Guinn Bros., LLC v. Jones Brothers, Inc. of Tennessee , 287 F. App'x 298 ( 2008 )


Menu:
  •            IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    July 10, 2008
    No. 07-30931                     Charles R. Fulbruge III
    Summary Calendar                           Clerk
    GUINN BROTHERS, LLC,
    Plaintiff-Appellant,
    v.
    JONES BROTHERS, INC. OF TENNESSEE,
    Defendant-Appellee,
    Appeal from the United States District Court
    for the Western District of Louisiana
    USDC No. 05-CV-1616
    Before STEWART, OWEN, and SOUTHWICK, Circuit Judges.
    PER CURIAM:*
    Plaintiff-Appellant Guinn Brothers, LLC (“Guinn”) appeals the district
    court’s grant of summary judgment to Defendant-Appellant Jones Brothers, Inc.
    (“Jones”) on its claim for damages arising from Jones’s alleged breach of
    contract. For the reasons discussed below, we affirm in part and reverse in part
    the district court’s grant of summary judgment.
    *
    Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH CIR.
    R. 47.5.4.
    No. 07-30931
    I.
    On March 23, 2000, Jones was awarded a contract with the Louisiana
    Department of Transportation (“DOTD”) for road and bridge construction on
    Louisiana Highway 171. Jones and Guinn entered a subcontract agreement
    under which Guinn would remove and construct four bridges for a price of
    $1,747,883.81. This subcontract incorporated by reference all of the terms and
    conditions of the DOTD contract, as well as all of the plans, specifications, and
    schedules between Jones and the DOTD. The subcontract also contained a
    mandatory notice provision pertaining to claims for additional compensation:
    [Guinn] agrees to give notice in writing and make all
    claims for which [DOTD] is, or may be, liable in the
    manner provided and in a time framework which is
    consistent with the Principal Contract so that [Jones]
    may timely give notice of such claim to [DOTD].
    Provided that the preceding sentence does not require
    earlier action, written notice of such claims shall be
    given by [Guinn] to [Jones] within one (1) week prior to
    the beginning of the Work or the event or condition for
    which such claim is to be made, or immediately upon
    [Guinn’s] first knowledge of the event or condition,
    whichever shall first occur. Otherwise, such claims
    shall be deemed waived. [Guinn] shall give written
    notice of all claims for which [Jones] is, or may be
    liable, within five (5) days of the beginning of the event
    for which claim is made; otherwise, such claims shall be
    deemed waived. This notice period takes precedence
    over any other notice provisions provided by, or in, this
    Subcontract.
    The contract between Jones and DOTD contained a similar mandatory notice
    provision. However, it also contained a requirement that notification of all
    claims must conform to the requirements of EDSM III.1.1.28, which sets forth
    specific information and documents which must be submitted in support of a
    claim.
    2
    No. 07-30931
    From the project’s inception, there were significant delays and Guinn’s
    work was stopped for a number of periods of time. It is these periods of delay,
    discussed more fully below, which primarily form the basis of this lawsuit.
    Eventually, in early 2004, a dispute arose between Jones and the DOTD
    that caused Jones to demobilize its equipment and discontinue all work on the
    project. On May 27, 2004, counsel for Jones sent correspondence to Guinn
    advising Guinn to cease all work on the project and also informing Guinn of
    settlement negotiations between Jones and DOTD. In response, Guinn indicated
    that it had “incurred significant down time with this project” and would be
    “examin[ing] their options closely as to how they should best address the down
    time issue.” As part of the settlement negotiations, DOTD permitted Jones to
    rebid the remaining portion, and Guinn submitted a revised bid to Jones on
    October 11, 2004. Guinn indicated that this revised bid did not include the delay
    and down time claim because Guinn did not yet have all the information and
    would submit the claim when it was complete.
    Ultimately, in February 2005, under a settlement agreement between
    Jones and DOTD (Plan Change No. 50) Jones’s involvement in the project was
    terminated. As part of the settlement agreement, Jones agreed to indemnify the
    DOTD for all claims arising out of the bridge construction project.
    Based on the delays and eventual termination of the contract, Guinn filed
    suit against Jones in August 2005. Guinn’s complaint contains six numbered
    causes of action, each describing a separate incident in which Jones allegedly
    breached the subcontract, causing Guinn to suffer delay damages. In its sixth
    cause of action, Guinn also sought lost profits and lost material resulting from
    Jones’s failure to allow Guinn to complete the job. After extensive discovery,
    Jones moved for summary judgment. On September 27, 2007, the district court
    granted summary judgment to Jones on all of Guinn’s claims. Guinn timely
    appealed.
    3
    No. 07-30931
    II.
    This Court reviews a district court’s grant of summary judgment de novo,
    applying the same standards as the district court. Strong v. Univ. Healthcare
    Sys., L.L.C., 
    482 F.3d 802
    , 805 (5th Cir. 2007). “Summary judgment is proper
    when there exists no genuine issue of material fact and the movant is entitled
    to judgment as matter of law.” 
    Id.
     (citing FED. R. CIV. P. 56(c)). “The evidence
    and inferences from the summary judgment record are viewed in the light most
    favorable to the nonmovant.” Minter v. Great Am. Ins. Co. of N.Y., 
    423 F.3d 460
    ,
    465 (5th Cir. 2005).
    The moving party “bears the initial responsibility of informing the district
    court of the basis for its motion, and identifying those portions of [the record] .
    . . which it believes demonstrate the absence of a genuine issue of material fact.”
    Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 323 (1986). Once the movant meets this
    burden, the burden shifts to the nonmovant “to make a showing sufficient to
    establish the existence of an element essential to that party’s case, and on which
    that party will bear the burden of proof at trial.” 
    Id. at 322
    . To survive a
    summary judgment motion, the nonmovant “need only present evidence from
    which a jury might return a verdict in his favor,” Anderson v. Liberty Lobby, Inc.,
    
    477 U.S. 242
    , 257 (1986), but mere allegations or denials will not defeat a
    well-supported motion for summary judgment. FED. R. CIV. P. 56(e)
    III.
    On appeal, Guinn first argues that the district court erred in granting
    summary judgment on its claims for lost profits and lost materials because Jones
    did not move for summary judgment on these claims. Generally, “a district court
    may not grant summary judgment sua sponte on grounds not requested by the
    moving party.” Baker v. Metro. Life Ins. Co., 
    364 F.3d 624
    , 632 (5th Cir. 2004)
    (quoting John Deere Co., v. Am. Nat’l Bank, 
    809 F.2d 1190
    , 1192 (5th Cir. 1987)).
    An exception exists when the district court gives a party ten days notice; in those
    4
    No. 07-30931
    situations a court may grant summary judgment sua sponte on grounds not
    urged in a pending motion. See Judwin Properties, Inc. v. U.S. Fire Ins. Co., 
    973 F.2d 432
    , 436-37 (5th Cir. 1992).
    We agree that Jones did not move for summary judgment on the lost
    profits and materials claims. Examining the record, Jones’s summary judgment
    motion does not ever reference or discuss Guinn’s claims for lost profits or lost
    material. Rather, the motion focuses on the six specific instances of delay
    alleged by Guinn. Further, Guinn’s opposition to the motion for summary
    judgment fully evidenced its understanding that these claims were not part of
    the motion for summary judgment.
    In addition, the record does not indicate that the district court gave any
    notice to Guinn before sua sponte dismissing its claims for lost profits and lost
    materials. Consequently, Guinn was not on notice to present arguments on
    these claims, and we reverse the district court’s grant of summary judgment
    with regard to these two claims.
    IV.
    Guinn also argues that the district court erred in dismissing each of its six
    delay claims because it provided proper written notification of its claims to Jones
    as required by the subcontract.
    In Louisiana, a contract is the law between the parties. Gen. Elec. Capital
    Corp. v. S.E. Health Care, Inc., 
    950 F.2d 944
    , 951 (5th Cir. 1991). Under the
    Civil Code, contract interpretation “is the determination of the common intent
    of the parties.” LA. CIV. CODE ANN. art. 2045. “When the words of a contract are
    clear and explicit and lead to no absurd consequences, no further interpretation
    may be made in search of the parties’ intent.” LA. CIV. CODE ANN. art. 2046.
    “The general rule in Louisiana is that a provision in a written construction
    contract that no claims for extra work or materials shall be allowed unless made
    in writing is valid and binding upon the parties, and that when the contract so
    5
    No. 07-30931
    provides, and there is no written order for such extras, no recovery can be had
    for them.” Meaux v. S. Const. Corp.,
    159 So. 2d 156
    , 161 (La. Ct. App. 1964).
    Here, under the plain language of the subcontract, Guinn was required to
    give written notice and make all claims within one of two time periods: (1) for
    claims for which DOTD is the responsible party, in the manner and timeframe
    provided in the primary contract, but no later than one week prior to the event
    for which such claim is to be made or immediately upon Guinn’s first knowledge
    of the event or condition; or (2) for claims for which Jones is the responsible
    party, within five days of the beginning of the event for which the claim is based.
    The subcontract is unambiguous that if timely notice is not provided, the claim
    is waived. Additionally, the subcontract incorporates the provisions of the
    contract between the DOTD and Jones, and thus requires documentation of all
    items and figures for claims against the DOTD that the subcontractor intends
    to bring.
    The district court concluded that, with respect to Guinn’s six down time
    claims, Guinn had failed to comply with the notice and documentation provisions
    of the subcontract. Accordingly, the district court granted summary judgment
    to Jones on these claim. We will examine each of Guinn’s claims in turn.
    First, Guinn alleges that on May 29, 2000, it had completed its excavating
    work and was prepared to proceed, but that it was unable to work from May 29,
    2000 until October 2, 2000, because of Jones’ refusal to timely install the
    surcharge1 material. On September 11, 2000, Guinn sent Jones notification of
    1
    Surcharge is excess material (usually dirt) placed on top of an embankment area to
    accelerate the compaction process of the underlying embankment. After the desired
    compaction level is reached, the surcharge material is removed. As originally bid, the project
    did not include a surcharge requirement, but after some issues arose with the installation of
    embankment material, the DOTD notified Jones in June 2000 that it was requiring the
    installation of a surcharge. On September 1, 2000, the DOTD issued Plan Change No. 2,
    “Surcharge Placement and Removal,” which modified the existing contract, the work schedule,
    and the specifications associated with the embankment material and the surcharge.
    6
    No. 07-30931
    the delays and Guinn’s intent to seek reimbursement for its additional costs.
    This letter was forwarded to the DOTD on September 13, 2000, and the DOTD
    responded that the impact of delays and additional costs would be assessed at
    a later date via the Critical Path Method (“CPM”) of construction scheduling.
    The parties disagree over whether DOTD or Jones is responsible for this claim,
    and thus, which notice period applies and whether Guinn was required to submit
    documentation in compliance with EDSM III.1.1.28. We need not resolve this
    dispute, because under either time period, Guinn’s notice was untimely. Guinn’s
    own petition states that its claim for surcharge delay began on May 29, 2000.
    However, Guinn did not submit notice of a possible claim for delay damages until
    September 11, 2000, over three months after discovery of the problem.
    Second, Guinn alleges that Jones negligently installed the control points2
    for one of the bridges, preventing Guinn from working from November 13, 2000
    through November 17, 2000. Guinn argues that it provided notice to Jones of
    this claim in an October 27, 2000 letter. However, although this letter indicates
    that there is a problem with the control points, and that Guinn will not be
    responsible for any incorrect layout, this letter does not state that Guinn would
    be asserting a claim based on any resulting delay. Accordingly, this letter
    cannot be said to constitute notice to Jones for a down time claim stemming from
    negligent installation of the control point.
    Third, Guinn alleges that Jones impeded Guinn from completing its work
    by failing to blade wet material off of the surcharge after a rainfall on four
    separate occasions: November 27, 2000; January 2, 2001 to January 8, 2001;
    January 10, 2001 to January 22, 2001; and March 8, 2001 to March 19, 2001.
    Guinn first contends that the September 11, 2000 letter served as adequate
    notice for each of these periods. This is untenable, given that the September 11,
    2
    Control points are the reference points set to determine where to place the pilings for
    the bridge.
    7
    No. 07-30931
    2000 letter dealt only with the pile driving delays associated with the surcharge.
    Jones’s alleged failure to blade wet material off of the surcharge is an entirely
    separate claim. Guinn refers the court to five other letters sent to Jones
    referencing surcharge removal and delays associated with the layout. None of
    these letters discuss or even mention any problem with removal of wet material
    off the surcharge after a rainfall. These letters cannot be deemed to have
    provided the notice envisioned by the contract.
    Fourth, Guinn alleges two additional periods of delay based on Jones’s
    negligent fixing of the control points: February 2, 2001 to March 1, 2001; and
    April 2, 2001 to April 26, 2001. As we noted above, the October 27, 2000 letter
    was insufficient to provide notice to Jones because it did not indicate that Guinn
    would be seeking delay damages stemming from this issue. Guinn also points
    the Court to four other letters dated: February 22, 2001; April 18, 2001; April 26,
    2001; February 1, 2002; and May 21, 2004. None of these letters could possibly
    have provided timely notice with regard to the February 2001 claim, as they
    were all submitted more than five days after the delay allegedly began.
    However, the February 22, 2001, letter clearly indicates that problems
    with the control points have continued to cause delays in the construction of
    Bridge #2 and that Guinn would not be able to continue its work until the layout
    problem was resolved. In this letter, Guinn also states that “it intends to submit
    to [Jones] all costs related to the delays.” Guinn provided evidence to the district
    court that the second delay period, April 2, 2001 to April 26, 2001, was also
    caused by the failure of the control points for Bridge #2 to be placed in the proper
    positions, the problem specifically discussed in the February 22, 2001, letter.
    Jones was therefore adequately notified of the potential for a down time claim
    resulting from the problems with the Bridge #2 control points prior to the April
    2001 delay period. Therefore, we find that Guinn provided sufficient notice with
    respect to its delay claim for the period April 2, 2001 to April 26, 2001.
    8
    No. 07-30931
    Next, Guinn alleges three periods of delay arising from Jones’s failure to
    properly install embankment material.3 From May 24, 2001, through July 20,
    2001, Guinn contends that it was unable to work because it was waiting for
    Jones to remove and re-install embankment material. Guinn alleges that it
    completed the embankment work itself, with the approval of Jones and the
    DOTD, but has not been reimbursed for the use of its equipment or labor. From
    July 30, 2001 to October 1, 2001, Guinn asserts that it was unable to work
    because of Jones’s failure to correctly install embankment material for the
    approach slab on the south side of Bridge #1 northbound. Finally, from October
    9, 2001 to October 23, 2001, Guinn was unable to work because it was waiting
    for Jones to install embankment material for both approach slabs at Bridge #1
    northbound. Guinn ultimately installed the material itself, but alleges it was
    not compensated by Jones. Guinn argues that it provided timely notice of all
    three claims in its April 18, 2001 letter to Jones. An examination of the record
    reveals that this letter focuses primarily on the control point problem, and only
    cursorily mentions that Guinn has asked Jones to have the approach slab
    graded. This letter does not discuss the three specific problems alleged by Guinn
    in its petition, nor does it discuss the removal and reinstallation of embankment
    material. The mere mention of a general problem with the “approach slabs” was
    not sufficient, under the subcontract, to serve as notice of any one of Guinn’s
    three distinct embankment related claims.
    Finally, Guinn alleges that from October 23, 2001 until May 27, 2004,
    Jones refused to allow Guinn to perform any work on the jobsite for no reason.
    The record contains two letters referencing the shut-down, one dated February
    1, 2002, and another on March 25, 2004. Neither of these could possibly provide
    timely notice for a claim allegedly commencing on October 23, 2001.
    3
    Embankment material is the road base leading up to bridges and between bridges.
    Embankment material must be in place before bridge construction can begin.
    9
    No. 07-30931
    In sum, with the exception of Guinn’s April 2, 2001 to April 26, 2001
    control point delay claim, we agree with the district court that Guinn failed to
    provide Jones with timely notice of these claims under the terms the
    subcontract.
    V.
    Perhaps recognizing the lack of timely notice, Guinn also argues that the
    notice and documentation provisions of the subcontract were modified by the
    written plan changes, letter modifications, actions of the parties, and oral
    modifications. Guinn argues that with respect to the surcharge installation,
    DOTD Plan Change No. 2 evidences a clear, written modification to the notice
    and documentation provisions of the original contract. Similarly, Guinn argues
    that the “problems and delays” with the control points and approach slabs
    evidence a modification of the notice provisions. The district court found that
    Guinn failed to present competent summary judgment evidence demonstrating
    that the parties modified the contractual language regarding the claim
    notification requirements.
    Under Louisiana law, written contracts for construction, including notice
    provisions, may be modified orally and by the conduct of the parties. Pelican
    Electrical Contractors v. Neumeyer, 
    419 So. 2d 1
    , 5 (La. App. 1982). Guinn, as
    the party asserting modification, must prove by a preponderance of the evidence
    facts or acts giving rise to the modification. LA. CIV. CODE ANN. art. 1831;
    Wisinger v. Casten, 
    550 So. 2d 685
     (La. App. 1989). Further, the party urging
    modification must establish that parties mutually consented to the agreement
    as modified. Taita Chem. Co. v. Westlake Styrene Corp., 
    246 F.3d 377
    , 386 (5th
    Cir. 2001) (citing LA. CIV. CODE ANN. art 1927).
    Guinn relies primarily on Big “D” Dirt Services, Inc. v. Westwood, Inc., 
    653 So. 2d 604
     (La. App. 1995), to support its argument that the conduct and letters
    of the parties orally modified the notice provision of the subcontract. In that
    10
    No. 07-30931
    case, Big “D,” a subcontractor, had completed its work under the subcontract,
    but the DOTD rejected the work and Westwood, the general contractor, hired a
    third party to correct the defects in Big “D”’s work. Id. at 1-2. Westwood then
    refused to pay Big “D” for its work on the project and Big “D” filed suit. Id.
    Among other things, Big “D” alleged that Westwood’s failure to comply with a
    seven-day written notice provision amounted to a breach of contract for which
    Westwood was liable. Id. at 9. In response, Westwood argued that the strict
    notice requirement was modified by a subsequent oral agreement between the
    parties. Id. The court found that, through their actions and oral discussions,
    Big “D” and Westwood “modified the written notice requirement to, in effect, do
    away with its necessity.” Id. at 14. The court indicated that Westwood provided
    evidence that Big “D” was orally told of DOTD’s rejection of the work; that both
    parties attended a lunch meeting where remediation measures were discussed;
    that, although not necessary, Big “D” never requested written notice; and the
    fact that Big “D” attempted to contract a third party to do the remediation work
    six weeks after notification (when remediation was required within seven days)
    belied its contention that the contract was not modified. Id. at 14-15.
    We agree with the district court that Big “D” Dirt Services is
    distinguishable. In that case, Westwood presented evidence that Big “D” had
    acted inconsistently with the notice provisions, and thus believed the provisions
    were modified. Guinn has presented no such evidence that Jones acted in a way
    consistent with its argument that the notice provisions had been modified, and
    thus has failed to demonstrate that the parties mutually agreed to modify the
    contract. See, e.g., Taita Chem. Co., 
    246 F.3d at 386
    . Guinn argues that Plan
    Change No. 2 and the issue with the control points indicates that the
    subcontract was modified. While this evidence does indicate that the parties
    may have modified the subcontract with respect to the layout, deadlines,
    materials, and other aspects of the construction of the project, it does not
    11
    No. 07-30931
    demonstrate a mutual agreement to modify the strict notice provisions. See L
    & A Contracting Co. v. Ram Indus. Coatings Inc., 
    762 So. 2d 1223
    , 1233 (La.
    App. 2000) (holding that although parties had orally modified contract to include
    additional work, no agreement was made with regards to when payment was
    due). None of the documents and letters pointed to by Guinn discuss such a
    modification of the claim notice provisions. In sum, the record is devoid of any
    evidence which supports Guinn’s argument that the parties orally modified the
    subcontract to remove the notification provision.
    Therefore, because Guinn failed to present sufficient evidence to create a
    genuine issue of material fact as to whether the parties orally modified the
    notice provisions of the subcontract, the district court correctly found that the
    notice provision is valid. Thus, as discussed above, with the exception of Guinn’s
    April 2, 2001 to April 26, 2001 control point delay claim, Guinn’s delay claims
    are barred because of its failure to comply with the notice provision and the
    district court’s grant of summary judgment was proper. However, because
    Guinn provided sufficient notice under the subcontract of the April 2, 2001 to
    April 26, 2001 control point delay claim, the district court erred in granting
    summary judgment to Jones on this claim.
    VI.
    In conclusion, we REVERSE the district court’s grant of summary
    judgment with regard to Guinn’s claims for lost profits and lost materials.
    Further, with the exception of Guinn’s April 2, 2001 to April 26, 2001 control
    point delay claim, we AFFIRM the district court’s grant of summary judgment
    with regard to these claims. With respect to Guinn’s April 2, 2001 to April 26,
    2001 control point delay claim, we REVERSE the district court’s grant of
    summary judgment. This case is REMANDED to the district court for further
    proceedings not inconsistent with this opinion.