Goldberg v. R.J. Longo Const. Co., Inc. ( 1995 )


Menu:
  •                  United States Court of Appeals,
    Fifth Circuit.
    No. 94-20470.
    Billy B. GOLDBERG, Plaintiff,
    v.
    R.J. LONGO CONSTRUCTION CO., INC., Defendant-Third Party
    Plaintiff-Appellant,
    v.
    MID-CONTINENT CASUALTY CO., Third-Party Defendant-Appellee.
    June 13, 1995.
    Appeal from the United States District Court for the Southern
    District of Texas.
    Before LAY,1 DUHÉ and DeMOSS, Circuit Judges.
    LAY, Circuit Judge:
    Southwest Crossing Joint Venture ("Southwest") contracted with
    R.J. Longo Construction Company ("Longo") to install two sewer
    lines and a force main for residential use in public easements
    adjacent to a tract of land in southwest Houston.   Two months after
    commencing work on the project, Longo and Southwest had a dispute
    over the terms of the contract and Longo ceased work.     Longo then
    filed a mechanic's and materialman's lien against the property.
    Because of the lien, title companies would not issue title policies
    to the land.   Certain title companies eventually agreed to issue
    policies, but only if Southwest and a surety would indemnify any
    loss arising from Longo's lien.       Mid-Continent Casualty Company
    1
    Circuit Judge of the Eighth Circuit, sitting by
    designation.
    1
    ("Mid-Continent") as surety and Southwest as principal executed an
    agreement    to    indemnify    the   title     companies    ("the      indemnity
    agreement").       Longo was neither a signatory to the indemnity
    agreement nor a named beneficiary of it.                   These transactions
    brought about a number of lawsuits.
    1)    The    Prior   Federal   Case   In   November    1983,      Longo   sued
    Southwest for breach of contract in federal court in New Jersey.
    The suit was transferred to the Southern District of Texas in March
    1984. Later that same month, Southwest filed suit against Longo in
    federal court in Houston, Texas, alleging Longo committed various
    torts in matters relating to the Southwest Crossing subdivision.
    These two cases were consolidated into Southwest Crossing Venture
    v. R.J. Longo Construction Co., Inc., C.A. No. H-84-1343, in the
    District Court for the Southern District of Texas—Houston Division.
    The court ordered the parties into binding arbitration.                   The
    arbitrator awarded Longo $649,500 and Southwest nothing on their
    respective claims.        The court affirmed the award and dismissed the
    consolidated cases with prejudice.
    2) The State Court Case In December 1986, Longo filed an
    abstract of its judgment against Southwest, thereby obtaining a
    judgment    lien    against    Southwest's      property    in   the    Southwest
    Crossing subdivision. Longo was unable to collect on the judgment.
    Longo also attempted to foreclose its mechanic's and materialmen's
    lien.
    In January 1987, Southwest filed suit in state court seeking
    to enjoin Longo from attempting to foreclose on its mechanic's and
    2
    materialman's    lien   and     to   have     the   lien   declared     invalid.
    Southwest Crossing Venture, Inc. v. R.J. Longo Constr., Inc., No.
    87-03691, (D. 164 Harris Co. Tex.).            Mid-Continent intervened in
    the lawsuit and supported Southwest's position that the lien was
    invalid.      Both   parties    argued      that    Longo's    lien   no   longer
    constituted a valid claim because Longo had either waived the claim
    by failing to raise it in its breach of contract suit filed in
    federal court or the claim was barred under the doctrine of res
    judicata.
    In February 1987, Longo cross-claimed, seeking a declaratory
    judgment that its lien was valid.             Longo also claimed it was a
    third-party beneficiary of the indemnity agreement executed by
    Southwest and Mid-Continent.         The third-party claim and the res
    judicata and waiver issues were tried separately in August 1989,
    but the trial judge never ruled on the issues due to illness.
    3) "The Case Below" The parties use this nomenclature for the
    suit involving this appeal, filed by a principal of Southwest,
    Billy    Goldberg,   against    Longo    in   state    court   for    wrongfully
    attempting to execute its judgment against Southwest and for other
    torts.     The case was removed to federal court on the basis of
    diversity jurisdiction.        Longo counter-claimed on grounds similar
    to those raised in the state court case.            Longo also impleaded Mid-
    Continent,    seeking    a     declaration      that    its    mechanic's    and
    materialman's lien was valid and that Longo was a third-party
    beneficiary of the indemnity agreement between Southwest and Mid-
    Continent.
    3
    Once it became clear the issues tried in the state court case
    were not going to be decided, Longo and Mid-Continent agreed to try
    the issues in this suit.             They made cross motions for summary
    judgment, and the court, the Honorable John D. Rainey presiding,
    decided in favor of Mid-Continent.                 The court found that under
    Texas law, an action brought on the debt secured by a lien must
    also assert the lien claim or it is deemed abandoned.                            Because
    Longo failed to foreclose its lien in its suit on the debt in the
    prior    federal     case,     the   court       held     that     Longo   had    waived
    foreclosure on the lien.         The court also ruled against Longo on the
    third-party beneficiary claim.                  The court found the indemnity
    agreement was ambiguous in certain respects and that under Texas
    law, it could not be construed to be made for the benefit of a
    third    party     unless    that    was       clearly     the     intention     of    the
    contracting parties as apparent from the four corners of the
    contract.     Longo appeals both decisions.
    THE MECHANIC'S AND MATERIALMAN'S LIEN
    Longo contends that it could not have brought a foreclosure
    claim   in   the     prior   federal    case      because      under    Texas    law    an
    arbitrator cannot foreclose a mechanic's and materialman's lien,
    Hearthshire Braeswood Plaza Ltd. Partnership v. Bill Kelly Co., 
    849 S.W.2d 380
    , 390 (Tex.Ct.App.1993).                On this basis, Longo asserts
    that under federal principles of res judicata its right to litigate
    its present foreclosure action on its mechanic's and materialman's
    lien is not barred.          Longo argues the district court erred in
    applying     state    rather     than   federal          law     in   determining      the
    4
    preclusive effect of the prior federal case.
    Longo brought the prior federal action before a federal
    district court which ordered Longo's claim on the debt be submitted
    to arbitration.   Sitting in diversity, the court applied Texas law
    to substantive issues.   That the court could not, under Texas law,
    have ordered an arbitrator to decide the foreclosure claim in no
    way implies the court could not decide the foreclosure claim on its
    own if such a claim had been brought before it.   Longo decided what
    claims to bring in its pleadings.    Its pleadings established the
    claims before the court, not the court's subsequent decision to
    order arbitration.   Assuming Longo's argument that this question
    must be resolved under federal principles of res judicata, Longo's
    claim is still not enforceable.       Under federal res judicata,
    Longo's lien claim is precluded by the judgment in the prior
    federal case.
    Under federal law, res judicata bars "all claims that were or
    could have been advanced in support of the cause of action on the
    occasion of its former adjudication ... not merely those that were
    adjudicated."   Travelers Ins. v. Saint Jude Hosp., 
    37 F.3d 193
    , 195
    (quoting In re Howe, 
    913 F.2d 1138
    , 1144 (5th Cir.1990) which
    quotes Nilsen v. City of Moss Point, 
    701 F.2d 556
    , 560 (5th
    Cir.1983) (en banc) (footnotes omitted)), cert. denied, --- U.S. --
    --, 
    115 S. Ct. 1696
    , --- L.Ed.2d ---- (1995).   In this case, Longo's
    mechanic's and materialman's lien arose out of the same "common
    nucleus of operative facts" as the damages Longo sought in its
    breach of contract claim.   Restatement (Second) of Judgments § 24
    5
    cmt. b (1982).
    One goal of prohibiting claim splitting is to avoid litigating
    matters   that    could   have    been       or   were    previously    litigated.
    Mechanic's and materialman's liens secure labor and materials.
    Longo's   breach    of    contract     claim       alleged   not    only    damages
    consequent to Longo's provision of labor and materials but also
    incidental damages, lost profits, delay damages, mobilization, and
    overhead.   The arbitrator made, and the court affirmed, a lump sum
    judgment for Longo.       The judgment did not specifically state the
    value of the labor and materials Longo provided.                   For a court to
    determine   now    the    value   of     the      labor   and   materials    would
    necessarily involve relitigating many of the issues adjudicated in
    the prior federal case.
    Texas case law specifically holds that a lien is inseparable
    from the debt giving rise to it.         Palmer v. Palmer, 
    831 S.W.2d 479
    ,
    482 (Tex.Ct.App.1992);        Taylor v. Rigby, 
    574 S.W.2d 833
    , 839
    (Tex.Civ.App.1978);       University Savings & Loan Ass'n v. Security
    Lumber Co., 
    423 S.W.2d 287
    , 292 (Tex.1967).               As the court stated in
    Taylor v. Rigby:
    [w]here there is ... a debt secured by a lien, the lien is an
    incident of and inseparable from the debt. When one sues on
    the debt, the lien is thereby necessarily implicated, and both
    must be put in issue. If the lien is not put in issue, it is
    
    abandoned. 574 S.W.2d at 839
    (citation omitted);             see also Hubble v. Lone Star
    Contracting Corp., 
    883 S.W.2d 379
    , 381 (Tex.Ct.App.1994);                   Shipley
    v. Biscamp, 
    580 S.W.2d 52
    , 54 (Tex.Civ.App.1979);                      Holcroft v.
    Wheatley, 
    112 S.W.2d 298
    , 299-300 (Tex.Ct.App.1937);                    Holford v.
    6
    Patterson, 
    257 S.W. 213
    , 214 (Tex.1923).           Whether one adopts
    federal principles of res judicata2 or the substantive provisions
    of Texas law, once Longo brought an action against Southwest on its
    debt, Longo also had to bring its claim on the lien or abandon it.
    THE INDEMNITY AGREEMENT
    In October 1986, Southwest as principal and Mid-Continent as
    surety executed the general indemnity agreement.        The agreement
    states the parties desire three named title insurance companies and
    one named title insurance agency to issue title insurance policies
    on land owned by Southwest without exception to Longo's lien claim
    affidavit.       Because of that desire, the agreement continues,
    Southwest and Mid-Continent promise to:
    1. ... hold [the named companies] harmless as to any loss or
    liability ... arising out of the [Longo lien] matter or claim
    ...;
    2.   ... reimburse [the named companies] for all Court Costs,
    Attorney's fees and expenses of trial and investigation
    incurred in connection with said matter of claim;
    3. ... pay and discharge, within five days after entry thereof, any
    final judgment establishing any matter or claim as a lien upon
    said property.
    Longo contends it is a third-party creditor beneficiary of the
    indemnity agreement executed by Southwest and Mid-Continent and as
    2
    Whether principles of federal or state res judicata apply
    to determine the preclusive effects of the prior federal judgment
    is not really germane to the resolution of this issue because
    both doctrines would preclude the separate action on the lien.
    Texas policies of res judicata bar "causes of action or defenses
    arising out of the same subject matter that might have been
    litigated in the first suit." Gracia v. R.C. Cola-7-Up Bottling
    Co., 
    667 S.W.2d 517
    , 519 (Tex.1984). The fact the district court
    ordered the claim on the debt into arbitration in no way
    prevented Longo from pursuing, or the court from adjudicating,
    the claim on the lien.
    7
    such can sue to enforce the agreement even if the agreement does
    not identify Longo by name.      See Quilter v. Wendland, 
    403 S.W.2d 335
    , 337 (Tex.1966);    Brunswick Corp. v. Bush, 
    829 S.W.2d 352
    , 354
    (Tex.Ct.App.1992).     Longo asserts it is a third-party creditor
    beneficiary because it would benefit if Southwest or Mid-Continent
    performed their promises under the agreement because Southwest has
    a duty to pay Longo under the judgment in the prior federal case.
    Cumis Ins. Soc'y v. Republic Nat'l Bank, 
    480 S.W.2d 762
    , 766-67
    (Tex.Civ.App.1972).
    We agree Longo's claim to be a creditor beneficiary of the
    agreement does not automatically fail simply because the agreement
    does not so identify Longo.      Restatement (Second) of Contracts §
    308 (1981).      This agreement, however, identifies its intended
    beneficiaries explicitly in paragraph 4 and Longo is not among
    them.   Under Texas law:
    [c]ourts will not create a third-party beneficiary contract by
    implication and the obligation must be clearly and fully
    spelled out or enforcement will be denied. MJR Corporation v.
    B & B Vending Company, 
    760 S.W.2d 4
    (Tex.App.—Dallas 1988,
    writ denied). In that case, the Court noted that a benefit to
    the third party must have been within the contemplation of the
    contracting parties.
    Foster, Henry, Henry & Thorpe, Inc. v. J.T. Constr. Co., 
    808 S.W.2d 139
    , 140 (Tex.Ct.App.1991).     Further, "[a] third party is entitled
    to recover upon a contract made between other parties only if the
    parties intended to secure some benefit to that third party, and
    only if the contract was entered into directly and primarily for
    the third party's benefit."        Economy Forms v. Williams Bros.
    Constr.   Co.,   
    754 S.W.2d 451
    ,    456   (Tex.Ct.App.1988)   (citing
    8
    Dairyland County Mut. Ins. Co. v. Childress, 
    650 S.W.2d 770
    , 775
    (Tex.1983) and Republic Nat'l Bank v. National Bankers Life Ins.
    Co., 
    427 S.W.2d 76
    , 79 (Tex.Ct.App.1968)) (emphasis in original).
    Even    if   it   is   assumed    that   Longo   is   a   third-party       creditor
    beneficiary under the agreement, Longo's claim would be defeated by
    the    express    language   of    the   agreement.       Paragraph     3    of   the
    indemnity agreement speaks of "any final judgment establishing any
    matter or claim as a lien upon said property."               (emphasis added).
    The prior federal case did not result in a judgment that Longo had
    a lien on the Southwest Crossing subdivision.                The court awarded
    Longo an in personam judgment against Southwest. Had Longo pursued
    its mechanic's and materialman's lien claim in that case, the court
    might have awarded Longo an in rem judgment against the property,
    but Longo did not bring the claim.
    As the district court noted, Longo retains its judgment lien
    against any property Southwest sold after Longo abstracted its
    judgment.     But Longo has no rights under the indemnity agreement
    and is barred from suing on its mechanic's and materialman's lien
    claim.
    We AFFIRM the judgment of the district court;              appellant to
    pay all costs.
    9