Dudley v. Jones , 77 Tex. 69 ( 1890 )


Menu:
  • HENRY, Associate Justice.

    —This suit was brought by appellee as: a subcontractor, against Hatcher & Hughes as contractors and H. W. and Lizzie Gr. Dudley as owners of the improved property, to recover a balance-due him for work done, and to enforce a mechanic’s lien.

    The contractors had agreed with the owners of the lot to perform the= wood work and painting upon a house for a stipulated price.

    Plaintiff had agreed with the contractors to do the painting for $195.. The contractors abandoned the construction of the building before it was completed. The subcontractor abandoned his contract when the contractors abandoned theirs. He claimed that the work done by him was worth in proportion to the whole contract price $135.53, for which,, after deducting a payment of $25, he proceeded to establish a mechanic’s, lien, and instituted this suit to recover the balance due him.

    The owners of the property answered, alleging that before any notice-of plaintiff’s account was given them the contractors, Hatcher & Hughes, had abandoned their contract, and defendants had paid them more than the material furnished and work and labor done by them were reasonably worth, and more than the proper proportion of the same under and by virtue of said contract, and that the amount they were compelled to pay to complete the building, added to the amount so paid Hatcher & Hughes,, made the building cost them more than the original contract price.

    The court sustained plaintiff’s exceptions to this answer, and after hearing evidence rendered judgment in favor of plaintiff for .the amount off his demand and foreclosing mechanic’s lien in his favor. Appellants assign as error the judgment sustaining the exceptions to their answer.

    The owners of the property were not liable to the subcontractor for any amount paid to the contractor before being served with notice of the subcontractor’s claim. By establishing his claim as a mechanic’s lien, the subcontractor’s right related back to the date of his notice to the owners and became a lien upon the property for any amount then due or subsequently-accruing in favor of the contractors, not exceeding the subcontractor’s demand, there being no other mechanic’s lien against the property.

    The right of protection through the instrumentality of a mechanic’s, lien is subject to the right of the owners of the property not to be compelled to pay a greater price for the improvement than they had contracted to do, unless such result was occasioned by their making payments after-notice of the claim was given to them.

    "We think the -answer presented a defense which, if proved, will entitle *71appellants to a judgment discharging them, and that the exception to it should have been overruled.

    The judgment is reversed and the cause is remanded.

    Reversed and remanded.

    Delivered April 25, 1890.

Document Info

Docket Number: No. 6713

Citation Numbers: 77 Tex. 69

Judges: Henry

Filed Date: 4/25/1890

Precedential Status: Precedential

Modified Date: 9/2/2021