VT Halter Marine, Inc. v. Wartsila North America, Inc. , 511 F. App'x 358 ( 2013 )


Menu:
  •      Case: 12-60051       Document: 00512139208         Page: 1     Date Filed: 02/08/2013
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    February 8, 2013
    No. 12-60051                        Lyle W. Cayce
    Clerk
    VT HALTER MARINE, INCORPORATED,
    Plaintiff–Appellant
    v.
    WARTSILA NORTH AMERICA, INCORPORATED,
    Defendant–Appellee
    Appeal from the United States District Court
    for the Southern District of Mississippi
    1:11-CV-250
    Before WIENER, CLEMENT, and PRADO, Circuit Judges.
    PER CURIAM:*
    VT Halter Marine, Inc. (“VTHM”) appeals the district court’s grant of
    Wartsila North America, Inc.’s (“Wartsila”) motion to compel arbitration.
    Because we hold that VTHM did not agree to arbitrate disputes with Wartsila,
    we REVERSE and REMAND to the district court for a determination of whether
    one of the exceptions that bind non-signatories to arbitration agreements applies
    here.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    *
    Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH CIR.
    R. 47.5.4.
    Case: 12-60051   Document: 00512139208      Page: 2   Date Filed: 02/08/2013
    No. 12-60051
    A.    Factual Background
    This case concerns three parties, two contracts, and one arbitration clause.
    Third-party ship operator Vessel Management Services, Inc. (“Vessel
    Management”) contracted with Plaintiff–Appellant VTHM (the “Construction
    Contract”) to construct several vessels, including the M/V Pride (the “Pride”).
    Under the Construction Contract, Vessel Management would supply VTHM with
    various components for the vessels, including the main engines, shaft, hub, and
    blades. VTHM would receive and store those parts at its shipyard pending
    installation in a vessel for Vessel Management.
    Vessel Management also entered into a contract with Defendant–Appellee
    Wartsila (the “Sales Contract”), under which Wartsila would provide components
    for Vessel Management’s vessels.     The Sales Contract between Wartsila and
    Vessel Management includes a mandatory arbitration clause, which states,
    This Agreement shall be construed in accordance with the laws of
    the State of New York, without reference to its conflict of laws
    provisions. Any dispute between the parties arising out of or in
    connection with this Agreement shall be finally settled under the
    Rules of Arbitration of the American Arbitration Association by one
    or more arbitrators appointed in accordance with the said rules, in
    New York, New York.
    To be clear, VTHM is not a party to the Sales Contract, and is thus a “non-
    signatory” with respect to it; VTHM and Wartsila have not entered into any
    contract with each other.
    Pursuant to the Sales Contract, Vessel Management bought propulsion
    systems (a/k/a shaft/hub assemblies) from Wartsila for the vessels VTHM was
    building, including the Pride. Wartsila delivered the propulsion systems directly
    to VTHM at its shipyard for storage until they could be installed. VTHM later
    installed a propulsion system in the Pride. Thereafter, the Pride’s propulsion
    2
    Case: 12-60051   Document: 00512139208     Page: 3   Date Filed: 02/08/2013
    No. 12-60051
    system failed inspection. VTHM claims that Wartsila represented to Vessel
    Management that VTHM’s poor workmanship caused the failure. Based on
    Wartsila’s representation, Vessel Management demanded that VTHM purchase
    a replacement propulsion system for the Pride. VTHM states that although it
    believed that Wartsila’s representation about VTHM’s workmanship was false,
    it purchased a new propulsion system to avoid liquidated damages under the
    Construction Contract.
    B.    Procedural Background
    VTHM sued Wartsila, seeking to recover damages that it alleges it
    sustained through having to replace Wartsila’s defective propulsion system and
    through Wartsila’s representation that VTHM was responsible for the Pride’s
    failure. VTHM alleges two causes of action: (1) breach of warranty and (2)
    tortious interference with contractual relations. First, as to the breach of
    warranty claim, VTHM contends that although it is not a party to the Sales
    Contract, it has the right, as an “equitable subrogee,” to stand in the shoes of
    Vessel Management to enforce Wartsila’s obligation to replace the failed
    propulsion system under the Sales Contract’s warranty. As to the second claim,
    VTHM asserted that Wartsila tortiously interfered with VTHM’s contractual
    relationship with Vessel Management (viz., the Construction Contract) by falsely
    telling Vessel Management that VTHM incorrectly installed the propulsion
    system.
    Wartsila moved to compel arbitration as to both claims. VTHM conceded
    that its first claim, breach of warranty, was subject to mandatory arbitration
    because the breach of warranty claim was derived from Vessel Management’s
    rights under its Sales Contract with Wartsila, which had a mandatory
    arbitration clause. VTHM made no such concession, however, as to its tortious
    interference claim. The district court granted Wartsila’s motion, ordering both
    3
    Case: 12-60051   Document: 00512139208     Page: 4    Date Filed: 02/08/2013
    claims to arbitration and dismissing both. VTHM appealed to this Court,
    arguing that, as a non-signatory to the arbitration agreement between Wartsila
    and Vessel Management, it is not bound by it. VTHM argues, further, that none
    of the exceptions that bind non-signatories to arbitration agreements applies in
    this case.
    II. JURISDICTION AND STANDARD OF REVIEW
    The district court entered final judgment on this matter on December 14,
    2011. This Court has jurisdiction pursuant to 
    28 U.S.C. § 1291
    .
    Generally, the Fifth Circuit reviews the grant or denial of a motion to
    compel arbitration de novo. Noble Drilling Servs., Inc. v. Certex USA, Inc., 
    620 F.3d 469
    , 472 n.4 (5th Cir. 2010). But, when a district court applies equitable
    estoppel to compel arbitration, this Court determines only whether the district
    court has abused its discretion. Id.; see also Grigson v. Creative Artists Agency
    L.L.C., 
    210 F.3d 524
    , 528 (5th Cir. 2000). VTHM argues that the district court
    did not rely on equitable estoppel, and so de novo review must be applied.
    Wartsila seeks to avoid de novo review by contending that although the
    district court did not expressly refer to equitable estoppel, it nevertheless relied
    on it. For Wartsila, because “[equitable] estoppel doctrine is the only basis by
    which VTHM could have been compelled to arbitrate its claims,” the district
    court must have relied on it without stating so. Wartsila fails to consider,
    however, that the district court may simply have erred in compelling arbitration
    on the tortious interference claim. The district court, in a three-page opinion,
    never refers to equitable estoppel or appeals to the policy justifications behind
    equitable estoppel.
    Wartsila provides no case, and we can find none, where this Court
    reviewed for abuse of discretion a district court order compelling arbitration that
    did not clearly apply equitable estoppel. Because there is no indication from the
    district court’s order that it applied equitable estoppel, we assume that it did
    not.
    4
    Case: 12-60051     Document: 00512139208      Page: 5    Date Filed: 02/08/2013
    III. DISCUSSION
    Arbitration is a contract matter between parties, and a court generally
    cannot compel a party to arbitrate a dispute unless the parties agreed to
    arbitrate the dispute in question. Pennzoil Exploration & Prod. Co. v. Ramco
    Energy Ltd., 
    139 F.3d 1061
    , 1064 (5th Cir. 1998) (citing AT&T Techs., Inc. v.
    Commc’ns Workers, 
    475 U.S. 643
    , 648 (1986)); see also Stolt–Nielsen S.A. v.
    AnimalFeeds Int’l Corp., 
    130 S. Ct. 1758
    , 1774 (2010) (“We think it is also clear
    from our precedents and the contractual nature of arbitration that parties may
    specify with whom they choose to arbitrate their disputes . . . . Nothing in the
    FAA authorizes a court to compel arbitration of any issues, or by any parties,
    that are not already covered in the agreement.” (internal quotation marks,
    citations, and alterations omitted)). This Court in Pennzoil articulated the two
    general requirements for compelling a party to arbitrate a particular dispute: the
    court must determine both that (1) the two parties have a valid agreement to
    arbitrate, and (2) the dispute in question falls within the scope of that
    arbitration agreement.     
    139 F.3d at 1065
    .      The district court most likely
    overlooked that VTHM is not a party to the Sales Contract containing the
    arbitration clause. The district court cited Pennzoil as the basis for its analysis,
    suggesting that it would evaluate first, whether the two parties had a valid
    agreement to arbitrate, and second, whether the dispute in question fell within
    the scope of that arbitration agreement. See 
    id.
     However, the district court
    appears to have skipped the first requirement (did the parties have a valid
    agreement to arbitrate?) and instead jumped straight to the second (did the
    dispute in question fall within the scope of the agreement?).
    There are two indications that the district court overlooked the first
    requirement. First, the court’s order cited the part of Pennzoil that addresses
    the second requirement. See Pennzoil, 
    139 F.3d at 1067
    . Moreover, the district
    court’s discussion includes references to two cases that addressed Pennzoil’s
    second step. The first case, Brandom v. Gulf Coast Bank & Trust Co., No. 00-
    5
    Case: 12-60051    Document: 00512139208       Page: 6   Date Filed: 02/08/2013
    11119, 
    2001 WL 498720
     (5th Cir. Apr. 16, 2001) (unpublished), concerns the
    “scope of the arbitration clause.” 
    Id. at *1
    . The second case, Prima Paint Corp.
    v. Flood & Conklin Manufacturing Co., 
    388 U.S. 395
    , 396–98 (1967), deals with
    whether fraud was within the scope of an arbitration agreement. In both cases
    cited by the district court, the threshold inquiry of whether the parties agreed
    to arbitrate in the first place was undisputed.
    Second, the order’s language focuses only on the broad scope of the
    arbitration agreement: “[t]his Court must resolve any doubts concerning the
    scope of coverage of a contractual arbitration clause in favor of arbitration”;
    “[t]he arbitration clause in this case encompasses ‘any dispute’ between the
    parties ‘arising out of’ or ‘in connection with’ the Agreement.” This focus on
    scope suggests the court evaluated only the second step. The district court never
    determined whether VTHM and Wartsila had a valid agreement to arbitrate in
    the first place. If the district court had undertaken that determination it would
    have concluded that they did not, ending the inquiry at requirement one; the
    district court should not have reached requirement two.
    The district court seems to have overlooked that there were two separate
    contracts mentioned in VTHM’s claims. The Sales Contract between Vessel
    Management and Wartsila contained a presumably valid agreement to arbitrate.
    VTHM acknowledges that because its breach of warranty claim is derived from
    the Sales Contract between Vessel Management and Wartsila, it must arbitrate
    that claim. But there is no contract between VTHM and Wartsila that would
    compel VTHM to arbitrate its tortious interference claim. The district court’s
    order never articulates a distinction between the two contracts. In fact, the
    district court references “the Arbitration Agreement at issue [10-1],” but that
    agreement is not between the two parties to the suit, Wartsila and VTHM.
    Rather, it is between Wartsila and third-party Vessel Management. This
    reference suggests that the district did not contemplate that there were two
    separate contracts at issue. The citation evidence, coupled with the order’s
    6
    Case: 12-60051        Document: 00512139208           Page: 7     Date Filed: 02/08/2013
    language, indicates that the court incorrectly assumed VTHM was the second
    party to the arbitration agreement, not Vessel Management.**
    Ultimately, regardless of whether the district court correctly understood
    the nature of the contracts between the parties, Wartsila concedes that it has no
    valid agreement to arbitrate with VTHM.                   Thus, the first requirement of
    Pennzoil cannot be satisfied; VTHM cannot be compelled to arbitrate under
    general arbitration principles and the district court erred in so holding.
    We decline to determine whether equitable estoppel compels arbitration
    at this point. Instead, we remand this case to the district court to determine
    whether direct benefits equitable estoppel applies, as Wartsila urges.
    For the foregoing reasons, we REVERSE the district court’s order and
    REMAND for further determination of whether equitable estoppel compels
    arbitration.
    **
    There was one part of the district court’s order that could be read to indicate that the
    court realized there were two separate contracts. The final page of the order states “the
    [c]ourt is of the view that Plaintiff’s tortious interference claim ‘arose out of or in connection
    with’ the contract between Wartsila and Vessel Management.” The district court correctly
    identifies the two parties to the Sales Contract containing the arbitration agreement. It is not
    clear, however, that the court realized that “the Plaintiff”—as it is referred throughout the
    order—is VTHM.
    7