SCD BLK 251 Houston v. Mt. Jefferson ( 2022 )


Menu:
  • Case: 21-20396     Document: 00516445992          Page: 1    Date Filed: 08/24/2022
    United States Court of Appeals
    for the Fifth Circuit                              United States Court of Appeals
    Fifth Circuit
    FILED
    August 24, 2022
    No. 21-20396                         Lyle W. Cayce
    Clerk
    SCD BLK 251 Houston LLC,
    Plaintiff—Appellant,
    versus
    Mt. Jefferson Holdings L.L.C.,
    Defendant—Appellee.
    Appeal from the United States District Court
    for the Southern District of Texas
    USDC No. 4:20-CV-3463
    Before King, Elrod, and Southwick, Circuit Judges.
    Per Curiam:*
    SCD BLK 251 Houston appeals from the district court’s grant of
    judgment on the pleadings for Mt. Jefferson Holdings. The district court
    assumed arguendo that an option contract existed to build a connection
    between a future building on a lot owned by SCD BLK 251 and a hotel owned
    by Mt. Jefferson Holdings, but found that SCD BLK 251 was not ready to
    *
    Pursuant to 5th Circuit Rule 47.5, the court has determined that this
    opinion should not be published and is not precedent except under the limited
    circumstances set forth in 5th Circuit Rule 47.5.4.
    Case: 21-20396     Document: 00516445992           Page: 2   Date Filed: 08/24/2022
    No. 21-20396
    perform its end of the bargain (constructing the connection) within a
    reasonable time of the end date specified in the agreement. We, however, find
    that the agreement at issue was not a binding contract and therefore
    AFFIRM on that ground.
    I.
    The facts of this case begin in 2000, when Crescent Real Estate
    Funding (“Crescent”), the predecessor-in-interest to SCD BLK 251, sold
    the Four Seasons Hotel in Houston (the “Hotel”) to HEF Houston LP
    (“HEF”), the predecessor-in-interest to Mt. Jefferson Holdings. As part of
    that agreement, HEF granted Crescent “the future right and option to
    connect a skybridge or tunnel to the Hotel” through a document referred to
    as the “Agreement Regarding Span” (the “Span Agreement”). The
    language of that agreement is as follows:
    Connection Right. HEF hereby grants and conveys to
    Crescent and the successors and assigns in ownership
    (each, a “Block 251 Owner”) of Block 251 S.S.B.B.,
    Houston, Texas (“Block 251”), the future right to connect
    an air bridge or tunnel (a “Connection”) to a point on the
    wall of the Improvements, provided (a) such right shall be
    limited to a Connection located on or below the third floor
    of the Improvements that is mutually agreed upon by the
    owner of the Property (“Property Owner”) and Block 251
    Owner, and (b) the Connection shall not, without the
    consent of Property Owner, interfere with the current
    configuration of the Hotel (for example, the Connection
    will not be permitted to attach at the location of the
    restaurant(s) or banquet rooms of the Hotel without the
    consent of Property Owner). Block 251 Owner and Property
    Owner may each use such Connection for access to and
    from the Improvements to “Class A” improvements to be
    constructed on Block 251, if any, pursuant to an agreement
    which shall generally be in the form of the existing span
    2
    Case: 21-20396      Document: 00516445992          Page: 3   Date Filed: 08/24/2022
    No. 21-20396
    agreements affecting the Property, except as otherwise
    provided herein. The form of such agreement shall
    incorporate provisions requiring the consent of Property
    Owner to the exact location of the Connection, the design
    of the Connection, the method of construction of the
    Connection, insurance coverage during and after the
    construction of the Connection and the timing of
    construction of the Connection. Property Owner agrees
    that it will not unreasonably withhold, condition or delay its
    consent to the construction of the Connection; however, it
    shall be reasonable for Property Owner to withhold its
    consent in the event Property Owner determines, using its
    reasonable discretion, that such a tunnel or air bridge, once
    constructed and fully functional, would adversely affect the
    operations of the Hotel, other than the imposition of
    increased operating costs resulting from the operation of
    the tunnel or air bridge. All costs of constructing the
    Connection shall be paid by Block 251 Owner, provided that
    fees and expenses incurred by Property Owner in
    negotiating and reviewing the plans for the Connection
    (including without limitation, legal, architectural and
    engineering fees) shall be paid by Property Owner. Block
    251 Owner and Property Owner shall share equally all costs
    thereafter incurred in the operation and maintenance of the
    Connection, but Block 251 Owner shall be solely
    responsible for all capital expenditures required for the
    upkeep of the Connection, except for the exterior doors
    from the Connection to the Hotel. The execution of a span
    agreement between Property Owner and the Block 251
    Owner shall supersede and cancel the retained rights set
    forth in this Agreement.
    The agreement stated that the right “shall run with the land and shall
    inure to the benefit of and be binding upon the heirs, personal
    representatives, successors and assigns in ownership of the Property [i.e., the
    Hotel] and Block 251 respectively.” The agreement additionally included a
    3
    Case: 21-20396      Document: 00516445992           Page: 4     Date Filed: 08/24/2022
    No. 21-20396
    clause that “[t]he right granted above shall be exercised, if at all, on or before
    December 31, 2020,” and that “[t]ime is of the essence in the performance
    of all obligations under the Agreement.” Along with executing the
    agreement, Crescent and HEF executed a “Recorded Memorandum of Span
    Agreement” that was filed with the Harris County Clerk’s office.
    After purchasing Block 251 in 2019, SCD BLK 251 (“SCD”) began
    discussions with Mt. Jefferson Holdings (“Mt. Jefferson”) (which had
    previously purchased the Hotel) regarding the details of the connection
    described in the Span Agreement and the possibility of entering into the
    secondary agreement contemplated therein. On April 8, 2020, SCD sent Mt.
    Jefferson a letter stating that “SCD has elected to exercise the right to
    connect given to SCD under the Span Agreement.”
    After further negotiations following this letter were unsuccessful,
    SCD sued Mt. Jefferson in state court, seeking “a judicial declaration that
    SCD exercised its right and option to connect a sky bridge from Block 251 to
    the [Hotel] by providing written notice that it exercised such right prior to
    December 31, 2020 [the expiration date included in the Span Agreement].”
    It is undisputed that, as of the filing of the lawsuit, no building existed on
    Block 251, which was instead an empty lot being used for parking.
    After the lawsuit was filed, Mt. Jefferson filed a general denial of
    SCD’s allegations and removed the case to federal court. The parties filed
    cross-motions for judgment on the pleadings. The district court granted
    judgment on the pleadings for Mt. Jefferson. It assumed without deciding
    that the Span Agreement was an enforceable contract and then found that the
    agreement required SCD to physically construct a structure to the Hotel to
    exercise the option and that it had to do so by the time specified in the
    agreement—December 31, 2020. Since, according to the district court, SCD
    had not done so nor demonstrated the ability to do so within a reasonable
    4
    Case: 21-20396      Document: 00516445992          Page: 5    Date Filed: 08/24/2022
    No. 21-20396
    time of that date, the court granted judgment for Mt. Jefferson. SCD timely
    appeals.
    II.
    When considering an appeal, “[w]e need not accept the district
    court’s rationale and may affirm on any grounds supported by the record.”
    McGruder v. Will, 
    204 F.3d 220
    , 222 (5th Cir. 2000). We therefore consider
    whether the Span Agreement was enforceable in the first instance, a question
    the district court did not answer.
    In interpreting the Span Agreement, the district court assumed
    arguendo that it was both (1) an enforceable contract, not an unenforceable
    “agreement to agree,” and (2) a unilateral option contract. As to the first
    assumption, “[i]n general, a contract is legally binding only if its terms are
    sufficiently definite to enable a court to understand the parties’ obligations.”
    Fort Worth Indep. Sch. Dist. v. City of Fort Worth, 
    22 S.W.3d 831
    , 846 (Tex.
    2000). Therefore, “when an agreement leaves material matters open for
    future adjustment and agreement that never occur, it is not binding upon the
    parties and merely constitutes an agreement to agree.” 
    Id.
     In determining
    whether an agreement is an enforceable contract or an unenforceable
    “agreement to agree,” we look to see if the agreement “address[es] all of its
    essential terms” and is “sufficiently definite to confirm that both parties
    actually intended to be contractually bound.” Fischer v. CTMI, L.L.C., 
    479 S.W.3d 231
    , 237 (Tex. 2016). “[M]aterial and essential terms are those that
    parties would reasonably regard as ‘vitally important ingredient[s]’ of their
    bargain.” 
    Id.
     (alteration in original) (quoting Neeley v. Bankers Tr. Co., 
    757 F.2d 621
    , 628 (5th Cir. 1985)). “Whether a term is material or essential is a
    legal question that the court examines on a case-by-case basis.” Coe v.
    Chesapeake Expl., L.L.C., 
    695 F.3d 311
    , 320 (5th Cir. 2012).
    5
    Case: 21-20396      Document: 00516445992            Page: 6   Date Filed: 08/24/2022
    No. 21-20396
    Turning to the second assumption, “[a]n option contract has two
    components: (1) an underlying contract that is not binding until accepted and
    (2) a covenant to hold open to the optionee the opportunity to accept.” N.
    Shore Energy, L.L.C. v. Harkins, 
    501 S.W.3d 598
    , 606 (Tex. 2016) (quoting
    Faucette v. Chantos, 
    322 S.W.3d 901
    , 908 (Tex. App.—Houston [14th Dist.]
    2010, no pet.)). This first aspect is critical because “once the option is
    exercised and the offer accepted within the time specified, the underlying
    agreement becomes a valid and enforceable bilateral contract.” 1 SAMUEL
    WILLISTON & RICHARD A. LORD, Williston on Contracts § 5:16
    (4th ed. 2007 & Supp. 2022).
    We find that the agreement was not sufficiently definite to serve as an
    enforceable contract but is instead an unenforceable “agreement to agree.”
    There was simply too much left to be determined through future negotiation
    for the agreement to be enforceable. First, there was no agreement on the
    location of the connection between the two structures. Common sense
    suggests, and Texas cases confirm, that location is a material term. See, e.g.,
    Copano Energy, LLC v. Bujnoch, 
    593 S.W.3d 721
    , 731 (Tex. 2020) (finding
    location essential in an analogous statute-of-frauds context); Aurora
    Petroleum, Inc. v. Cholla Petroleum, Inc., No. 07-10-0035-CV, 
    2011 Tex. App. LEXIS 1382
    , at *6 (Tex. App.—Amarillo Feb. 23, 2011, no pet.) (location for
    drilling test wells was an essential term); MPG Petroleum, Inc. v. Crosstex
    CCNG Mktg., Ltd., No. 13-05-609-CV, 
    2006 Tex. App. LEXIS 8895
    , at *10
    (Tex. App.—Corpus Christi-Edinburg Oct. 5, 2006, pet. denied) (delivery
    location was an essential term).
    That the agreement put in some specification for location by
    mandating that any connection be on or below the third floor of the Four
    Seasons does not save the agreement. Even given that constraint, the tunnel
    or skybridge could still be located anywhere from twenty feet below ground
    to thirty or forty feet in the air. The structure of the agreement also
    6
    Case: 21-20396       Document: 00516445992            Page: 7     Date Filed: 08/24/2022
    No. 21-20396
    demonstrates the essential nature of the location of the connection; it used
    conditional language to grant the right to connect, but only so long as that
    connection was in a particular location. And as will become a running theme,
    the agreement provided no framework for how that location would be
    chosen—except for by mutual agreement. That is the exact type of “promise
    to negotiate towards a future bargain” that forms the basis of an
    unenforceable agreement to agree, not an enforceable contract. Dall./Fort
    Worth Int’l Airport Bd. v. Vizant Techs., LLC, 
    576 S.W.3d 362
    , 371 (Tex.
    2019).
    The same issue exists for the myriad particularities that would go into
    constructing the connection. The agreement did not specify the design of the
    connection nor answer any questions about how or when it would be
    constructed. It is clear that the agreement left those questions open,
    contemplating that they would be answered in a secondary agreement and
    even specifying that the owner of the Hotel would be responsible for “fees
    and expenses incurred . . . in negotiating and reviewing the plans for the
    Connection.” For a construction agreement, the design of what is to be
    constructed and the manner in which it is to be built are material. DKH
    Homes, LP v. Kilgo, No. 03-10-006-CV, 
    2011 WL 1811435
     (Tex. App.—
    Austin May 11, 2011, no pet.), is instructive. There, the Texas Court of
    Appeals was considering an agreement where the buyers of a lot “agree[d] to
    commence       construction    of    a   single    family    residence . . . on   the
    Property . . . within twelve (12) months” and to use DKH as the contractor.
    Id. at *1. The court found that agreement insufficiently definite because it
    “[did] not include any of the information essential to define the undertaking
    such as the size of the house contemplated, the price of the house on a per-
    square-foot or other basis, or the time for completing the construction.” Id.
    at *3. The same is true here. The Span Agreement does not specify the design
    of the connection, the size of the connection, or even the type of connection
    7
    Case: 21-20396      Document: 00516445992           Page: 8     Date Filed: 08/24/2022
    No. 21-20396
    (which could be either a tunnel or a skybridge). It does not specify the time
    for completing the construction. It does not specify the method of
    construction or questions of how that construction project will be insured.
    Each of these is a material term that is to be agreed upon later, rendering the
    agreement unenforceable.
    In addition, and as with location, the agreement does not determine
    exactly how those decisions are to be made. This is not an agreement where
    a formula has been provided, with only the inputs left to be plugged in later.
    Contra Fischer, 479 S.W.3d at 241 (“[T]he agreement provided a clear
    formula or standard by which to determine the payments[.]”). Instead, the
    agreement requires the parties to negotiate and then mutually agree on the
    answers to these questions; each of these decisions required “the consent of
    [the Hotel] Owner.” It is not enough that the agreement states that the Hotel
    owner “will not unreasonably withhold, condition or delay its consent to the
    construction of the Connection.” Texas courts have consistently found that
    “agreements to negotiate toward a future contract are not legally
    enforceable . . . even if the party agreed to negotiate in good faith.” Dall./Fort
    Worth Int’l Airport Bd., 576 S.W.3d at 371. Nor is it sufficient that the
    agreement stated that the secondary agreement “shall generally be in the
    form of the existing span agreements affecting the [Hotel].” That language
    provides only a shell for what the future agreement will look like in form; it
    still does not provide a method for how the decisions themselves will be
    made. The agreement was an agreement to agree.
    Last, considering the agreement as a purported option contract
    confirms our conclusion. As stated above, an option contract at bottom
    requires an enforceable underlying contract that goes into effect once the
    option is triggered. But in this case, the underlying “contract” is simply more
    negotiations. There is nothing for the court to compel Mt. Jefferson to do
    once SCD decided to elect its “option.” See Jarvis v. Peltier, 
    400 S.W.3d 644
    ,
    8
    Case: 21-20396      Document: 00516445992          Page: 9    Date Filed: 08/24/2022
    No. 21-20396
    650 (Tex. App.—Tyler 2013, pet. denied) (“But the option agreement does
    not give [the buyer] a right to compel [the seller] to sell the property.”). And
    there is no way for a court to determine what decisions the parties would
    reach in negotiating the secondary span agreement and “no implication of
    what the parties will agree upon.” Gerdes v. Mustang Expl. Co., 
    666 S.W.2d 640
    , 644 (Tex. App.—Corpus Christi-Edinburg 1984, no writ.) (quoting
    Radford v. McNeny, 
    104 S.W.2d 472
    , 475 (Tex. 1937)). A court would be
    unable to ensure that SCD’s election of the option was honored by enforcing
    an underlying contract; all it could order is that the parties come back to the
    negotiating table. See 1 Williston on Contracts § 4:29 (4th ed. 2007
    & Supp. 2022) (“[I]f an essential element is reserved for the future
    agreement of both parties . . . the promise can give rise to no legal obligation
    until such future agreement. Because either party in such a case may, by the
    very terms of the promise, refuse to agree to anything to which the other
    party will agree, it is impossible for the law to affix any obligation to such a
    promise.”). In the end, what the parties to the agreement seemed to have
    sought was leverage in the necessary future negotiations that were required
    to occur, supported by the specter of litigation. Litigation they may have
    gotten; an enforceable agreement, they did not. The agreement lacks the
    material terms necessary for an enforceable agreement and is instead an
    unenforceable agreement to agree.
    III.
    For the foregoing reasons, we AFFIRM the judgment of the district
    court.
    9