United States v. CITGO Petroleum Corporation , 711 F. App'x 237 ( 2018 )


Menu:
  •      Case: 16-30515      Document: 00514346807         Page: 1    Date Filed: 02/14/2018
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    United States Court of Appeals
    Fifth Circuit
    FILED
    No. 16-30515                            February 14, 2018
    Lyle W. Cayce
    Clerk
    UNITED STATES OF AMERICA, on behalf of Administrator of
    Environmental Protection Agency,
    Plaintiff - Appellee Cross-Appellant
    v.
    CITGO PETROLEUM CORPORATION,
    Defendant - Appellant Cross-Appellee
    Appeals from the United States District Court
    for the Western District of Louisiana
    USDC No. 2:08-CV-893
    Before DENNIS, CLEMENT, and GRAVES, Circuit Judges.
    PER CURIAM:*
    This case stems from the spillage of wastewater into navigable waters at
    a CITGO plant in Lake Charles, Louisiana. CITGO has conceded liability and
    the only issue in this protracted litigation is the amount of the resulting civil
    penalty, which the district court has determined on two separate occasions.
    * Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH
    CIR. R. 47.5.4.
    Case: 16-30515    Document: 00514346807     Page: 2   Date Filed: 02/14/2018
    No. 16-30515
    The parties appealed both. On first appeal, we vacated and remanded for
    further proceedings. Now, we AFFIRM.
    BACKGROUND
    The underlying facts of this case are set out in our initial decision. See
    United States ex rel. v. CITGO Petro. Corp. (“CITGO I”), 
    723 F.3d 547
    , 549-50
    (5th Cir. 2013). Pertinent to this appeal, CITGO conceded liability for the
    spillage of wastewater into navigable waters at a Louisiana plant. 
    Id.
     After a
    two-week bench trial, the district court fined CITGO $6 million. 
    Id. at 550
    . The
    United States appealed that penalty, arguing that the district court failed to
    make the necessary fact-finding on the economic benefit to CITGO of delaying
    necessary prevention measures. 
    Id. at 551
    . We agreed, and remanded in order
    to make “a reasonable approximation” of the economic benefit to CITGO. 
    Id.
    On remand, the district court conducted a thorough analysis and
    concluded that CITGO realized an economic benefit of $91.7 million. See
    United States v. Citgo Petro. Corp., Civ. Action No. 08-893, 
    2015 WL 9692957
    ,
    at *6 (W.D. La. Dec. 23, 2015). In reaching that number, the district court
    considered the costs of CITGO providing a third and fourth waste water tank,
    an aeration filter, and an API separator. Id. at *5. The court then applied a
    rate of 10.04% weighted average cost of capital (“WACC”) to those funds over
    a number of years. Id. at *6. Finally, after finding CITGO acted with gross
    negligence, the court considered all the remaining Clean Water Act (“CWA”)
    penalty factors, ultimately deciding to depart downward from the economic
    benefit determination to impose a fine of $81 million. Id. at *7-8. Both parties
    timely appealed.
    STANDARD OF REVIEW
    “The assessment of civil penalties under the CWA is left to the district
    court’s discretion.” CITGO I, 723 F.3d at 551. The exercise of that discretion is
    guided by the factors articulated in the CWA. See id. (citing 33 U.S.C.
    2
    Case: 16-30515    Document: 00514346807       Page: 3   Date Filed: 02/14/2018
    No. 16-30515
    § 1321(b)(8)). The Supreme Court has described the process of weighing the
    penalty factors as “highly discretionary.” Tull v. United States, 
    481 U.S. 412
    ,
    425 (1987). Accordingly, this court reviews the district court’s WACC
    determination for abuse of discretion, United States v. Allegheny Ludlum
    Corp., 
    366 F.3d 164
    , 184 (3d Cir. 2004), and factual findings in support of the
    penalty calculation for clear error, Sierra Club, Lone Star Chapter v. Cedar
    Point Oil Co., 
    73 F.3d 546
    , 573 (5th Cir. 1996).
    DISCUSSION
    Both parties have appealed the district court’s civil penalty. We address
    CITGO’s arguments first before turning to the government’s. None of the
    parties’ arguments have merit and we affirm in full.
    I.    CITGO’s Assertions
    CITGO presents two arguments on appeal. First, CITGO claims that the
    district court failed to properly consider the least costly alternative to prevent
    the spillage. Second, CITGO claims the district court erred in applying a
    10.04% WACC rate. Neither argument has merit.
    a.    Least Costly Alternative
    The district court determined that the “least costly alternative would
    have been to provide adequate [storage] capacity.” Citgo Petro., 
    2015 WL 9692957
    , at *5. This determination is supported by the government expert’s
    testimony that CITGO needed “more than 20 million gallons of additional
    water capacity.” To meet that need, the court found that CITGO should have
    installed a third and fourth water tank, as well as an aeration tank and API
    separator. 
    Id.
     CITGO contends this analysis was error because only a third
    storage tank was needed to prevent overflow.
    According to CITGO, a third tank would have provided 10.7 million
    gallons of capacity, which, combined with the storage dike’s 11.8 million
    gallons of capacity, would have provided sufficient storage to prevent overflow.
    3
    Case: 16-30515    Document: 00514346807     Page: 4   Date Filed: 02/14/2018
    No. 16-30515
    This calculation, however, is based on a scenario where “all tanks were
    operated at the minimum level and all conditions were perfect.” There is ample
    record evidence that this best-case-scenario does not conform to the realities of
    running the plant.
    The government’s expert testified that a fourth tank was necessary “no
    matter what” because tanks must be taken out of service periodically for
    maintenance. Therefore, a fourth tank was mandatory in order to ensure that
    a third tank was always operational. Further, CITGO planned to use the dike’s
    capacity to compensate for lost storage when a tank was taken out for
    maintenance. Because of these issues, even assuming that a third tank and the
    dike would mathematically provide sufficient storage, in reality, CITGO was
    not always “maintaining that reserve capacity.”
    Compounding these issues, CITGO “failed to maintain the limited
    capacity it had, allowing the tanks to fill with sludge and waste.” See Citgo
    Petro., 
    2015 WL 9692957
    , at *7. Accumulation of this debris was the result of
    inadequate filtration systems and led to the storage tanks having a functional
    storage capacity below the best-case-scenario capacity asserted on appeal by
    CITGO. To remedy this issue, the government’s expert testified that CITGO
    needed a fifth API separator and another aeration tank.
    In short, CITGO’s argument is based on mathematical calculations of
    storage capacities at “optimum conditions.” The district court credited the
    government’s expert that such calculations are “disconnect[ed]” from the “real
    world” operation of the plant. There is no clear error in that determination.
    b.    The WACC Determination
    CITGO next contends that the district court abused its discretion when
    it applied a 10.04% WACC to determine the present value of the economic
    benefit calculation. In CITGO’s view, the 10.04% rate was not based on sound
    4
    Case: 16-30515   Document: 00514346807     Page: 5   Date Filed: 02/14/2018
    No. 16-30515
    methodology and was unreasonable because CITGO could have obtained the
    same funding at a much lower cost.
    In essence, CITGO asks us to credit the testimony of CITGO’s expert
    witness over the testimony of the government’s expert. At trial, the
    government’s financial expert testified at length regarding the reasons that a
    WACC rate of 10.04% should be used to calculate the present value of CITGO’s
    avoided expenditure. CITGO’s expert, of course, offered a contradicting
    analysis urging a rate far lower. CITGO urges us to accept their expert’s rate
    on appeal. We decline to do so. When a district court is tasked with crediting
    battling experts, “the factfinder’s choice between them cannot be clearly
    erroneous.” CITGO I, 723 F.3d at 556 (quoting Bertucci Contracting Corp. v.
    M/V ANTWERPEN, 
    465 F.3d 254
    , 258 (5th Cir. 2006)).
    II.    The Government’s Arguments
    The government, for its part, also asserts two errors on appeal. First the
    government argues that the district court erred in departing downward from
    its economic benefit determination in imposing a penalty. Second, the
    government challenges the adequacy of the district court’s explanation
    pertaining to the CWA penalty factors. Neither argument has merit.
    a.    The Downward Departure
    The government first appeals the district court’s grant of a below-
    economic-benefit penalty, arguing that the district court should have imposed
    a penalty equal to, or above, its economic benefit determination.
    To the extent that the government believes that a CWA penalty should
    never depart downward from an economic benefit determination, we have
    recognized that in the “bottom up” approach district courts adjust a penalty
    “upward or downward” from the economic benefit calculation. See CITGO I,
    723 F.3d at 552 (quoting Allegheny Ludlum, 
    366 F.3d at
    178 n.6).
    5
    Case: 16-30515     Document: 00514346807    Page: 6   Date Filed: 02/14/2018
    No. 16-30515
    Here, the court employed the bottom up approach, but chose to depart
    downward from its $91.7 million economic benefit determination. The court
    presumably did so, at least in part, on its consideration of CITGO’s $65 million
    effort to clean up the spill. Compare United States v. Citgo Petro. Corp., Civ.
    Action 08-893, 
    2011 WL 13047364
    , at *3 (W.D. La. Sept. 29, 2011) (noting $65
    million clean-up effort), with Citgo Petro., 
    2015 WL 9692957
    , at *8 (leaving
    findings as to CITGO’s clean-up efforts “unchanged”). The district court’s $10
    million downward departure in light of that fact is not an abuse of the district
    court’s “highly discretionary” determination of the penalty. See Tull, 
    481 U.S. at 427
    .
    b.       The Adequacy of the District Court’s Penalty Explanation
    The government next contends that the district court abused its
    discretion because it did not provide a sufficiently detailed explanation for its
    penalty award.
    In accordance with our decision in CITGO I, the district court gave a
    detailed description of its economic benefit calculation, addressing the costs of
    each step CITGO should have taken, the time period underlying the economic
    benefit calculation, and the 10.04% rate it used to determine present value of
    those delayed expenditures. See Citgo Petro., 
    2015 WL 9692957
    , at *5-6. Next,
    in finding that CITGO acted with gross negligence, the district court discussed
    the substantial evidence indicating CITGO’s long-history of awareness that its
    storage systems were inadequate at the Lake Charles plant. Id. at *7-8.
    Finally, the district court considered the “remaining penalty factors,” directly
    addressing in detail the level of seriousness of the violations, the degree of
    CITGO’s culpability, CITGO’s prior history of violations, CITGO’s mitigation
    efforts, the impact of a penalty on CITGO, and any other interests of justice.
    Id. at *8-9.
    6
    Case: 16-30515     Document: 00514346807     Page: 7   Date Filed: 02/14/2018
    No. 16-30515
    There is no error in the district court’s detailed and thorough calculation
    of the penalty in this case. Though the district court did not explicitly describe
    the exact effect each factor had in reaching the downward penalty calculation,
    it need not do so. The “calculation of discretionary penalties is not an exact
    science, and few courts could comply with [the government’s] request that the
    importance of each factor be precisely delineated.” See United States v. Marine
    Shale Processors, 
    81 F.3d 1329
    , 1338 (5th Cir. 1996).
    CONCLUSION
    The district court did not commit clear error in its factual
    determinations. Nor did it abuse its discretion in calculating the $81 million
    penalty imposed against CITGO. Accordingly, we AFFIRM.
    7
    Case: 16-30515     Document: 00514346807      Page: 8   Date Filed: 02/14/2018
    No. 16-30515
    EDITH BROWN CLEMENT, Circuit Judge, Dissenting in part:
    I concur in the majority’s decision to affirm the district court’s WACC
    determination, below-economic benefit penalty, and penalty explanation.
    However, for the reasons below, I dissent as to the majority’s affirmance of the
    district court’s least costly alternative analysis.
    The majority’s rejection of CITGO’s “third tank only argument,” finding
    that a third and fourth storage tank were necessary, is correct. However, the
    majority does exactly what I believe the district court incorrectly did—adopt
    the government’s proposed least costly alternative in full without an
    individualized consideration. I would hold that the district court clearly erred
    in including the API separator and the aeration tank in the determination.
    The only items that should be included in the least costly alternative
    analysis are the items that were necessary to prevent the charged violation.
    The record on appeal and the parties’ briefs focus on CITGO’s failure to have
    sufficient stormwater storage tank capacity and its failure to adequately
    maintain and clean the tanks, all of which undoubtedly led to the 2006 CWA
    violation. But, there is no basis in the record for the district court’s inclusion—
    and this court’s affirmance—of the API separator and the aeration tank.
    Neither the district court nor this court addresses how or why these two items
    were necessary to the prevention of CITGO’s CWA violation, beyond their being
    good business practices.
    Although it may have been good practice to have the API separator and
    the aeration tank, the record makes abundantly clear that CITGO needed only
    a third and fourth storage tank—that were cleaned and maintained—to
    prevent the CWA violation in question. Accordingly, I would vacate the
    judgment as to the inclusion of the API separator and the aeration tank.
    Further, because the cost of each item is unclear, I would remand for the
    district court to recalculate the economic benefit and adjust the civil penalty
    8
    Case: 16-30515    Document: 00514346807     Page: 9   Date Filed: 02/14/2018
    No. 16-30515
    as the district court deems appropriate with the guidance that this court does
    not find error as to its determination in any other respect.
    9