Horst Masonry v. ProControls ( 2000 )


Menu:
  •                     United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    _____________
    No. 99-2186SD
    _____________
    Horst Masonry Construction, Inc.,     *
    United States of America for the use  *
    and benefit of Plaintiff; Horst       *
    Acoustical Company, Inc., USA for     *
    the use and benefit of Horst Acoustical
    * On Appeal from the United
    Co., Inc.,                            * States District Court
    * for the District of
    Appellees,                * South Dakota.
    *
    v.                               * [Not To Be Published]
    *
    ProControls Corporation; Capitol      *
    Indemnity Corporation,                *
    *
    Appellants.               *
    ___________
    Submitted: February 29, 2000
    Filed: March 10, 2000
    ___________
    Before RICHARD S. ARNOLD, BOWMAN, and BEAM, Circuit Judges.
    ___________
    PER CURIAM.
    ProControls Corporation and Capitol Indemnity Corporation appeal from the
    District Court’s1 award of attorneys’ fees to the United States “for the use of” Horst
    Masonry Construction, Inc. and Horst Acoustical Co., Inc. in this Miller Act case.2 We
    affirm.
    In July 1998, Horst Masonry and Horst Acoustical, construction subcontractors,
    sued ProControls, the general contractor, and Capitol, the surety on a payment bond,
    for unpaid labor and materials. Defendants initially denied liability and asserted a
    number of defenses, including an offset defense. In February 1999, two days prior to
    trial, defendants stipulated with Horst Masonry and Horst Acoustical to a judgment on
    the Miller Act claims for the full amount claimed. The sole issues remaining for trial
    were the claim for attorneys’ fees and the appropriate rate of prejudgment interest. At
    the conclusion of the trial, the District Court awarded Horst Masonry and Horst
    Acoustical attorneys’ fees.
    Initially, we conclude that the District Court correctly applied federal rather than
    state law in determining whether to award attorneys’ fees. See F. D. Rich Co. v.
    United States for use of Indus. Lumber Co., 
    417 U.S. 116
    , 127 (1974) (finding no
    evidence of “congressional intent to incorporate state law to govern such an important
    element of Miller Act litigation as liability for attorneys’ fees”); see also United States
    for use of Olson v. W.H. Cates Constr. Co., 
    972 F.2d 987
    , 990 (8th Cir. 1992)
    1
    The Honorable Andrew W. Bogue, United States District Judge for the District
    of South Dakota.
    2
    Under the Miller Act, 40 U.S.C. §§ 270a-270b, a person who receives a federal
    public works contract must furnish to the United States a payment bond for the
    protection of both the United States and qualified individuals who have not been paid
    after furnishing labor and materials for the project. Persons asserting Miller Act claims
    must bring their claims in the name of the United States “for the use of” the person
    suing.
    -2-
    (“[f]ederal law, not state law, governs the scope of the remedy afforded by the Miller
    Act”).
    Only defendants’ post-litigation conduct, and not pre-litigation conduct, is
    relevant when awarding plaintiffs attorneys’ fees. See Chambers v. NASCO, Inc., 
    501 U.S. 32
    , 53 (1991) (court’s inherent power to award attorneys’ fees against litigant
    guilty of bad faith “depends not on which party wins the lawsuit, but on how the parties
    conduct themselves during the litigation” (emphasis added)); Lamb Eng’g & Constr.
    Co. v. Nebraska Pub. Power Dist., 
    103 F.3d 1422
    , 1437 (8th Cir. 1997) (“the district
    court’s inherent power to award attorneys’ fees as a sanction for bad faith conduct does
    not extend to pre-litigation conduct”).
    Because we conclude the District Court did not abuse its discretion in
    determining that defendants acted in bad faith in their litigation conduct, we affirm the
    Court’s award of attorneys’ fees. See 
    Lamb, 103 F.3d at 1434
    (standard of review).
    First, the undisputed evidence indicated ProControls knew the offset defense was
    without merit and Capitol did not investigate why ProControls had not paid Horst
    Masonry or Horst Acoustical on the subcontracts, and thus, did not know whether an
    offset defense was appropriate. Second, notwithstanding the early knowledge that
    Horst Masonry and Horst Acoustical had not been paid all they were due, defendants
    failed to acknowledge this until their settlement two days before trial. The District
    Court thus could conclude that asserting the offset defense and delaying settlement rose
    to the level of “knowing and unreasonable conduct” so as to warrant an award of
    attorneys’ fees. See 
    Chambers, 501 U.S. at 46
    (delaying or disrupting litigation
    constitutes bad faith); United States for use of Yonker Constr. Co. v. Western
    Contracting Corp., 
    935 F.2d 936
    , 942 (8th Cir. 1991) (“knowing and unreasonable
    conduct” constitutes “bad faith” for purposes of justifying award of attorneys’ fees);
    10 James Wm. Moore et al., Moore’s Federal Practice § 54.171[2][c][iii] (3d ed. 1997)
    (“the requisite bad faith may be inferred from the absolute lack of merit in the litigant’s
    actions”).
    -3-
    Accordingly, we affirm.
    A true copy.
    Attest:
    CLERK, U.S. COURT OF APPEALS, EIGHTH CIRCUIT.
    -4-