Superior Derrick Svcs, L.L.C. v. Lonestar 203, et , 547 F. App'x 432 ( 2013 )


Menu:
  •      Case: 12-30904       Document: 00512426170         Page: 1     Date Filed: 10/31/2013
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    October 31, 2013
    No. 12-30904                        Lyle W. Cayce
    Clerk
    SUPERIOR DERRICK SERVICES, L.L.C.,
    Plaintiff - Appellee - Cross- Appellant
    v.
    LONESTAR 203, her engines, boilers, tackle, furniture, apparel, etc., in rem;
    LONESTAR 204, her engines, boilers, tackle, furniture, apparel, etc., in rem,
    Defendants - Appellants - Cross Appellees
    v.
    INTERCONTINENTAL BANK, P.L.C.; LONESTAR DRILLING NIGERIA,
    LIMITED,
    Claimants - Appellants - Cross - Appellees
    Appeals from the United States District Court
    for the Western District of Louisiana
    USDC No. 6:09-CV-484
    Before REAVLEY, ELROD, and, HAYNES, Circuit Judges.
    PER CURIAM:*
    *
    Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH CIR.
    R. 47.5.4.
    Case: 12-30904     Document: 00512426170        Page: 2   Date Filed: 10/31/2013
    No. 12-30904
    This appeal involves breach of contract claims arising from agreements
    between Superior Derrick Services, Inc. (“Superior”) and Lonestar Drilling
    Nigeria, Ltd. (“Lonestar”) for the refurbishment of two drilling barges. Although
    the parties entered into separate contracts covering different scopes of work, the
    common purpose of all the agreements was for Superior to complete the barge
    work so that Lonestar could employ the barges on a drilling job in Nigeria. The
    district court granted partial summary judgment in favor of Superior on what
    was known as the “Turnkey agreement” because of Lonestar’s failure to pay the
    contract price, and it dismissed Lonestar’s counterclaims. The court conducted
    a bench trial on Superior’s remaining claims, allowing some of them but
    disallowing others. Both parties appeal. We AFFIRM.
    I.
    In April 2006, Superior and Lonestar entered into two identical Barge
    Refurbishment Agreements (“the Refurbishment Agreements”) for Superior to
    perform refurbishment work on two drilling barges known as LONESTAR 203
    and LONESTAR 204. The contract price was $14,490,462 for each barge. The
    Refurbishment Agreements set forth the scope of work by Superior but they did
    not include all of the work necessary for the refurbishment. According to the
    trial testimony, Lonestar reserved to itself some of this work. The barges were
    delivered to Superior’s facility in New Iberia, Louisiana, where the project would
    be completed. Pursuant to the contract, Lonestar employees were given office
    space at the facility and access to the job site.
    The project was beset almost immediately by disputes and delays related
    to the scope of the work, the time line for completion, and payment. During the
    course of the job more than one hundred written change orders were issued
    altering the scope of Superior’s work, some of which included work that Lonestar
    was originally supposed to perform. As a result of the numerous change orders,
    the parties verbally agreed in April 2007 that Superior would undertake
    2
    Case: 12-30904    Document: 00512426170     Page: 3   Date Filed: 10/31/2013
    No. 12-30904
    additional work outside the original scope of the Refurbishment Agreements
    under a time and materials arrangement (the “Time and Materials agreement”).
    Unfortunately for the parties, this Time and Materials agreement did not resolve
    the problems. Superior believed that it was owed a substantial amount of money
    under the Time and Materials agreement, while Lonestar claimed that Superior
    unreasonably delayed the work and that funding was not a legitimate issue. At
    one point in December 2007, Superior threatened to shut down the project and
    stop working in a dispute over payment of $3 million for change orders.
    By February 2008, Superior claimed in correspondence that Lonestar owed
    it more than $5 million for change orders related to the work under the Time
    and Materials agreement. In an effort to resolve their ongoing dispute, the
    parties met on March 11, 2008, and agreed to abandon the Time and Materials
    agreement and continue the project under a written turnkey agreement (the
    “Turnkey” or “Turnkey contract”).
    The Turnkey contract specifically stated that it was meant to replace the
    Time and Materials agreement but not to alter the original scope of the work set
    forth in the Refurbishment Agreements. The Turnkey, which essentially settled
    the parties’ differences over the amounts due under the Time and Materials
    agreement, set forth a scope of work and provided for payment to Superior. The
    Turnkey scope of work included both work already completed and work yet to be
    done. After providing for various credits to Lonestar, a Turnkey price was
    established. In relevant part, the Turnkey indicated that the “total outstanding
    monies due to [Superior] and payable to [Superior] by [Lonestar] on account of
    [Superior’s] claims on the discarded Time and Materials arrangement, . . . after
    the payment on account of $5,400,000 . . . is $3,396,901.37.” The Turnkey stated
    that “save and except for this amount” Lonestar “is not indebted and [Superior]
    is not entitled to any further claim or amount.” The Turnkey referenced an
    3
    Case: 12-30904     Document: 00512426170     Page: 4   Date Filed: 10/31/2013
    No. 12-30904
    attached “Final Reconciliation,” which also set forth a “Balance due and payable
    to Superior” of $3,396,901.37.
    The parties executed the Turnkey on March 26, 2008, but they made it
    effective as of December 28, 2007. Lonestar made the $5.4 million payment on
    account in March, and in April 2008 it also made a partial payment to Superior
    of $396,901.37, leaving an even $3 million owed under the Turnkey. In the
    ensuing months, the parties’ dispute continued over the scope of the work, delays
    in the project, and payment due, and more change orders were issued. On April
    15 and May 20, 2008, Superior sent emails to Lonestar asking about the money
    still due under the Turnkey, while Lonestar continued to complain about alleged
    project delays. In October 2008, Superior made a demand for payment, but no
    further payment under the Turnkey has ever been made.
    In March 2009, Superior filed an in rem complaint, asserting maritime
    liens and requesting arrest of the barges. Superior claimed that it was owed
    damages of approximately $8 million under both the original Refurbishment
    Agreements and the Turnkey. Lonestar counterclaimed against Superior for
    contractual delay damages of approximately $28 million. Prior to trial, the
    district court held in a partial summary judgment ruling that Lonestar breached
    the Turnkey and owed Superior $3 million under that contract because Lonestar
    had not paid the Turnkey price immediately upon execution of the agreement.
    Because of Lonestar’s breach, the district court also dismissed Lonestar’s
    counterclaims for delay damages.
    After a subsequent bench trial, the district court held that Superior
    suffered damages from breach of the Refurbishment Agreements in the amount
    of $5,667,554.25. Because Superior had completed 97% of the work under the
    contract, however, it allowed Lonestar a three percent credit off the price of the
    Refurbishment Agreements. The court awarded Superior $4,798,126.53. Both
    parties appeal.    Lonestar challenges the district court’s dismissal of its
    4
    Case: 12-30904     Document: 00512426170      Page: 5   Date Filed: 10/31/2013
    No. 12-30904
    counterclaims in the summary judgment ruling and the court’s failure to apply
    a larger credit on the Refurbishment Agreements. Superior challenges the
    court’s disallowance of certain claims under the Refurbishment Agreements, as
    well as its claims for extra-contractual work purportedly done under verbal
    agreements. Superior also challenges the court’s calculation of interest. We first
    address Lonestar’s appeal before turning to Superior’s arguments.
    II.
    We review de novo the district court’s ruling on summary judgment.
    Haverda v. Hays Cnty., 
    723 F.3d 586
    , 591 (5th Cir. 2013). In an admiralty case
    tried to the bench, we review the district court’s legal conclusions de novo and
    its factual findings for clear error. Stevens Shipping & Terminal Co. v. JAPAN
    RAINBOW II MV, 
    334 F.3d 439
    , 443 (5th Cir. 2003).
    III.
    A.
    As a preliminary matter, the parties dispute which law governs this
    appeal. Although the Barge Refurbishment Agreements contained a choice-of-
    law clause designating Louisiana law as controlling the contracts, the Turnkey
    contract did not contain such a clause. Lonestar contends that federal maritime
    law should therefore apply to the Turnkey. The Turnkey contract specifically
    refers to the Refurbishment Agreements, however, and provides that, with the
    exception of certain paragraphs related to payment and the scope of work, the
    Turnkey does not alter or void any provisions of the original Refurbishment
    Agreements. The Louisiana choice-of-law provision was thus not affected.
    Although the Turnkey was a separate contract, we agree with the district court
    that the Turnkey incorporated the choice-of-law clause, and Louisiana law
    applies. See, e.g., One Beacon Ins. Co. v. Crowley Marine Servs., Inc., 
    648 F.3d 258
    , 267 (5th Cir. 2011); see also 11 Williston on Contracts § 30:25 (4th ed. 2013)
    (“When a writing refers to another document, that other document, or the
    5
    Case: 12-30904    Document: 00512426170     Page: 6    Date Filed: 10/31/2013
    No. 12-30904
    portion to which reference is made, becomes constructively a part of the writing,
    and in that respect the two form a single instrument.”).
    Lonestar argues that the district court erroneously concluded that it
    breached the Turnkey, thereby requiring dismissal of its counterclaims for delay
    damages, because it did not immediately pay $3 million due under the
    agreement. Lonestar contends that the “due and payable” language of the
    Turnkey was ambiguous and that it was not required to pay until the scope of
    work was complete. We agree with the district court that “due and payable”
    under the circumstances of this case established a debt that was presently due,
    not an amount that was to be paid only upon completion of the work.
    Lonestar points to dictionary definitions of the words “due” and “payable”
    as support for its claim that the terms are ambiguous. Words in a contract are
    given their “generally prevailing meaning.” LA. CIV. CODE art. 2047. We have
    previously acknowledged that “payable” “normally means that the debt is
    payable at once.” In re Ripley, 
    926 F.2d 440
    , 444 (5th Cir. 1991) (Internal
    quotation marks and citation omitted). But rather than consider the terms of a
    contract in a vacuum, we must also look at the contract as a whole and interpret
    its provisions in light of each other. See LA. CIV. CODE art. 2050. Here, the
    Turnkey contract referred to the “total outstanding” money due from Lonestar
    to Superior and noted that this was the amount for which Lonestar was
    “indebted.” The Final Reconciliation attached to the Turnkey provided for a $5.4
    million payment on account for work already completed and left a “balance due
    and payable” of $3.39 million. Taken together, these terms show that the
    outstanding amount for which Lonestar was indebted to Superior, assuming the
    $5.4 million payment on account, was $3.39 million, which is the amount left
    “due and payable” at the time of the contract in March 2008. We need not
    resolve whether the amount was due on March 11, when the parties met and
    agreed to the Turnkey, or on March 26, when the parties formally executed the
    6
    Case: 12-30904     Document: 00512426170      Page: 7   Date Filed: 10/31/2013
    No. 12-30904
    Turnkey. The fact remains that the Turnkey’s terms in the context of the whole
    contract refer to a presently owed debt.
    Any doubt about this meaning is resolved against Lonestar because a
    presently owed debt rather than a debt to be paid in the future is consistent with
    the parties’ conduct both before and after the Turnkey. See LA. CIV. CODE art.
    2053 (“A doubtful provision must be interpreted in light of the nature of the
    contract, equity, usages, the conduct of the parties before and after the formation
    of the contract, and of other contracts of a like nature between the same
    parties.”). Prior to the Turnkey agreement, the record shows a dispute between
    the parties about payment and supports Superior’s contention that it had not
    been paid for a significant amount of work under the Time and Materials
    agreement. Superior clearly expected immediate payment of amounts due as
    part of continuing to work under the Turnkey.
    This conclusion is supported by a pre-Turnkey letter dated February 27,
    2008, from Lonestar’s Chief Idisi to Superior in which Idisi affirmed that
    Lonestar expected to release $5.4 million to Superior and that the “balance if any
    would be paid” after Idisi’s trip to Louisiana on March 10. Indeed, Idisi did
    travel to Louisiana on March 10. On March 11, he met with Superior and agreed
    to the Turnkey contract, which was a formalization of the parties’ discussions to
    that point. Then, after execution of the Turnkey, Lonestar paid the $5.4 million
    as promised and also made a partial payment on the $3.39 million balance. If
    there was no debt presently owed and the Turnkey balance was not due until
    completion of the work, Lonestar would not have been required to make the
    partial payment. Lonestar provides no other explanation for why it did so.
    Moreover, Superior made repeated inquiry of Lonestar (in April, May, and
    October 2008) about payment of the Turnkey amount. Although early inquiries
    were more like friendly reminders rather than terse demands for payment, these
    inquiries would have been unnecessary and unwarranted if an amount was not
    7
    Case: 12-30904     Document: 00512426170    Page: 8   Date Filed: 10/31/2013
    No. 12-30904
    presently due. Indeed, Lonestar points to no contemporaneous responses to
    those inquiries indicating its belief that the Turnkey amounts were not due until
    some future date. Instead, Lonestar’s responses merely reiterated Lonestar’s
    complaint that Superior was delaying the work. These circumstances show that
    the balance under the Turnkey contract was presently due, that the parties
    knew and expected that the balance was due, but that Lonestar breached the
    Turnkey contract by failing to pay.
    As a result of Lonestar’s failure to pay the amount owed under the
    Turnkey, we can find no fault in the district court’s dismissal of Lonestar’s
    counterclaims for delay damages. “Louisiana recognizes the principle that where
    one party substantially breaches a contract the other party to it has a defense
    and an excuse for non-performance.” Olympic Ins. Co. v. H. D. Harrison, Inc.,
    
    463 F.2d 1049
    , 1053 (5th Cir. 1972). In other words, having failed to make
    payment as required by the contract, Lonestar cannot complain and seek
    damages because Superior did not deliver the barges when Lonestar wanted
    them.
    Lonestar makes essentially two arguments in response to the district
    court’s finding that its breach of the Turnkey contract excused Superior’s
    performance and mandated dismissal of its counterclaims. It argues in part that
    its counterclaims included claims for damages under both the Turnkey contract
    and the original Refurbishment Agreements, as well as a claim that Superior
    wrongfully refused to return the barges without a release of liability. Lonestar
    argues that its claims for damages arising under the Refurbishment Agreements
    and for Superior’s failure to return the barges are independent of the Turnkey
    contract, and therefore the claims should not have been dismissed. Lonestar did
    not raise this argument in opposition to Superior’s motion for summary
    judgment, however, and may not raise it on appeal. See Colony Creek, Ltd. v.
    Resolution Trust Corp., 
    941 F.2d 1323
    , 1326 (5th Cir. 1991) (“Appellants ‘cannot
    8
    Case: 12-30904     Document: 00512426170       Page: 9   Date Filed: 10/31/2013
    No. 12-30904
    attack summary judgment on appeal by raising distinct issues that were not
    before the district court.’” (citation omitted)). Lonestar doubly waived this
    argument on appeal by raising it only in its reply brief. See, e.g., Valle v. City of
    Houston, 
    613 F.3d 536
    , 544 n.5 (5th Cir. 2010).
    Lonestar also argues that, by continuing to perform under the Turnkey
    contract, Superior waived any claim that Lonestar’s failure to pay the amount
    due excused Superior’s alleged untimely performance. Lonestar further argues
    that Superior did not place it on notice that because of Lonestar’s failure to pay
    Superior considered the contract dissolved or its own performance excused. We
    are unpersuaded.
    Here, Lonestar failed to pay the Turnkey amount that was owed and that
    Superior was entitled to receive. Although Superior continued to perform work
    on the barges (which it was still required to do under the Refurbishment
    Agreements), it did not merely accept Lonestar’s deficient performance.
    Superior inquired more than once about Lonestar’s missing payment. Superior
    did not waive its right to insist on payment owed and due under the contract.
    Cf. 8 Corbin on Contracts § 40.5, at 544–45 (Revised Edition 1999) (recognizing
    that a builder’s continuing to perform after non-payment “does not mean that
    the builder must now continue to wait forever”); see also La. Highway Comm’n
    v. Farnsworth, 
    74 F.2d 910
    , 914 (5th Cir. 1935).
    B.
    Next, Lonestar and Superior both challenge the district court’s credit to
    Lonestar of three percent of the contract price in the Refurbishment Agreements
    because Superior had completed only 97% of the work assigned to it. The
    Refurbishment Agreements contained a schedule of progress payments calling
    for a final payment of $2,120,231 per barge “[at] completion.” Lonestar reasons
    that because the barges were not complete Superior was not entitled to any of
    the final payment and the court should have credited it the full amount of
    9
    Case: 12-30904     Document: 00512426170       Page: 10    Date Filed: 10/31/2013
    No. 12-30904
    $4,240,462 for both barges. As part of its cross-appeal, Superior argues that
    because it substantially completed the barges, it was entitled to full payment of
    the price under the Refurbishment Agreements. It contends that Lonestar was
    not entitled to any credit at all unless it produced evidence showing the nature
    and extent of the unfinished work and the amount of the costs to Lonestar to
    complete the work.
    Under Louisiana law, a contractor who substantially performs on a
    building contract is entitled to recover the contract price even though defects or
    omissions may be present. See Airco Refrigeration Serv., Inc. v. Fink, 
    134 So. 2d 880
    , 882 (La. 1961); Rice v. Mesa Gen. Contractor, L.L.C., 
    986 So. 2d 122
    , 129
    (La. Ct. App. 2008). The owner may have “the price reduced by the amount
    necessary to perfect or complete the work, i.e. damages attributable to the
    [contractor’s] breach” by failing to perform the contract completely. Neel v.
    O’Quinn, 
    313 So. 2d 286
    , 290 (La. Ct. App. 1975).
    Substantial performance occurs when a building or other construction may
    be used for the purpose intended despite defects or omissions in the construction.
    
    Id. “[T]his is
    a question of fact for the trial judge.” 
    Rice, 986 So. 2d at 129
    ; 
    Neel, 313 So. 2d at 290
    . “Among the facts to be considered include the extent of the
    defect or non-performance, the degree to which the purpose of the contract is
    defeated, the ease of correction, and the use or benefit to the owner of the work
    performed.” 
    Neel, 313 So. 2d at 290
    . The contractor bears the burden of proving
    substantial performance, while the owner bears the burden of proving the
    existence and nature of alleged defects. 
    Id. In the
    instant case, evidence from both sides supports the district court’s
    finding that Superior had completed at least 97% of the work on the barges.
    Lonestar’s project manager, Howard Berisford, admitted in a deposition that the
    work was 97% complete when the barges were arrested, while Superior’s general
    10
    Case: 12-30904    Document: 00512426170       Page: 11   Date Filed: 10/31/2013
    No. 12-30904
    manager, Andy Gardner, estimated the work was 99% to 100% complete. The
    court’s acceptance of the 97% figure is not clearly erroneous.
    Although Lonestar agreed that 97% of the work was completed, there was
    contradictory testimony about which tasks had been performed and when, as
    well as what was supposed to be in the scope of work. The district court was
    required to resolve the contradictory evidence, and by doing so it at least
    implicitly found substantial performance. See, e.g., Karno v. Bourbon Burlesque
    Club Inc., 
    931 So. 2d 1111
    , 1120 (La. Ct. App. 2006) (finding no error in a trial
    court’s implicit finding of substantial performance); see also United States ex rel.
    Riley v. Diran Co., 
    597 F.2d 446
    , 448 (5th Cir. 1979) (affirming district court’s
    finding that substantial performance occurred where subcontractor had
    performed at least 90% of masonry work required in contract). The burden then
    fell to Lonestar to prove its damages and what it had to do to complete the work.
    Lonestar presented the testimony of John Esiegbuya that Lonestar spent $15
    million to complete the work that Superior allegedly failed to perform. There
    was no documentary evidence, such as contracts, invoices, or payment vouchers,
    supporting Esiegbuya’s testimony.
    In any event, the scope of work required for completing the vessels was
    also a highly contested point, as the parties disputed the contractual
    requirement for the barges’ status at completion. Lonestar believed the barges
    were supposed to be fully functional and meet the specifications of the American
    Bureau of Shipping classification society (“ABS class”), while Superior took the
    position that its scope of work did not require it to meet ABS class specifications.
    In fact, the contracts do not specifically state that the barges are to be ABS
    classed and fully functional, although certain items in the Turnkey refer to ABS.
    But Esiegbuya also testified that had Superior performed the intended work
    under the contracts (i.e., the Refurbishment Agreements and the Turnkey), the
    barges would have been ABS classed and fully operational. If that is so, the
    11
    Case: 12-30904     Document: 00512426170      Page: 12   Date Filed: 10/31/2013
    No. 12-30904
    starting point must be the contract price, and without non-speculative evidence
    of actual costs incurred above the contract price, Lonestar must settle for a
    reduction of the contract price for the percentage of uncompleted work, as
    calculated by the district court. Cf. Ducote v. Arnold, 
    416 So. 2d 180
    , 183 (La.
    Ct. App. 1982) (“[T]he damages for breach of contract should be limited to the
    cost of completing the contract, under the same specifications, over the original
    contract price.”). We find no basis to reverse the district court’s decision to
    award as a credit to Lonestar only the percentage of unperformed work under
    the Refurbishment Agreements. We next turn to Superior’s cross-appeal.
    IV.
    A.
    Superior argues first that the district court erroneously held that it could
    not recover for work that was performed outside the scope of the Refurbishment
    Agreements, the Turnkey, and the change orders, but that was never invoiced
    to Lonestar. The district court held that the parties entered into an implied-in-
    fact contract governing this work and that pursuant to the implied contract
    Lonestar would not be required to pay additional sums for the work. We find no
    error in the district court’s holding.
    “An implied in fact contract is one which rests upon consent implied from
    facts and circumstances showing mutual intention to contract.”            Morphy,
    Makofsky & Masson, Inc. v. Canal Place 2000, 
    538 So. 2d 569
    , 573 (La. 1989).
    Superior does not contest the district court’s finding that there was an implied
    oral contract governing the work at issue. It contends, instead, that because the
    implied contract did not contain a price for the work, the court should have
    supplied that missing term and allowed Superior to recover a reasonable sum for
    its services. Superior is correct that if an implied contract for services contains
    no term for remuneration, the plaintiff is ordinarily compensated at a price
    determined by the court. See id.; Dubois Constr. Co. v. Moncla Constr. Co., 907
    12
    Case: 12-30904     Document: 00512426170       Page: 13    Date Filed: 10/31/2013
    No. 12-30904
    So. 2d 855, 857 (La. Ct. App. 2005) (“Where an agreement exists but the price to
    be paid is not stated, the court in the context of contractual interpretation must
    supply the missing price.”)
    Here, however, the district court did make a finding about the price and
    concluded that the parties intended Superior’s compensation to be zero. This
    finding was not clearly erroneous. See Gebreyesus v. F.C. Schaffer & Assocs.,
    Inc., 
    204 F.3d 639
    , 642 (5th Cir. 2000) (“Where a court determines that
    ambiguity exists and makes factual determinations of intent, we review those
    factual findings for clear error.”). The district court reasoned that Superior’s
    general manager, Andy Gardner, testified that Superior did not intend to bill
    Lonestar for the work and subsequently sought payment only when Lonestar
    failed to pay the Turnkey price. The court noted that Lonestar personnel
    observed Superior performing the additional work and did not object, thereby
    consenting to it under the presumed belief that the work was being done as a
    business accommodation. Superior asserts that there was never an agreement
    to do the work without compensation and that Lonestar understood it would
    have to pay for the work because Berisford testified that he knew Superior “don’t
    do nothing for nothing.” But, as noted by the district court, Superior’s CFO,
    George Tannehill, testified at the hearing on the motion to vacate the arrest of
    the barges that Superior had intended to perform the work as a concession. He
    also testified that this was discussed between Superior’s Rodney Verret and
    Lonestar’s Chief Idisi. In light of this testimony, Superior fails to show that the
    district court’s finding was clearly erroneous.        See Lyondell Chem. Co. v.
    Occidental Chem. Corp., 
    608 F.3d 284
    , 301 (5th Cir. 2010) (“A finding of fact is
    not clearly erroneous ‘if it is plausible in the light of the record read as a whole.”
    (internal quotation marks and citation omitted)).
    13
    Case: 12-30904    Document: 00512426170       Page: 14   Date Filed: 10/31/2013
    No. 12-30904
    B.
    Superior next argues that the district court incorrectly denied its claim for
    reimbursement for the premiums it paid to obtain builder’s risk insurance on the
    barges. The Refurbishment Agreements required that the barges be insured
    during the course of construction and that the insurance be “at the expense of
    Owner.” Although Superior alleged that it obtained an insurance policy at a cost
    of $216,000, Lonestar refused to reimburse Superior for this amount because it
    asserted that it had its own policy. The district court denied Superior’s claim,
    reasoning that Superior failed to show that the policy Lonestar had obtained was
    insufficient, and that Superior also failed to introduce copies of the policies. The
    court further reasoned that the insurance was meant to benefit Lonestar, and
    therefore Lonestar could waive that condition of the contract.
    The contract arguably required Superior to obtain a builder’s risk policy
    at Lonestar’s expense because it used the word “also” when referring to
    Superior’s additional obligation to obtain insurance for employer’s liability and
    worker’s compensation, although that policy was to be at its own expense. See
    LA. CIV. CODE art 2050 (“Each provision in a contract must be interpreted in
    light of the other provisions so that each is given the meaning suggested by the
    contract as a whole.”). But even assuming that is so, the contract required a
    policy that fully insured the barges, that covered specified risks, and that
    expressly named Lonestar. As noted by the district court, Superior never offered
    the policy to show what insurance it had obtained. Because Superior did not
    produce the policy or prove the terms of its coverage, we cannot fault the district
    court for denying the recovery.
    C.
    Superior also argues that the district court erred by not awarding it costs
    incurred for work that Lonestar requested to clean the tanks of each barge.
    Lonestar approved and paid for the amount Superior estimated as the cost for
    14
    Case: 12-30904     Document: 00512426170      Page: 15    Date Filed: 10/31/2013
    No. 12-30904
    tank cleaning but refused to pay an additional amount that Superior claimed
    was necessary because the job required more actual work than originally
    estimated.    The only admissible evidence of the additional cost was the
    testimony of Superior’s general manager, who testified that he could not recall
    the details of the claimed extra work. The district court specifically discredited
    the testimony. Superior does not address the basis for the district court’s denial
    of the cost, and we otherwise see no reason to disturb the court’s decision on this
    issue. See Canal Barge Co. v. Torco Oil Co., 
    220 F.3d 370
    , 375 (5th Cir. 2000)
    (“The burden of showing that the findings of the district court are clearly
    erroneous is heavier if the credibility of witnesses is a factor in the trial court’s
    decision.” (internal quotation marks and citation omitted)); see also Brinkmann
    v. Dallas County Deputy Sheriff Abner, 
    813 F.2d 744
    , 748 (5th Cir. 1987) (failure
    to challenge the basis for the district court’s decision is same as abandoning
    arguments regarding that ruling).
    D.
    Superior next argues that it should have been permitted to recover costs
    that it paid on Lonestar’s behalf for the living and incidental expenses of
    Lonestar employees who were on the job site in Louisiana. These expenses,
    amounting to $743,081.61, included money for the employees’ cell phones,
    lodging at hotels, meals, plane tickets to fly to and from New Iberia, and petty
    cash for incidental expenses connected to the operation. The district court held
    that costs associated with the living expenses were not “necessaries” within the
    meaning of the Federal Maritime Lien Act and could not be recovered.
    Pursuant to the Federal Maritime Lien Act, “a person providing
    necessaries to a vessel” may assert a lien against the vessel and sue in rem to
    enforce the lien. 46 U.S.C. § 31342(a). The term “necessaries” is given “a broad
    meaning.” J. Ray McDermott & Co. v. Off-Shore Menhaden Co., 
    262 F.2d 523
    ,
    525 (5th Cir. 1959). It includes “most goods or services that are useful to the
    15
    Case: 12-30904     Document: 00512426170      Page: 16   Date Filed: 10/31/2013
    No. 12-30904
    vessel, keep her out of danger, and enable her to perform her particular function.
    Necessaries are the things that a prudent owner would provide to enable a ship
    to perform well the functions for which she has been engaged.” Equilease Corp.
    v. M/V SAMPSON, 
    793 F.2d 598
    , 603 (5th Cir. 1986) (en banc). By statute,
    necessaries include repairs and supplies, 46 U.S.C. § 31301(4), and they may
    come in the form of “money, labor and skill, and personal services as well as
    materials.” 
    Equilease, 793 F.2d at 603
    . It is the “want of the vessel, not the
    character of the thing supplied, which makes it a necessary.” 
    Id. (internal quotation
    marks and citation omitted); see, e.g., Sasportes v. M/V SOL DE
    COPACABANA, 
    581 F.2d 1204
    , 1210 (5th Cir. 1978) (noting that advances made
    for “telephone calls, hotel rooms and similar items” may or may not be
    necessaries, and remanding for further findings by the district court).
    The district court here reasoned that the living expenses of the Lonestar
    employees for which Superior provided payment were not necessaries because
    there was no showing that the employees were actively engaged in repair or
    refurbishment work, nor was their presence reasonably needed for the repair or
    refurbishment of the barges. We agree with the district court.
    The evidence of the work done by the Lonestar employees on the site is
    sparse. According to the trial testimony, the employees on the site included
    mechanics, barge engineers, and electricians, but there are no details about
    these employees. Lonnie Barkaskas, Lonestar’s chief mechanic, testified that his
    job was to ensure that the work was completed according to Lonestar’s
    requirements. In other words, it appears that he monitored Superior’s work to
    protect the interests of Lonestar. Barkaskas also testified that he and other
    employees went on board the barges daily, but he provided no further detail
    about their work. It is true, as noted above, that necessaries are generally given
    a broad interpretation. J. Ray McDermott & 
    Co., 262 F.2d at 525
    . But it is also
    true that “[m]aritime liens are stricti juris and will not be extended by
    16
    Case: 12-30904    Document: 00512426170       Page: 17   Date Filed: 10/31/2013
    No. 12-30904
    construction, analogy, or inference.” Racal Survey U.S.A., Inc. v. M/V COUNT
    FLEET, 
    231 F.3d 183
    , 192 (5th Cir. 2000). The work of the Lonestar employees
    might have contributed to the refurbishment operation, but we conclude that the
    evidence here is insufficient to show that the advances for these employees’
    living expenses were necessary in order for the repairs and refurbishment of the
    barges to take place.     Therefore, we find no error in the district court’s
    disallowance of this claim.
    E.
    Finally, Superior challenges the district court’s calculation of prejudgment
    interest, arguing that the interest rate should have been higher and that
    interest should have begun running from the date of loss rather than from the
    date of judicial demand. The setting of prejudgment interest rates is committed
    to the broad discretion of the district court, which “may look to state law or other
    reasonable guideposts indicating a fair level of compensation.” Marine Overseas
    Servs., Inc. v. Crossocean Shipping Co., 
    791 F.2d 1227
    , 1236 (5th Cir. 1986)
    (internal quotation marks and citation omitted). The district court here acted
    well within its discretion by ordering a rate established pursuant to 28 U.S.C.
    § 1961. See Reeled Tubing, Inc. v. M/V CHAD G, 
    794 F.2d 1026
    , 1029 (5th Cir.
    1986). Although interest generally runs from the date of loss, the district court
    also acted within its discretion by ordering interest from the date of judicial
    demand based on its findings that Superior delayed in filing the suit, that the
    amount awarded was less than the amount initially claimed, and that the sums
    awarded were due at varying times, making the precise date of loss difficult if
    not impossible to determine. See id.; Howell v. Marmpegaso Compania Naviera,
    S.A., 
    578 F.2d 86
    , 87 (5th Cir. 1978).
    V.
    We conclude that the district court did not err in its construction of the
    Turnkey contract or in awarding the credit to Lonestar. We also conclude that
    17
    Case: 12-30904   Document: 00512426170    Page: 18   Date Filed: 10/31/2013
    No. 12-30904
    the court did not err in its determination of the amounts recoverable by
    Superior.
    AFFIRMED.
    18
    

Document Info

Docket Number: 12-30904

Citation Numbers: 547 F. App'x 432

Judges: Elrod, Haynes, Per Curiam, Reavley

Filed Date: 10/31/2013

Precedential Status: Non-Precedential

Modified Date: 8/31/2023

Authorities (23)

Canal Barge Company, Inc. v. Torco Oil Company Gulfstream ... , 220 F.3d 370 ( 2000 )

Olympic Insurance Company v. H. D. Harrison, Inc. , 463 F.2d 1049 ( 1972 )

Reeled Tubing, Inc. v. M/v Chad G, Her Engines, Etc., in ... , 794 F.2d 1026 ( 1986 )

Valle v. City of Houston , 613 F.3d 536 ( 2010 )

United States of America Ex Rel. Charles R. Riley v. The ... , 597 F.2d 446 ( 1979 )

Marine Overseas Services, Inc., Cross-Appellee v. ... , 791 F.2d 1227 ( 1986 )

Racal Survey U.S.A., Inc. v. M/V Count Fleet , 231 F.3d 183 ( 2000 )

stevens-shipping-and-terminal-company-stevens-shipping-and-terminal , 334 F.3d 439 ( 2003 )

LYONDELL CHEMICAL CO. v. Occidental Chemical Corp. , 608 F.3d 284 ( 2010 )

julien-andre-sasportes-v-mv-sol-de-copacabana-her-engines-etc-and , 581 F.2d 1204 ( 1978 )

colony-creek-ltd-plaintiff-counter-v-resolution-trust-corp-as , 941 F.2d 1323 ( 1991 )

Reginald R. Brinkmann, Jr. v. Dallas County Deputy Sheriff ... , 813 F.2d 744 ( 1987 )

equilease-corporation-cross-appellee-v-mv-sampson-etc-cross-appellees , 793 F.2d 598 ( 1986 )

J. Ray McDermott & Co., Inc. v. The Off-Shore Menhaden ... , 262 F.2d 523 ( 1959 )

In Re James and Dianne Ripley, Debtors. United States of ... , 926 F.2d 440 ( 1991 )

endrias-gebreyesus-doing-business-as-oda-trading-agency-v-fc-schaffer , 204 F.3d 639 ( 2000 )

Neel v. O'QUINN , 313 So. 2d 286 ( 1975 )

Louisiana Highway Commission v. Farnsworth , 74 F.2d 910 ( 1935 )

Airco Refrigeration Service, Inc. v. Fink , 242 La. 73 ( 1961 )

Morphy, Makofsky & Masson, Inc. v. CANAL PLACE 2000 , 538 So. 2d 569 ( 1989 )

View All Authorities »