Miller Act lends itself to the idea that some exertion is cognizable while
    30
    USCA4 Appeal: 21-1160      Doc: 33          Filed: 04/26/2023     Pg: 31 of 34
    other exertion is not. Yet the majority’s approach to Dickson’s labor implicitly relies on
    just such an amorphous spectrum of physicality. Did he not exert enough pounds of force
    on the items that he manipulated? Did the items only shift a few inches rather than a few
    feet? We lack both the nuanced details of his exertion, as well as a practical way of
    evaluating sufficiency such that the majority’s definition of labor offers a workable
    approach.
    In addition to its resounding absence from the text of the Miller Act, an arbitrarily
    gauged physicality requirement corrupts any sound application of the Act in the context of
    modern construction.     Consider, for example, the operation of a modern excavator,
    bulldozer, crane, drum roller, haul truck, grader, or even the formidable earth-moving
    scraper. These vehicles often serve as the bedrock of modern construction in heavy-civil
    contexts—contexts to which the Miller Act is essential.          But the operators of such
    machinery, particularly in models manufactured in the last decade or so, effectuate
    substantial labor by lifting hardly more than a hand, and sometimes little more than a finger.
    Envisioning the cab of a modern excavator, an operator need only manipulate two joysticks
    to perform many impressive feats. Surely it cannot be said that such operators fail to
    perform actionable labor under the Miller Act. And yet, applying the majority’s approach,
    Dickson physically exerted himself as much or more by lifting and handling inventory
    31
    USCA4 Appeal: 21-1160         Doc: 33      Filed: 04/26/2023     Pg: 32 of 34
    items than many operators of modern equipment would in the course of displacing ton after
    ton of aggregate. 8
    Put differently, my analogy to modern construction equipment bears two
    conclusions. First, insufficient grounds exist to disqualify Dickson’s claim for his having
    not physically exerted himself enough. If physical exertion is the touchstone of this
    analysis, as the majority purports it to be, then Dickson’s inventory handily qualifies,
    particularly when it would defy commonsense to exclude other activities (like equipment
    operation) performed with even less physical exertion than that required by Dickson’s
    work. Second, the modern era demands a more judicious approach to labor than the
    majority’s narrow view. If an individual must surpass a threshold of physicality under the
    Miller Act to have a cognizable claim, then the Act no longer coexists with the realities of
    modern construction, and its remedy falls to pieces as applied to countless situations. In
    other words, the analogy bespeaks the impracticality of the majority’s position as applied
    to both the instant dispute and modern building. 9 Thus, recognition of a mental component
    to labor is essential to the Miller Act’s continued viability after nearly a century of
    successfully effectuating subcontractor protections on federal projects.
    Similarly troubling comparisons could be drawn between Dickson’s task and tasks
    8
    completed by other laborers with the aid of powered hand-tools.
    9
    Even in 1935, the majority’s physicality test would have excluded plenty of
    actionable, machine-aided labor, thus further bespeaking the necessity of a broader
    definition of the term—consistent with how it was surely understood at the time.
    32
    USCA4 Appeal: 21-1160       Doc: 33          Filed: 04/26/2023    Pg: 33 of 34
    Turning to the Miller Act’s statute-of-limitations bar, Dickson’s suit cannot proceed
    unless it was filed “no later than one year after the day on which the last of the labor was
    performed.” 
    40 U.S.C. § 3133
    (b)(4). Because I view Dickson’s work on February 8, 2019,
    as actionable labor, he had until February 8, 2020, to file the instant suit. 10 He met that
    deadline when he filed his civil action on February 5, 2020. Consequently, I would hold
    that the Miller Act’s statute of limitations does not bar Dickson’s claim, and I would reverse
    the district court’s opposite conclusion. 11
    III.
    I see no justification for circumscribing the meaning of labor as the majority does
    today. The majority’s contrived standard ignores the relevant definitions of labor that
    existed during the Miller Act’s enactment, and it also contradicts our common sense in
    10
    The majority notes that it is “unclear whether the work [on February 8] was
    ‘provided for in the contract’ because it was performed after the contract was terminated.”
    Majority Op. 16 n.8 (quoting § 3131(b)(2)). But the record seems clear. On December 20,
    2018, WHS told Dickson that he “must provide an inventory of all materials on-site and at
    any off-site locations as soon as practicable, but not later than 31 Dec 2018.” J.A. 1113
    (emphasis added). By January 31, 2019, WHS told Dickson that it never received a
    materials invoice, and by February 8, 2019, it again requested this submission. See J.A.
    1126–28. WHS then provided Dickson with another extension to submit the materials
    invoice. See J.A. 1125 (“The due date is extended from 5 PM ET on 11 Feb 2019 to 5 PM
    ET on 14 Feb 2019.”). So WHS repeatedly extended Dickson’s contractual obligations as
    Fidelity seems to virtually concede in its briefing. Fidelity’s Resp. Br. 4 (“[T]he Owner
    allowed FEI until February 11, 2019 to submit the requested materials inventory under a
    full reservation of rights, including the contractually required completion date of
    December 31, 2018.” (emphasis added) (citing J.A. 1127)).
    11
    At oral argument, Fidelity conceded that Dickson’s suit was timely if he
    performed qualifying labor on February 8, 2019.
    33
    USCA4 Appeal: 21-1160      Doc: 33         Filed: 04/26/2023      Pg: 34 of 34
    2023. Labor is a broad term that captures both an individual’s physical and mental
    exertion. And indeed, it contemplates the very mental energies that my colleagues and I
    have expended in fashioning these respective opinions.
    Because I view labor as encompassing far more than the majority, I would reverse
    the district court’s grant of summary judgment to Fidelity and remand this case with
    instructions to the court to grant summary judgment in favor of Dickson on the meaning of
    labor, which would preclude Fidelity’s statute-of-limitations defense. Alternatively, I
    would hold that Dickson’s inventory was sufficiently physical to qualify as labor even
    under the majority’s restrictive definition and remand with the same instructions. 12 I would
    then allow the district court—in the first instance—to determine the proper amount of
    Dickson’s damages or to proceed to a damages trial if appropriate. I respectfully dissent.
    12
    At the very least, assuming application of the majority’s definition of labor, I
    would hold that a genuine factual dispute exists as to the degree of physicality in which
    Dickson engaged during the inventory, thereby precluding summary judgment.
    34
    

Document Info

Docket Number: 21-1160

Filed Date: 4/26/2023

Precedential Status: Precedential

Modified Date: 4/27/2023

Authorities (36)

Sylvia Development Corp. v. Calvert County , 48 F.3d 810 ( 1995 )

Bankers' Surety Co. of Cleveland v. Maxwell , 222 F. 797 ( 1915 )

N. Brown FELTY, Plaintiff-Appellant, v. GRAVES-HUMPHREYS ... , 818 F.2d 1126 ( 1987 )

The United States of America for the Use of Magna Masonry, ... , 709 F.2d 249 ( 1983 )

United States v. Wood , 99 F.2d 80 ( 1938 )

United States v. Abdelshafi , 592 F.3d 602 ( 2010 )

Brockway v. Innes , 39 Mich. 47 ( 1878 )

Knight v. Norris , 13 Minn. 473 ( 1868 )

United States v. Seaboard Surety Co. , 26 F. Supp. 681 ( 1938 )

American Surety Co. of New York v. United States ex rel. ... , 76 F.2d 67 ( 1935 )

Title Guaranty & Trust Co. v. Puget Sound Engine Works , 163 F. 168 ( 1908 )

United States ex rel. T.M.S. Mechanical Contractors, Inc. v.... , 942 F.2d 946 ( 1991 )

Price v. Kirk , 90 Pa. 47 ( 1879 )

Field Slocomb v. Mineral Water Co. , 25 R.I. 319 ( 1903 )

Clifford F. MacEvoy Co. v. United States Ex Rel. Calvin ... , 64 S. Ct. 890 ( 1944 )

Mining Co. v. Cullins , 26 L. Ed. 704 ( 1881 )

Church of the Holy Trinity v. United States , 12 S. Ct. 511 ( 1892 )

Title Guaranty & Trust Co. of Scranton v. Crane Co. , 31 S. Ct. 140 ( 1910 )

Fleisher Engineering & Construction Co. v. United States Ex ... , 61 S. Ct. 81 ( 1940 )

United States Ex Rel. Sherman v. Carter Constr. Co. , 77 S. Ct. 793 ( 1957 )

View All Authorities »