Alliance for the Protection of the Auburn Community Environment v. County of Placer CA3 ( 2015 )


Menu:
  • Filed 8/31/15 Alliance for the Protection of the Auburn Community Environment v. County of Placer CA3
    NOT TO BE PUBLISHED
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    THIRD APPELLATE DISTRICT
    (Placer)
    ----
    ALLIANCE FOR THE PROTECTION OF THE                                                           C077308
    AUBURN COMMUNITY ENVIRONMENT etc., et
    al.,                                                                           (Super. Ct. No. SCV0034435)
    Plaintiffs and Appellants,
    v.
    COUNTY OF PLACER,
    Defendant and Respondent;
    WALMART STORES, INC.,
    Real Party in Interest and Respondent.
    After losing its first challenge to the adequacy of the environmental review of a
    proposed project to build a retail center, including a Walmart store, and before County of
    Placer (County) undertook any further discretionary approvals, the Alliance for the
    Protection of the Auburn Community Environment (APACE) filed a petition for a writ of
    mandamus alleging the County violated the California Environmental Quality Act
    1
    (CEQA; Pub. Resources Code, § 21000 et seq.) by failing to prepare a subsequent
    environmental impact report (EIR) in light of “new information” about soil
    contamination on the project site. The trial court sustained the County and Walmart
    Stores, Inc.’s (Walmart) demurrer without leave to amend. We affirm the judgment of
    dismissal because plaintiff alleges on the face of the complaint that the County has not
    granted a discretionary approval, by issuing a building permit or any other approval, and
    “[i]n the absence of such discretionary approval, the agency has no jurisdiction to prepare
    a subsequent or supplemental EIR.” (San Diego Navy Broadway Complex Coalition v.
    City of San Diego (2010) 
    185 Cal. App. 4th 924
    , 935 (San Diego); Cucamongans United
    for Reasonable Expansion v. City of Rancho Cucamonga (2000) 
    82 Cal. App. 4th 473
    , 479
    (Cucamongans).)
    FACTUAL AND PROCEDURAL BACKGROUND
    In September 2010 the County certified the final EIR for the development of a
    155,000-square-foot building. Three days after the 30-day statute of limitations had run,
    APACE filed a petition for a writ of mandate alleging various CEQA violations. The
    trial court sustained the demurrer of the County and real party in interest Bohemia
    Properties, LLC, without leave to amend, and we affirmed the judgment of dismissal.
    (Alliance for Protection of Auburn Community Environment v. County of Placer (2013)
    
    215 Cal. App. 4th 25
    , 28 (Alliance).)
    APACE’s second petition for a writ of mandate alleges that newly discovered
    information about elevated levels of dioxins and furans in the ground soil rendered the
    initial environmental review obsolete and the dangers to health unaddressed in both the
    draft EIR and the final EIR. The petition further alleges that on December 10, 2013,
    APACE formally requested the County to prepare a subsequent EIR to consider the new
    information, and on December 27, 2013, Walmart submitted building plans and building
    permit applications, as well as related permits. APACE alleges “[t]hese plans and permit
    applications have yet to be approved.”
    2
    The petition references the “County Grading Ordinance” but does not allege that
    anyone has applied for a grading permit. The petition states: “Mitigation Measure 11-
    2(b) of the [final EIR] requires Walmart conform its plan to the County Grading
    Ordinance. The County Grading Ordinance (‘the Grading Ordinance’) at § 15.48.240(A)
    in turn requires conformity to the General Plan. The Grading Ordinance also requires at
    § 15.48.240(C) that the approving agency impose whatever conditions on a grading
    permit necessary to protect the ‘health, safety, and general welfare,’ of the public.”
    The County did not act on APACE’s request to prepare a subsequent EIR and,
    according to the petition, did not give any indication it would do so.
    The trial court sustained Walmart and the County’s demurrer without leave to
    amend. APACE appeals.
    DISCUSSION
    I
    Standard of Review
    A demurrer tests the legal sufficiency of the petition. Our determination whether
    the petition states a viable cause of action therefore is de novo. A demurrer admits the
    truth of all material factual allegations, which we read as a whole and to which we give a
    reasonable interpretation. 
    (Alliance, supra
    , 215 Cal.App.4th at p. 29.) We independently
    construe the meaning of statutes and regulations, as they present questions of law, and if
    no liability exists as a matter of law we must affirm the trial court’s order sustaining the
    demurrer. (City of Morgan Hill v. Bay Area Air Quality Management Dist. (2004)
    
    118 Cal. App. 4th 861
    , 870.)
    II
    Jurisdiction
    Once an EIR has been certified, there is a statutory presumption against requiring
    further environmental review of the same project. (Moss v. County of Humboldt (2008)
    
    162 Cal. App. 4th 1041
    , 1049-1050.) Public Resources Code section 21166 provides:
    3
    “When an [EIR] has been prepared for a project pursuant to this division, no subsequent
    or supplemental [EIR] shall be required by the lead agency or by any responsible agency,
    unless one or more of the following events occurs: [¶] . . . [¶] (c) New information,
    which was not known and could not have been known at the time the [EIR] was certified
    as complete, becomes available.” “ ‘This provision represents a shift in the applicable
    policy considerations. The low threshold for requiring the preparation of an EIR in the
    first instance is no longer applicable; instead, agencies are prohibited from requiring
    further environmental review unless the stated conditions are met.’ ” (Melom v. City of
    Madera (2010) 
    183 Cal. App. 4th 41
    , 48-49.)
    The CEQA Guidelines add more muscle to the statutory limitation.1
    Section 15162, subdivision (c) of the Guidelines states: “Once a project has been
    approved, the lead agency’s role in project approval is completed, unless further
    discretionary approval on that project is required. Information appearing after an
    approval does not require reopening of that approval. If after the project is approved, any
    of the conditions described in subdivision (a) occurs, a subsequent EIR or negative
    declaration shall only be prepared by the public agency which grants the next
    discretionary approval for the project, if any. In this situation no other responsible
    agency shall grant an approval for the project until the subsequent EIR has been certified
    or subsequent negative declaration adopted.”
    The County argues that its role is completed because it has not granted a “further
    discretionary approval.” The County’s position finds support in San 
    Diego, supra
    ,
    
    185 Cal. App. 4th 924
    and 
    Cucamongans, supra
    , 
    82 Cal. App. 4th 473
    . Both cases held that
    a public agency can require a supplemental or subsequent EIR only when the agency
    grants a discretionary approval. (San Diego, at p. 935; Cucamongans, at p. 479.) “In the
    1 CEQA is augmented by the Guidelines for Implementation of the California
    Environmental Quality Act. (Cal. Code Regs., tit. 14, § 15000 et seq. (Guidelines).)
    4
    absence of such discretionary approval, the agency has no jurisdiction to prepare a
    subsequent or supplemental EIR. (
    Cucamongans, supra
    , 82 Cal.App.4th at p. 479.) This
    jurisdictional limitation is consistent with the notion that it is nonsensical to require an
    agency to prepare a subsequent or supplemental EIR unless the agency has the authority
    to take action that would respond to any concerns that might be raised in the updated
    EIR.” (San 
    Diego, supra
    , 185 Cal.App.4th at pp. 935-936.) Simply put, “ ‘once all
    discretionary approvals have been obtained, no agency has jurisdiction to require a
    further EIR.’ ” (Cucamongans, at p. 479.)
    In Cucamongans, the public agency had denied the applicant’s design review
    application before the petitioners requested further environmental review. Since a
    subsequent EIR can only be prepared in connection with a discretionary approval and the
    design review application had been denied, “there was no discretionary approval that
    would authorize the preparation of [a subsequent EIR].” (
    Cucamongans, supra
    ,
    82 Cal.App.4th at p. 479.)
    The facts before us are analogous to those presented in Cucamongans. The only
    difference is timing. In Cucamongans, the application had been denied, and as a result,
    there was no discretionary approval to challenge. According to APACE’s petition,
    building permits are pending but the County has not approved the permits. Thus,
    whereas in Cucamongans there was no discretionary approval because the application
    had been denied, in the instant case there has been no discretionary approval because the
    application has not been acted on.
    Because here, as in Cucamongans, there is no approval, we need not address the
    more difficult issue presented in San Diego as to whether the approval that was granted
    was discretionary. Approval is not discretionary if it does not allow the agency to shape
    the project. (Friends of Westwood, Inc. v. City of Los Angeles (1987) 
    191 Cal. App. 3d 259
    , 266-267.) The “touchstone” for determining whether an approval is “discretionary”
    5
    is whether the agency would be able to meaningfully address the environmental concerns
    that might be identified in the EIR or subsequent EIR. (Ibid.)
    In San Diego, the court found the approval was not discretionary because the
    agency had no authority to modify the project based on additional environmental analysis
    of global climate change. (San 
    Diego, supra
    , 185 Cal.App.4th at p. 938.) Rather, the
    agency’s authority was limited to a determination whether the aesthetics of the project
    were consistent with the development agreement. (Id. at p. 940.) If, and when, there is
    an approval of Walmart’s building permits, the issue might arise whether the public
    agency with authority to approve the permits also has the discretion to modify the project
    in accordance with environmental concerns identified in a subsequent EIR. In short, the
    question will be whether the approval of a building permit is discretionary or ministerial
    under the applicable municipal ordinances. But that issue is not before us now.2 The
    issue before us is much simpler. Since there has been no approval of the building permit
    application, the law is clear that the County is without jurisdiction to require a
    supplemental or subsequent EIR.
    APACE complains that the law does not match its notion of common sense. It is
    true that one of CEQA’s purposes is to provide early environmental review to inform
    decision makers of potential adverse environmental impacts of a proposed project. (Pub.
    Resources Code, § 21002; Guidelines, § 15003.) APACE fails to distinguish the
    difference between the policies fostering thorough environmental review before a project
    is approved and the policies favoring finality once the EIR is certified and the project is
    2 We reject APACE’s accusation in its opposition to the demurrer that the County
    “implicitly concede[d]” sufficient new information was discovered which would
    generally trigger the duty to prepare a subsequent EIR. Because the case was decided on
    the threshold issue of jurisdiction does not mean there was any concession that the
    remaining issues were without merit. Rather, the jurisdictional issue is dispositive and
    the County simply did not address, nor do we, issues that are unnecessary to resolution of
    the matter.
    6
    approved. Once the project is approved, finality trumps reopening the environmental
    review process except in the narrow circumstances defined in Public Resources Code
    section 21166 and Guidelines section 15162, subdivision (c). And it is the Legislature
    and the regulatory bodies that define jurisdiction, not petitioner’s amorphous and pliable
    notion of common sense.
    APACE also criticizes the court’s rationale for the ruling, including its discussion
    of ripeness. Because statutory construction presents a question of law, we are not bound
    by the trial court’s reasoning. We need not, therefore, consider the nuances and
    exceptions to the ripeness doctrine, having resolved the matter based on a jurisdictional
    defect.
    Yet APACE insists our rationale “would lead to the anomalous result that
    supplemental or subsequent environmental review is appropriate only in cases where no
    agency has jurisdiction to require supplemental or subsequent environmental review.”
    Not so. Guidelines section 15162, subdivision (c) assigns “the public agency which
    grants the next discretionary approval for the project” the task of preparing the
    subsequent EIR. APACE’s petition acknowledges that no agency has approved the
    building permit, nor does it allege that any grading permits have been approved.3
    Whether the approval of building or grading permits is discretionary within the meaning
    of CEQA is one of many issues we need not consider at this juncture.
    Rebutting the trial court’s finding that its challenge was not authorized because the
    County had not made a “determination” or “decision” pursuant to Public Resources Code
    sections 21168 and 21168.5, APACE argues for the first time on appeal that the County
    3 APACE mischaracterizes the allegations of the petition. In its opening brief, it argues
    that the approval of grading permits is a discretionary approval. But while the petition
    quotes from the ordinance governing grading permits, it certainly does not allege that
    Walmart or any other entity has specifically applied for grading permits, let alone that
    any grading permits have been approved.
    7
    impliedly exempted the project from further environmental review. APACE insists the
    trial court applied an “overly-narrow understanding of a ‘determination’ under CEQA.”
    It may be, as APACE suggests, that the decision not to conduct further environmental
    review constitutes a determination under CEQA without any need to characterize the
    determination as finding an exemption. But even if we were to accept APACE’s
    argument, it would not cure the jurisdictional defect. And the jurisdictional defect alone
    justifies the ruling sustaining the demurrer without leave to amend and requires us to
    affirm the judgment of dismissal.
    A very old case proves the enduring nature of this basic principle. In Heap v. City
    of Los Angeles (1936) 
    6 Cal. 2d 405
    (Heap), an ex-employee, after discharge, sought an
    investigation and hearing by the civil service commission. The City of Los Angeles
    demurred to the ex-employee’s petition for a writ of mandate for reinstatement. (Id. at
    p. 406.) On appeal, the court upheld the judgment of dismissal, finding the civil service
    commission had exhausted its jurisdiction when it adopted its first resolution sustaining
    his discharge. (Id. at pp. 406-407.) The city charter did not give the commission a grant
    of power to entertain a motion for a new trial or for a rehearing and review with the
    possibility of setting aside its prior order. (Id. at p. 407.) Thus, because the commission
    did not have jurisdiction to issue a subsequent order, the demurrer was properly
    sustained. (Id. at p. 408.)
    Similarly, the County, like the civil service commission in Heap, did not have
    jurisdiction to require a supplemental or subsequent EIR once the EIR was certified and
    the project was approved unless one of the limited circumstances encompassed by Public
    Resources Code section 21166 occurred and a discretionary approval was granted
    pursuant to Guidelines section 15162, subdivision (c). In the absence of jurisdiction, a
    court could not order the County to act, and therefore the demurrer, as in Heap, was
    properly sustained.
    8
    DISPOSITION
    The judgment is affirmed.
    RAYE   , P. J.
    We concur:
    ROBIE            , J.
    DUARTE           , J.
    9
    

Document Info

Docket Number: C077308

Filed Date: 8/31/2015

Precedential Status: Non-Precedential

Modified Date: 4/17/2021