USA v. Luminant Generation Co.,L.L.C., et a , 905 F.3d 874 ( 2018 )


Menu:
  •      Case: 17-10235   Document: 00514663975     Page: 1   Date Filed: 10/01/2018
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    No. 17-10235                United States Court of Appeals
    Fifth Circuit
    FILED
    October 1, 2018
    UNITED STATES OF AMERICA,
    Lyle W. Cayce
    Plaintiff - Appellant                                  Clerk
    SIERRA CLUB,
    Intervenor Plaintiff - Appellant
    v.
    LUMINANT GENERATION COMPANY, L.L.C.; BIG BROWN POWER
    COMPANY, L.L.C.,
    Defendants - Appellees
    Appeals from the United States District Court
    for the Northern District of Texas
    Before JOLLY, DENNIS, and ELROD, Circuit Judges.
    E. GRADY JOLLY, Circuit Judge:
    Today we are presented with claims brought by the United States
    asserting that Luminant Generation Company and Big Brown Power Company
    violated the Clean Air Act by failing to obtain a statutorily mandated
    preconstruction permit for the modification of their facilities. The government
    seeks civil penalties and injunctive relief. Because the government filed its
    action more than five years after construction began on the facilities, the
    Case: 17-10235     Document: 00514663975     Page: 2   Date Filed: 10/01/2018
    No. 17-10235
    district court dismissed the government’s civil-penalty and injunctive-relief
    claims as time barred under Federal Rule of Civil Procedure 12(b)(6). The
    court also held that the injunctive-relief claims were subject to dismissal under
    Rule 12(b)(1) for lack of jurisdiction.
    We join the other circuits in holding that such an action to recover civil
    penalties for violation of the Preconstruction requirements for major emitting
    facilities under 42 U.S.C § 7475(a) must be brought within five years of the
    first day of the alleged construction period. Because the government waited
    more than five years to file the instant suit, its legal claims are time barred.
    Therefore, we affirm dismissal of the legal claims.
    But the government also asks for injunctive relief. We hold that the
    government, in its sovereign capacity, is exempted from the concurrent-
    remedies doctrine. We reach this conclusion because, generally, government
    claims, brought in its sovereign capacity, are not subject to any limitations
    period, unless Congress expresses its clear consent thereto. Here, the only
    applicable statute of limitations makes no reference to injunctive relief. Thus,
    the statute of limitations does not apply to the government’s claims for
    injunctive relief that are not civil fines, penalties, or forfeitures. Finally, we
    find no support for the district court’s assumption that it was without
    jurisdiction to entertain any injunctive relief based on past violations of
    § 7475(a). Of course, that is not to say that the government is entitled to
    injunctive relief here. We hold only that the district court is not barred by the
    statute of limitations, nor by the absence of jurisdiction, from further
    considering whether equitable relief may in some form be available to the
    government. We remand the injunctive-relief claims to the district court for
    further consideration.
    2
    Case: 17-10235       Document: 00514663975         Page: 3    Date Filed: 10/01/2018
    No. 17-10235
    I.
    The Clean Air Act (“CAA”), through the Prevention of Significant
    Deterioration Program, 1 mandates the following two “Preconstruction
    requirements,” codified at 42 U.S.C § 7475(a), that are central to this appeal:
    No major emitting facility on which construction is commenced
    after August 7, 1977, may be constructed . . . unless--
    (1) a permit has been issued for such proposed facility . . .
    setting forth emission limitations . . . ;
    ....
    (4) the proposed facility is subject to the best available
    control technology [“BACT”] for each pollutant subject to
    regulation . . . .
    42 U.S.C. § 7475(a) (2012). In other words, proposed facilities require a permit
    to begin construction, and those proposed facilities must be “subject to” the
    BACT in order to get a permit. 2 Each state must adopt a state implementation
    plan (“SIP”) to meet these goals, and Texas’s SIP, which the EPA has approved,
    requires “Permits for New Construction or Modification.” 3
    Important here, major emitting facilities built before August 1977 do not
    escape the Preconstruction requirements because the term “construction”
    “includes the modification” of a facility. 42 U.S.C. § 7479. “Modification” is
    defined as “any physical change in, or change in the method of operation of a
    stationary source which increases the amount of any air pollutant emitted by
    1   We have written extensively on the history and intent of the CAA and, more
    specifically, the Prevention of Significant Deterioration Program. See CleanCOALition v.
    TXU Power, 
    536 F.3d 469
    , 471–73 (5th Cir. 2008).
    2 “[B]est available control technology” is not technology in the general sense, but
    instead “an emission limitation based on the maximum degree of reduction of each pollutant
    subject to regulation . . . .” 42 U.S.C. § 7479(3).
    3 Specifically, the Texas SIP requires that “[b]efore any actual work is begun on the
    facility, any person who plans to construct any new facility or to engage in the modification
    of any existing facility which may emit air contaminants into the air of this state” must get
    a permit or satisfy certain conditions. 30 Tex. Admin. Code § 116.110.
    3
    Case: 17-10235       Document: 00514663975          Page: 4     Date Filed: 10/01/2018
    No. 17-10235
    such source or which results in the emission of any air pollutant not previously
    emitted.” 
    Id. § 7411.
    In short, all pre-1977 major emitting facilities must
    comply with the § 7475(a) permit requirements before undergoing a physical
    change or change in operation that increases pollution above a set floor.
    Now for the facts.         We are concerned today with two power-plant
    facilities built before 1977, each of which houses multiple power-generating
    units. The first is the Martin Lake Power Plant, owned and operated by
    defendant Luminant Generation Company, LLC. And the second is the Big
    Brown Power Plant, 4 owned by Big Brown Power Company, LLC, and operated
    by Luminant (collectively, “the defendants”). 5
    The district court did not address and the defendants do not contest on
    appeal whether the defendants’ facilities were required to comply with the
    § 7475(a) Preconstruction requirements, so we proceed on the basis that they
    were. 6 And at this early stage of the litigation, we must assume the defendants
    constructed their respective facilities without a permit or ensuring the post-
    construction facilities would be subject to BACT. In response to these alleged
    violations, the government took legal action on August 16, 2013, filing suit in
    Texas federal court. The government alleged that the defendants violated, and
    are continuing to violate, the § 7475(a) Preconstruction requirements and
    Texas SIP by (1) having constructed their facilities without obtaining the
    4   Big Brown decommissioned and retired on February 12, 2018.
    5   An environmental organization ranked Martin Lake 8th and Big Brown 72nd on a
    list of “100 Most-Polluting Power Plants” in the United States. Jordan Schneider & Julian
    Boggs, America’s Dirtiest Power Plants, ENVIRONMENT AMERICA 26, 28 (Sept. 2014),
    https://environmentamericacenter.org/sites/environment/files/reports/EA_Dirtiest_power_pl
    ants_scrn_0.pdf.
    6 “We are fundamentally a court of review, not of first analysis.” La. World Exposition
    v. Fed. Ins. Co., 
    858 F.2d 233
    , 253 (5th Cir. 1988).
    4
    Case: 17-10235       Document: 00514663975          Page: 5     Date Filed: 10/01/2018
    No. 17-10235
    requisite permit and (2) operating without a permit and continuously failing
    to meet BACT emission limitations. 7
    Dates are important here. The original complaint alleges nine CAA
    violations, the following six of which are violations of the § 7475(a)
    Preconstruction requirements:
    (1) Martin Lake Unit 1 underwent major capital projects from
    March 4, 2006 – April 13, 2006 without a permit.
    (2) Martin Lake Unit 2 underwent major capital projects from
    February 16, 2007 – April 5, 2007 without a permit.
    (3) Martin Lake Unit 3 underwent major capital projects from
    February 26, 2005 – April 2, 2005 without a permit.
    (4) Martin Lake Unit 1 underwent major capital projects from
    March 1, 2009 – April 1, 2009 and “at or near the same time . . .
    Luminant changed the method of operation of the boiler” without
    a permit.
    (5) Martin Lake Unit 3 underwent major capital projects from
    February 10, 2008 – April 5, 2008 and “at or near the same
    time . . . and/or within about a year thereafter, Luminant changed
    the method of operation of the boiler” without a permit.
    (6) Big Brown Unit 2 underwent major capital projects from
    October 15, 2005 – November 13, 2005 without a permit.
    According to the government, these “unlawful major modifications” of major
    emitting facilities caused “significant amounts of SO2 and NOx pollution.” As
    to each claim, the government asks for civil penalties and injunctive relief
    under 42 U.S.C. § 7413(b). 8
    7  The statutory basis for these claims is 42 U.S.C. § 7475 (2012) (Preconstruction
    requirements), Texas Administrative Code §§ 116.110, 116.111, 116.160 (2001) (Texas SIP),
    and 40 C.F.R § 52.21 (1996).
    8 In total, the government raises six § 7475(a) claims, two Title V claims, and one § 114
    claim. The plaintiffs have withdrawn their fourth § 7475(a) claim and additional § 114
    procedural claim. And although the district court dismissed the Title V claims, the plaintiffs
    do not argue on appeal that the district court erred in doing so.
    5
    Case: 17-10235      Document: 00514663975    Page: 6   Date Filed: 10/01/2018
    No. 17-10235
    The defendants moved to dismiss § 7475(a) claims one, two, three, five,
    and six (not four) as time barred, arguing that the alleged unpermitted
    construction periods occurred outside the five-year statute of limitations, i.e.
    before August 16, 2008. In response, the government primarily argued that
    claims under § 7475(a) do not need to be brought within five years of
    construction because the Preconstruction requirements apply to constructing
    a facility and operating it. Thus, according to the government, each day a post-
    construction facility operates without a permit or BACT is a new, discrete
    § 7475(a) violation. In a footnote, the government also argued that it pleaded
    a construction in claim five—a change in the method of operation of the
    boiler—that occurred as late as April 2009, which falls within the limitations
    period. So even if § 7475(a) claims accrue at the time of construction, the
    government argued that the boiler-operation allegation in claim five should
    have nevertheless survived.
    The district court acknowledged the government’s argument that the
    boiler-operation allegation fell within the five-year period but, without further
    explanation, found that claim five accrued more than five years before suit was
    filed.    Ultimately, the district court agreed with the defendants that the
    government’s claims “first accrued on the modification start dates,” and
    dismissed claims one, two, three, five, and six (civil penalties and injunctive
    relief) as time-barred under Federal Rule of Civil Procedure 12(b)(6). The court
    also found that the claims for injunctive relief, as reflected in the complaint,
    were subject to dismissal under Rule 12(b)(1).
    After the district court’s dismissal ruling, only the government’s fourth
    § 7475(a) claim and an additional procedural claim survived. Once Sierra Club
    intervened as of right, joining the government as plaintiff (collectively, “the
    plaintiffs”), the plaintiffs then filed a second amended complaint withdrawing
    the surviving claims.       The district court entered final judgment for the
    6
    Case: 17-10235      Document: 00514663975         Page: 7    Date Filed: 10/01/2018
    No. 17-10235
    defendants. The plaintiffs now appeal the district court’s judgment dismissing
    all claims. But they challenge only the dismissal of the first, second, third,
    fifth, and sixth § 7475(a) claims.
    II.
    We review dismissals under Federal Rules of Civil Procedure 12(b)(1)
    and 12(b)(6) de novo. Zephyr Aviation, L.L.C. v. Dailey, 
    247 F.3d 565
    , 570 (5th
    Cir. 2001). Dismissal under Rule 12(b)(6) based on statute of limitations is
    proper only “where it is evident from the [complaint] that the action is barred
    and the [complaint] fail[s] to raise some basis for tolling.” Jones v. Alcoa, Inc.,
    
    339 F.3d 359
    , 366 (5th Cir. 2003). It is well established that “the limitations
    period runs from the moment a plaintiff’s claim ‘accrues.’”                King-White v.
    Humble Indep. Sch. Dist., 
    803 F.3d 754
    , 762 (5th Cir. 2015).
    III.
    We start our review by addressing two preliminary matters. First, we
    hold that any challenge to the district court’s holding that the relevant
    unpermitted construction periods fell outside the five-year statute of
    limitations has been abandoned. 9 See Edwards v. Johnson, 
    209 F.3d 772
    , 775
    n.1 (5th Cir. 2000); see also Jackson Women’s Health Org. v. Currier, 
    760 F.3d 448
    , 452 (5th Cir. 2014). For purposes of this appeal, each of the unlawful
    construction periods alleged in the relevant claims took place more than five
    years before the government filed suit.
    9  In its reply brief, Sierra Club re-urges the government’s argument made below that
    the complaint’s fifth claim alleges a construction period that began within the five-year
    limitations period. But that argument is not presented in either the government’s or Sierra
    Club’s opening briefs. Moreover, Sierra Club, who now pushes the argument at this late
    hour, explains in its opening brief that the complaint “alleged [the defendants] made six
    [unpermitted] modifications,” seemingly ignoring the additional boiler-operation
    modification in claim five. (Emphasis added). Therefore, we find this argument to be too
    little, too late.
    7
    Case: 17-10235     Document: 00514663975     Page: 8   Date Filed: 10/01/2018
    No. 17-10235
    Second, the parties do not dispute that 28 U.S.C § 2462 generally bars
    all CAA claims for the enforcement of any civil fine, penalty, or forfeiture that
    accrued more than five years before suit was filed. See United States v. Marine
    Shale Processors, 
    81 F.3d 1329
    , 1357 (5th Cir. 1996). The government filed
    suit on August 16, 2013, so the plaintiffs may enforce a civil fine, penalty, or
    forfeiture only for violations accruing on or after August 16, 2008. Thus, the
    legal question presented today is when does a § 7475(a) violation accrue as a
    matter of law, i.e. what event(s) trigger the running of the statute of
    limitations.   The defendants contend that a facility modified without a
    preconstruction permit violates § 7475(a) as a one-time occurrence:           the
    moment construction begins without a preconstruction permit. The five-year
    clock then begins to tick away, never to be restarted for a § 7475(a) claim
    related to that unpermitted construction period. The plaintiffs argue, on the
    other hand, that a facility modified without a permit continuously violates §
    7475(a) anew each day it operates post-construction. Stated differently, a new
    five-year clock begins to run each day a modified facility operates without a
    permit. Under the plaintiffs’ interpretation, the defendants could be held
    liable for civil penalties for each day their modified facilities operated without
    a permit on or after August 16, 2008; on the other hand, the defendants’
    interpretation means that all of the claims for civil fines, penalties, or
    forfeitures are time barred.
    Thus, we will now proceed to address when § 7475(a) violations occur as
    a matter of law, which determines the date the statute of limitations begins to
    run on the respective claims. Once that date has been established, we will
    decide whether any of the civil-penalty claims on appeal are time barred. In
    the light of that holding, we will then turn to the availability of injunctive
    relief. Taking the issues in that order, we begin.
    8
    Case: 17-10235       Document: 00514663975          Page: 9     Date Filed: 10/01/2018
    No. 17-10235
    A.
    Civil Penalties
    The parties’ disagreement over when § 7475(a) claims accrue focuses on
    the point in time that a complete violation of the Preconstruction requirements
    occurs: whether, as the defendants argue, only at the moment unpermitted
    construction commences or, as the government argues, also each day thereafter
    that the plant operates without a permit post-construction. See United States
    v. Core Labs., Inc., 
    759 F.2d 480
    , 482 (5th Cir. 1985) (“[T]he date of the
    underlying violation has been accepted without question as the date when the
    claim first accrued, and, therefore, as the date on which the statute [of
    limitations] began to run.”). The district court held that a § 7475(a) claim
    accrues “when construction or modification begins without the permit in hand.”
    Unsurprisingly, the defendants urge us to accept that clear and relatively early
    point in time. The plaintiffs, however, argue that a discrete violation occurs at
    the moment unpermitted construction begins and each day thereafter that the
    facility operates without a permit. 10
    We are not the first appellate court to consider whether the
    Preconstruction requirements apply also to the daily operation of a facility,
    such that the operation of an unpermitted facility is a fresh, daily violation of
    § 7475(a). The Third, Seventh, Eighth, Tenth, and Eleventh Circuits each have
    10  Apparently, the government’s argument would mean that each day an unpermitted
    facility is not in operation does not violate § 7475(a) anew. In any event, the underlying point
    is that operation is one thing, and construction is another. The statute we are interpreting,
    § 7475(a), is a statute relating to construction only, not to post-construction operation.
    On a related note, the plaintiffs do not argue that a new § 7475(a) claim accrues each
    day of unpermitted construction. See Sierra Club v. Oklahoma Gas & Elec. Co., 
    816 F.3d 666
    , 671–74 (10th Cir. 2016) (rejecting argument “that the statute of limitations resets on
    each day of unpermitted construction”). Thus, we do not consider that theory. Today, we
    decide only whether a § 7475(a) violation is a one-time event occurring at the moment
    construction begins or whether operating a modified facility without having obtained a
    preconstruction permit also violates the statute post-construction.
    9
    Case: 17-10235         Document: 00514663975           Page: 10     Date Filed: 10/01/2018
    No. 17-10235
    held that a violation of the § 7475(a) Preconstruction requirements occurs only
    at some point during the construction period, and not to the subsequent
    operation of the modified facility. Sierra Club v. Oklahoma Gas & Elec. Co.,
    
    816 F.3d 666
    , 674 (10th Cir. 2016); United States v. EME Homer City
    Generation, L.P., 
    727 F.3d 274
    , 284 (3d Cir. 2013); United States v. Midwest
    Generation, LLC, 
    720 F.3d 644
    , 647 (7th Cir. 2013); Sierra Club v. Otter Tail
    Power Co., 
    615 F.3d 1008
    , 1018 (8th Cir. 2010).; Nat’l Parks & Conservation
    Ass’n, Inc. v. Tennessee Valley Auth., 
    502 F.3d 1316
    , 1322 (11th Cir. 2007). For
    the reasons that follow, we will follow the other circuits.
    We quite naturally begin with the text of § 7475(a). 11 “Unless otherwise
    defined, statutory terms are generally interpreted in accordance with their
    ordinary meaning.” BP Am. Prod. Co. v. Burton, 
    549 U.S. 84
    , 91 (2006).
    Starting with the title of the statute, it reads “Preconstruction requirements,”
    not “Operating requirements” nor even “Preconstruction and Operating
    requirements.” Then scrolling down to the text of subsection a, Congress tells
    us that the § 7475(a) requirements must be met before a facility “may be
    constructed.” As we see it, this language can be read only one way: the
    Preconstruction requirements are terms and conditions with which the facility
    must comply in order for the facility to begin construction. They are not
    requirements that arise at a point in time after the facility has begun
    11   We repeat, § 7475(a) requires:
    No major emitting facility on which construction is commenced after August 7,
    1977, may be constructed . . . unless--
    (1) a permit has been issued for such proposed facility . . . setting forth
    emission limitations . . . ;
    ....
    (4) the proposed facility is subject to the best available control
    technology [“BACT”] for each pollutant subject to regulation . . . .
    10
    Case: 17-10235       Document: 00514663975          Page: 11     Date Filed: 10/01/2018
    No. 17-10235
    construction or resumed operation. By its plain language, § 7475(a) itself does
    not impose post-construction operational obligations on facilities. 12
    The plaintiffs point us to other related provisions of the CAA in support
    of their position, but those CAA sections do not change the plain meaning of
    § 7475(a). For example, there are two CAA provisions that explicitly refer to
    the operation of a facility. See, e.g., 42 U.S.C § 7411(e) (“[I]t shall be unlawful
    . . . to operate such source in violation of any standard of performance
    applicable to such source.”); 
    id. § 7661a(a)
    (“[I]t shall be unlawful for any
    person to . . . operate an affected source . . . except in compliance with a permit
    issued by a permitting authority . . . .”). “[W]here Congress includes particular
    language in one section of a statute but omits it in another section of the same
    Act, it is generally presumed that Congress acts intentionally and purposely
    in the disparate inclusion or exclusion.” United States v. Wong Kim Bo, 
    472 F.2d 720
    , 722 (5th Cir. 1972).
    Although the statutory text of § 7475(a) leads us to a clear answer, i.e.
    § 7475(a) violations do not extend into post-construction operation, the
    plaintiffs suggest that our jurisprudence offers a nod to their view. In United
    States v. Marine Shale Processors, the government sued Marine Shale, a
    hazardous waste-treatment facility, for, inter alia, “operating several minor
    emission sources without a permit in violation of the 
    [CAA].” 81 F.3d at 1352
    .
    Marine Shale argued in defense that “because emissions from each minor
    source began more than five years before the United States filed suit,” those
    12 Our conclusion that § 7475(a) imposes only preconstruction obligations on a facility
    does not conflict with our opinion in Sierra Club, Inc. v. Sandy Creek Energy Associates, L.P.,
    
    627 F.3d 134
    , 141 (5th Cir. 2010). In Sandy Creek, we held that a violation of 42 U.S.C § 7414,
    which has statutory language similar to § 7475(a), occurs as long as construction is ongoing.
    As we have noted, the plaintiffs in this case do not argue that a facility violates § 7475(a)
    each day it constructs without a permit; instead, they argue a facility violates § 7475(a) each
    day it operates without a permit. Our opinion in Sandy Creek does not speak to the question
    of operational obligations.
    11
    Case: 17-10235          Document: 00514663975          Page: 12      Date Filed: 10/01/2018
    No. 17-10235
    claims were barred by the five-year statute of limitations. 
    Id. at 1357.
    A panel
    of this court disagreed, holding that because 42 U.S.C § 7413(b), the civil-
    enforcement statute, “contemplates a fine for each day a minor source operates
    in violation of law,” minor-source emissions from unpermitted facilities
    occurring within the five-year limitations period are actionable even if the
    unpermitted emissions began more than five years before suit was filed. 
    Id. Importantly, §
    7413(b) is the civil-enforcement statute for violation of
    § 7475(a). 13
    Marine Shale does not, however, control our decision today. As Marine
    Shale explained, “The CAA statutory scheme contemplates at least two
    different types of air permits unhappily named ‘preconstruction permits’ and
    ‘operating permits,’” and “[t]he distinction between [them] is critical.” 
    Id. at 1355–56.
    14        Marine Shale addressed a violation concerning a facility’s
    operation without a permit. See, e.g., 
    id. at 1352
    (referring only to “permit”
    13   The civil-enforcement statute, 42 U.S.C. § 7413(b), reads:
    The Administrator shall . . . commence a civil action for a permanent or
    temporary injunction, or to assess and recover a civil penalty of not more than
    $25,000 per day for each violation, or both, in any of the following instances:
    (1) Whenever such person has violated, or is in violation of, any
    requirement or prohibition of an applicable implementation plan or
    permit. . . .
    (2) Whenever such person has violated, or is in violation of, any other
    requirement or prohibition of this subchapter, section 7603 of this title,
    subchapter IV-A, subchapter V, or subchapter VI of this chapter . . . .
    (3) Whenever such person attempts to construct or modify a major
    stationary source in any area with respect to which a finding under
    subsection (a)(5) of this section has been made.
    14 The Marine Shale panel noted that “confusion easily result[s]” in distinguishing
    between the two types of permits “from the fact that preconstruction permits often include
    limits upon a source’s 
    operations.” 81 F.3d at 1356
    . For the reasons explained, however,
    there is no indication that § 7475(a) per se limits a source’s operations. That is not to say
    that a preconstruction permit may never impose such limits. But of course, we are here
    because the defendants never obtained a permit.
    12
    Case: 17-10235       Document: 00514663975          Page: 13     Date Filed: 10/01/2018
    No. 17-10235
    and “air permit”). 15 In contrast today, however, we are solely addressing the
    preconstruction permit mandated by § 7475(a). Moreover, in the context of
    statute of limitations, the Marine Shale panel addressed only the government’s
    claim that Marine Shale failed to get a permit for operating minor-source
    emissions; and § 7475(a) applies only to major-emitting facilities. So, there is
    no indication that the Marine Shale opinion, in discussing the statute-of-
    limitations issue there, was considering preconstruction permits under §
    7475(a). 16 These distinctions between Marine Shale and our case illustrate the
    complexity of environmental statutes and regulations, as well as the
    importance in not confusing the myriad permits, pollutants, and prohibitions
    that are implicated in regulating the environment.
    Accordingly, we conclude that Marine Shale does not address the case
    we have today, and considering the clear statutory language of § 7475(a), we
    hold that a violation of the Preconstruction requirements under § 7475(a)
    occurs on the first day of unpermitted construction and the violation does not
    extend into operation. Let us be clear: any claim asserted under § 7475(a)
    accrues at the moment unpermitted construction commences.
    Finally, the plaintiffs argue that, even if the violation of § 7475(a) is a
    single occurrence at the commencement of construction, the Texas SIP
    construction-permit requirements obligate facilities to apply BACT during
    15  As to one of the permits at issue, Marine Shale “in effect conced[ed]” that it was a
    “preconstruction 
    permit,” 81 F.3d at 1356
    , but the government’s position is unknown. And
    in any event, it is uncertain whether that preconstruction permit was the absent permit at
    the center of the statute-of-limitations dispute. Indeed, the government here refers to the
    permit at issue in Marine Shale as “another type of [CAA] permit.”
    16 Other courts have eschewed Marine Shale’s conclusory analysis in the context of
    the § 7475(a) statute-of-limitations issue. See, e.g., United States v. Murphy Oil USA, Inc.,
    
    143 F. Supp. 2d 1054
    , 1082–83 (W.D. Wis. 2001); see also Ivan Lieben, Catch Me If You Can
    - the Misapplication of the Federal Statute of Limitations to Clean Air Act Psd Permit Program
    Violations, 38 ENVTL. L. 667, 692–93 (2008) (“Without any useful discussion of much
    significance to the PSD statute of limitations issue, the [Marine Shale] court also found that
    the statute of limitations did not apply to the minor source permitting violations.”).
    13
    Case: 17-10235         Document: 00514663975           Page: 14      Date Filed: 10/01/2018
    No. 17-10235
    operation. 17 See Nat’l Parks Conservation Ass’n, Inc. v. Tennessee Valley Auth.,
    
    480 F.3d 410
    , 418–19 (6th Cir. 2007) (holding the Tennessee SIP imposed
    ongoing operational obligations and avoiding the necessity of any statutory
    analysis of § 7475 itself).          We have previously held, however, that “the
    preconstruction requirements set forth in [Title 30 of the Texas Administrative
    Code, section 116.111(a)], such as evidence that the facility will utilize the best
    available control technology, are preconditions for granting a preconstruction
    permit.” CleanCOALition v. TXU Power, 
    536 F.3d 469
    , 477 (5th Cir. 2008)
    (emphasis in original). That is to say, Texas SIP section 116.111(a) instructs
    facilities what they must do to get a permit, not what obligations are imposed
    on the continuing operations of the facility.
    We sum up what we have decided: Section 7475(a) violations occur on
    the first day of construction, and the Texas SIP does not alter that holding. As
    we have said, for purposes of this appeal, each construction period that the
    plaintiffs say the defendants embarked upon in violation of § 7475(a)
    commenced more than five years before the government filed suit to recover
    civil penalties. Thus, the government’s claims for civil fines, penalties, and
    forfeitures are time barred under the five-year statute of limitations set in 28
    U.S.C. § 2462. 18 The district court, therefore, did not err in dismissing claims
    one, two, three, five and six asking for that legal relief.
    17 The plaintiffs point to Texas SIP § 116.111(a)(2)(C–D), under which a “new
    construction or modification” permit application must include information demonstrating:
    (C) Best available control technology (BACT). The proposed facility will utilize
    BACT . . . .
    (D) New Source Performance Standards (NSPS). The emissions from the
    proposed facility will meet the requirements of any applicable NSPS . . . .
    30 Tex. Admin. Code § 116.111(a)(2)(C–D) (2001) (emphasis added).
    18 The plaintiffs do not appeal the district court’s ruling on the applicability of a tolling
    agreement between the parties.
    14
    Case: 17-10235        Document: 00514663975          Page: 15     Date Filed: 10/01/2018
    No. 17-10235
    B.
    Injunctive Relief
    In addition to asking for civil penalties under 42 U.S.C § 7413(b), the
    government also requests injunctive relief. 19 And the plain language of § 2462
    does not explicitly bar the claims for injunctive relief. 20 Nevertheless, the
    district court dismissed the government’s equitable claims on two bases. First,
    the district court held that because the legal claims are time barred by § 2462,
    the injunctive-relief claims are also barred under the concurrent-remedies
    doctrine.    And second, the court held that “Congress did not provide for
    injunctive relief for past violations in the [CAA].” On appeal, we limit our
    analysis to whether the district court erred in dismissing the injunctive-relief
    claims for those two reasons.
    1.
    Concurrent-Remedies Doctrine
    The Supreme Court has long recognized that “when the jurisdiction of
    the federal court is concurrent with that of law, or the suit is brought in aid of
    19 At oral argument, counsel for the government was asked why the government had
    chosen to bring its claims expressly and only under § 7475 of the CAA instead of an
    alternative CAA section perhaps more friendly to the operational claims it seeks to assert
    here. Counsel explained that requiring the defendants to comply with § 7475(a) was the only
    way to impose BACT emission limitations on their respective facilities for certain pollutants.
    20 Under 28 U.S.C. § 2462:
    [A]n action, suit or proceeding for the enforcement of any civil fine, penalty, or
    forfeiture, pecuniary or otherwise, shall not be entertained unless commenced
    within five years from the date when the claim first accrued . . . .
    So injunctive-relief claims are barred under § 2462 if they are a “penalty.” The defendants
    concede they have not yet argued to the district court that the injunctive relief sought here is
    a penalty. And we do “not consider issues raised for the first time on appeal except in
    extraordinary instances when such consideration is required to avoid a miscarriage of
    justice.” Bayou Liberty Ass’n, Inc. v. U.S. Army Corps of Engineers, 
    217 F.3d 393
    , 398 (5th
    Cir. 2000). This case presents no such extraordinary instance. For the life of this case, the
    defendants have been free to argue to the district court that the relief requested was a
    penalty; but they have not yet done so. See, e.g., S.E.C. v. Bartek, 484 F. App’x 949, 956 (5th
    Cir. 2012) (affirming certain equitable remedies are penalties under § 2462).
    15
    Case: 17-10235    Document: 00514663975      Page: 16   Date Filed: 10/01/2018
    No. 17-10235
    a legal right, equity will withhold its remedy if the legal right is barred by the
    local statute of limitations.” Russell v. Todd, 
    309 U.S. 280
    , 289 (1940); see also
    Cope v. Anderson, 
    331 U.S. 461
    , 464 (1947); Nilsen v. City of Moss Point, Miss.,
    
    674 F.2d 379
    , 387 (5th Cir. 1982), on reh’g, 
    701 F.2d 556
    (5th Cir. 1983). For
    the reasons we have explained, § 2462 clearly bars the legal claims here. The
    question is whether the government’s equitable claims are also barred.
    At the outset of our analysis, we should make clear that, in the case of
    private litigants, the concurrent-remedies doctrine appears to be alive, well,
    and strong. For example, here, the concurrent-remedies doctrine may properly
    be invoked against Sierra Club, a private party acting on its own behalf. See,
    e.g., Oklahoma Gas & Elec. 
    Co., 816 F.3d at 675
    . Indeed, to allow equitable
    claims to proceed where the legal claims are time barred is counter-intuitive
    to general legal thought and reasoning. So we make clear, we address a very
    narrow set of circumstances: the sovereign acting in its sovereign capacity
    when it has not legislatively conceded, in any explicit terms, that a time bar
    may be applied to its equitable claims. It is that set of narrow circumstances
    that informs the following discussion.
    The plaintiffs argue that the concurrent-remedies doctrine does not bar
    their equitable claims for two reasons. First, Sierra Club argues that the
    concurrent-remedies doctrine does not apply to actions under the CAA because
    the civil-penalty and injunctive-relief provisions of the CAA are not concurrent.
    But courts agree “civil penalties and equitable relief . . . are concurrent [where]
    ‘an action at law or equity could be brought on the same facts.’” Tennessee
    Valley 
    Auth., 502 F.3d at 1327
    (quoting United States v. Telluride Co., 
    146 F.3d 1241
    , 1248 n.12 (10th Cir. 1998)). The parties do not dispute that the legal and
    equitable claims appealed here are brought on the same facts. The concurrent-
    remedies doctrine, therefore, is not inapt to this CAA action. See Otter Tail
    
    Power, 615 F.3d at 1018
    –19; Tennessee Valley 
    Auth., 502 F.3d at 1327
    .
    16
    Case: 17-10235        Document: 00514663975           Page: 17     Date Filed: 10/01/2018
    No. 17-10235
    Second, the plaintiffs urge us to follow the Tenth and Eleventh Circuits
    and acknowledge an exception to the concurrent-remedies doctrine in actions
    brought by the government in its sovereign capacity. 
    Telluride, 146 F.3d at 1248
    –49 (analyzing application of general statute of limitations, § 2462, to
    Clean Water Act claim asking for legal and equitable relief); United States v.
    Banks, 
    115 F.3d 916
    , 919 (11th Cir. 1997) (same).                     This issue is of first
    impression for our court, and there is, frankly, minimal precedent to guide our
    analysis. 21
    The Supreme Court has been unequivocal in its general demand that
    equitable relief is prohibited when a concurrent legal remedy is barred. See,
    e.g., 
    Russell, 309 U.S. at 289
    . But the Supreme Court has not had occasion to
    apply that doctrine to an action brought by the government in its sovereign
    capacity. Furthermore, the Supreme Court has been equally clear in holding
    that “an action on behalf of the United States in its governmental capacity . . .
    is subject to no time limitation, in the absence of congressional enactment
    clearly imposing it.” E. I. Du Pont De Nemours & Co. v. Davis, 
    264 U.S. 456
    ,
    462 (1924); see also United States v. P/B STCO 213, 
    756 F.2d 364
    , 368 (5th
    Cir. 1985) (“The sovereignty of the United States exempts it from all periods of
    21  In Federal Election Commission v. Williams, the Ninth Circuit, finding the Federal
    Election Commission’s legal claims barred by § 2462, applied the concurrent-remedies
    doctrine to also bar the Commission’s equitable claims. 
    104 F.3d 237
    , 240 (9th Cir. 1996).
    But in our view, there is no circuit split on the narrow issue before us because the Ninth
    Circuit did not consider that the government, acting in its sovereign capacity, is subject to no
    time limitation in the absence of clear consent. See 
    Banks, 115 F.3d at 919
    n.6 (“[Williams]. . .
    failed to distinguish between the application of the statute of limitations to the United States
    in its private versus its sovereign capacity. No other circuit has addressed this issue.”). The
    Ninth Circuit held only that “because the claim for injunctive relief is connected to the claim
    for legal relief, the statute of limitations [§ 2462] applies to both.” 
    Williams, 104 F.3d at 240
    .
    17
    Case: 17-10235       Document: 00514663975          Page: 18     Date Filed: 10/01/2018
    No. 17-10235
    limitations except where, by legislation, it expressly has consented to a time
    bar.”). 22
    It is somewhat problematic to reconcile these two rules when they
    coincide in a single case. Even though the government has subjected itself to
    the limitations imposed by § 2462 in CAA actions, the application of that
    statute “must receive a strict construction in favor of the Government.” E.I.
    
    Dupont, 264 U.S. at 462
    . To apply the concurrent-remedies doctrine here and
    thus bar the government’s equitable claims would exceed those explicit
    boundaries of sovereign consent.           After all, the government has expressly
    consented to a statutory time bar only in “the enforcement of any civil fine,
    penalty, or forfeiture.” 28 U.S.C. § 2462. We therefore can find no error in the
    Tenth and Eleventh Circuits’ decision to exempt actions brought by the
    government in its sovereign capacity from the application of the concurrent-
    remedies doctrine. In short, Congress has given no express consent. Thus, the
    district court erred in dismissing the government’s equitable-relief claims
    under Rule 12(b)(6) based on the concurrent-remedies doctrine.
    2.
    Jurisdiction
    The district court also dismissed the injunctive-relief claims on
    jurisdictional grounds under Rule 12(b)(1). The district court “assume[d]” that
    its “jurisdiction over Clean Air Act claims does not extend to injunctive relief”
    because “Congress did not provide for injunctive relief for past violations in the
    [CAA] but did provide a remedy for Prevention of Significant Deterioration
    violations before construction or modification” under 42 U.S.C § 7477. 23
    22  This rule “rests upon the general principle of policy applicable to all governments
    that the public interest should not be prejudiced by the default or negligence of public
    officers.” Bowers v. New York & Albany Lighterage Co., 
    273 U.S. 346
    , 349–50 (1927).
    23 Section 7477 states:
    18
    Case: 17-10235        Document: 00514663975          Page: 19      Date Filed: 10/01/2018
    No. 17-10235
    We have been referred to no authority that § 7477 is meant to displace
    the enforcement authority provided under § 7413. 24 See Alaska Dep’t of Envtl.
    Conservation v. E.P.A., 
    540 U.S. 461
    , 490 (2004) (referring to § 7413 and § 7477
    as “two independent CAA provisions”); Miller v. French, 
    530 U.S. 327
    , 340
    (2000) (“[W]e should not construe a statute to displace courts’ traditional
    equitable authority absent the ‘clearest command,’ or an ‘inescapable
    inference’ to the contrary . . . .” (citation omitted)).
    Nor can we agree with the district court’s broad holding that it simply
    lacks jurisdiction to consider any aspect of the injunctive relief requested here.
    Section 7413(b) plainly gives district courts jurisdiction to restrain a violation,
    require compliance, and award any other appropriate relief whenever a person
    has committed a § 7475 violation. The district court cited United States v. EME
    The Administrator shall, and a State may, take such measures, including
    issuance of an order, or seeking injunctive relief, as necessary to prevent the
    construction or modification of a major emitting facility which does not conform
    to the requirements of this part . . . .
    42 U.S.C. § 7477.
    24 We repeat, § 7413(b) states:
    The Administrator shall . . . commence a civil action for a permanent or
    temporary injunction, or to assess and recover a civil penalty of not more than
    $25,000 per day for each violation, or both, in any of the following instances:
    (1) Whenever such person has violated, or is in violation of, any
    requirement or prohibition of an applicable implementation plan or
    permit. . . .
    (2) Whenever such person has violated, or is in violation of, any other
    requirement or prohibition of this subchapter, section 7603 of this title,
    subchapter IV-A, subchapter V, or subchapter VI of this chapter . . . .
    ....
    Any action under this subsection may be brought in the district court of the
    United States for the district in which the violation is alleged to have occurred,
    or is occurring . . . and such court shall have jurisdiction to restrain such
    violation, to require compliance, to assess such civil penalty, to collect any fees
    owed . . . , and to award any other appropriate relief.
    42 U.S.C. § 7413(b) (emphasis added).
    19
    Case: 17-10235       Document: 00514663975          Page: 20     Date Filed: 10/01/2018
    No. 17-10235
    Homer City Generation, L.P. as the basis for its assuming the absence of
    jurisdiction in this case.           That case, in a critical way, is factually
    distinguishable from the case we consider today. The Third Circuit addressed
    injunctive relief against former owners of a facility who “cannot violate the Act
    in the future.” 
    25 727 F.3d at 292
    . The district court also relied on the Seventh
    Circuit’s opinion in United States v. Midwest Generation, LLC. But that case
    appears to have applied the concurrent-remedies doctrine, see United States v.
    U.S. Steel Corp., 
    16 F. Supp. 3d 944
    , 950–51 (N.D. Ind. 2014), which, in this
    case, we have found does not apply to the United States as a sovereign. Thus,
    the district court erred when it assumed that injunctive relief was beyond the
    authority granted in the statute.
    This opinion, however, should not be read as either favoring or
    disfavoring the grant of equitable relief. We hold only that the statute of
    limitations that barred the legal relief does not itself bar equitable relief unless
    it constitutes a penalty. On remand, the district court must further consider
    whether any equitable relief is appropriate and proper under the legal and
    factual circumstances of this case in which the legal relief has been time
    barred. 26 We recognize that we are not giving the district court much guidance
    in this task. Nevertheless, this case does come to us from a dismissal under
    12(b)(6) and 12(b)(1); and here the question of injunctive relief when no legal
    relief is available, is not an up or down question, especially since we have held
    25 The Third Circuit “express[ed] no opinion” on whether injunctions are “available in
    general to remedy ongoing harm from wholly past violations.” Homer 
    City, 727 F.3d at 291
    n.19. And as to current owners, the court there explained that the government could, after
    completion of a facility’s modification, “obtain an injunction requiring the owner and operator
    to comply with the PSD requirements.” 
    Id. at 289.
           26 In considering whether equitable relief, if any, is available, we simply note without
    further comment the Seventh Circuit’s holding, “Once the statute of limitations expired, [the
    defendant-facility] was entitled to proceed as if it possessed all required construction
    permits.” Midwest 
    Generation, 720 F.3d at 648
    .
    20
    Case: 17-10235        Document: 00514663975          Page: 21      Date Filed: 10/01/2018
    No. 17-10235
    that the doctrine of concurrent remedies does not apply against the sovereign.
    Perhaps the answer to this knotty question of injunctive relief will reveal itself
    after a full hearing and the presentations of the parties. And we hope that we
    are not being too cowardly when we sincerely wish the district court good luck.
    IV.
    Now, we briefly summarize our holdings:                        The Preconstruction
    requirements under § 7475(a) impose a one-time obligation on facilities to get
    a permit before they begin construction. So when a facility violates § 7475(a),
    it violates the statute on that singular occurrence when construction
    commences without a permit in hand.                    Section 7475(a) actions for the
    enforcement of any civil fine, penalty, or forfeiture must be brought within five
    years. The plaintiffs, having waited more than five years, are time barred from
    pursing § 7475 claims for civil fines, penalties, and forfeitures.
    Whether such injunctive relief is, in any of its aspects, considered a
    penalty has not been addressed in this appeal. See supra note 19. Because the
    government has brought this suit in its sovereign capacity, those injunctive-
    relief claims—which are determined not to be penalties under § 2462—are not
    subject to the limitation bar here. Thus the concurrent-remedies doctrine itself
    does not bar the government from pursuing non-penalty claims for injunctive
    relief. Moreover, we find no support for the district court’s holding that its
    “jurisdiction” does not “extend to injunctive relief” based on past violations of
    the CAA. 27
    We repeat that we do not prejudge whether equitable relief is available
    here. Inasmuch as this case comes to us on a motion to dismiss, there is more
    27  The role Sierra Club seeks to play in this litigation is unclear. But in any event, we
    have noted that the concurrent-remedies doctrine is properly applied as to it. So we remand
    the injunctive-relief claims to the district court, but once there, only the government may
    pursue them. We make no suggestion as to whether the government may pursue injunctive
    relief as to the now-closed Big Brown plant.
    21
    Case: 17-10235    Document: 00514663975        Page: 22   Date Filed: 10/01/2018
    No. 17-10235
    left to be done on remand. We leave it to the district court on remand to
    consider further the availability of equitable relief as we have noted above.
    The judgment of the district court is therefore
    AFFIRMED in part, REVERSED in part,
    and REMANDED.
    22
    Case: 17-10235       Document: 00514663975    Page: 23   Date Filed: 10/01/2018
    No. 17-10235
    JENNIFER WALKER ELROD,                Circuit Judge, concurring in part and
    dissenting in part:
    I concur in full with the portion of the majority opinion that holds—in
    alignment with all other circuits to consider the question—that a violation of
    42 U.S.C. § 7475(a) occurs only at the time of a facility’s unpermitted
    construction or modification, and that the operation of an unpermitted facility
    is not itself a violation of the statute. As such, I concur with the majority
    opinion’s determination that the appellants’ civil-penalty claims are now time-
    barred by 28 U.S.C. § 2462.         I also concur with the majority opinion’s
    determination that the concurrent-remedies doctrine bars Sierra Club’s claims
    for injunctive relief.
    I dissent from the majority opinion’s decision to remand this case for
    further consideration of the government’s claims for purported injunctive
    relief. It is a well-settled principle that “[t]he function of an injunction is to
    afford preventative relief, not to redress alleged wrongs which have been
    committed already.”        Lacassagne v. Chapuis, 
    144 U.S. 119
    , 124 (1892).
    Because the statute is concerned only with the construction or modification of
    a facility, and not its subsequent operation, there is no ongoing or future
    unlawful conduct to enjoin. As the Supreme Court has explained, granting an
    injunction without alleging an ongoing or future violation of the statute “makes
    a sword out of a shield.” Steel Co. v. Citizens for a Better Env’t, 
    523 U.S. 83
    ,
    109 (1998) (Scalia, J.).
    The fact that the government applies the term “injunction” to its
    requested remedies does not mean those remedies are actually injunctive. In
    remanding this case, the majority opinion focuses on the label and ignores the
    substance.    The remedies being sought by the government simply cannot
    properly be classified as injunctive. The remedies are being sought to redress
    23
    Case: 17-10235      Document: 00514663975         Page: 24    Date Filed: 10/01/2018
    No. 17-10235
    alleged past wrongs, and they are punitive in nature. As such, they are time-
    barred, no matter what label they may be masquerading under. The district
    court was correct to deny the government’s request for injunctions designed to
    redress wrongs that are alleged to have occurred wholly in the past, and there
    is no need for this case to be remanded for further consideration.
    I.
    The majority opinion explains why a violation of § 7475(a) can occur only
    at the time of construction or modification. Understanding that point is critical
    to understanding why the government’s requested relief is not properly
    categorized as injunctive. That categorization—whether the relief is or is not
    injunctive—is important in a case such as this, where the government has
    failed to prosecute its case for an alleged failure to obtain a permit within the
    applicable statute of limitations. As a result of the government’s delay, the
    court cannot enforce “any civil fine, penalty, or forfeiture, pecuniary or
    otherwise,” related to that failure to obtain a permit. 28 U.S.C. § 2462. 1
    The government’s brief lacks clarity as to the specific remedies it seeks
    under the banner of “injunctive relief.”           However, at oral argument, the
    government explained that the injunctive relief it seeks would take the form of
    compelling the appellees to: (1) apply for permits (which presumably would
    only be granted with an update of their emission technologies); and (2) “clean
    up the pollution” (which presumably refers to the surrender of cap-and-trade
    1 During oral argument, the government conceded, as it rightly should have, that if
    this court determines that a § 7475(a) violation occurs at the time of construction or
    modification, then 28 U.S.C. § 2462 would bar the government from seeking penalties for the
    alleged permitting violations at issue here. Oral Argument at 37:50, United States v.
    Luminant Generation Co., L.L.C. (No. 17-10235), http://www.ca5.uscourts.gov/oral-
    argument-information/oral-argument-recordings.
    24
    Case: 17-10235      Document: 00514663975       Page: 25     Date Filed: 10/01/2018
    No. 17-10235
    emissions credits requested in their complaint). 2             Unfortunately for the
    government, neither of those remedies are properly categorized as injunctive.
    First, the operation of the facilities without proper permitting under
    § 7475(a) is not a violation of the statute. As such, the court cannot use an
    injunction to compel the appellees to stop operations until they receive such
    permitting. “The sole function of an action for injunction is to forestall future
    violations,” United States v. Oregon State Med. Soc’y, 
    343 U.S. 326
    , 333 (1952),
    and unpermitted operation simply does not violate the statute.                See also
    Citizens for a Better 
    Env’t, 523 U.S. at 109
    (1998) (“Because respondent alleges
    only past infractions of [the relevant statute], and not a continuing violation or
    the likelihood of a future violation, injunctive relief will not redress its
    injury.”). Thus, as Judge Easterbrook has said for the Seventh Circuit (and
    which the majority opinion here notes without offering comment): “[o]nce the
    statute of limitations expired, [the defendant-facility] was entitled to proceed
    as if it possessed all required construction permits.” United States v. Midwest
    Generation, LLC, 
    720 F.3d 644
    , 648 (7th Cir. 2013).
    Second, to the extent that the government seeks for the appellees to be
    compelled to surrender their emission allowances to offset the additional
    pollution caused by their past failure to obtain a permit, that requested remedy
    cannot properly be considered injunctive either.           Such a remedy does not
    prevent future permitting infractions.         Instead, that remedy would quite
    clearly be a form of redress for operating today with permitting infractions that
    occurred in the past. As the Third Circuit correctly held in a similar case,
    “[s]uch injunctive cap-and-trade relief is the equivalent of awarding monetary
    relief and could not be reasonably characterized as an injunction. . . . It would
    2 Oral Argument at 7:30, United States v. Luminant Generation Co., L.L.C. (No. 17-
    10235), http://www.ca5.uscourts.gov/oral-argument-information/oral-argument-recordings.
    25
    Case: 17-10235       Document: 00514663975          Page: 26     Date Filed: 10/01/2018
    No. 17-10235
    amount to little more than an end-run around the five-year statute of
    limitations on any civil fine, penalty, or forfeiture.” United States v. EME
    Homer City Generation, LP, 
    727 F.3d 274
    , 295–96 (3rd Cir. 2013) (citations
    omitted).
    Thus, both of these so-called forms of injunctive relief are really just
    time-barred penalties in disguise. See, e.g., Kokesh v. S.E.C., 
    137 S. Ct. 1635
    ,
    1643–45 (2017) (identifying the hallmarks of a 28 U.S.C. § 2462 penalty as: (1)
    a violation committed against the government rather than against an
    aggrieved individual; and (2) a remedy that is imposed, at least in part, for
    punitive rather than solely compensatory purposes). 3
    There may be good policy arguments for prohibiting the operation of
    unpermitted facilities in addition to prohibiting their unpermitted construction
    or modification. On the other hand, there may be good policy arguments for
    grandfathering in changes to emissions requirements by tying them to each
    facility’s construction or modification. See generally Homer 
    City, 727 F.3d at 289
    –90 (summarizing arguments as to why Congress may or may not have
    drafted the statute to apply only to a facility’s construction or modification).
    However, in reaching our determination, such an argument is beyond the
    proper role of Article III courts. See Rodriguez v. United States, 
    480 U.S. 522
    ,
    526 (1987) (noting that when statutory language is clear, the courts should not
    examine additional considerations of policy that may or may not have
    influenced the lawmakers). Simply put, as it is currently written, 42 U.S.C.
    § 7475(a) cannot be read to permit the government to obtain the remedies it is
    requesting when it has waited longer than five years to initiate proceedings
    3 The Supreme Court decided Kokesh during the pendency of this appeal. On remand,
    the district court is of course free to consider the so-called injunctive relief sought by the
    government through the helpful lens of Kokesh.
    26
    Case: 17-10235       Document: 00514663975          Page: 27     Date Filed: 10/01/2018
    No. 17-10235
    alleging unpermitted construction or modification. If that outcome needs to be
    changed, the remedy properly lies with Congress and not with the courts.
    II.
    Unfortunately, in its failure to remove the mask from the government’s
    requested forms of relief and call them the time-barred penalties that they are,
    the majority opinion unnecessarily dives into a circuit split on the question of
    whether the courts should judicially create a sovereign actor exception to the
    judicially-created doctrine of concurrent-remedies. Compare United States v.
    Banks, 
    115 F.3d 916
    , 918–19 (11th Cir. 1997), and United States v. Telluride
    Co., 
    146 F.3d 1241
    , 1248–49 (10th Cir. 1998), with Fed. Election Comm’n v.
    Williams, 
    104 F.3d 237
    , 240 (9th Cir. 1996). By siding with the Tenth and
    Eleventh Circuits in creating such an exception, the majority opinion throws
    itself behind a holding that is, at the very least, questionable. 4 I would not be
    so hasty. At this juncture, I see little wisdom in rushing headlong to judicially-
    create yet another doctrinal exception that will generate a possibility of never-
    ending liability in tension with statutory language. See Delek Ref., Ltd. v.
    Occupational Safety & Health Review Comm’n, 
    845 F.3d 170
    , 177 (5th Cir.
    2016). As such, I would not in this case reach the question of whether a
    4 The Banks opinion (which the Telluride court adopts without additional analysis)
    rests on a shaky foundation for at least two different reasons. First, the Banks opinion is
    built around an assertion that the Supreme Court has since contradicted, which is that “[t]he
    plain language of section 2462 does not apply to equitable remedies.” 
    Banks, 115 F.3d at 919
    .
    Except that it does. See 
    Kokesh, 137 S. Ct. at 1645
    (holding that the SEC’s disgorgement
    actions are time-barred as a penalty under 28 U.S.C. § 2462); Tull v. United States, 
    481 U.S. 412
    , 424 (1987) (noting that disgorgement is traditionally considered an equitable remedy).
    Second, the Banks opinion (and all those that adopt it without further analysis, to include
    this majority opinion) appears to conflate two entirely distinct but nuanced concepts: statutes
    of limitations, from which the sovereign remains exempt unless it has clearly bound itself,
    and the scope of equity’s reach, which is cabined by the concurrent-remedies rule. See also
    United States v. U.S. Steel Corp., 
    966 F. Supp. 2d 801
    , 812–16 (N.D. Ind. 2013) (reversed in
    part on reconsideration on other grounds) (analyzing how the Banks opinion appears to have
    conflated these distinct concepts, and noting that its holding has since been parroted by many
    other courts).
    27
    Case: 17-10235    Document: 00514663975     Page: 28   Date Filed: 10/01/2018
    No. 17-10235
    sovereign actor exception should be created for the concurrent-remedies
    doctrine.
    III.
    In remanding this case, the majority opinion takes great care to stress
    that further review of the facts may lead to the conclusion that the
    government’s remaining claims for “injunctive” relief are nonetheless time-
    barred or otherwise inappropriate. However, I believe that this is all but a
    foregone conclusion. I would affirm the district court’s judgment in full and
    without remand. Therefore, I respectfully dissent in part.
    28
    

Document Info

Docket Number: 17-10235

Citation Numbers: 905 F.3d 874

Filed Date: 10/1/2018

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (31)

united-states-v-telluride-company-named-the-telluride-company-mountain , 146 F.3d 1241 ( 1998 )

National Parks & Conservation Ass'n v. Tennessee Valley ... , 502 F.3d 1316 ( 2007 )

Isaiah Russell Jones Robert Sparks, Jr. Herman Parks, Jr. v.... , 339 F.3d 359 ( 2003 )

CleanCOALition v. TXU POWER , 536 F.3d 469 ( 2008 )

Zephyr Aviation, L.L.C., Zephyr Aviation, L.L.C. v. Robert ... , 247 F.3d 565 ( 2001 )

United States of America, Plaintiff-Counter-Defendant-... , 115 F.3d 916 ( 1997 )

United States v. Core Laboratories, Inc. , 759 F.2d 480 ( 1985 )

United States of America, United States of America, State ... , 81 F.3d 1329 ( 1996 )

Sierra Club, Inc. v. SANDY CREEK ENERGY ASSOCIATES , 627 F.3d 134 ( 2010 )

Louisiana World Exposition v. Federal Insurance Company , 858 F.2d 233 ( 1988 )

Agnes E. NILSEN, Plaintiff-Appellant, v. the CITY OF MOSS ... , 674 F.2d 379 ( 1982 )

United States v. Wong Kim Bo, A/K/A Yee Kuk Ho, Etc. , 472 F.2d 720 ( 1972 )

Bayou Liberty Ass'n v. United States Army Corps of Engineers , 217 F.3d 393 ( 2000 )

anthony-a-edwards-v-johnson-mr-education-specialist-at-federal , 209 F.3d 772 ( 2000 )

Federal Election Commission v. Larry R. Williams , 104 F.3d 237 ( 1996 )

Bowers v. New York & Albany Lighterage Co. , 273 U.S. 346 ( 1927 )

National Parks Conservation Association, Inc. Sierra Club, ... , 480 F.3d 410 ( 2007 )

Sierra Club v. Otter Tail Power Co. , 615 F.3d 1008 ( 2010 )

Russell v. Todd , 309 U.S. 280 ( 1940 )

Agnes E. NILSEN, Plaintiff-Appellant, v. the CITY OF MOSS ... , 701 F.2d 556 ( 1983 )

View All Authorities »