In Re: Katrina Canal Breaches ( 2010 )


Menu:
  •          IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT United States Court of Appeals
    Fifth Circuit
    FILED
    September 14, 2010
    Lyle W. Cayce
    Clerk
    No. 09-30449
    IN RE: KATRINA CANAL BREACHES LITIGATION.
    STEERING COMMITTEE,
    Plaintiff-Appellant,
    versus
    WASHINGTON GROUP INTERNATIONAL, INC.,
    Defendant-Appellee.
    ***************
    No. 09-30428
    IN RE: KATRINA CANAL BREACHES LITIGATION.
    QUINTESSA HUEY,
    CARYN L. FONG, as Trustees of the Huey & Fong Trust;
    AMY HUEY, as Trustee of the Kenneth Huey Family Trust;
    RADIO PARTS, INC.; ENTERCOM COMMUNICATIONS CORPORATION;
    ET AL.,
    Plaintiffs-Appellants,
    versus
    WASHINGTON GROUP INTERNATIONAL, INC.,
    Defendant-Appellee.
    ***************
    No. 09-30438
    IN RE: KATRINA CANAL BREACHES LITIGATION.
    BETTY LUNDY; FREDERICK ADAMS; JEAN ADDISON;
    JONATHAN AKERS; OLLIE P. ALEXANDER; ET AL.,
    Plaintiffs-Appellants,
    versus
    WASHINGTON GROUP INTERNATIONAL, INC.,
    Defendant-Appellee.
    2
    Appeals from the United States District Court
    for the Eastern District of Louisiana
    Before SMITH, WIENER, and ELROD, Circuit Judges.
    JERRY E. SMITH, Circuit Judge:
    Washington Group International, Inc. (“WGI”) provided engineering, con-
    struction, and management services. The United States Army Corps of Engin-
    eers (“the Corps”) contracted with WGI for a large project in New Orleans. The
    plaintiffs sued WGI, claiming that its negligent and improper actions in fulfilling
    the contract were a cause of flood damage resulting from Hurricane Katrina.
    The district court granted summary judgment for WGI based on government-
    contractor immunity (“GCI”). Because the specifications for the work at issue
    were not reasonably precise, WGI has no GCI, so we reverse the summary judg-
    ment and remand.
    I.
    In 1994, the Corps and WGI entered into an indefinite delivery/indefinite
    quantity contract for the remediation of some hazardous, toxic, and radioactive
    waste sites in the southwestern United States. That “umbrella contract,” known
    as the Total Environmental Restoration Contract (“TERC”), set forth general re-
    quirements for all of WGI’s anticipated work in the region, with the understand-
    ing that the Corps would approve a specific Statement of Work (“SOW”) for each
    Task Order it would issue to WGI.
    3
    Nos. 09-30449, 09-30428, 09-30438
    In 1999, the Corps began its Inner Harbor Navigation Canal Lock Replace-
    ment Project in New Orleans, one aspect of which was the cleanup of the East
    Bank Industrial Area. Pursuant to the TERC, WGI was obligated (1) to demol-
    ish existing structures in that area by removing surface and subsurface obstruc-
    tions, (2) to characterize contaminants on the site, and (3) to remediate the site
    in accordance with any applicable environmental standards. This specific task
    was contracted for and identified as Task Order 26 of the TERC.
    In June 1999, the Corps issued a SOW for Task Order 26 that was brief
    and provided only a general description of the work to be done. From that SOW,
    WGI submitted a more detailed work plan to the Corps. After receiving the work
    plan, the Corps engaged WGI in a review process during which the Corps would
    comment on issues it had with WGI’s proposals, solicit a response from WGI on
    those comments, and continue in such a back-and-forth manner until the Corps
    and WGI had come to an agreement regarding any matters that were in conflict.
    The review process included the completion of various technical analyses
    and recommendation reports by the Corps and additional work plans by WGI.
    A final Recommendation Report was formally issued in January 2000, after
    which it became “the basis of subsequent specifications for work and work orders
    and proposals.”
    After completion of the Recommendation Report process, the Corps issued
    another SOW that, once again, provided general directions to WGI. From that
    SOW, WGI drafted eight work plans for the specific project and submitted them
    to the Corps for comment and approval. The most important of those work
    plans, for our purposes, was the Project Work Plan, which dealt with the equip-
    ment, the excavation, and the remediation process for the areas at issue in the
    plaintiffs’ claim.
    4
    Nos. 09-30449, 09-30428, 09-30438
    Once work had begun, WGI discovered previously unknown subsurface
    structures in the area to be remediated. In August 2001, the Corps issued an-
    other SOW to address the excavation and disposal of those newly discovered
    structures. Pursuant to that SOW, and in compliance with all the previously ap-
    proved plans, WGI submitted Proposal #113, which dealt with the excavation
    and disposal of the new subsurface structures.
    In its Technical Analysis of Proposal #113, the Corps deemed WGI’s pro-
    posal too costly, rejected it, and suggested several elements of the proposal as to
    which cost savings could be achieved. One of those suggestions was to use on-
    site borrow matter as the primary source of backfill material.1 The final propos-
    al submitted by WGI, and approved by the Corps, incorporated that suggestion
    by stating that “[t]he excavations . . . will be backfilled with borrow material
    obtained from either the on-site borrow source or an off-site source.”
    The final approved proposal also stated that the backfill “material will be
    placed in lifts and compacted; however, no compaction testing will be required.”2
    The work plans derived from the final proposal also specified that compaction
    should occur “with previous excavated soil in 2' lifts,” that “[i]nitial backfill oper-
    ations will be to the bottom of the whalers inside the [subsurface obstruction],”
    and that backfilling should be completed “to the top of sheet piles with material
    to be provided by WGI after whalers are removed.” Working from that approved
    proposal and from subsequent work plans derived from it, WGI completed the
    project in the spring of 2005.
    1
    Backfill material is the physical matter used to refill holes created by the removal of
    subsurface structures.
    2
    Compaction is the process of increasing the bulk density of an aggregate of matter by
    driving out air.
    5
    Nos. 09-30449, 09-30428, 09-30438
    In August 2005, Hurricane Katrina made landfall near New Orleans. As
    a result, the flood protection system in the Inner Harbor Navigation Canal pro-
    ject, consisting of levees and floodwalls, failed. Two of the breaches in the levees
    were near areas that were part of the zone where WGI had conducted extensive
    work. The plaintiffs claim that the failure of those levees was a result of the
    negligent and improper backfilling and compaction of the excavated locations by
    WGI in violation of a state-law duty of care. Specifically, the plaintiffs allege
    that the method of excavation and backfilling employed by WGI allowed for un-
    derseepage, which undermined the integrity of the levees, resulting in their fail-
    ure and the subsequent flooding of New Orleans East, the Lower Ninth Ward,
    and St. Bernard Parish.
    II.
    In 2007, the plaintiffs, in several consolidated actions, sued WGI, the
    Corps, and numerous other defendants for harm resulting from Hurricane Ka-
    trina-related damages. In 2008, WGI moved for summary judgment, asserting
    the GCI defense. The plaintiffs opposed summary judgment on the grounds that
    (1) GCI does not apply because there was no conflict with state law, and (2) even
    assuming such a conflict, WGI failed to satisfy the Supreme Court’s three-part
    test for GCI. The district court granted summary judgment for WGI, concluding
    that displacement of state law is built into the GCI defense and that WGI had
    satisfied all the requirements for GCI.
    III.
    We review a summary judgment de novo, “using the same standard as that
    employed by the district court under Rule 56.” Kerstetter v. Pac. Scientific Co.,
    6
    Nos. 09-30449, 09-30428, 09-30438
    
    210 F.3d 431
    , 435 (5th Cir. 2000). Summary judgment is warranted where
    “there is no genuine issue as to any material fact and [] the movant is entitled
    to judgment as a matter of law.” FED. R. CIV. P. 56(c)(2). There is no genuine is-
    sue for trial “[i]f the record, taken as a whole, could not lead a rational trier of
    fact to find for the nonmoving party.” Kipps v. Caillier, 
    197 F.3d 765
    , 768 (5th
    Cir. 1999).
    A.
    The Supreme Court first recognized the federal GCI defense to state tort
    law in Boyle v. United Technologies Corp., 
    487 U.S. 500
     (1988). The GCI defense
    preempts state law to immunize government contractors from liability in spite
    of the absence of legislation specifically immunizing them.3 The rationale for
    GCI flows from two basic principles: “[S]tate tort law is preempted by federal
    common law in areas of unique federal interests” and “the procurement of equip-
    ment by the United States is such an area.” Trevino v. Gen. Dynamics Corp.,
    
    865 F.2d 1474
    , 1479 (5th Cir. 1989). In Boyle, the Court specified the precise
    scope of the displacement of state law, using a three-part test:
    Liability for design defects in military equipment cannot be im-
    posed, pursuant to state law, when (1) the United States approved
    reasonably precise specifications; (2) the equipment conformed to
    those specifications; and (3) the supplier warned the United States
    about the dangers in the use of the equipment that were known to
    the supplier but not to the United States.
    3
    In their reply brief, the plaintiffs contend that the GCI defense from Boyle is applica-
    ble only to military contractors and should not be extended. That argument is waived, because
    it was not made in the plaintiffs’ opening brief. Morgan v. Swanson, 
    610 F.3d 877
    , 884 n.10
    (5th Cir. 2010) (stating that issues raised for the first time in appellant’s reply brief are
    waived).
    7
    Nos. 09-30449, 09-30428, 09-30438
    Boyle, 
    487 U.S. at 512
    .
    B.
    The plaintiffs argue that the district court erred in failing to conduct a
    threshold inquiry into the existence of a significant conflict between federal poli-
    cy and state law. They incorrectly assert that this inquiry is necessary to an
    application of the Boyle test. Although a conflict between federal policy and
    state law is a necessary element of any finding of GCI, a threshold inquiry on
    that specific issue is not necessary but, rather, is built into the three-part Boyle
    test.
    Following oral argument in the instant case, a different panel of this court
    decided Jowers v. Lincoln Electric Co., No. 09-60396, 
    2010 U.S. App. LEXIS 17862
     (5th Cir. Aug. 26, 2010). There, the district court had included in the jury
    instructions a threshold inquiry that the government contractor challenged on
    appeal. This court held that “an additional instruction that the jury find a ‘sig-
    nificant conflict’ between federal interests and Mississippi law in the instant
    matter is superfluous and forces the jury to construe an issue of law, which is
    outside its purview as a fact-finder.” Id. at *9. Though the panel focused on the
    role of the jury as a factfinder, its conclusion that a threshold inquiry is “super-
    fluous” is a statement on the general applicability of the GCI defense.
    Additionally, though this circuit never had occasion, before Jowers, to ad-
    dress the “significant conflict” issue, we have consistently applied the Boyle test
    without conducting any sort of threshold inquiry similar to the one these plain-
    8
    Nos. 09-30449, 09-30428, 09-30438
    tiffs request.4 Preemption of state law by federal law without a statutory man-
    date can occur only where “a ‘significant conflict’ exists between an identifiable
    federal policy or interest and the operation of state law, or the application of
    state law would frustrate specific objections of federal legislation,” Boyle, 
    487 U.S. at 507
     (internal quotation marks and citations omitted), but, importantly,
    “[t]he first two of these conditions assure that the suit is within the area where
    the policy of the ‘discretionary function’ would be frustrated,” 
    id. at 512
    .
    By assuring that the suit involves a situation in which the discretionary
    function is frustrated, the first of the three Boyle conditions necessarily satisfies
    the earlier-stated requirement of a significant conflict. See Lewis v. Babcock In-
    dus., Inc., 
    985 F.2d 83
     (2d Cir. 1993); Kerstetter, 
    210 F.3d at 438
    . “Whether [the
    GCI defense] will apply to a particular claim depends only upon whether Boyle’s
    three conditions are met with respect to the particular product feature upon
    which the claim is based.” Bailey, 989 F.2d at 801-02 (5th Cir. 1993) (emphasis
    in original). A threshold inquiry into whether there is a significant state conflict
    has never been required by any court,5 nor should it be. The only analysis
    4
    See, e.g., Miller v. Diamond Shamrock Co., 
    275 F.3d 414
    , 419 (5th Cir. 2001); Kerstet-
    ter, 
    210 F.3d at 435
    ; In re Air Disaster at Ramstein Air Base, Germany, 
    81 F.3d 570
    , 574 (5th
    Cir. 1996); Bailey v. McDonnell Douglas Corp., 
    989 F.2d 794
    , 798 (5th Cir. 1993); Stout v.
    Borg-Warner Corp., 
    933 F.2d 331
    , 334 (5th Cir. 1991); Trevino, 
    865 F.2d at 1479
    .
    5
    In Lewis, 
    985 F.2d at 83
    , the court directly addressed the issue of whether the Boyle
    test requires a threshold inquiry into the presence of a “significant conflict” with state law. It
    held that “answering the question whether the Government approved reasonably precise
    specifications for the design feature in question necessarily answers the question whether the
    federal contract conflicts with state law.” 
    Id. at 86
    .
    The plaintiffs argue that Lewis was implicitly overruled by In re World Trade Center
    Disaster Site Litigation, 
    521 F.3d 169
     (2d Cir. 2008), in which the court stated that “[a]s a
    threshold matter, the defense only arises in an area of uniquely federal interest, where a sig-
    (continued...)
    9
    Nos. 09-30449, 09-30428, 09-30438
    necessary to determine the application and scope of government contractor im-
    munity is the three-step Boyle test.
    C.
    The first Boyle step requires that the government approved reasonably
    precise specifications. That entails both the existence of reasonably precise spe-
    cifications and the approval of those specifications by the government.
    Specifications are reasonably precise “as long as the specifications address,
    in reasonable detail, the product design feature, alleged to be defective.” Kerstet-
    ter, 
    210 F.3d at 438
    . See also Trevino, 
    865 F.2d at 1481
    . “The requirement that
    the specifications be precise means that the discretion over significant details
    and all critical design choices will be exercised by the government.” 
    Id.
     Reason-
    ably precise specifications for one aspect of a large project do not create an um-
    brella of protection for an entire project. Instead, the requirement of reasonably
    5
    (...continued)
    nificant conflict exists between an identifiable federal policy or interest and the [operation] of
    state law.” Id. at 194 (internal quotation marks and citations omitted). The plaintiffs read too
    much into the wording of that sentence. The court in World Trade Center did not believe a
    threshold inquiry was necessary. Rather, it merely stated that, as a matter of first principles
    (i.e., as a “threshold matter”), GCI arises from the significant conflict between federal interests
    and state law.
    Importantly, the court went on to apply the Boyle factors without conducting, or even
    mentioning again, any sort of threshold inquiry. Furthermore, the court specifically stated
    that the first Boyle factor was “designed to ensure that a conflict with state law exists, and,
    along with the second requirement, to assure that the suit is within the area where the policy
    of the discretionary function would be frustrated.” Id. at 196 (internal quotation marks and
    citations omitted). With this statement, World Trade Center not only did not implicitly over-
    rule Lewis but explicitly reaffirmed it.
    10
    Nos. 09-30449, 09-30428, 09-30438
    precise specifications must be met by the specific feature at issue in the claim.6
    In this case, the specific features at issue are the backfill material used and the
    method of compaction employed by WGI.7
    1.
    The Corps, driven by cost concerns, approved specifications that mandated
    on-site material as the primary source of the backfill material. The Corps also
    specified that if there was insufficient on-site material, WGI should import off-
    site backfill material to complete the project. Two factors render those specifica-
    tions imprecise.
    First, the specifications that authorized the use of on-site backfill material
    were not reasonably precise in regard to how WGI should parse through all the
    on-site material to determine which was suitable. The Corps neither mandated
    the composition of the backfill material nor established precise procedures to test
    material for its suitability as backfill. The only Corps specification was that the
    material had to be clean, not contaminated, and not full of debris. Given, how-
    6
    See Trevino, 
    865 F.2d at 1486
     (“The government contractor defense as reformulated
    in Boyle protects government contractors from liability for defective designs if discretion over
    the design feature in question was exercised by the government.” (emphasis added)).
    7
    At various points in their briefs, the plaintiffs seem to urge that the government failed
    to provide reasonably precise specifications for dealing with the possibility of underseepage in
    the area near the project. That argument, however, is irrelevant to our current analysis of the
    scope of GCI, because the reasonably precise specifications that are required by the first prong
    of the Boyle test “need not address the specific defect alleged; the government need only
    evaluate the design feature in question.” Kerstetter, 
    210 F.3d at 435
     (emphasis added). The
    underseepage erosion of the flood walls is not a design feature; it is a defect that is alleged to
    be the result of two design features (i.e., the backfill material used and the compaction method
    employed). Thus, under the first prong, the government must only have approved precise spe-
    cifications for the backfill material and the method of compaction; it need not have addressed
    underseepage erosion specifically.
    11
    Nos. 09-30449, 09-30428, 09-30438
    ever, the wide variety in the types of matter that could be used as backfill mate-
    rial, that specification is not reasonably precise.8 The composition of the backfill
    used by WGI serves as one factor in plaintiffs’ tort claim, so it cannot be said
    that “the specifications address, in reasonable detail, the product design feature,
    alleged to be defective.” Kerstetter, 
    210 F.3d at 438
    .
    The Corps did not approve any specifications regarding the precise compo-
    sition of the on-site backfill material. As Guillory noted in his deposition,
    Q: And there were no real specifications for backfill in terms of what
    they could use and the degree of compaction, right?
    A: Right. We just backfilled with the adjacent soil that was excavat-
    ed out, removed, stockpiled on the side. After the lift station was re-
    moved, that soil was put back in layers and compacted to the com-
    paction of the adjacent soil.
    Later in that deposition, Guillory confirmed that the specifications were “gen-
    eral” and did not indicate the type of backfill material that could be used to back-
    fill the hole:
    Q: And Number 7 is a discussion of the backfill. It says, the excava-
    tion resulting from concrete foundation removal will be backfilled
    with borrowed material obtained from either the on-site borrow
    source or an off-site source as required. An estimated 900 Cys will
    be needed . . . . Okay, so would you regard this as a general specifi-
    cation?
    A: Yes.
    8
    As the Corps’s Contracting Officer Representative, Lee Guillory, acknowledged, back-
    fill material need not be homogenous and could consist of various types of matter, including
    crushed stone, clays, silts, sand layers, wood debris, and more.
    12
    Nos. 09-30449, 09-30428, 09-30438
    Q: Okay. It’s certainly not a prescribed specification, right?
    A: Right.
    Q: And it doesn’t indicate what kind of material you can use to back-
    fill the hole, does it?
    A: No, it doesn’t.
    The second reason that the specifications are imprecise concerns the off-
    site material imported by WGI and used as backfill material. The Corps provid-
    ed no reasonably precise specifications regarding the composition of that off-site
    backfill material. The Corps was not even fully aware of the contents of the
    backfill material used to fill the holes it had created. Guillory’s statements dur-
    ing his deposition are indicative of the degree of precision of the Corps’s specifi-
    cations:
    Q: Okay. So we really don’t know what’s in the hole, do we?
    ...
    A: I cannot tell you for a fact of everything that’s in that hole, no.
    Q: All right. It says, additional fill material necessary to complete
    the backfill operations will be provided by WGI.
    Q: Doesn’t that allow WGI to use other kinds of material to fill up
    the hole?
    A: It just says provided to the subcontractor. It could be indigenous,
    on site clay material, it could have been commercially truck hauled
    clay material.
    It is true that in addition to the Corps’s standing requirement that the
    backfill material be clean, not contaminated, and not full of debris, any off-site
    13
    Nos. 09-30449, 09-30428, 09-30438
    backfill material imported by WGI had to receive some sort of approval from the
    Corps before it could be used. But there is no information in the record indicat-
    ing that the Corps imposed additional requirements regarding the composition
    of the off-site material, nor is there any indication that the Corps applied any
    testing process to evaluate the off-site backfill material before approving its use.9
    Given the absence of reasonably precise specifications in the proposal under
    which WGI was operating, any such additional evidence is necessary to find that
    the Corps approved reasonably precise specifications and did not merely allow
    WGI to exercise principal discretion over the composition of the off-site backfill
    material.
    Significantly, the evidence in the record shows that the sole consideration
    for the Corps in evaluating the backfill was the cost of the material. If that was
    the extent of its analysis, the Corps cannot be said to have approved reasonably
    precise specifications regarding the composition of the off-site backfill material.
    Given that the Corps provided imprecise, and at times non-existent, speci-
    fications regarding the composition of the on-site and off-site backfill material,
    WGI is not entitled to claim GCI for its exercise of discretion in choosing the
    composition of that material.
    9
    There is also no evidence that the approval given by the Corps for the off-site backfill
    material was anything more than a rubber stamp, which is unacceptable under the Boyle test.
    See Trevino, 
    865 F.2d at 1480
     (“If the government contractor exercised the actual discretion
    over the defective feature of the design, then the contractor will not escape liability via the gov-
    ernment contractor defenseSSthe government’s rubber stamp on the design drawings not-
    withstanding.”). We focus our discussion, however, on the precision of the specifications, not
    the process of approval. Although those two issues are intertwined as elements of the first
    prong of Boyle, they are still two separate conditions that can be analyzed independently. If
    the specifications are not reasonably precise, it does not matter whether the imprecise specifi-
    cations were properly approved: The first prong would not be satisfied.
    14
    Nos. 09-30449, 09-30428, 09-30438
    2.
    The Corps specified that the backfill “material will be placed in lifts and
    compacted.” The Corps also directed that compaction occur “with previous exca-
    vated soil in 2' lifts,” that “[i]nitial backfill operations will be to the bottom of the
    whalers inside the [subsurface obstruction],” and that backfilling should be com-
    pleted “to the top of sheet piles with material to be provided by WGI after whal-
    ers are removed.”
    The WGI Project Manager, Dennis O’Connor, described, in his deposition,
    his understanding of the specifications for compaction in his deposition:
    Q: Tell me what was the specification for compaction?
    A: There were no specifications for compaction.
    Q: OK.
    A: Simply a general directive that if we backfilled the hole, depend-
    ing on the piece of equipment and size of the hole, we would compact
    the soil mechanically, be it with an excavator or backhoe if it was
    very small, or a wheel roller if it was extremely small. And it would
    depend on the size of the lifts and we would bring it up to grade.
    As O’Connor admitted, WGI understood there to be no precise specifications for
    compaction. Additionally, though we do not ascribe a legal conclusion to O’Con-
    nor’s declaration that the Corps’s directive was a “general” specification, his de-
    tailed statement of what the general directive entailed shows the lack of rea-
    sonable precision. By his own terms, WGI could have used an excavator, back-
    hoe, or wheel roller for compaction, based on the size of the hole and the size of
    the lifts. There is no information in the record, however, to show that the Corps
    provided specifications for when a certain piece of equipment should be used for
    15
    Nos. 09-30449, 09-30428, 09-30438
    a particular type of hole.
    Furthermore, the specifications are not reasonably precise, because they
    fail to dictate any standards for compaction. The extent of compaction can be
    measured using a proctor compaction test. The Corps chose not to require any
    specific standard that could be measured by that test. Instead, it unequivocally
    emphasized its lack of interest in mandating specifications for compaction densi-
    ty by stating that “no compaction testing will be required.” To explain this lack
    of specification, the Corps cited cost concerns and the fact that the Corps could
    visually observe the result of the compaction method that WGI used. That ex-
    planation, even if it is credible, has no effect on our conclusion that the specifica-
    tions that were approved were not reasonably precise.
    The Corps’s failure to specify a standard for compaction also meant that
    WGI could choose a method of compaction that did not require a particular final
    result. For example, if the Corps had specified that the holes should be compact-
    ed to 95% Standard Proctor density,10 WGI would be limited, in its choice of a
    compaction method, to a process that would achieve that result. By not specify-
    ing any compaction method, the Corps allowed WGI the discretion to choose a
    method without a required result.
    One could argue that the Corps’ failure to provide standards for compac-
    10
    These plaintiffs suggest the “95 percent Standard Proctor density” standard. We use
    it, however, only as an example of a possible standard of compaction, not as an approval of that
    standard. The issue is not whether the government chose the correct standard, because the
    GCI defense is meant to prevent the second-guessing of such decisions. See Boyle, 
    487 U.S. at 511
     (stating that “permitting ‘second guessing” of these judgments through state tort suits
    against contractors would produce the same effect sought to be avoided by the FTCA exemp-
    tion”) (internal citation omitted). Rather, the issue is whether the government chose any stan-
    dard of compaction at all. There is no second-guessing here of a government decision, because
    none was made.
    16
    Nos. 09-30449, 09-30428, 09-30438
    tion or to provide details for the equipment to be employed was, in itself, a pre-
    cise specification. The approved work plan stated that “[t]he material will be
    placed in lifts and compacted” and affirmed that “no compaction testing will be
    required.” Given that those general specifications were the result of an intricate
    approval process, it is reasonable to conclude that the decision not to specify
    more than basic compaction was a decision made by the Corps, as WGI contends
    in its brief.
    The question, however, is not whether the Corps approved of any decision
    regarding the compaction method. The relevant inquiry, instead, is whether the
    Corps approved sufficiently precise specifications, such that it is evident that the
    government was the primary agent of decision over the compaction method. “If
    the government approved imprecise or general guidelines, then discretion over
    important design choices would be left to the government contractor.” Trevino,
    
    865 F.2d at 1481
    . By providing only general instructions regarding the compac-
    tion method, the Corps ensured that WGI would have significant discretion over
    the method chosen. The exercise of that discretion by WGI is not protected by
    the GCI doctrine.
    To decide otherwise would lead to an absurdity: The government could
    provide general specifications, inform the court that it “precisely” chose to ap-
    prove only general specifications, and thus render all subsequent, discretionary
    decisions of a government contractor protected under the GCI doctrine. Such an
    analysis would controvert the very purpose of the GCI defense. The government
    contractor defense in Boyle, “[s]tripped to its essentials,” is fundamentally a
    17
    Nos. 09-30449, 09-30428, 09-30438
    claim that “[t]he Government made me do it.”11 To adhere to this basic principle,
    it is essential that the specifications approved by the government are reasonably
    precise. “If the government approved imprecise or general guidelines, then dis-
    cretion over important design choices would be left to the government contrac-
    tor.” Trevino, 
    865 F.2d at 1481
    .
    The Corps did not “make” WGI use the exact backfill material that was
    utilized, nor did it “require” WGI select the compaction method that was em-
    ployed. In the absence of reasonably precise Corps specifications, those decisions
    were made by WGI. Thus, WGI fails the first step of the Boyle test and is not en-
    titled to GCI for its choice of backfill material and compaction method. The sum-
    mary judgment is REVERSED, and this matter is REMANDED for further pro-
    ceedings as needed. We impose no limitations on what matters the district court
    can consider on remand, and we express no view as to what decisions that court
    should make.
    11
    In re Joint E. & S. Dist. N.Y. Asbestos Litig., 
    897 F.2d 626
    , 632 (2d Cir. 1990). See
    also Trevino, 
    865 F.2d at 1482
     (“[T]he purpose of the [Boyle] test is to deny the defense to a
    government contract that is itself ultimately responsible for the defect.”) (internal quotation
    marks and citation omitted).
    18