Mary Williams v. City of Gulfport, Mississi , 454 F. App'x 270 ( 2011 )


Menu:
  •      Case: 11-60148     Document: 00511665887         Page: 1     Date Filed: 11/15/2011
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    November 15, 2011
    No. 11-60148                          Lyle W. Cayce
    Summary Calendar                             Clerk
    GEORGE BUSH; GCW, L.L.C.,
    Plaintiffs – Appellants
    v.
    CITY OF GULFPORT, MISSISSIPPI;
    JOHN DOES 1-5, in their individual capacities,
    Defendants – Appellees
    Appeal from the United States District Court
    for the Southern District of Mississippi
    USDC No. 1:07-CV-906
    Before KING, JOLLY, and GRAVES, Circuit Judges.
    PER CURIAM:*
    Appellants GCW, L.L.C. and George L. Bush appeal the district court’s
    dismissal of their lawsuit against the City of Gulfport, Mississippi, and certain
    unidentified city officials. Appellants claim that the City violated their
    substantive due process and equal protection rights when it improperly denied
    their building permit application. We affirm.
    *
    Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH CIR.
    R. 47.5.4.
    Case: 11-60148      Document: 00511665887        Page: 2     Date Filed: 11/15/2011
    No. 11-60148
    I. FACTUAL AND PROCEDURAL BACKGROUND
    Large sections of Gulfport, Mississippi, were heavily damaged when
    Hurricane Katrina came ashore on August 29, 2005. One of the buildings
    destroyed by the storm was owned by Plaintiff-Appellant GCW, L.L.C. and
    leased by Plaintiff-Appellant George Bush (collectively, “Appellants”). Since
    2001, Bush had operated a nightclub on the property called “Club Illusions.” The
    property neighbored a strip mall owned by the father of former Gulfport Mayor
    Brent Warr (“Warr”). After the hurricane came ashore, only a concrete slab
    remained where the building that housed Club Illusions had once stood.
    Appellants started rebuilding efforts shortly after they were allowed back onto
    the property to survey the damage. Bush engaged an architectural firm in March
    2006, and made contact with officials at the Planning and Urban Development
    Department of Defendant-Appellee City of Gulfport (“the City” or “Appellee”).
    Removal of the existing slab and debris began in April 2006.
    Appellants allege that their rebuilding efforts were blocked when, in July
    2006, Mayor Warr “undertook by executive fiat to amend the City’s Zoning
    Ordinance in an apparent effort to exclude the [Appellants’] operation of Club
    Illusions in front of his father’s strip mall.” The amendment was formally
    accomplished through City Ordinance 2482 (“Ordinance 2482”), which was
    passed by the city counsel on July 18, 2006.1 Relevant here, Ordinance 2482
    provides:
    Should [a] nonconforming structure of commercial use be destroyed
    or damaged by an act of God, including tornado, hurricane, flood,
    wind, earthquake, etc., . . . the structure may be replaced or
    repaired. However, such replacement or repair shall be subject to
    the following provision: Application for a building permit must be
    1
    Appellants had alleged in their amended complaint that Ordinance 2482 was not
    properly enacted, or was enacted specifically to target them, but they do not argue this on
    appeal. The record reflects that Ordinance 2482 was considered and passed at a “duly
    constituted meeting of the City Council and the Mayor of the City of Gulfport.”
    2
    Case: 11-60148   Document: 00511665887      Page: 3   Date Filed: 11/15/2011
    No. 11-60148
    made to the building official within one year of the time that the
    structure was destroyed. However, in cases of hardship the mayor
    and city council shall at their sole discretion have the authority to
    extend such one-year limitation for additional periods of time up to
    six (6) months each upon application of the owner or leaseholder
    prior to the expiration of the allowable nonconformity. (emphasis
    added)
    The relevant provision in effect before the amendment (since 1979) provided for
    repair or replacement of non-conforming structures, with the following
    qualification:
    Application for a building permit must be made to the Building
    Official within one year of the time that the structure was destroyed.
    However, in cases of hardship the Mayor and Board of
    Commissioners shall at its discretion have the authority to extend
    said one-year limitations for additional periods of time upon
    application of the owner or leaseholder. (emphasis added)
    Thus, even prior to Ordinance 2482, building permits were subject to a one year
    time limitation. The purpose of the 2006 amendment was to extend the time
    period for applications to rebuild residential structures from one to two years.
    The City recognized that existing limitations would “work a severe hardship on
    those residential property owners who owned nonconforming structures that
    received total or substantial destruction by Hurricane Katrina,” and enforcement
    of those limitations would “have an overall detrimental impact on restoration of
    the City of Gulfport.” The time limitations on non-conforming commercial
    structures were left unchanged.
    Appellants applied for a building permit on September 19, 2006, and the
    City Planning Department approved the building plans in October 2006, but not
    the permit itself. Appellants’ application was submitted soon after the City
    adopted a flood damage prevention ordinance, with guidance from the Federal
    Emergency Management Agency (“FEMA”) on September 5, 2006. On December
    18, 2006, the City denied Appellants’ application because it was incomplete and
    3
    Case: 11-60148    Document: 00511665887      Page: 4   Date Filed: 11/15/2011
    No. 11-60148
    violated the one year limitation of Ordinance 2482. On appeal, the City’s Board
    of Adjustment affirmed the denial on the basis that Appellants’ application was
    made outside the one year time limitation. This decision was subsequently
    upheld by the Gulfport City Council.
    Displeased with this resolution, Appellants filed suit in the district court
    on June 27, 2007 against the City and certain John Doe defendants (unknown
    City agents). Appellants brought claims under 
    42 U.S.C. § 1983
     for violation of
    procedural and substantive due process rights, equal protection, and state law
    claims for civil conspiracy and intentional infliction of emotional distress.
    Underlying Appellants’ claims was their allegation that Mayor Warr had a
    personal interest in preventing Appellants from building on the property. This
    claim was based upon the fact that Warr’s father owned a strip mall next to the
    nightclub, and had made statements to Bush that he would take whatever steps
    were necessary to shut down Club Illusions. Appellants contend that, after
    Hurricane Katrina, Mayor Warr had given himself the authority to personally
    review and approve all commercial building permit applications along the
    coastal area (including Appellants’ property), and used his authority to ensure
    that Appellants’ application was denied.
    The district court granted Appellee’s summary judgment motion, and
    dismissed Appellants’ suit, including their due process and equal protection
    claims. The court declined to retain supplemental jurisdiction over Appellants’
    state law causes of action. Appellants timely appealed the district court’s
    decision with respect to their substantive due process and equal protection
    claims. We now affirm.
    II. STANDARD OF REVIEW
    We review the district court’s grant of summary judgment de novo and
    apply the same standard as the district court. First Am. Bank v. First Am.
    Transp. Title Ins. Co., 
    585 F.3d 833
    , 836-37 (5th Cir. 2009). Summary judgment
    4
    Case: 11-60148    Document: 00511665887      Page: 5    Date Filed: 11/15/2011
    No. 11-60148
    is proper “if the movant shows that there is no genuine dispute as to any
    material fact and the movant is entitled to judgment as a matter of law.” FED.
    R. CIV. P. 56(a). We review the evidence in the light most favorable to the non-
    moving party. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 
    475 U.S. 574
    ,
    587 (1986). “A genuine issue of material fact exists if a reasonable jury could
    enter a verdict for the non-moving party.” Castellanos-Contreras v. Decatur
    Hotels, LLC, 
    622 F.3d 393
    , 397 (5th Cir. 2010).
    III. DISCUSSION
    A. Substantive Due Process
    Appellants contend that their substantive due process rights were violated
    when the City denied their building permit for irrational reasons, and that
    personal animosity was the actual motive behind the denial.
    We have explained that “[a] violation of substantive due process . . . occurs
    only when the government deprives someone of liberty or property; or, to use the
    current jargon, only when the government works a deprivation of a
    constitutionally protected interest.” Simi Inv. Co., Inc. v. Harris Cnty., Tex., 
    236 F.3d 240
    , 249 (5th Cir. 2000). A plaintiff who brings a substantive due process
    claims must satisfy two considerations. “First, he must allege a deprivation of
    a constitutionally protected right.” Mikeska v. City of Galveston, 
    451 F.3d 376
    ,
    379 (5th Cir. 2006). Second, he must demonstrate that the government action is
    not “rationally related to a legitimate governmental interest.” 
    Id.
    When we review a substantive due process claim, we pursue “either of two
    analytical tracks. A regulatory decision can be legislative or it can be
    adjudicative, and it will be reviewed differently depending on which category it
    is placed into.” Shelton v. City of College Station, 
    780 F.2d 475
    , 479 (5th Cir.
    1986); see also Vulcan Materials Co. v. City of Techuacana, 
    238 F.3d 382
    , 388
    (5th Cir. 2001) (citing Shelton, 
    780 F.2d at 479-84
    ). Under the adjudicative
    model, “actions by state officials are tested by historical facts and “adequate
    5
    Case: 11-60148    Document: 00511665887       Page: 6    Date Filed: 11/15/2011
    No. 11-60148
    evidence found within a defined record.” Mahone v. Addicks Util. Dist. of Harris
    Cnty., 
    836 F.2d 921
    , 934 (5th Cir. 1988) (citing Shelton, 
    780 F.2d at 479
    ). As
    such, a court “using the adjudicative model must focus on what actually
    motivated the conduct.” 
    Id.
     In contrast, if the action is evaluated under the
    legislative model, the court asks only whether there was “a conceivable factual
    basis for the specific decision made?” Shelton, 
    780 F.2d at 479
    . “In practical
    terms, therefore, evidence that an official was motivated by an illegitimate
    purpose when he took an action cannot, under the legislative model, invalidate
    the official’s action. Instead, if a court is able to hypothesize a legitimate purpose
    to support the action, the action must be treated as valid.” Mahone, 
    836 F.2d at 934
    .
    The district court concluded that Appellants could not establish a
    substantive due process violation because the City articulated a legitimate
    reason for denying Appellants’ building permit, namely that the permit
    application was not submitted within one year after destruction of the non-
    conforming structure. The district court also concluded that enforcing this
    deadline is “rationally related to the City’s interest in reducing the number of
    structures that are not compatible with the neighborhood around them.”
    We conclude that Appellants’ substantive due process claim cannot survive
    summary judgment. We assume for purposes of this discussion that Appellants
    had a protected property interest in the building permit. See Vineyard
    Investments, L.L.C. v. The City of Madison, Miss., No. 10-60968, 
    2011 WL 3911071
    , at *3 (5th Cir. Sept. 2, 2011) (assuming without deciding that applicant
    had property interest in building permit). Appellee argues that we should apply
    the legislative or quasi-legislative analytical framework, applicable to regulatory
    decisions regarding zoning and land use. The district court determined that the
    decision at issue was “quasi-legislative.” While we have recognized that zoning
    decisions are “legislative” or at least “quasi-legislative,” Shelton, 
    780 F.2d at 483
    ,
    6
    Case: 11-60148   Document: 00511665887      Page: 7   Date Filed: 11/15/2011
    No. 11-60148
    we have not categorically said that building permit decisions fall into this
    classification, and have recently proceeded on the assumption that they are
    “adjudicative.” See Vineyard Investments, 
    2011 WL 3911071
    , at *3. In this case,
    however, the distinction between the adjudicative and legislative analysis is
    minimal, as we are provided with an actual reason for the government action at
    issue here, and need not hypothesize a legitimate purpose to support the
    municipal action.
    The evidence demonstrates that the City ultimately denied Appellants’
    building application because it was not submitted within the one year
    application period. It is undisputed that Appellants’ building permit application
    was submitted on September 19, 2006, more than one year after the destruction
    of the property on August 29, 2005. Imposition of a one year deadline is
    rationally related to a legitimate government interest. The district court found
    a legitimate government interest in “reducing the number of structures that are
    not compatible with the neighborhood around them,” and the City asserts such
    an interest as well. We also find that the one year limitation serves the
    legitimate interest of encouraging property owners to rebuild quickly, rather
    than allow their properties to remain in disrepair indefinitely. Enforcing the one
    year deadline by rejecting untimely applications is rationally related to these
    legitimate government interests, and we therefore do not find a violation of
    Appellants’ substantive due process rights.
    We are not persuaded by Appellants’ primary argument on appeal, namely
    that the City’s denial of their building permit was motivated by Mayor Warr’s
    economic interest in their property and his personal animosity towards them.
    Abuse of executive power may, in some limited cases, constitute a violation of
    substantive due process. Substantive due process “bars certain arbitrary,
    wrongful government actions regardless of the fairness of the procedures used
    to implement them.” Zinermon v. Burch, 
    494 U.S. 113
    , 125, (1990) (internal
    7
    Case: 11-60148    Document: 00511665887      Page: 8   Date Filed: 11/15/2011
    No. 11-60148
    quotation marks omitted). To state a substantive due process claim based upon
    an abuse of executive power, “the plaintiff must demonstrate that the state
    official acted with culpability beyond mere negligence. . . . [T]he Supreme Court’s
    discussions of abusive executive action have repeatedly emphasized that only the
    most egregious official conduct can be said to be arbitrary in the constitutional
    sense. . . . The plaintiff must therefore demonstrate that the abuse of power by
    the state official shocks the conscience.” Marco Outdoor Adver., Inc. v. Reg’l
    Transit Auth., 
    489 F.3d 669
    , 671 n.3 (5th Cir. 2007) (citations and internal
    quotation marks omitted); Cnty. of Sacramento v. Lewis, 
    523 U.S. 833
    , 846
    (1998) (“[F]or half a century now we have spoken of the cognizable level of
    executive abuse of power as that which shocks the conscience.”).
    The Supreme Court’s decision in City of Cuyahoga Falls, Ohio v. Buckeye
    Community Hope Foundation, 
    538 U.S. 188
     (2003) is instructive. There, the
    plaintiffs asserted, inter alia, a substantive due process claim after their
    building permit requests for a low-income housing complex were denied.
    Numerous citizens, city officials, and even the mayor opposed the project and
    voiced their opposition at various city council meetings. When the city council
    approved the project and issued an ordinance to that effect, a group of citizens
    petitioned for a referendum challenging the ordinance. While the referendum
    was pending, plaintiffs applied for their building permit. The city engineer,
    however, denied the request after being advised by the city law director that the
    permits could not be issued because the referendum delayed the effective date
    of the ordinance. The plaintiffs argued that their substantive due process rights
    were violated because the city engaged in arbitrary conduct in denying the
    permit and in allowing the approval to be subject to a referendum. 
    Id. at 191-92, 198-99
    . The Court found no merit to these claims, and concluded that the city
    engineer’s refusal to issue the permits “in no sense constituted egregious or
    arbitrary government conduct.” 
    Id. at 198
    . The Court explained that the “law
    8
    Case: 11-60148    Document: 00511665887       Page: 9    Date Filed: 11/15/2011
    No. 11-60148
    director’s instruction to the engineer not to issue the permits represented an
    eminently rational directive,” given that “the [project’s] site plan, by law, could
    not be implemented until the voters passed on the referendum.” 
    Id. at 199
    . Thus,
    plaintiffs’ substantive due process claim failed in light of the City’s rational basis
    for its decision, even with evidence that many government officials were
    personally opposed to the project. Id.; see also Greenbriar Vill., L.L.C. v.
    Mountain Brook, City, 
    345 F.3d 1258
    , 1264 (11th Cir. 2003) (“[E]ven with . . .
    evidence that the City targeted Greenbriar out of animosity, it is equally clear
    that the City was also motivated in part by a legitimate desire to enact a
    comprehensive and internally consistent land use system. It follows from these
    reasonable and legitimate governmental objectives that even if the Permit was
    a fundamental right protected by substantive due process, the City’s actions
    were not constitutionally arbitrary and irrational.”).
    Appellants cite several portions of the record in support of their claim that
    their permit was denied due to Mayor Warr’s own economic and personal
    motivations. These include statements by Mayor Warr’s father that he wanted
    to shut down the club because it was a nuisance; hearsay statements that the
    permitting process was “political”; deposition testimony by building official Ron
    Jones that Mayor Warr had to personally approve post-Katrina commercial
    building permits in certain areas of the City; and an affidavit by Patricia Short,
    a former city employee who repeated hearsay statements from two other city
    officials (Ron Jones and Mike Edwards) that Mayor Warr had told them to
    ensure that Mr. Bush did not get a building permit. Mayor Warr denied personal
    involvement, but Appellants attack his credibility by noting that he was indicted
    for fraud following Hurricane Katrina in August 2009. Even viewed in the light
    most favorable to Appellants, we do not believe this evidence creates a genuine
    factual dispute as to whether Mayor Warr engaged in “egregious official
    conduct,” or that his alleged actions constitute an “abuse of power by [a] state
    9
    Case: 11-60148       Document: 00511665887          Page: 10     Date Filed: 11/15/2011
    No. 11-60148
    official [that] shocks the conscience.” Marco Outdoor Adver., 
    489 F.3d at
    671 n.3.
    Mayor Warr may have taken a personal interest in the property, but none of his
    actions rise to the level of a constitutional violation. This conclusion is reinforced
    by the fact that the permit’s untimeliness provided the City with an undisputed,
    rational basis for the denial.
    We are also not persuaded by Appellants’ other arguments on appeal.
    First, Appellants argue that imposition of the one year time limit is not
    rationally related to a legitimate government interest because they filed their
    application shortly after the City enacted a new flood plain ordinance, and that
    ordinance controlled development in the City. They also contend that City
    officials should have exercised their discretion to excuse the one year limitation,
    as Appellants were not able to inspect the property in the period immediately
    after the storm. It is not our purpose, however, to determine whether it would
    have been better for the City to suspend the one year limitation period, or grant
    an extension in Appellants’ case. The fact that City officials declined to utilize
    their discretion in Appellants’ case does not mean that their decision is not
    rationally related to a legitimate governmental interest. Simply put, “the Due
    Process Clause does not empower the judiciary to sit as a superlegislature to
    weigh the wisdom of legislation” or policy decisions. Exxon Corp. v. Governor of
    Md., 
    437 U.S. 117
    , 124 (1978) (internal quotation marks omitted).2
    Second, Appellants contend that the City’s December 18, 2006 letter
    denying their permit application was “pretextual and . . . not supported by the
    facts.” They dispute the City’s initial determination that their plans were
    2
    Appellants also contend that Ordinance 2482 provides city officials with “unfettered
    discretion” to grant extensions to the one year limitation period, and that such discretion is
    “repugnant to the Fourteenth Amendment’s notion of fair play and equal treatment under the
    law.” They do not argue this point in significant detail, and so we do not consider it further.
    Sanders v. Unum Life Ins. Co. of Am., 
    553 F.3d 922
    , 926 (5th Cir. 2008) (“A party waives an
    issue if he fails to adequately brief it on appeal.”) (internal quotation marks omitted).
    10
    Case: 11-60148     Document: 00511665887      Page: 11    Date Filed: 11/15/2011
    No. 11-60148
    “incomplete.” They also note that certain City officials, when deposed, either
    confirmed that the plan was complete or could not explain how it was lacking.
    Appellants’ arguments, however, are not reflected by the facts. First, the
    December 18 denial letter not only concludes that the plans were “incomplete,”
    but also specifically states that the permit application “violates Zoning text
    Ordinance 1501 (as amended by Ordinance 2482) Section VII(C)(3)(A),” which
    sets out the one year time limitation described above. In the same vein,
    Appellants entirely ignore the City’s appellate decision, which again determined
    that the application should be denied as untimely. Appellants have failed to
    demonstrate that this reason was “pretextual” or even incorrect. In fact, they
    even readily admit that their application was not timely.
    Even if the City’s initial determination regarding whether the plans were
    “complete” was actually incorrect, an erroneous decision does not itself give rise
    to a constitutional claim. We have explained that “the power to decide, to be
    wrong as well as right on contestable issues, is both [a] privilege and curse of
    democracy.” FM Properties Operating Co. v. City of Austin, 
    93 F.3d 167
    , 174 (5th
    Cir. 1996). Further, “the due process clause does not require a state to
    implement its own law correctly,” or “insist that a local government be right.” 
    Id.
    Indeed, “[c]onverting alleged violations of state law into federal . . . due process
    claims improperly bootstraps state law into the Constitution.” 
    Id.
     (quoting Stern
    v. Tarrant Cnty. Hosp. Dist., 
    778 F.2d 1052
    , 1056 (5th Cir. 1985) (en banc)). As
    such, “a violation of state law is alone insufficient to state a constitutional claim
    under the Fourteenth Amendment.” 
    Id.
     (emphasis added). A panel of this court
    recently rejected an argument very similar to the one that Appellants advance
    here. In Vineyard Investments, L.L.C., the panel rejected the appellant’s
    argument that the city’s denial of a building permit could not withstand rational
    basis review because a state appellate court had found that the city’s reason for
    the denial was incorrect under Mississippi law. The panel explained that a
    11
    Case: 11-60148       Document: 00511665887         Page: 12     Date Filed: 11/15/2011
    No. 11-60148
    legally incorrect decision “does not automatically characterize the City’s action
    as arbitrary and capricious.” Vineyard Investments, L.L.C., 
    2011 WL 3911071
    ,
    at *2. The same rationale applies here. Even if the City had rested solely on the
    allegedly incorrect conclusion that the building permit application was
    incomplete, this would not be sufficient to state a substantive due process
    violation.3
    Finally, Appellants contend that the City waived the twelve month
    application requirement through its conduct (namely processing the application
    without raising the time limitation and making certain representations), and is
    equitably estopped from attempting to enforce it under the present facts. The
    district court rejected this argument, holding that Appellants could not establish
    the necessary factual prerequisites, and that unofficial acts preceding the City’s
    permitting process could not give rise to an equitable estoppel claim. We need
    not address this argument at length. As an initial matter, although Appellants
    raised an equitable estoppel theory on summary judgment, they never asserted
    such a claim in their amended complaint. Second, Appellants’ estoppel argument
    lacks a direct bearing upon their constitutional claims. Section 1983 is a remedy
    for violations of constitutional rights, not violations of state law. See, e.g.,
    Woodard v. Andrus, 
    419 F.3d 348
    , 353 (5th Cir. 2005). In other words, even if the
    City were estopped from enforcing the time limitation under state law, this
    would not necessarily demonstrate a substantive due process or equal protection
    violation. Third, Appellants’ equitable estoppel argument fails on the merits.
    Under Mississippi law, “the doctrine of equitable estoppel may be applied
    3
    In this regard, Appellants also argue that their reconstruction of the property began
    in April 2006, and reference Section 7(a)(2) of Ordinance 2482, which provides an exception
    to the Ordinance for structures “on which actual construction was lawfully begun prior to the
    effective date of this ordinance.” Because the one year limitation was in effect even prior to
    Ordinance 2482, we do not believe that this exception applies. Even if it should have applied,
    Appellants cannot base a substantive due process claim upon a merely incorrect state decision.
    See FM Properties Operating Co. v. City of Austin, 
    93 F.3d 167
    , 174 (5th Cir. 1996).
    12
    Case: 11-60148    Document: 00511665887       Page: 13   Date Filed: 11/15/2011
    No. 11-60148
    against the state and its municipalities.” Suggs v. Town of Caledonia, 
    470 So. 2d 1055
    , 1057 (Miss. 1985). The Mississippi Supreme Court has further explained
    that “the unauthorized acts of one of [a municipality’s] officials does not estop a
    municipality from acting in its governmental capacity.” Suggs, 470 So. 2d at
    1057. Consistent with this rule, the Mississippi Supreme Court has declined to
    apply the doctrine when an equitable estoppel claim is based upon the informal
    actions of governmental employees, rather than an official government act. See
    id.; see also Moore ex rel. Benton Cnty. v. Renick, 
    626 So. 2d 148
    , 153 (Miss. 1993)
    (rejecting equitable estoppel argument based upon unauthorized advisory
    opinion of an ethics panel). The district court properly rejected Appellants’
    equitable estoppel argument because Appellants have not shown the existence
    of an official government action prior to denial of the permit. The unofficial
    representations of certain city employees cannot form the basis of an equitable
    estoppel claim under Mississippi law. Suggs, 470 So. 2d at 1057; Renick, 626 So.
    2d at 153.
    In sum, the district court properly concluded that Appellants’ substantive
    due process claims cannot survive summary judgment.
    B. Equal Protection
    Appellants also allege that the City’s denial of their building permit
    violated their rights under the Equal Protection Clause of the Fourteenth
    Amendment. As the district court recognized, Appellants allege a “class of one”
    equal protection claim, as they contend that Mayor Warr singled them out for
    different treatment because of his personal animus against their business and
    his own economic motives.
    It is well established that “[a] violation of equal protection occurs only
    when the government treats someone differently than others similarly situated.”
    Nat’l Fed. of the Blind of Texas, Inc. v. Abbott, 
    647 F.3d 202
    , 214 (5th Cir. 2011).
    The Supreme Court has “recognized successful equal protection claims brought
    13
    Case: 11-60148    Document: 00511665887       Page: 14   Date Filed: 11/15/2011
    No. 11-60148
    by a ‘class of one,’ where the plaintiff alleges that she has been intentionally
    treated differently from others similarly situated and that there is no rational
    basis for the difference in treatment.” Vill. of Willowbrook v. Olech, 
    528 U.S. 562
    ,
    564 (2000). An equal protection challenge to a municipality’s permitting decision
    requires a plaintiff to “show that the difference in treatment with others
    similarly situated was irrational.” Mikeska, 
    451 F.3d at 381
    ; see also Lindquist
    v. City of Pasadena, Tex., 
    525 F.3d 383
    , 386 (5th Cir. 2008) (holding that
    Mikeska applies to plaintiffs’ equal protection claim based upon allegations that
    the city council refused to grant plaintiffs a car dealer license while granting
    licenses to others similarly situated, without a rational basis).
    The district court granted summary judgment on Appellants’ equal
    protection claim because they failed to show the existence of similarly situated
    entities. Appellants argue that a facility called Grass Lawn was “similarly
    situated,” as its reconstruction permit was approved even though it was
    submitted three years after the structure was destroyed. The district court
    concluded that the Grass Lawn project was not similarly situated, as the
    application for the project involved a “non-conforming use,” not a “non-
    conforming structure,” and the one year limit at issue is applicable only to “non-
    conforming structures.”
    We agree with the district court that the Grass Lawn project is not
    “similarly situated,” but for a different reason. The Grass Lawn property is not
    “similarly situated” because the record demonstrates that it is a recreational
    rather than commercial structure. A letter from architect Frank Genzer to the
    City of Gulfport Planning Commission explains that Grass Lawn is “listed on the
    National Register of Historic Places,” and that reconstruction “of this iconic
    building on its original site will re-establish its use as a museum, providing
    14
    Case: 11-60148      Document: 00511665887         Page: 15    Date Filed: 11/15/2011
    No. 11-60148
    educational tours and lectures, as well as a location for community receptions.”4
    Ordinance 2482 and its one-year limitation period applies by its own terms only
    to “structure[s] of commercial use.” The Grass Lawn historical and recreational
    structure is not similarly situated to Appellants’ proposed nightclub. A better
    comparator would be another nightclub, bar, or commercial establishment whose
    permit was approved despite being untimely. Appellants have no evidence of any
    such entity.
    As Appellants have failed to demonstrate the existence of others “similarly
    situated,” summary judgment on their equal protection claim was proper.
    C. Discovery Issue
    Finally, Appellants take issue with the district court’s handling of
    discovery in this litigation. This court “review[s] a district court’s discovery
    rulings, including the denial of a motion to compel, for abuse of discretion.” Wiwa
    v. Royal Dutch Petroleum Corp., 
    392 F.3d 812
    , 817 (5th Cir. 2004). “We will
    affirm such decisions unless they are arbitrary or clearly unreasonable.” 
    Id.
    (internal quotation marks omitted). Thus, “[a] trial court’s decision pertaining
    to discovery should be reversed only in an unusual and exceptional case.” Unger
    v. Taylor, 368 F. App’x 526, 535 (5th Cir. 2010) (citing O’Malley v. U.S. Fid. &
    Guar. Co., 
    776 F.2d 494
    , 499 (5th Cir. 1985)) (internal quotation marks omitted);
    see also Marathon Fin. Ins., Inc., RRG v. Ford Motor Co., 
    591 F.3d 458
    , 469 (5th
    Cir. 2009) (“[A] district court’s discretion in discovery matters will not be
    disturbed ordinarily unless there are unusual circumstances showing a clear
    abuse.”). Further, we will “disregard a district court’s discovery error unless that
    error affected the substantial rights of the parties.” Marathon, 
    591 F.3d at 469
    (internal quotation marks omitted). When contesting a discovery issue, “[t]he
    burden of providing substantial error and prejudice is upon the appellant.” 
    Id.
    4
    Appellants describe Grass Lawn as “essentially a wedding chapel that the City rented
    out commercially.” The available evidence does not support this characterization.
    15
    Case: 11-60148        Document: 00511665887          Page: 16     Date Filed: 11/15/2011
    No. 11-60148
    Appellants argue that the district court erred when it granted Appellee’s
    summary judgment motion without ruling on Appellants’ two motions to compel
    discovery, despite having granted Appellants’ motion under former Federal Rule
    of Civil Procedure 56(f) to seek additional discovery before responding to a
    previous summary judgment motion.5 One motion to compel sought a response
    to interrogatories, requests for production, and requests for admission, and
    another sought to re-depose City employee Michael Edwards. Appellants filed
    the motion after Mr. Edwards allegedly told Mr. Bush and Mary Wood (of GCW)
    that he had mispoken at his first deposition, and would gladly discuss the
    political nature of the permitting process if re-deposed.
    We conclude that Appellants waived the issue of inadequate discovery by
    failing to seek relief under Rule 56(f). Although Appellants contend that the
    district court should have taken up their motions to compel, “particularly after
    having granted a Rule 56(f) motion,” the record reflects that no Rule 56(f) relief
    was ever filed with respect to the pending motion for summary judgment.
    Rather, Appellants sought relief under Rule 56(f) when they were confronted
    with an earlier summary judgment motion in July 2008. In that motion, they
    explained that they required “the deposition testimony of the Mayor, the Mayor’s
    father, and certain officers and employees of the City’s Planning and Zoning
    Department.” The district court granted that Rule 56(f) motion, and denied the
    summary judgment motion without prejudice in February 2009. Appellants did
    not seek relief pursuant to former Rule 56(f) when faced with Appellee’s June
    5
    In 2007, Federal Rule of Civil Procedure 56(f) provided: “[s]hould it appear from the
    affidavits of a party opposing the motion that the party cannot for reasons stated present by
    affidavit facts essential to justify the party’s opposition, the court may refuse the application
    for judgment or may order a continuance to permit affidavits to be obtained or depositions to
    be taken or discovery to be had or may make such other order as is just.” FED. R. CIV. P. 56(f)
    (2007). Rule 56 was amended in 2010, and the advisory committee notes to the 2010
    amendments state that “Subdivision (d) carries forward without substantial change the
    provisions of former subdivision (f).” FED. R. CIV. P. 56(d) advisory committee’s note.
    16
    Case: 11-60148     Document: 00511665887       Page: 17    Date Filed: 11/15/2011
    No. 11-60148
    2010 motion for summary judgment. While Appellants sought one extension to
    respond to the pending summary judgment motion, it was only to incorporate an
    “additional affidavit of an important witness” into the response, and not to
    include any other discovery. This affidavit was ultimately included in the
    response that Appellants filed on July 8, 2010. Appellants’ failure to seek relief
    under Rule 56(f) constitutes waiver. We have consistently held that a party
    “waive[s] the issue of inadequate discovery” when it fails to seek relief under
    Rule 56(f). Access Telecom, Inc. v. MCI Telecomms. Corp., 
    197 F.3d 694
    , 719 (5th
    Cir. 1999); see Jefferson v. Christus St. Joseph Hosp., 374 F. App’x 485, 492 n.13
    (5th Cir. 2010) (“Though appellants also claim they were afforded insufficient
    discovery, they failed to move for relief under Federal Rule of Civil Procedure
    56(f) and therefore have waived this argument on appeal.”); 27A CHARLES ALAN
    WRIGHT & ARTHUR R. MILLER, FEDERAL PRACTICE AND PROCEDURE § 62:645 (3d
    ed. 2011) (“Failure to file a FED. R. CIV. P. 56(f) motion is itself a sufficient
    ground to reject a claim that discovery was inadequate, and is also a factor
    favoring the granting of summary judgment to the movant.”). Simply put,
    Appellants cannot fault the district court for not allowing them additional time
    to conduct discovery when they did not seek such relief in the first place. See
    Potter v. Delta Air Lines, Inc., 
    98 F.3d 881
    , 887 (5th Cir. 1996) (“If [the plaintiff]
    needed more discovery in order to defeat summary judgment, it was up to her
    to move for a continuance pursuant to rule 56(f). Because she did not, she is
    foreclosed from arguing that she did not have adequate time for discovery.”).
    Even if Appellants’ argument were considered on the merits, the record
    demonstrates that the district court did not abuse its discretion. Assuming for
    the moment that the district court erred in granting Appellee’s summary
    judgment motion in September 2010 without ruling on the motions to compel
    discovery or otherwise resolving discovery disputes between the parties, it
    corrected this error when it vacated its order and final judgment, so that the
    17
    Case: 11-60148    Document: 00511665887     Page: 18   Date Filed: 11/15/2011
    No. 11-60148
    case could be resolved on the merits and the issues could be reconsidered “with
    the benefit of Plaintiffs’ additional evidence.” Although the district court
    provided Appellants with an additional opportunity to defeat the summary
    judgment motion, they made no filings in the nearly three month period between
    the November 22, 2010 reconsideration order and the district court’s February
    7, 2011 order granting Appellee’s summary judgment motion. Appellants did not,
    for example, file supplemental briefs, re-urge their motions to compel discovery,
    seek sanctions for failure to comply with discovery requests, or take any other
    steps to obtain the additional discovery that they now claim to have been denied.
    The onus was ultimately on Appellants to seek the court’s assistance in
    addressing Appellee’s recalcitrance, and there is no evidence that Appellants
    attempted to do so in the period leading up to the court’s February 2011
    summary judgment order.
    IV. CONCLUSION
    For the foregoing reasons, the judgment of the district court is
    AFFIRMED.
    18
    

Document Info

Docket Number: 11-60148

Citation Numbers: 454 F. App'x 270

Judges: Graves, Jolly, King, Per Curiam

Filed Date: 11/15/2011

Precedential Status: Non-Precedential

Modified Date: 8/5/2023

Authorities (26)

Greenbriar Village, L.L.C. v. Mountain Brook, City , 345 F.3d 1258 ( 2003 )

Marathon Financial Ins., Inc., RRG v. Ford Motor Co. , 591 F.3d 458 ( 2009 )

Vulcan Materials Co. v. City of Tehuacana , 238 F.3d 382 ( 2001 )

FM Properties Operating Co. v. City of Austin , 93 F.3d 167 ( 1996 )

Potter v. Delta Air Lines, Inc. , 98 F.3d 881 ( 1996 )

Simi Investment Company Inc v. Harris County Texas , 236 F.3d 240 ( 2000 )

Woodard v. Andrus , 419 F.3d 348 ( 2005 )

Sanders v. Unum Life Insurance Co. of America , 553 F.3d 922 ( 2008 )

Access Telecom, Inc. v. MCI Telecommunications Corp. , 197 F.3d 694 ( 1999 )

First American Bank v. First American Transportation Title ... , 585 F.3d 833 ( 2009 )

Lindquist v. City of Pasadena, Tex. , 525 F.3d 383 ( 2008 )

Castellanos-Contreras v. Decatur Hotels, LLC , 622 F.3d 393 ( 2010 )

Fred B. Shelton Iii, and John Paul Jones, Cross v. City of ... , 780 F.2d 475 ( 1986 )

Marco Outdoor Advertising, Inc. v. Regional Transit ... , 489 F.3d 669 ( 2007 )

Mikeska v. City of Galveston , 451 F.3d 376 ( 2006 )

National Federation of the Blind of Texas, Inc. v. Abbott , 647 F.3d 202 ( 2011 )

Paul v. O'Malley v. United States Fidelity and Guaranty ... , 776 F.2d 494 ( 1985 )

Paul A. Stern v. Tarrant County Hospital District v. George ... , 778 F.2d 1052 ( 1985 )

ken-wiwa-individually-and-as-of-the-estate-of-his-deceased-father-ken , 392 F.3d 812 ( 2004 )

Randolph Mahone v. Addicks Utility District of Harris County , 836 F.2d 921 ( 1988 )

View All Authorities »