United States Ex Rel. Told v. Interwest Construction Co. , 267 F. App'x 807 ( 2008 )


Menu:
  •                                                                              FILED
    United States Court of Appeals
    Tenth Circuit
    March 4, 2008
    UNITED STATES COURT OF APPEALS Elisabeth A. Shumaker
    Clerk of Court
    FOR THE TENTH CIRCUIT
    UNITED STATES OF AMERICA
    ex rel. MORRIS TOLD; and MORRIS
    TOLD, on his own behalf,
    Plaintiff-Appellant,
    v.                                                     No. 07-4156
    (D.C. No. 2:03-CV-751-PGC)
    INTERWEST CONSTRUCTION CO.,                              (D. Utah)
    INC., a Utah Corporation; and
    DOES 1-100, inclusive,
    Defendant-Appellee.
    ORDER AND JUDGMENT *
    Before LUCERO, HARTZ, and HOLMES, Circuit Judges.
    Morris Told filed this qui tam action, as a relator, against Interwest
    Construction Co., Inc. (“Interwest”), alleging: (1) violations of the False Claims
    Act (“FCA”), see 
    31 U.S.C. §§ 3729
    (a) & 3730(b),(h); and (2) acts of common
    law fraud and unjust enrichment under Utah law. The district court found that all
    *
    After examining the briefs and appellate record, this panel has determined
    unanimously to grant the parties’ request for a decision on the briefs without oral
    argument. See Fed. R. App. P. 34(f); 10th Cir. R. 34.1(G). The case is therefore
    ordered submitted without oral argument. This order and judgment is not binding
    precedent, except under the doctrines of law of the case, res judicata, and
    collateral estoppel. It may be cited, however, for its persuasive value consistent
    with Fed. R. App. P. 32.1 and 10th Cir. R. 32.1.
    of Told’s claims were time barred under the applicable statutes of limitations, and
    granted summary judgment to Interwest. Exercising jurisdiction under 
    28 U.S.C. § 1291
    , we AFFIRM.
    I
    Between 1992 and 1994, Told’s company, M.T. Enterprises, Inc.
    (“Enterprises”), worked as a subcontractor for Interwest, the general contractor
    selected by the United States to perform construction work at the Veterans
    Administration Hospital in Salt Lake City, Utah (“VA project”). 1 In August 2003,
    Told filed the present action against Interwest, claiming that it had violated the
    FCA and state common law by: (1) wrongfully retaining funds owed to
    Enterprises, as well as other subcontractors, in relation to the VA project, and
    (2) failing to timely pay Enterprises and other subcontractors for work performed
    during the project.
    Following the completion of scheduled discovery, Interwest moved for
    summary judgment, arguing that Told’s federal and state claims were barred by
    the applicable statutes of limitations. The district court agreed. It concluded that
    all of Told’s claims were time barred. See 
    31 U.S.C. § 3731
    (b)(1) (setting forth a
    six-year statute of limitations for FCA actions brought by relators); 
    Utah Code Ann. §§ 78-12-26
    (3) & 78-12-25 (setting forth statutes of limitations for state law
    1
    In 1995, Enterprises sued Interwest over the parties’ respective obligations
    under their VA project subcontract. The district court dismissed that suit in 2004
    for failure to prosecute.
    -2-
    claims of fraud and unjust enrichment). Additionally, the court concluded that
    insofar as Told’s opposition to Interwest’s motion for summary judgment could
    be read to assert a new allegation of a timely claim under the FCA, such a claim
    would not be allowed at the summary judgment stage. Otherwise, the court
    reasoned, Interwest would be unfairly prejudiced. 2 The court therefore entered
    summary judgment in favor of Interwest on all claims. This timely appeal
    followed.
    II
    “We review the district court’s grant of summary judgment de novo,
    applying the same legal standard employed by the district court. Summary
    judgment is appropriate only where there is no genuine issue of material fact and
    one party is entitled to judgment as a matter of law.” MediaNews Group, Inc. v.
    McCarthey, 
    494 F.3d 1254
    , 1260 (10th Cir. 2007) (quotations omitted). Told
    brings three arguments on appeal. 3 He first claims that we should revisit the prior
    2
    The scheduling order entered by the district court provided deadlines of
    March 2, 2007, to amend the pleadings, and April 2, 2007, to complete discovery.
    Nevertheless, rather than request permission from the district court to amend his
    complaint to include new claims prior to the end of either the amendment period
    or the discovery period, see Fed. R. Civ. P. 15(a), Told waited to raise the two
    additional claims he now asserts until he filed his opposition to Interwest’s
    motion for summary judgment on May 18, 2007.
    3
    Because Told does not address that portion of the district court’s summary
    judgment order holding that his state law claims for fraud and unjust enrichment
    were barred by the applicable state statutes of limitations, Told has waived those
    issues on appeal. See State Farm Fire & Cas. Co. v. Mhoon, 
    31 F.3d 979
    , 984 n.7
    (continued...)
    -3-
    Tenth Circuit precedent that required the district court to determine that his
    well-pleaded FCA claims were time barred. Told next contends that the district
    court erred in dismissing an additional FCA claim related to the VA project that
    would have been timely, urging that his original complaint was sufficiently broad
    to encompass this claim, or alternatively, that the district court should have
    allowed him to amend his complaint to include it. Finally, Told alleges that he
    raised yet another FCA claim in both his complaint and his opposition to
    Interwest’s motion for summary judgment that was unrelated to the VA project,
    and that the district court failed to rule on that claim.
    A
    As to the statute of limitations issue, Told concedes that his claims are time
    barred under this court’s interpretation of 
    31 U.S.C. § 3731
    (b) in United States
    ex rel. Sikkenga v. Regence Bluecross Blueshield of Utah, 
    472 F.3d 702
    , 725
    (10th Cir. 2006), in which we held that the FCA’s six-year statute of limitations
    applies to actions pursued by private qui tam relators. Nonetheless, he “believes
    that this Court should reconsider and reverse itself on this issue for sound policy
    reasons.” Because “[w]e are bound by the precedent of prior panels absent en
    banc reconsideration or a superseding contrary decision by the Supreme Court,”
    3
    (...continued)
    (10th Cir. 1994). He has also waived challenges to any other orders issued by the
    district court that he has not addressed in his briefings, despite his declared intent
    to appeal from more than simply the district court’s summary judgment order.
    See 
    id.
    -4-
    United States v. Meyers, 
    200 F.3d 715
    , 720 (10th Cir. 2000) (quotation omitted),
    we decline Told’s novel invitation to revisit our decision in Sikkenga.
    B
    Told next urges that the district court erred in granting summary judgment
    to Interwest on an additional VA project claim that was unrelated to his time-
    barred claims. Specifically, he complains that the district court should have
    considered the merits of his allegations that Interwest violated the FCA in relation
    to its 1999 receipt of a $375,000 settlement from the government in relation to the
    VA project. According to Told, this claim was not time barred because it
    “occurred on or after August 29, 1997,” and his lawsuit was filed within six years
    of that date.
    As to this claim, the district court found that Told had failed to state the
    relevant allegations in the complaint itself, and thus construed the argument Told
    raised in his opposition motion as an implicit motion to amend the pleadings. It
    then denied that motion. Before us, Told contends that his complaint did, in fact,
    plead this additional claim, or, in the alternative, that the court should have
    allowed him to amend his complaint to add it. We disagree.
    The “heightened pleading requirements [of Rule 9(b) of the Federal Rules
    of Civil Procedure] apply to actions under the FCA.” Sikkenga, 
    472 F.3d at 726
    .
    “At a minimum, Rule 9(b) requires that a plaintiff set forth the who, what, when,
    where and how of the alleged fraud.” 
    Id. at 726-27
     (quotation omitted). In
    -5-
    reviewing whether the complaint pleads fraud with the requisite particularity, “we
    accept as true all well-pleaded facts, as distinguished from conclusory allegations,
    and view those facts in the light most favorable to the non-moving party.” 
    Id. at 726
    . Our analysis is necessarily limited to the text of the complaint. 
    Id.
    According to Told, the following paragraph in his complaint set forth his
    additional FCA claim with the particularity required:
    Upon information and [b]elief, these defendants almost certainly
    have committed these same kinds of violations of the False Claims
    Act in connection with all other projects that they have been engaged
    which were funded in any way by Federal funds; and have violated
    said False Claims Act in connection with all said projects up through
    the filing of this complaint and through the date of trial.
    As we see it, this statement, when considered together with the remainder of the
    complaint, “falls woefully short of adequately pleading” an FCA violation in
    relation to the claim Told now attempts to put forth. See 
    id. at 727
    . Although we
    read the complaint to generally set forth the “who,” and perhaps the “what,” of
    the additional claim, that pleading clearly fails to allege well-pleaded facts related
    to the “when,” “where,” and “how” of the purported FCA violation.
    Furthermore, Told’s contention that the district court should have allowed
    him to amend his complaint is without merit. “The decision to grant leave to
    amend a complaint, after the permissive period, is within the trial court’s
    discretion, and will not be disturbed absent an abuse of that discretion.” Orr v.
    City of Albuquerque, 
    417 F.3d 1144
    , 1153 (10th Cir. 2005) (quotations omitted).
    -6-
    Such an abuse does not occur unless the district court’s decision “is arbitrary,
    capricious, whimsical, or manifestly unreasonable.” 
    Id.
     (quotations omitted). In
    providing Told the benefit of the doubt in entertaining a potential amendment, the
    district court stated that it “could overlook [his] failure to timely add this claim if
    pursuing it now would not subject Interwest to prejudice. But at this point in the
    proceedings, an amendment to [the] pleadings would substantially prejudice
    Interwest and would lead to judicial inefficiency.”
    On the record before us, we cannot say that the district court abused its
    discretion in disallowing this additional claim, particularly considering that
    discovery was already complete and the court had a fully submitted motion for
    summary judgment before it. “Courts typically find prejudice . . . when the
    amendment unfairly affects the defendants in terms of preparing their defense to
    the amendment. Most often, this occurs when the amended claims arise out of a
    subject matter different from what was set forth in the complaint and raise
    significant new factual issues.” Minter v. Prime Equip. Co., 
    451 F.3d 1196
    , 1208
    (10th Cir. 2006) (citation and quotation omitted). Although Told’s belated claim
    purportedly arose under the FCA, it involved entirely different facts (i.e., the
    settlement agreement between the government and Interwest). As the district
    court recognized, requiring Interwest to defend against this claim late in the
    proceedings would “place a serious burden on Interwest, effectively putting the
    parties back at square one.”
    -7-
    C
    Lastly, Told argues that the district court erred by failing to dispose of his
    claim regarding Interwest’s alleged FCA violations on certain United States post
    office projects. Although we conclude that the district court should have
    explicitly addressed this additional claim, we discern no reversible error on this
    issue.
    As an initial matter, it is apparent that Told never alleged any FCA
    violations in his complaint in relation to Interwest’s activities on federally funded
    post office projects, at least not with the specificity required under Rule 9(b). See
    Sikkenga, 
    472 F.3d at 726-27
    . His contention on appeal related to this alleged
    claim can therefore only be based on his argument that he raised an implicit
    motion to amend the complaint when he mentioned the post office allegations in
    his opposition to Interwest’s motion for summary judgment.
    Told is correct that the district court failed to rule separately on his alleged
    post office claim; the court’s order disposing of the case mentions only Told’s
    attempt to add the claim related to the $375,000 settlement payment. In light of
    the court’s failure to address the post offices claim, we consider the district
    court’s decision to be an implicit denial of the purported motion to amend, and
    will review that decision for an abuse of discretion. See Orr, 
    417 F.3d at 1153
    (setting forth abuse of discretion standard of review); cf. Spencer v. Wal-Mart
    Stores, Inc., 203 F. App’x 193, 195 (10th Cir. 2006) (unpublished) (construing a
    -8-
    district court’s failure to explicitly deny a motion to amend as an implicit denial
    of such motion).
    As the Supreme Court has recognized, an “outright refusal to grant [] leave
    [to amend] without any justifying reason appearing for the denial is not an
    exercise of discretion; it is merely abuse of that discretion and inconsistent with
    the Federal Rules” of Civil Procedure. Foman v. Davis, 
    371 U.S. 178
    , 182
    (1962). We therefore assume that the district court abused its discretion in not
    providing any reasons to justify its refusal to allow Told to add his post office
    claim. Nevertheless, we need not reverse the judgment based on such an error if
    the error is otherwise harmless. See Lambertsen v. Utah Dep’t of Corr., 
    79 F.3d 1024
    , 1029 (10th Cir. 1996). Harmless error in this context occurs if “the record
    contains an apparent reason justifying the denial of [the] motion to amend.” 
    Id.
    Based on our independent review of the record, we conclude that there is a clear
    reason for the implicit denial. To be sure, the very same reasons given by the
    district court for its explicit denial of Told’s implicit motion to amend the
    complaint to add a claim related to the $375,000 settlement payment also support
    the denial of Told’s attempt to add any claims related to federal post office
    projects. See 
    id.
    AFFIRMED.
    ENTERED FOR THE COURT
    Carlos F. Lucero
    Circuit Judge
    -9-