Louisiana State v. U.S. Army Corps of Engineers, e , 834 F.3d 574 ( 2016 )


Menu:
  •      Case: 15-30962   Document: 00513648548   Page: 1   Date Filed: 08/23/2016
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT   United States Court of Appeals
    Fifth Circuit
    FILED
    No. 15-30962                     August 23, 2016
    Lyle W. Cayce
    Clerk
    LOUISIANA STATE, through the Coastal Protection and Restoration
    Authority Board and the Coastal Protection and Restoration Authority,
    Plaintiff - Appellee
    v.
    UNITED STATES ARMY CORPS OF ENGINEERS; RICHARD L. HANSEN,
    Colonel, in his official capacity as District Commander for the New Orleans
    District of the United States Army Corps of Engineers; MICHAEL C. WEHR,
    Major, in his official capacity as Commander for the Mississippi Valley
    Division of the United States Army Corps of Engineers; THOMAS P.
    BOSTICK, Lieutentant General, in his official capacity as Chief of Engineers
    and Commanding General of the United States Army Corps of Engineers;
    STEVEN L. STOCKTON, in his official capacity as Director of Civil Works of
    the United States Army Corps of Engineers; JO-ELLEN DARCY, in her official
    capacity as Assistant Secretary of the Army (Civil Works),
    Defendants - Appellants
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    Before DAVIS, JONES, and GRAVES, Circuit Judges.
    EDITH H. JONES, Circuit Judge:
    Following Hurricane Katrina, in which the breach of the Mississippi
    River-Gulf Outlet (“MR-GO”) channel caused massive flooding, Congress
    directed the U.S. Army Corps of Engineers (“Corps”) to close the MR-GO as a
    federal navigation project and restore the surrounding ecosystem.                   To
    Case: 15-30962     Document: 00513648548     Page: 2   Date Filed: 08/23/2016
    No. 15-30962
    implement Congress’s 2007 mandate that the deauthorization be “cost
    effective” and in accordance with a 2006 appropriation bill, the Corps sought a
    cost-sharing arrangement with the State of Louisiana. Louisiana objected to
    any cost-sharing arrangement and sued the Corps under the Administrative
    Procedure Act (“APA”), contending that the Corps’ decision, expressed in two
    Corps reports to Congress, was arbitrary and capricious and an abuse of
    discretion because the relevant statutes require the federal government to bear
    100 percent of the costs.
    The district court agreed with Louisiana. The court rejected a statute of
    limitations challenge to the suit and concluded that the relevant statutes
    unambiguously require the Corps to bear all of the costs of deauthorizing the
    MR-GO. We bifurcate the limitations issue and find Louisiana’s APA challenge
    to the closure portion of the deauthorization project timely filed, but we dismiss
    the challenge to the Corps’ decision concerning the ecosystem restoration
    project because the agency has not taken final action under the APA. On the
    merits, we reverse the district court’s judgment that overturned the required
    cost-sharing between Louisiana and the Corps, which constitutes a reasonable
    interpretation of ambiguous statutes.
    BACKGROUND
    The MR-GO is a 76-mile deep-draft navigation channel that was
    constructed by the Corps at the direction of Congress and opened in 1968. See
    In re Katrina Canal Breaches Litig., 
    696 F.3d 436
    , 441 (5th Cir. 2012). The
    MR-GO cut through virgin Louisiana coastal wetlands to provide a shorter
    commercial route between the Gulf of Mexico and the Port of New Orleans. 
    Id. at 441–42.
    The project designers opted not to armor the banks of the MR-GO
    with foreshore protection and thus exposed the canal to erosion from the wake
    of passing ships. Over the years, the channel expanded to well over three times
    its original width. 
    Id. at 442,
    443 n.1. Local groups have contended that
    2
    Case: 15-30962    Document: 00513648548     Page: 3   Date Filed: 08/23/2016
    No. 15-30962
    erosion and the mixing of saltwater and freshwater severely damaged the
    channel’s ecosystem. In the aftermath of Hurricane Katrina, some blamed the
    Corps’ design for exacerbating the Hurricane’s devastation.
    Congressional Response Post-Hurricane Katrina: Deauthorization of MR-GO
    In 2007, Congress passed the Water Resources Development Act (“2007
    WRDA”), part of which directed the Corps to close the MR-GO to navigation
    and restore the ecosystem. This goal was to be accomplished in two steps.
    First, Congress directed the Assistant Secretary of the Army (Civil Works) to
    submit a report to Congress detailing how the Corps would, inter alia,
    “physically modify” the MR-GO and restore the “natural features of the
    ecosystem.” Pub. L. No. 110-114, § 7013(a)(3)(B)(i)–(ii), 121 Stat. 1041, 1281
    (2007). Upon submission of this report, the MR-GO would be “deauthorized”
    as a federal project. 
    Id. § 7013(a)(1).
    Second, the 2007 WRDA instructed the
    Assistant Secretary to “carry out a plan to close the Mississippi River-Gulf
    Outlet and restore and protect the ecosystem substantially in accordance with
    [the report submitted to Congress] . . . if the Secretary determines that the
    project is cost-effective, environmentally acceptable, and technically feasible.”
    
    Id. § 7013(a)(4).
    Additionally, and as relevant to this case, in order to finance
    the deauthorization of the MR-GO, Congress instructed the Corps to undertake
    closure and restoration “in a manner that is consistent with the cost-sharing
    requirements specified in the Emergency Supplemental Appropriations Act for
    Defense, the Global War on Terror, and Hurricane Recovery, 2006 (Public Law
    109-234).” 
    Id. § 7012(b).
          The bill referenced by the 2007 WRDA’s cost sharing provision is the
    fourth of four supplemental appropriations bills passed by Congress in the
    wake of Hurricane Katrina. See Emergency Supplemental Appropriations Act
    for Defense, the Global War on Terror, and Hurricane Recovery, 2006, Pub. L.
    109-234, tit. II, ch. 3, 120 Stat. 418, 453–55 (2006) (“Fourth Supplemental”).
    3
    Case: 15-30962       Document: 00513648548         Page: 4    Date Filed: 08/23/2016
    No. 15-30962
    The last two of the four bills appropriated funds to the Corps to complete a
    variety of relief and restoration tasks in New Orleans and throughout the
    country.
    Two provisions in the Fourth Supplemental relate to the MR-GO. 1
    First, under the heading “Investigations,” the Fourth Supplemental
    appropriated $3.3 million to the Corps to “develop a comprehensive plan, at
    full Federal expense, to deauthorize deep draft navigation” on the MR-GO. 120
    Stat. at 453. Second, through the Fourth Supplemental, Congress amended a
    provision in the Third Supplemental that appropriated $75 million of a
    $327,517,000 appropriation “for authorized operation and maintenance
    activities along the [MR-GO].”               Department of Defense, Emergency
    Supplemental Appropriations to Address Hurricanes in the Gulf of Mexico, and
    Pandemic Influenza Act, 2006, div. B, tit. I, ch. 3, 119 Stat. 2690, 2762 (2005)
    (“Third Supplemental”). With the amendment, Congress added a provision to
    the Third Supplemental, earmarking “$75,000,000 of the funds provided
    herein . . . for the repair, construction or provision of measures or structures
    necessary to protect, restore, or increase wetlands, to prevent saltwater
    intrusion or storm surge.” Fourth Supplemental § 2304, 120 Stat. at 456.
    The Corps’ Implementation of the 2007 WRDA
    In January 2008, the Army’s Chief of Engineers (“Chief”) reported to the
    Assistant Secretary his recommendations concerning the closure of the MR-
    GO. The Chief recommended that the channel be closed to navigation by a
    1 Other provisions of the Fourth Supplemental appropriated funds to the Corps to
    undertake various reparation and restoration projects in the New Orleans area, such as
    raising levee heights, repairing drainage canals throughout the City, and armoring the City’s
    storm damage reduction system. See Fourth Supplemental, 120 Stat. at 454–55. The parties
    substantially agree about the two provisions of the Fourth Supplemental that appropriated
    funds for the MR-GO.
    4
    Case: 15-30962       Document: 00513648548         Page: 5     Date Filed: 08/23/2016
    No. 15-30962
    rock wall spanning its width. The Chief recommended that the rock structure
    be completed at full federal expense, but also recommended that a non-federal
    sponsor bear the cost for the lands, easements, rights-of-way, relocations and
    disposal areas (“LEERDs”), as well as for operation, maintenance, repair,
    rehabilitation, and replacement (“OMRR&R”) of the structure. 2 Louisiana’s
    Coastal Protection and Restoration Authority (“CPRA”) was identified as the
    non-federal sponsor, and the Chief noted that his recommendation was “subject
    to the non-Federal sponsor executing an agreement with the Department of
    the Army prior to the Federal Government initiating construction of the
    closure structure.” Importantly, this report only dealt with closing the MR-
    GO, as the Chief indicated that the Corps’ proposal for ecosystem restoration
    would be addressed in a supplemental report to be submitted at a later date.
    On June 5, 2008, the Assistant Secretary transmitted the Chief’s report
    to Congress and signed a record of decision, determining that the Chief’s plan
    was “cost-effective, environmentally acceptable, and technically feasible.” On
    October 31, 2008, the Corps and the State of Louisiana (acting through the
    CPRA) entered into a Memorandum of Agreement (“MOA”) whereby both
    parties agreed to the cost allocation set out in the Chief’s report. Despite the
    CPRA’s explicit agreement to pay for LEERDs and OMRR&R by the terms of
    the MOA, it insisted on inserting a provision that the CPRA “maintains that
    the cost sharing and other non-Federal obligations that are required under the
    2 This cost sharing allocation was determined by reference to the cost sharing
    provisions of the 1986 Water Resources Development Act (“1986 WRDA”), which sets forth
    cost sharing formulas that apply to projects when cost sharing allocations are not established
    by another statute. See 33 U.S.C. § 2218. The Corps relied on 33 U.S.C. § 2213(i), which
    provides that “non-Federal interests . . . shall provide all lands, easements, rights-of-way,
    and dredged material disposal areas required for the project and perform all necessary
    relocations,” and 33 U.S.C. § 2213(j)(1), which provides that “[a]ny project to which this
    section applies . . . shall be initiated only after non-Federal interests have entered into
    binding agreements with the Secretary to pay 100 percent of the operation, maintenance, and
    replacement and rehabilitation costs of the project.”
    5
    Case: 15-30962      Document: 00513648548        Page: 6     Date Filed: 08/23/2016
    No. 15-30962
    MOA are inconsistent with the intentions of Congress as it relates to the
    closure and ecosystem restoration plan.”
    The Corps addressed the second half of the MR-GO project—restoring
    the ecosystem—in September 2012 when the Chief submitted a supplemental
    report to the Assistant Secretary. The Supplemental Report recommended
    that the federal government would pay for 65 percent of the restoration project
    and a non-federal sponsor would pay for the other 35 percent. 3 Adhering to its
    belief that the 2007 WRDA and the Fourth Supplemental required the federal
    government to bear 100 percent of the far more costly restoration project (in
    addition to the full cost of the closure project), the CPRA refused to become the
    non-federal sponsor. Consequently, when the Assistant Secretary transmitted
    the Supplemental Report to Congress on September 23, 2013, her transmission
    letter declared only $1.3 billion of the $2.9 billion restoration plan to be “cost-
    effective, environmentally acceptable and technically feasible.” The Assistant
    Secretary “defer[red] . . . a determination” on the remaining $1.6 billion. Even
    with respect to the portion of the plan that the Assistant Secretary determined
    to be cost-effective, however, she acknowledged that a non-federal sponsor had
    yet to be identified and that the Office of Management & Budget “noted that
    any construction work would require a cost sharing non-federal sponsor.”
    Consequently, the Assistant Secretary’s record of decision approved a “portion”
    of the plan as cost-effective, environmentally acceptable, and technically
    feasible, “subject to identification of a cost-sharing” partner.
    3   The Corps’ cost sharing allocation was based upon the cost sharing formula
    established by the 1986 WRDA, see supra note 2, the relevant portion of which provides that
    “[t]he non-Federal share of the cost assigned to “environmental protection and restoration”
    projects “shall be” 35 percent. See 33 U.S.C. § 2213(c)(7).
    6
    Case: 15-30962      Document: 00513648548        Page: 7     Date Filed: 08/23/2016
    No. 15-30962
    The Corps has completed building the rock wall to close the MR-GO to
    navigation, but the ecosystem restoration portion of the project has not moved
    forward.
    Procedural History
    On October 28, 2014, Louisiana (acting through the CPRA) sued the
    Corps under Section 706 of the APA. The district court granted Louisiana’s
    motion for summary judgment. The court first held that Louisiana’s lawsuit
    was not barred by the six-year statute of limitations, 28 U.S.C. § 2401, which
    applies to civil actions against the United States. The court rejected the Corps’
    argument that the State’s claim accrued when the Corps submitted to
    Congress its June 5, 2008 Deauthorization Report. Instead, the court held that
    the MOA entered into by Louisiana and the Corps on October 31, 2008 was the
    relevant final agency action because the MOA determined Louisiana’s “rights
    and obligations” and was the agency action from which “legal consequences
    could flow.” 4
    The court then held that the Corps’ interpretation of the 2007 WRDA
    and the Fourth Supplemental was not entitled to Chevron deference. The court
    held that the Corps’ interpretation of the relevant statutes failed Step 1 of
    Chevron because the “WRDA 2007, read in conjunction with the 4th
    Supplemental, unambiguously requires the Corps to complete the MRGO
    closure and ecosystem restoration project at full federal expense.” Though the
    court acknowledged that the Fourth Supplemental is “silent as to how such
    project [MR-GO deauthorization] would ultimately be funded,” the court drew
    4  Louisiana filed this lawsuit on October 28, 2014. The lawsuit would be time-barred
    by 28 U.S.C. § 2401 if the final agency action were determined to be the June 5, 2008
    transmission of the Deauthorization Report to Congress, but the lawsuit would be timely if
    the final agency action resulted from the October 31, 2008 MOA.
    7
    Case: 15-30962    Document: 00513648548     Page: 8   Date Filed: 08/23/2016
    No. 15-30962
    a parallel between the use of the heading “Construction” in both the 2007
    WRDA and the Fourth Supplemental.
    Under the “Construction” heading in the Fourth Supplemental, Congress
    appropriated $20.2 million to reduce the risk of storm damage to the greater
    New Orleans metropolitan area—at full Federal expense—by restoring
    surrounding wetlands affected by “navigation, oil and gas, and other channels.”
    Because the restoration of wetlands affected by “navigation . . . and other
    channels” was to be carried out at full Federal expense, the district court
    reasoned, Congress’s direction to the Corps to close the MR-GO and restore its
    wetlands in the 2007 WRDA must also be done at full Federal expense because
    both statutes utilize the “Construction” heading. Given this interpretation
    that the statutes unambiguously require the Corps to carry out the MR-GO
    deauthorization at full Federal expense, the district court held that the Corps’
    contrary interpretation permitting cost sharing was arbitrary and capricious
    and an abuse of discretion. The Corps has appealed.
    STANDARD OF REVIEW
    “We review a grant of summary judgment de novo, applying the same
    standard as the district court.” Buffalo Marine Servs. Inc. v. United States,
    
    663 F.3d 750
    , 753 (5th Cir. 2011). As this case arises under the Administrative
    Procedure Act (“APA”), this court may set aside agency action “only if it is
    arbitrary, capricious, an abuse of discretion, not in accordance with law, or
    unsupported by substantial evidence on the record taken as a whole.” 
    Id. (citation omitted);
    5 U.S.C. § 706(2). However, “we owe substantial deference
    to an agency’s construction of a statute that it administers.” Alwan v. Ashcroft,
    
    388 F.3d 507
    , 510 (5th Cir. 2004) (citing Chevron U.S.A, Inc. v. Nat. Res. Def.
    Council, 
    467 U.S. 837
    , 842, 
    104 S. Ct. 2778
    , 2781–82 (1984)). “Under Chevron
    we presume that when an agency-administered statute is ambiguous with
    respect to what it prescribes, Congress has empowered the agency to resolve
    8
    Case: 15-30962   Document: 00513648548      Page: 9   Date Filed: 08/23/2016
    No. 15-30962
    the ambiguity. The question for a reviewing court is whether in doing so the
    agency has acted reasonably and thus has ‘stayed within the bounds of the
    law.’” Utility Air Regulatory Grp. v. EPA, 
    134 S. Ct. 2427
    , 2439 (2014) (citation
    omitted).
    DISCUSSION
    We consider in turn the Corps’ arguments that Louisiana’s suit is barred
    by the six-year statute of limitations and, alternatively, that its cost-sharing
    decisions are permissible.
    I.    Statute of Limitations & Final Agency Action
    28 U.S.C. § 2401(a) states: “every civil action commenced against the
    United States shall be barred unless the complaint is filed within six years
    after the right of action first accrues.” Because neither the 2007 WRDA nor
    the Fourth Supplemental provides for judicial review of the Corps’ decisions,
    Louisiana’s lawsuit was brought under the APA, which subjects to judicial
    review “final agency action for which there is no other adequate remedy in a
    court.” 5 U.S.C. § 704. Since Louisiana’s “right of action first accrues” under
    the APA when the agency takes “final agency action,” the State must have
    sought review of final agency action that occurred within the six years before
    it filed suit on October 28, 2014. Resolution of the timeliness issue thus turns
    on whether the agency action Louisiana is challenging was final.
    A.    Governing Principles
    Agency action is “final” if two conditions are satisfied: “First, the action
    must mark the consummation of the agency’s decisionmaking process—it must
    not be of a merely tentative or interlocutory nature. And second, the action
    must be one by which rights or obligations have been determined, or from
    which legal consequences will flow.” Bennett v. Spear, 
    520 U.S. 154
    , 177–78,
    
    117 S. Ct. 1154
    , 1168 (1997) (internal quotation marks and citations omitted).
    “The APA’s judicial review provision also requires that the person seeking APA
    9
    Case: 15-30962       Document: 00513648548         Page: 10     Date Filed: 08/23/2016
    No. 15-30962
    review of final agency action have ‘no other adequate remedy in a court,’
    5 U.S.C. § 704.” Sackett v. EPA, 
    132 S. Ct. 1367
    , 1372 (2012).
    Agency     action    may     mark     the   consummation        of   the    agency’s
    decisionmaking process if the agency action “is not subject to further agency
    review,” 
    id. at 1372,
    which occurs when the agency has “asserted its final
    position on the factual circumstances underpinning” the agency action,
    Alaska Dep’t of Envtl. Conservation v. EPA, 
    540 U.S. 461
    , 483, 
    124 S. Ct. 983
    ,
    999 (2004) (internal citation and quotation marks omitted). Additionally, as
    we recently noted, “legal consequences are created whenever the challenged
    agency action has the effect of committing the agency itself to a view of the law
    that, in turn, forces the plaintiff either to alter its conduct, or expose itself to
    potential liability.” Texas v. EEOC, 
    2016 WL 3524242
    , at *8 (5th Cir. June 27,
    2016); see also U.S. Army Corps of Eng’rs v. Hawkes Co., Inc., 
    136 S. Ct. 1807
    ,
    1814 (2016) (noting that “legal consequences” were created by the Corps’
    issuance of a “negative jurisdictional determination”—a document indicating
    that the regulated party’s land does not contain “waters of the United States”—
    because such a determination “narrows the field of potential plaintiffs and
    limits the potential liability” of the regulated party).
    B.     The Closure Project
    1. The Assistant Secretary’s Record of Decision Transmitting the 2008
    Deauthorization Report
    The Corps argues that the 2008 Deauthorization Report constitutes final
    agency action for the closure portion 5 of the deauthorization project, and
    5 Louisiana contends that the deauthorization of the MR-GO is one indivisible project
    made up of both closure and ecosystem restoration, both of which had to be addressed by the
    Corps before there could be final agency action. The Corps, in contrast, conceives of the
    deauthorization project as proceeding in two discrete steps—first closure, then ecosystem
    restoration. The Corps argues that it has discretion to choose to tackle a large project such
    10
    Case: 15-30962       Document: 00513648548          Page: 11     Date Filed: 08/23/2016
    No. 15-30962
    Louisiana’s APA challenge to this portion of the project was untimely because
    the Assistant Secretary transmitted the Report to Congress more than six
    years before Louisiana sued. The Corps contends that the transmission of the
    Deauthorization Report by the Assistant Secretary, the highest ranking officer
    of the Army and the person who oversees the Corps, consummated the agency
    decisionmaking process.          The Corps also argues that transmittal of the
    Deauthorization Report had legal consequences: deauthorizing the MR-GO,
    obliging the Corps to begin effectuating the plan outlined in the Report, and
    requiring the State to agree to share the costs of closure and maintaining the
    rock wall.
    Although this issue is not free from doubt, we disagree with the Corps’
    position.    It is true that the Assistant Secretary’s transmission of the 2008
    Report to Congress bears some indicia of finality. The Report is titled “Final
    Deauthorization Report,” the Assistant Secretary certified the closure plan as
    “cost-effective, environmentally acceptable, and technically feasible,” and the
    Corps’ statutory duty to carry out the closure in substantial accordance with
    the Report was triggered by its transmission. Crucially, however, with regard
    to the key question of cost-sharing, the 2008 Deauthorization Report is
    decidedly less definite. Indeed, the Report—which the Assistant Secretary’s
    as this one in multiple steps and that its decision to proceed in multiple steps does not mean
    that earlier steps are ipso facto non-final.
    We agree with the Corps that it was permissible for the agency to address the
    deauthorization project in two steps, dealing with the closure first and the ecosystem
    restoration second. “[O]rdinarily, agencies have wide latitude to attack a regulatory problem
    in phases and [] a phased attack often has substantial benefits.” Grand Canyon Air Tour
    Coalition v. Fed. Aviation Admin., 
    154 F.3d 455
    , 471 (D.C. Cir. 1998); see also Mass. v. EPA,
    
    549 U.S. 497
    , 524, 
    127 S. Ct. 1438
    , 1457 (2007) (“Agencies, like legislatures, do not generally
    resolve massive problems in one fell regulatory swoop . . . . They instead whittle away at
    them over time, refining their preferred approach as circumstances change and as they
    develop a more nuanced understanding of how best to proceed.”); Cobell v. Norton,
    
    240 F.3d 1081
    , 1095 (D.C. Cir. 2001) (noting that “a single step or measure [of an on-going
    program] is reviewable” if it is a final agency action).
    11
    Case: 15-30962      Document: 00513648548       Page: 12   Date Filed: 08/23/2016
    No. 15-30962
    record of decision incorporated by reference—states that the recommendation
    as to MR-GO’s closure is “made with the provision that, prior to
    implementation, the non-Federal sponsor [CPRA] agrees with responsibilities
    and cost sharing requirements.”        Further, in his January 2008 letter
    transmitting the report to the Assistant Secretary, the Chief noted that his
    recommendation “is subject to the non-Federal sponsor executing an
    agreement with the Department of the Army prior to the Federal Government
    initiating construction of the closure structure.”
    Therefore, the Assistant Secretary’s record of decision transmitting the
    Deauthorization Report appears to be “interlocutory,” in that it anticipates the
    necessity of further agency action before the closure project can be
    implemented. 
    Bennett, 520 U.S. at 178
    , 117 S. Ct. at 1168–69. Because only
    the MOA could bind Louisiana to contribute financially to the deauthorization
    project, the execution of the MOA was not simply a ministerial act
    implementing final agency action, as the Corps contends.               Instead, the
    certification of the Assistant Secretary that the project was cost-effective
    hinged directly on the federal government’s obtaining a non-federal sponsor to
    share the costs. Cf. Texas v. EEOC, 
    2016 WL 3524242
    , at *6 (“the Guidance
    suggests that its provisions are to be taken as conclusive”).
    Had the government been unable to obtain Louisiana’s assent to cost-
    sharing, it is likely that the closure project proposed in the 2008 Report could
    not have gone forward. That this would have been much more than “a mere
    possibility that the agency might reconsider in light of ‘informal discussion’
    and invited contentions of inaccuracy,” 
    Sackett, 132 S. Ct. at 1372
    , is evidenced
    by the fact that Louisiana’s refusal to enter into an MOA sharing ecosystem
    restoration    costs    has     stymied     that      portion     of    the    MR-
    GO project. With the key provision of how to finance the closure yet to be
    finalized, the Assistant Secretary’s transmission of the 2008 Deauthorization
    12
    Case: 15-30962     Document: 00513648548      Page: 13   Date Filed: 08/23/2016
    No. 15-30962
    Report to Congress did not mark the consummation of the agency’s
    decisionmaking process.
    The 2008 Deauthorization Report also failed to determine “rights and
    obligations” of the parties or give rise to “direct and appreciable legal
    consequences.” 
    Bennett, 520 U.S. at 178
    , 117 S. Ct. at 1168–69. Unlike an
    administrative rulemaking or adjudication that purports to bind parties and
    alter their conduct, the Secretary’s transmission of the Deauthorization Report
    to Congress could not “force [Louisiana] to alter its conduct, or expose itself to
    potential liability.” Texas v. EEOC, 
    2016 WL 3524242
    , at *8. Nothing about
    the Assistant Secretary’s transmission of the 2008 Deauthorization Report to
    Congress regulated Louisiana or could have bound the State to pay for the
    LEERDs and OMRR&R of the rock structure used to close the MR-GO.
    Viewed from the State’s perspective, although the Corps’ insistence on
    cost sharing may have put pressure on Louisiana to comply or else risk
    protracted negotiations with the Corps and a lengthy timetable for completing
    the closure of the MR-GO, any such consequences are practical, as opposed to
    legal, ones. See Reliable Automatic Sprinkler Co., Inc. v. Consumer Prod.
    Safety Comm’n, 
    324 F.3d 726
    , 732 (D.C. Cir. 2003) (distinguishing between
    practical harms and legal harms for purposes of the final agency action
    requirement under the APA); Flue-Cured Tobacco Cooperative Stabilization
    Corp. v. EPA, 
    313 F.3d 852
    , 859 (4th Cir. 2002) (noting that an EPA Report
    submitted to Congress “carrie[d] no legally binding authority” and the “coercive
    pressures” produced by the Report were not “direct and appreciable legal
    consequences”).
    The Assistant Secretary’s transmission of the 2008 Deauthorization
    Report thus failed to create any legal consequences for Louisiana and differs
    significantly from the legal consequences that typify final agency action
    reviewable under the APA. Judicially reviewable agency actions normally
    13
    Case: 15-30962    Document: 00513648548      Page: 14    Date Filed: 08/23/2016
    No. 15-30962
    affect a regulated party’s possible legal liability; these consequences tend to
    expose parties to civil or criminal liability for non-compliance with the agency’s
    view of the law or offer a shelter from liability if the regulated party complies.
    Cf. Hawkes 
    Co., 136 S. Ct. at 1814
    (noting that a negative JD from the Corps
    “both narrows the field of potential plaintiffs and limits the potential liability”
    of the regulated party); 
    Bennett, 520 U.S. at 170
    , 
    178, 117 S. Ct. at 1165
    , 1168–
    69 (noting that the Fish and Wildlife Service’s “Biological Opinion,” which
    stated that the Bureau of Reclamation’s operation of a federal reclamation
    scheme threatened two endangered species of fish, had “direct and appreciable
    legal consequences” because disregarding the Biological Opinion’s conclusions
    threatened the future prospect of substantial civil and criminal penalties);
    Frozen Food Express v. United States, 
    351 U.S. 40
    , 44, 
    76 S. Ct. 569
    , 571 (1956)
    (order of Interstate Commerce Commission was final agency action because it
    “warns every carrier, who does not have authority from the Commission to
    transport [specified] commodities, that it does so at the risk of incurring
    criminal penalties.”); see also Texas v. EEOC, 
    2016 WL 3524242
    , at *8 (EEOC
    Guidance document provides regulated entities a “safe harbor from DOJ
    referral, and thus ultimately liability, only if employers alter their hiring
    policies to comply with the Guidance’s directives”).
    2. The October 31, 2008 Memorandum of Agreement
    The MOA, in contrast, is the relevant final agency action with respect to
    cost allocation of the closure project. First, the MOA is the consummation of
    the Corps’ decision-making process: it is not tentative or interlocutory, as it is
    a binding agreement between the Corps and Louisiana that clearly sets out the
    cost allocation for the closure project. The MOA therefore fulfills the condition
    that   the   Assistant   Secretary’s   recommendation       of   cost-effectiveness
    contemplated:    agreement of the non-federal sponsor to the cost-sharing
    14
    Case: 15-30962      Document: 00513648548         Page: 15    Date Filed: 08/23/2016
    No. 15-30962
    allocation set forth in the Deauthorization Report. The agreement marks the
    consummation of the agency’s decision-making process.
    Second, the MOA determines the parties’ rights and obligations and has
    legal consequences. Importantly, unlike the Assistant Secretary’s record of
    decision transmitting the Deauthorization Report, legal consequences ensue
    from the MOA’s contractual nature; had Louisiana broken the terms of this
    agreement, the Corps could have sued the State to enforce its terms.
    Because the October 31, 2008 MOA, not the Assistant Secretary’s
    transmission of the 2008 Deauthorization Report, constituted the final agency
    action, Louisiana’s suit filed on October 28, 2014 was within the statute of
    limitations. 6
    C.     Ecosystem Restoration
    The Corps does not contest the timeliness of Louisiana’s challenge to the
    cost allocation provision of the ecosystem restoration project contained in the
    2012 Supplemental Report, and timeliness does not raise a jurisdictional issue
    in this court.    Clymore v. United States, 
    217 F.3d 370
    , 374 (5th Cir. 2000).
    Final agency action, however, is a jurisdictional prerequisite of judicial review.
    Am. Airlines, Inc. v. Herman, 
    176 F.3d 283
    , 287 (5th Cir. 1999). For many of
    the same reasons that the Assistant Secretary’s transmission of the 2008
    Deauthorization Report was not final agency action, we conclude that the
    transmission of the 2012 Supplemental Report likewise fails the test of finality,
    and judicial review is premature.
    First, even more so than the 2008 Report, the transmission of the 2012
    Supplemental Report does not mark the consummation of the Corps’ decision-
    making regarding the financing of the ecosystem restoration project. This
    Louisiana also has “no other adequate remedy in a court,” 5 U.S.C. § 704, as neither
    6
    the 2007 WRDA nor the Fourth Supplemental provides for judicial review of the Corps’
    implementation of the MR-GO deauthorization. 
    Sackett, 132 S. Ct. at 1372
    .
    15
    Case: 15-30962      Document: 00513648548      Page: 16   Date Filed: 08/23/2016
    No. 15-30962
    action is both tentative and interlocutory, 
    Bennett, 520 U.S. at 178
    , 117 S. Ct.
    at 1168, as it necessarily contemplates future agency action. The Assistant
    Secretary approved only part of the ecosystem restoration plan—$1.3 billion of
    the $2.9 billion projected cost—as cost effective; the Assistant Secretary
    “defer[red] . . . a determination” on the remaining $1.6 billion. As to the
    approved portion, the Assistant Secretary cautioned that implementation
    could not proceed under the plan submitted to Congress until a non-federal
    sponsor agrees to bear 35 percent of the costs. Without a non-federal sponsor,
    to arrive at a cost effective plan the Corps may need to alter the current cost
    allocation. That the agency may need to re-work its cost allocation does not
    appear to be a “mere possibility,” 
    Sackett, 132 S. Ct. at 1372
    , because Louisiana
    has refused to be the non-federal sponsor under the Corps’ 65-35 allocation,
    and the ecosystem restoration plan has yet to be implemented.
    Further, the Secretary’s transmission of the 2012 Supplemental Report
    does not “determine rights or obligations” or create “legal consequences.” Like
    the 2008 Deauthorization Report, the 2012 Report does not regulate Louisiana
    and cannot bind the State to pay for 35 percent of the ecosystem restoration
    project. Nor does this report inflict legal consequences on Louisiana for the
    State’s non-acquiescence, such as exposure to civil or criminal liability for
    failure to comply. Cf. Hawkes 
    Co., 136 S. Ct. at 1814
    ; 
    Bennett, 520 U.S. at 170
    ,
    
    178, 117 S. Ct. at 1168
    –69; Texas v. EEOC, 
    2016 WL 3524242
    , at *8.
    Because    the   Assistant    Secretary’s    transmission    of   the   2012
    Supplemental Report was not a final agency action, we lack jurisdiction to
    consider Louisiana’s APA challenge to the cost-share allocation set out in that
    Report. We must vacate the district court’s judgment to the extent it opined
    on the cost-sharing proposal set forth in the 2012 Supplemental Report.
    16
    Case: 15-30962   Document: 00513648548       Page: 17    Date Filed: 08/23/2016
    No. 15-30962
    II.     Chevron Deference
    The second issue on appeal concerns the district court’s application of the
    Chevron doctrine to the Corps’ interpretation of two statutes, the 2007 WRDA
    and the Fourth Supplemental, to support cost-sharing mandated in its 2008
    Deauthorization Report.       Under Chevron, “we must first decide whether
    ‘Congress has directly spoken to the precise question at issue,’ and if it has, we
    apply Congress’s answer to the question.” Contender Farms LLP v. United
    States Dep’t of Agric., 
    779 F.3d 258
    , 268 (5th Cir. 2015) (citing 
    Chevron, 467 U.S. at 842
    –43, 104 S. Ct. at 2781–82). The court evaluates a statute using
    the “traditional tools of statutory construction:” text, structure, and legislative
    history. 
    Id. Second, “if
    the statute is silent or ambiguous with respect to the
    specific issue, the question for the court is whether the agency’s answer is
    based on a permissible construction of the statute.” 
    Id. Louisiana argues
    that the Corps’ interpretation of the 2007 WRDA and
    Fourth Supplemental fails both steps of Chevron analysis.
    A.     Chevron Step 1
    The 2007 WRDA directs the Corps to carry out deauthorization of the
    MR-GO in a manner consistent with the cost-sharing requirements in the
    Fourth Supplemental; consequently we look to that law to determine whether
    Congress unambiguously spoke to the question who must pay for the closure
    project. See 2007 WRDA, §7012(b). Louisiana points to two provisions of the
    Fourth       Supplemental   that,   the   State    contends,    reflect   Congress’s
    unambiguously expressed intention for the Corps to bear 100 percent of the
    costs to close MR-GO: (1) the Fourth Supplemental’s amendment to the Third
    Supplemental, which provides $75 million for “repair, construction or provision
    of measures or structures necessary to protect, restore, or increase wetlands,
    to prevent saltwater intrusion or storm surge”; and (2) the Fourth
    Supplemental’s appropriation of $20.2 million for “reducing the risk of storm
    17
    Case: 15-30962    Document: 00513648548     Page: 18   Date Filed: 08/23/2016
    No. 15-30962
    damage to the greater New Orleans metropolitan area, at full federal expense,
    by restoring the surrounding wetlands.”
    We disagree with Louisiana’s proffered interpretation of these
    provisions.   As previously mentioned, two provisions of the Fourth
    Supplemental expressly relate to the MR-GO.               Under the heading
    “Investigations,” $3.3 million is appropriated to the Corps to “develop a plan,
    at full Federal expense to deauthorize deep draft navigation” on the MR-GO,
    120 Stat. at 453. While this provision states that the plan will be produced at
    full federal expense, it says nothing about who will pay for the implementation
    of the plan. The other provision, on which Louisiana focuses, amends the Third
    Supplemental. Under the “Operations and Maintenance” heading, the Third
    Supplemental provides that, out of $325,517,000 appropriated to “dredge
    navigation channels and repair other Corps projects” in the wake of Hurricane
    Katrina, $75 million of that amount “shall be used for authorized operation
    and maintenance activities along the [MR-GO].” 119 Stat. at 2762. The Fourth
    Supplemental’s amendment adds to that a provision stating that $75 million
    “of the funds provided herein shall be used for the repair, construction or
    provision of measures or structures necessary to protect, restore, or increase
    wetlands, to prevent saltwater intrusion or storm surge.” 120 Stat. at 456.
    In addition to the $75 million appropriated for operation and
    maintenance activities of the MR-GO, then, this amendment earmarks another
    $75 million for general purposes necessary to protect or restore wetlands.
    While this allocation might provide a source of federal funds for closing the
    MR-GO, it does not compel the federal government to bear the entire cost of
    constructing a structure, let alone the additional cost of LEERDs and
    OMRR&R. It is arguable, but hardly unambiguous, to infer that the Third
    Supplemental’s provision of $75 million for “authorized operation and
    maintenance activities along the” MR-GO renders the federal government
    18
    Case: 15-30962       Document: 00513648548         Page: 19     Date Filed: 08/23/2016
    No. 15-30962
    responsible for the OMRR&R of the closure structure.                    Indeed, once the
    Deauthorization Report was transmitted to Congress, the MR-GO was no
    longer an “authorized operation and maintenance activit[y]” and may have
    become ineligible for those funds. See 2007 WRDA § 7013(a)(1) (noting that,
    upon submission of the Deauthorization Report, the MR-GO “is not
    authorized”).
    We also reject Louisiana’s argument that the Fourth Supplemental’s
    appropriation of $20.2 million to the Corps unambiguously establishes that the
    closure of the MR-GO must be done at full federal expense. The $20.2 million
    “may be used to reduce the risk of storm damage to the New Orleans
    metropolitan area, at full federal expense, by restoring surrounding wetlands
    through measures to begin to reverse wetland losses in areas affected by
    navigation, oil and gas, and other channels.”                120 Stat. at 454.         This
    appropriation facilitates the Corps’ general handling of ecosystem restoration
    but it does not address a closure structure for the MR-GO, much less who will
    bear the cost for the operations and maintenance of the structure. 7
    Even if the statutory text included the construction of a MR-GO closure
    structure within the ambit of “reduc[ing] the risk of storm damage,” the
    expenditure of the $20.2 million is discretionary, as evidenced by the term
    “may be used” in the statute, and the Corps did not draw upon this particular
    appropriation to finance the closure of the MR-GO. Finally, even if, as the
    district court concluded, this appropriation could impute some responsibility
    to the Corps for constructing the closure structure because it appears under
    7 Moreover, there is reason to think that these funds are inapplicable to the MR-GO
    deauthorization, as the Conference Report indicates that the $20.2 million was to be used for
    projects unrelated to the MR-GO closure. See H.R. Conf. Rep. 109-494, at 114 (“The Corps is
    further directed to use these funds in the following manner: $10,100,000 to modify the
    Caernarvon Freshwater Diversion structure or its operations; and $10,100,000 to protect the
    shoreline along the Barataria Basin Landbridge in Jefferson Parish, Louisiana”).
    19
    Case: 15-30962       Document: 00513648548        Page: 20     Date Filed: 08/23/2016
    No. 15-30962
    the statutory heading “Construction,” it does not follow that the provision could
    also be construed to require the federal government to bear the entire cost for
    operation and maintenance of the structure in perpetuity. Such an approach
    is totally inconsistent with the 2007 WRDA’s overarching goal of deauthorizing
    the MR-GO.
    Because no provision in the Fourth Supplemental establishes how the
    closure of the MR-GO should be financed, this detail was left to be resolved by
    the Corps. At best, from the State’s standpoint, the relevant statutes are
    ambiguous with respect to who will bear the costs of the MR-GO closure. 8
    B.     Chevron Step 2
    Accepting the possibility of statutory ambiguity, Louisiana alternatively
    argues that the Corps’ cost-share allocation is not even a permissible
    interpretation of the 2007 WRDA and Fourth Supplemental.                       The State
    contends that the Corps’ decision to derive its cost-sharing allocation from the
    cost-sharing formulas laid down in the 1986 WRDA was impermissible because
    the Corps relied on the wrong provision. The Corps should have derived the
    cost-sharing allocation from 33 U.S.C. § 2212, which sets out cost-sharing
    formulas for “inland waterway transportation” projects and directs the federal
    government to bear 100 percent of the cost for LEERDs and OMRR&R of such
    projects, not 33 U.S.C. § 2213, which sets out cost-sharing formulas for flood
    control projects and projects with “other purposes,” 
    id. § 2213(c).
    8   Louisiana also contends that the history of the MR-GO project supports the
    argument that Congress instructed that the MR-GO deauthorization should be completed at
    full federal expense. Louisiana relies on Congress’s instruction in the 1950s that the MR-GO
    be constructed in accordance with a 1951 Corps Engineers Report, which stated that the
    construction of the MR-GO would not require local cooperation; and a 2007 floor statement
    by Louisiana Senator David Vitter. Neither a 1951 Corps Report nor a lone floor statement
    from the State’s own Senator, however, provides insight into the intent of the 2007 Congress
    or clarifies an otherwise ambiguous text.
    20
    Case: 15-30962      Document: 00513648548         Page: 21    Date Filed: 08/23/2016
    No. 15-30962
    “Chevron directs courts to accept an agency’s reasonable resolution of an
    ambiguity in a statute that the agency administers.”                 Michigan v. EPA,
    
    135 S. Ct. 2699
    , 2707 (2015). “Even under this deferential standard, however,
    ‘agencies must operate within the bounds of reasonable interpretation.’” 
    Id. (citing Utility
    Air Regulatory Grp. v. EPA, 
    134 S. Ct. 2427
    , 2442 (2014)). “And
    reasonable statutory interpretation must account for both the specific context
    in which language is used and the broader context of the statute as a whole.”
    Utility Air Regulatory 
    Grp., 134 S. Ct. at 2442
    (citations, ellipses, and
    quotation marks omitted). “Thus, an agency interpretation that is inconsistent
    with the design and structure of the statute as a whole does not merit
    deference.”    
    Id. (citation and
    quotation marks omitted).             “If the agency’s
    reasons and policy choices conform to minimal standards of rationality, then
    its actions are reasonable and must be upheld.” Tex. Oil & Gas Ass’n v. EPA,
    
    161 F.3d 923
    , 934 (5th Cir. 1998).
    The Corps’ interpretation of the 2007 WRDA and the Fourth
    Supplemental is well within the bounds of permissible interpretation. As we
    noted, the Fourth Supplemental appropriates funds to the Corps to deal with
    the fallout from Hurricane Katrina. To achieve its various reparation and
    restoration goals, Congress employed different methods of instructing the
    Corps how to finance certain projects. For example, Congress appropriated
    funds for some purposes to assist in repairing hurricane damage, but it did not
    specify that the projects be undertaken at full federal expense. 9               In other
    cases, Congress directed the federal funds to specific projects and instructed
    9 See, e.g., 120 Stat. at 454 (“to dredge navigation channels and repair other Corps
    projects related to the consequences of Hurricane Katrina and other hurricanes of the 2005
    season, $3,200,000 to remain available until expended”).
    21
    Case: 15-30962       Document: 00513648548          Page: 22     Date Filed: 08/23/2016
    No. 15-30962
    that the projects be undertaken at “full federal expense.” 10                Significantly,
    however, for many of those “full federal expense” projects, Congress expressly
    directed the Corps to refrain from expending funds until “nonfederal interests
    have entered into binding agreements with the Secretary requiring the non-
    Federal interests to pay 100 percent of the operation, maintenance, repair,
    replacement, and rehabilitation costs of the project.” 120 Stat. at 455.
    The Corps’ cost sharing allocation as regards OMRR&R of the closure
    structure, then, mirrors one of the funding choices set out in the Fourth
    Supplemental: while the Corps would pay to construct the closure structure,
    Louisiana would be responsible for the OMRR&R.                     By employing a cost-
    sharing method utilized in the Fourth Supplemental itself, the Corps has
    clearly sought to carry out the closure of the MR-GO “in a manner consistent
    with the cost-sharing requirements in the [Fourth Supplemental],” 2007
    WRDA § 7012(b). This is unquestionably “within the bounds of reasonable
    interpretation,” Utility Air Regulatory 
    Grp., 134 S. Ct. at 2442
    .
    It was also reasonable for the Corps to rely, in the absence of direction
    from the Fourth Supplemental, on the cost-sharing provisions set forth in the
    1986 WRDA that apply to “all projects in this Act” “unless otherwise specified”
    when arriving at its cost-sharing allocation for obtaining the LEERDs.
    33 U.S.C. § 2218. 11 Louisiana argues that the Corps should have followed the
    10 See, e.g., 120 Stat. at 454–55 (directing the Corps to use funds to “modify, at full
    federal expense, authorized projects in southeast Louisiana . . . $530,000,000 shall be used
    to modify the 17th Street, Orleans Avenue, and London Avenue drainage canals and install
    pumps and closure structures at or near the lakefront; $250,000,000 shall be used for storm-
    proofing interior pump stations . . . $350,000,000 shall be used to improve protection at the
    Inner Harbor Navigation Canal”).
    11See generally NICOLE T. CARTER & CHARLES V. STERN, CONG. RESEARCH SERV.,
    R41243, ARMY CORPS OF ENGINEERS: WATER RESOURCE AUTHORIZATIONS, APPROPRIATIONS,
    AND ACTIVITIES 17–18 (2016) (detailing the “Evolution of [the] Corps[’s] Civil Works Mission”
    and noting that the 1986 WRDA “fundamentally transformed the rules for Corps water
    22
    Case: 15-30962       Document: 00513648548        Page: 23     Date Filed: 08/23/2016
    No. 15-30962
    provision of the 1986 WRDA that sets forth the cost sharing formula for “inland
    waterway transportation” projects. This assertion, however, does not render
    impermissible the Corps’ reliance on the catchall provision for projects with
    purposes other than flood control and inland waterway transportation.                   See
    33 U.S.C. § 2213(c).
    While section 2212 sets forth the cost share formulas for inland
    waterway transportation projects, section 2213 announces cost share formulas
    for flood control projects, nonstructural flood control projects, and projects with
    other purposes. The Corps could have reasonably concluded that, given section
    2212’s instruction that the federal government is to bear 100 percent of cost for
    operations and maintenance of inland waterway transportation projects, the
    cost-sharing formulas in this section are more appropriate for federal projects
    designed to facilitate “navigation on the inland waterways,” 33 U.S.C.
    § 2212(b), instead of projects designed to close such waterways to navigation.
    Indeed, requiring the federal government to continue to operate and maintain
    a project after the Corps relinquished control would be inconsistent with the
    very purpose of deauthorization.         It was clearly reasonable for the Corps to
    adopt the cost-sharing formulas outlined in the catchall category for projects
    with other purposes when determining the cost-share for the closure portion of
    the MR-GO project. Because the Corps’ reliance on the cost-sharing provisions
    in the 1986 WRDA was reasonable, we defer to that judgment under Chevron.
    CONCLUSION
    For the foregoing reasons we reverse and render judgment for the Corps
    in part as concerns the cost allocation formula in the MOA with Louisiana that
    accompanied closure of the MR-GO, but we dismiss for lack of jurisdiction
    projects and their funding” in part by “establish[ing] new cost-share formulas, resulting in
    greater financial and decision-making roles for local stakeholders.”).
    23
    Case: 15-30962   Document: 00513648548     Page: 24   Date Filed: 08/23/2016
    No. 15-30962
    Louisiana’s challenge to the proposed, but not final, agency action for cost
    allocation concerning the MR-GO ecosystem restoration.
    REVERSED AND RENDERED IN PART, DISMISSED IN PART.
    24
    

Document Info

Docket Number: 15-30962

Citation Numbers: 834 F.3d 574

Filed Date: 8/23/2016

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (18)

flue-cured-tobacco-cooperative-stabilization-corporation-universal-leaf , 313 F.3d 852 ( 2002 )

Clymore v. United States , 217 F.3d 370 ( 2000 )

Alwan v. Ashcroft , 388 F.3d 507 ( 2004 )

American Airlines, Inc. v. Herman , 176 F.3d 283 ( 1999 )

Buffalo Marine Services Inc. v. United States , 663 F.3d 750 ( 2011 )

texas-oil-gas-association-marathon-oil-company-trustees-for-alaska , 161 F.3d 923 ( 1998 )

Cobell, Elouise v. Norton, Gale A. , 240 F.3d 1081 ( 2001 )

Army Corps of Engineers v. Hawkes Co. , 136 S. Ct. 1807 ( 2016 )

Grand Canyon Air Tour Coalition v. Federal Aviation ... , 154 F.3d 455 ( 1998 )

Reliable Automatic Sprinkler Co. v. Consumer Product Safety ... , 324 F.3d 726 ( 2003 )

Frozen Food Express v. United States , 76 S. Ct. 569 ( 1956 )

Bennett v. Spear , 117 S. Ct. 1154 ( 1997 )

Alaska Department of Environmental Conservation v. ... , 124 S. Ct. 983 ( 2004 )

Massachusetts v. Environmental Protection Agency , 127 S. Ct. 1438 ( 2007 )

Sackett v. Environmental Protection Agency , 132 S. Ct. 1367 ( 2012 )

Utility Air Regulatory Group v. EPA , 134 S. Ct. 2427 ( 2014 )

Michigan v. EPA , 135 S. Ct. 2699 ( 2015 )

Chevron U. S. A. Inc. v. Natural Resources Defense Council, ... , 104 S. Ct. 2778 ( 1984 )

View All Authorities »