Texaco Expl Prod Co v. AmClyde Eng Prod Co ( 2003 )


Menu:
  •                                                              United States Court of Appeals
    Fifth Circuit
    F I L E D
    February 28, 2001
    REVISED, MARCH 29, 2001                Charles R. Fulbruge III
    Clerk
    UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    _______________________
    No. 00-30799
    _______________________
    TEXACO EXPLORATION AND PRODUCTION COMPANY
    AND MARATHON OIL COMPANY,
    Plaintiffs-Appellants,
    versus
    AMCLYDE ENGINEERED PRODUCTS COMPANY, Inc., ET AL,
    Defendants.
    __________________________________________
    AMCLYDE ENGINEERED PRODUCTS COMPANY, Inc.,
    Third-Party Plaintiffs,
    versus
    J. RAY McDERMOTT, Inc.,
    Third-Party Defendant-Appellee.
    _________________________________________________________________
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    _________________________________________________________________
    Before GOODWIN*, GARWOOD, and JONES, Circuit Judges.
    *
    Circuit Judge of the United States Court of Appeals of the Ninth
    Circuit, sitting by designation.
    EDITH H. JONES, Circuit Judge:
    At issue in this appeal is whether to carve out an
    exception to the Federal Arbitration Act (FAA), 
    9 U.S.C. § 3
    ,
    where, in admiralty cases, its enforcement would deny a party the
    ability to implead a third-party defendant pursuant to Federal Rule
    of Civil Procedure 14(c).          We conclude that the policy of liberal
    joinder in maritime cases embodied in Rule 14(c) does not supersede
    the statutory right to enforce contractual arbitration guaranteed
    by the FAA.    The district court’s decision to the contrary must be
    reversed and remanded for the entry of a stay of litigation between
    Texaco and McDermott, pending arbitration.
    BACKGROUND
    This case arises from an accident during the construction
    of Texaco’s Petronius oil and gas production facility in the Gulf
    of Mexico off the coast of Alabama.           A barge-mounted crane failed,
    causing a deck module to fall into the sea.              The crane involved in
    this incident was owned and operated by J. Ray McDermott, Inc.
    (“McDermott”) and had been designed and manufactured by AmClyde
    Engineered Products Company, Inc. (“AmClyde”).
    In    the   wake    of    the   accident,   Texaco    sued   AmClyde,
    Williamsport Wirerope Works, Inc., the manufacturer of the failed
    wire rope line, Lowrey Brothers Rigging Center, Inc., the seller of
    the   failed    line,   and        Lloyd’s    Register    of   Shipping,   the
    classification society that inspected and certified the crane and
    2
    line.   Because of a mandatory arbitration clause in its contract
    with McDermott, Texaco did not file a complaint against McDermott.
    The    Texaco-McDermott       contract   includes   a   dispute
    resolution clause stating that “[t]he Parties shall reserve any
    controversy or claim, whether based in contract, tort or otherwise,
    arising out of, relating to or in connection with the Agreement”
    pursuant     to   a   mandatory   three-step    process   consisting   of
    negotiation, mediation, and binding arbitration. This provision is
    mandatory.
    Texaco attempted to avail itself of this alternative
    dispute resolution provision, but was frustrated when AmClyde
    tendered McDermott as a third-party defendant under Federal Rule of
    Civil Procedure 14(c).      The rule provides for liberal joinder in
    admiralty actions. Texaco moved to strike the joinder. Before the
    district court ruled on the motion to strike, McDermott moved for
    partial summary judgment against Texaco.            Texaco opposed this
    motion, asserting that the district court was obliged by section 3
    of the FAA to stay the proceedings between Texaco and McDermott
    pending their arbitration.        After hearing argument, the district
    court denied Texaco’s motion to strike, denied its request for stay
    and granted McDermott’s motion.          Texaco now appeals the district
    court’s denial of the requested stay.
    3
    DISCUSSION
    Appellate review of the district court’s refusal to stay
    litigation pending arbitration is de novo.            See Hornbeck Offshore
    Corp. v. Coastal Carriers Corp., 
    981 F.2d 752
    , 754 (5th Cir. 1993);
    Neal v. Hardee’s Food Systems, Inc., 
    918 F.2d 34
    , 37 (5th Cir.
    1990).
    As an initial matter, McDermott argues that Texaco’s
    appeal is not properly before this court.          McDermott contends that
    Texaco never formally moved for a stay and that it never had a
    chance to oppose Texaco’s informal “request” for a stay.                     We
    disagree. While Texaco did not file any document captioned “Motion
    to Stay,” Texaco gave both written and oral notice adequate to
    apprise   both    McDermott    and   the   district    court    that   it   was
    requesting a stay and of its supporting arguments.             Five pages of
    Texaco’s memorandum in opposition to McDermott’s motion for partial
    summary judgment are dedicated to the stay issue.              Additionally,
    the record indicates that Texaco moved for a stay at the June 21,
    2000 oral argument before the district court and that this motion
    was promptly denied without discussion.1 McDermott did not contest
    1
    At that hearing, Texaco urged that “[u]nder the Federal Arbitration
    Act, any claim that we make . . . against McDermott, must be stayed pending that
    arbitration.”   The district court then stated that Rule 14(c) can not be
    circumvented, impliedly denying Texaco’s motion to strike the Rule 14(c) tender.
    Without further discussion of the stay from either Texaco or McDermott, the
    district court announced its grant of partial summary judgment for McDermott.
    Texaco requested a clarification of the court’s ruling, specifically asking if
    the district court was “also denying our request that the matter be stayed
    pending arbitration?”   The district court responded “correct.”      Texaco then
    4
    the stay issue during the hearing because the district court had
    already   denied     relief.      Procedurally,     the    issue       is   properly
    preserved and fully briefed for this court.
    Moving to the merits, the Supreme Court has observed that
    the FAA    “is   a   congressional     declaration    of       a    liberal   policy
    favoring arbitration.”         Moses H. Cone Memorial Hospital v. Mercury
    Construction Corp., 
    460 U.S. 1
    , 24 (1983).                Further, there is a
    “strong    federal      policy    in   favor   of    enforcing         arbitration
    agreements.”     Dean Witter Reynolds Inc. v. Byrd, 
    470 U.S. 213
    , 217
    (1985).    The language of the FAA is unambiguous:
    If any suit or proceeding be brought in any of the courts
    of the United States upon any issue referable to
    arbitration . . . the court . . . shall on application of
    one of the parties stay the trial of the action until
    such arbitration has been had in accordance with the
    terms of the agreement . . . .
    
    9 U.S.C. § 3
    .          The FAA specifically applies to both maritime
    transactions     and    interstate     commerce.2         An       application   for
    stated its desire to appeal the denial of the stay immediately and the district
    court invited Texaco to prepare an appropriate order. The order stated that
    Texaco’s “instanter motion in open court . . . to stay claims . . . [is denied].”
    Taken together with Texaco’s extensive briefing on the stay issue in its
    memorandum opposing McDermott’s motion for partial summary judgment, there is no
    doubt that Texaco sufficiently presented a motion to stay. See Fed. R. Civ. P.
    7(b)(1).
    2
    The FAA dictates that “[a] written provision in any maritime
    transaction or a contract evidencing a transaction involving commerce to settle
    by arbitration . . . shall be valid, irrevocable, and enforceable.” 
    9 U.S.C. § 2
    . The Act defines “maritime transaction” as “charter parties, bills of lading
    of water carriers, agreements relating to wharfage, supplies furnished vessels
    or repairs to vessels, collisions, or any other matters in foreign commerce
    which, if the subject of controversy, would be embraced within admiralty
    jurisdiction.”     
    9 U.S.C. § 1
    .     So regardless of whether the Petronius
    5
    arbitration by either party under section 3 “requests the district
    court to refrain from further action in a suit pending arbitration,
    and requires the court to first determine whether there is a
    written agreement to arbitrate between the parties, and then
    whether any of the issues raised are within the reach of the
    agreement.”    Midwest Mechanical Contractors, Inc. v. Commonwealth
    Construction Co., 
    801 F.2d 748
    , 750 (5th Cir. 1986).                   “[I]f the
    issues in a case are within the reach of that [arbitration]
    agreement, the district court has no discretion under section 3 to
    deny the stay.”     Hornbeck, 
    981 F.2d at 754
    .
    Here, an arbitration agreement governed by section 3 of
    the FAA exists between Texaco and McDermott.                The arbitration
    clause is one this court has termed a “broad” agreement because it
    covers “any dispute” between the parties.                As a result, any
    litigation arguably arising under such a clause should be stayed
    pending the arbitrator’s decision as to whether the dispute is
    covered.      
    Id. at 754-55
    .       See also Sedco, Inc. v. Petroleos
    Mexicanos Mexican Nat’l Oil, 
    767 F.2d 1140
    , 1145 n. 10 (5th Cir.
    1985); Mar-Len of La., Inc. v. Parsons-Gilbane, 
    773 F.2d 633
    , 635
    (5th Cir. 1985).3
    construction contract is treated as a maritime      transaction   or    simply   as
    interstate commerce, the FAA applies.
    3
    McDermott’s request for a remand to determine the scope of
    arbitration conflicts with these authorities that squarely allow the arbitrator
    to initially make that decision where a clause is “broad.”
    6
    In the absence of the Rule 14(c) exception carved out by
    the district court, the Texaco-McDermott dispute would have been
    subject to arbitration.        However, the smooth operation of the
    arbitration process was disrupted by AmClyde’s Rule 14(c) tender of
    McDermott    as   a   third-party   defendant    to   Texaco.        McDermott
    contends, and the district court accepted, that Rule 14(c) “trumps”
    section 3 of the FAA, preventing enforcement of the arbitration
    clause.
    The logical basis for the district court’s conclusion is
    unclear.    There seems upon analysis to be no real conflict between
    Rule 14(c) and the FAA.
    Rule 14(c) was designed to expedite and consolidate
    admiralty actions by permitting a third-party plaintiff to demand
    judgment against a third-party defendant in favor of the plaintiff.
    As a consequence, the plaintiff is then required to assert his
    claims directly against the third-party defendant. See 6 Charles
    Alan Wright & Arthur R. Miller, FEDERAL PRACTICE         AND   PROCEDURE § 1465
    (2d. ed. 1990).       This unique liberal joinder policy served to
    reduce the possibility of inconsistent results in separate actions,
    eliminate    redundant    litigation,    and   prevent    a    third   party’s
    disappearing if jurisdiction and control over the party and his
    assets were not immediately established. See id. at 481.
    The FAA’s purpose, as has been noted, is to enforce
    private arbitration agreements “even if the result is ‘piecemeal
    7
    litigation,’ at least absent a countervailing policy manifested in
    another federal statute.”           Dean Witter Reynolds Inc. v. Byrd, 
    470 U.S. 213
    ,     219-20      (1985).     As    a    tangential       benefit,   however,
    arbitration usually provides a speedier, more economical form of
    dispute resolution.
    These two policies do not necessarily conflict.                           If
    arbitration goes forward between Texaco and McDermott, it need not
    hold up or interfere with the admiralty litigation between Texaco
    and the other defendants.             Apportionment of liability exists
    whether or not McDermott is impleaded under Rule 14(c).                      Moreover,
    the essential functions of Rule 14(c) are accomplished because
    McDermott will have to face Texaco directly as a defendant, albeit
    in arbitration.
    A conflict arises only if Rule 14(c) is held to thwart
    enforcement of the arbitration agreement pursuant to the district
    court’s order.       That result allows AmClyde, though not a party to
    the   arbitration        agreement,    to       override    the    Texaco-McDermott
    contract    and     fundamentally     thwart       the     purposes   of     the    FAA.
    Further, to carve out a Rule 14(c) exception to the FAA could
    severely undermine maritime arbitration clauses, inspiring abuse
    and   opportunistic       behavior,    as      third     parties    are   allowed    or
    encouraged to do what the parties to a contract themselves are not:
    to    put   aside    a    mandatory    arbitration          provision      and     force
    litigation.       It is perhaps no accident that AmClyde did not even
    8
    file a brief in this appeal and by its silence rests on McDermott’s
    arguments      against   enforcing     the    Texaco-McDermott      arbitration
    clause.
    There is little caselaw to guide our analysis.               However,
    in the only previous decision to analyze this precise issue, the
    court refused to create a Rule 14(c) exception to the FAA on
    essentially similar facts.          Shipping Corp. of India v. American
    Bureau of Shipping, No. 84 CIV. 1920, 
    1989 WL 97821
     (S.D.N.Y. Aug.
    17, 1989).     The India court concluded that an outside party cannot
    use Rule 14(c) to override an arbitration agreement previously
    reached between a plaintiff and a third-party defendant.
    The cases cited by McDermott in favor of carving out a
    Rule   14(c)     exception     to   section    3   of   the   FAA   are    either
    unpersuasive or irrelevant.         In General Marine Construction Corp.
    v. United States, 
    738 F.Supp. 586
     (D. Mass. 1990), the court held
    that “once a case is properly commenced as an admiralty matter in
    the District Court, Rule 14(c) governs related claims even if the
    issues raised by those related claims, standing alone, would
    otherwise be subject to the CDA [Contract Dispute Act] procedural
    scheme.” 
    Id. at 590
    .         General Marine has no bearing on the instant
    case for three reasons: 1) it involves the Contracts Disputes Act,
    
    41 U.S.C. § 605
    (a), not the FAA; 2) it does not involve a motion to
    stay proceedings, but rather a motion to dismiss claims resulting
    from a Rule 14(c) tender; and 3) the claims for which dismissal was
    9
    sought were not covered by the CDA.               General Marine makes no
    mention   of   the   FAA    or    the   strong   presumption     in   favor    of
    arbitration.
    McDermott       also   invokes    National   Gypsum    Co.   v.    NGC
    Settlement Trust & Asbestos Management Corp., 
    118 F.3d 1056
    , 1069
    (5th Cir. 1997), in which this court held that a bankruptcy court
    may refuse one party’s demand to arbitrate if the cause of action
    is “derived entirely from the federal rights conferred by the
    Bankruptcy Code . . . .”          McDermott cites National Gypsum for the
    general proposition that the FAA is not absolute and can yield,
    upon a proper showing, to other discrete bodies of federal law.
    But McDermott ignores the fact that under the Supreme Court case
    controlling National Gypsum, Shearson/American Express, Inc. v.
    McMahon, 
    482 U.S. 220
    , 227 (1987), “[t]he burden is on the party
    opposing arbitration . . . to show that Congress intended to
    preclude a waiver of judicial remedies for the statutory rights at
    issue.”   McDermott does not even attempt to bear this burden and
    has not made such a showing on behalf of Rule 14(c).
    McDermott’s reliance on Zimmerman v. Int’l Companies &
    Consulting, Inc., 
    107 F.3d 344
    , 345-46 (5th Cir. 1997) is also
    misplaced.     Zimmerman held that a defendant-insurer with the
    contractual right to arbitrate with the insured cannot force a
    plaintiff who is not a party to the contract to arbitrate.                   Here
    10
    Texaco seeks only to compel McDermott, the party to the contract
    containing the arbitration clause, to arbitrate.
    Nor does Pensacola Construction Co. v. St. Paul Fire and
    Marine Insurance Co., 
    705 F.Supp. 306
     (W.D. La. 1989), support
    McDermott’s    position.       The   plaintiff    in   Pensacola    sued   two
    defendants, only one of which had an arbitration agreement with the
    plaintiff.     The Pensacola court allowed the defendant with the
    contractual right to arbitration to stay the plaintiff’s action
    against it, but the court refused to stay the proceeding between
    the plaintiff and the other defendant.            
    Id. at 308
    .       Pensacola
    would be relevant if Texaco had sought to stay the proceedings
    involving AmClyde and the other defendants.            As Texaco only wants
    to stay the proceedings between itself and McDermott, the two
    signatories to the relevant contract, Zimmerman and Pensacola
    actually support Texaco’s position.4
    For these reasons, we conclude that the district court
    erred in refusing to stay the Texaco-McDermott aspect of this
    controversy pending arbitration.5
    McDermott alternatively contends that Texaco has waived
    its right to arbitrate.         Normally, waiver occurs when a party
    4
    McDermott’s reliance on Montauk Oil Transp. Corp. v. Steamship Mut.
    Underwriting Ass’n., Ltd., 859 F.Supp 669 (S.D.N.Y. 1994), is similarly
    misplaced.
    5
    It follows that the district court’s partial summary judgment in
    favor of McDermott must be vitiated by this ruling.
    11
    initially pursues litigation and then reverses course and attempts
    to arbitrate, but waiver can also result from “some overt act in
    Court that evinces a desire to resolve the arbitrable dispute
    through litigation rather than arbitration.”                            Subway Equipment
    Leasing Corp. v. Forte, 
    169 F.3d 324
    , 329 (5th Cir. 1999).                               There
    is a strong presumption against waiver, and any doubts thereabout
    must be resolved in favor of arbitration.                    
    Id. at 326
    .
    McDermott       does    not    assert     that       Texaco        attempted   to
    litigate any       claims    against      it    stemming         from    the     crane    line
    collapse.    To the contrary, Texaco did not sue McDermott for its
    role   in   this   accident        and    has    tried      to    compel       arbitration.
    Instead, McDermott’s waiver argument is based on Texaco’s actions
    in other litigation, Shell Offshore, Inc. Et. Al. v. Heerema
    Offshore Construction Group, Inc. Et Al., Civil Action No. H-98-
    1090, S.D. Texas.
    In Shell, Texaco has alleged certain antitrust violations
    against McDermott and other defendants relating to the Petronius
    construction contract and other Gulf projects.                      However, Shell is
    only tangentially related to the crane accident.                           On January 7,
    2000 McDermott requested arbitration relating to the Petronius
    contract    and    the   crane      accident,        claiming           that    Texaco     was
    wrongfully    withholding      payment          of   some    $23        million    dollars.
    Because Texaco wanted to use certain antitrust arguments in the
    arbitration against McDermott and because those antitrust issues
    12
    were already before the district court in Shell, Texaco petitioned
    the Shell court to stay the Petronius arbitration pending the
    outcome   in   Shell.       The   district   court   declined     to   stay   the
    arbitration altogether, but it did limit the scope of arbitration
    to the Petronius contract alone, thereby keeping Texaco’s antitrust
    defenses out of the hands of the arbitrator and before the district
    court.
    McDermott contends that Texaco’s request for a stay
    pending the outcome of the Shell antitrust litigation satisfies the
    Subway test and constitutes a waiver of arbitration.               While it is
    true that Texaco’s actions delayed the arbitration proceeding and
    narrowed its scope, Texaco never demonstrated the requisite desire
    to resolve the arbitrable issues related to the crane accident
    through litigation rather than arbitration.               In order to waive
    arbitration,    a   party    must   “do   more   than   call    upon   unrelated
    litigation to delay an arbitration proceeding.”                Subway, 
    169 F.3d at 328
    .     This is precisely what Texaco has done by requesting a
    stay of arbitration pending the outcome of the ongoing and largely
    unrelated antitrust lawsuit.         Moreover, mere delay falls far short
    of the waiver requirements of Subway.             See 
    id. at 326
    .        Texaco
    never manifested any desire to litigate rather than to arbitrate
    its claims against McDermott stemming from the December 3, 1998
    incident.
    13
    CONCLUSION
    Given the broad and unequivocal language of section 3 of
    the Federal Arbitration Act, this court refuses to create a Rule
    14(c) exception that would allow third parties unilaterally to
    nullify an arbitration clause.    Enforcing the arbitration clause
    does not conflict with Rule 14(c) on the facts before us, whereas
    the rigid enforcement of Rule 14(c) would utterly thwart the policy
    of the FAA.   In light of our analysis, and because Texaco has not
    waived its right to arbitrate, this case is remanded to the
    district court for the issuance of an order staying this litigation
    pending the outcome of the contractually mandated arbitration.
    This stay is limited in scope to the proceedings between Texaco and
    McDermott and should not affect Texaco’s actions against AmClyde or
    the other defendants.   REVERSED and REMANDED.
    14