D2 Excavating, Incorporated v. Thompson Thrift Con ( 2020 )


Menu:
  • Case: 19-40745      Document: 00515550522         Page: 1    Date Filed: 09/02/2020
    United States Court of Appeals
    for the Fifth Circuit
    United States Court of Appeals
    Fifth Circuit
    FILED
    September 2, 2020
    No. 19-40745                           Lyle W. Cayce
    Clerk
    D2 Excavating, Incorporated,
    Plaintiff—Appellee,
    versus
    Thompson Thrift Construction, Incorporated; Fidelity
    and Deposit Company of Maryland,
    Defendants—Appellants.
    Appeal from the United States District Court
    for the Southern District of Texas
    USDC No. 2:16-CV-538
    Before Stewart, Clement, and Costa, Circuit Judges.
    Gregg Costa, Circuit Judge:
    Contracts do not always turn out the way a party expects. Sometimes
    it takes less time or money to perform than anticipated; other times it takes
    more. This case is of the latter variety. A subcontractor doing excavation
    work ended up having to remove a lot more dirt from the construction site
    than the parties anticipated. The resulting lawsuit over this “excess dirt” led
    to a judgment for the subcontractor exceeding half a million dollars. The
    principal issue on appeal is whether the subcontractor was entitled to
    Case: 19-40745          Document: 00515550522               Page: 2       Date Filed: 09/02/2020
    No. 19-40745
    additional money for the “excess dirt” removal or whether it was stuck with
    the price the parties agreed to.
    I.
    Thompson Thrift Construction, Inc. was the general contractor for a
    new apartment complex in Corpus Christi. 1 It solicited a bid from D2
    Excavating, Inc. for site grading and excavation work. Thompson sent D2
    documents which included proposed contract terms, a topographical survey
    of the site, and the planned final elevations.
    The proposed terms included the following language:
    Execution of this Agreement by the Subcontractor is a
    representation that the Subcontractor has visited the Project
    site, become familiar with local conditions under which the
    Work is to be performed and correlated personal observations
    with requirements of the Contract Documents. The
    Subcontractor shall evaluate and satisfy itself as to the
    conditions and limitations under which the Work is to be
    performed, including without limitation: (1) the location,
    condition, layout, and nature of the Project site and
    surrounding          areas;    (2)    generally     prevailing      climactic
    conditions; (3) anticipated labor supply and costs; (4)
    availability and cost of materials, tools, and equipment; and (5)
    other similar issues. Accordingly, Subcontractor shall not be
    entitled to an adjustment in the Contract Price or an extension
    of time resulting from Subcontractor’s failure to fully comply
    with this paragraph.
    1
    These facts come from the findings the district court entered after the bench trial.
    2
    Case: 19-40745      Document: 00515550522         Page: 3     Date Filed: 09/02/2020
    No. 19-40745
    ...
    This is a balanced site. It shall be this subcontractor’s
    responsibility to balance site. Change orders for import/export
    will not be accepted. Consider all spoils from other trades, and
    create berms where necessary.
    A site is “balanced” if the work will not require importing or exporting dirt
    to achieve the planned elevations. In that case, the dirt need only be
    transferred within the site.
    Despite its representation, Thompson did not actually determine
    whether the site was balanced. The proposed terms were its standard
    template for all excavation projects. D2 also declined to investigate the site—
    two months of heavy rain limited its ability to physically examine the site, and
    Thompson was eager to begin construction as soon as the rain ceased.
    Instead, D2 used a software program to determine the site was balanced, after
    accounting for dirt that other contractors would produce. The inputs for this
    analysis came from the topographical survey Thompson provided.
    After performing its simulations, D2 agreed to do the excavation.
    Under the final contract, Thompson was to pay D2 $630,000. The parties
    included the proposed terms that Thompson originally provided to D2 in the
    contract as an exhibit with slight modifications. The final agreement also
    anticipated the possibility of modifying the scope of the work and included
    unit pricing for additional tasks that would be executed as written change
    orders.
    About one month after D2 began excavating, it became clear that the
    site was not balanced. Excavation was producing a lot more dirt than
    expected and some would need to be removed from the site. D2 and
    Thompson disagreed about whose fault the excess dirt was. Thompson
    argued that the imbalance was due to D2’s inaccurate computer analysis,
    3
    Case: 19-40745        Document: 00515550522            Page: 4      Date Filed: 09/02/2020
    No. 19-40745
    D2’s excess import of fill, or D2’s overexcavation of the site; D2 countered
    that the topographical survey was flawed. Regardless of who was responsible
    for the misestimate, D2 promptly notified Thompson that there was
    unanticipated dirt that needed to be removed. The parties negotiated and
    decided that Thompson would cover D2’s costs for the additional work.
    Thompson told D2 it would issue a written change order for the additional
    work once it was finished so that it would be easier to calculate what it owed.
    With Thompson’s promise to pay for unanticipated exporting work in
    hand, D2 continued excavating. In addition to the unexpected exporting of
    excess dirt, Thompson repeatedly asked D2 to re-excavate and regrade areas
    that other subcontractors’ activity had disturbed. In one case, Thompson’s
    mismanagement of other subcontractors required D2 to excavate the same
    area six times.
    D2 became concerned that Thompson would not actually pay for this
    work. It began sending fewer employees to the site, which prompted
    negotiations with Thompson about D2’s compensation. Those negotiations
    were ultimately unfruitful, and Thompson never provided a change order.
    When it became clear that Thompson was not going to pay additional
    amounts for the removal of dirt, D2 stopped working. At that point, 98.6% of
    the excavation was complete.
    D2 then sued for breach of contract, quantum meruit, violations of the
    Texas prompt pay statute, and to foreclose on a statutory and constitutional
    lien. 2 Thompson, in turn, argued that D2 breached the contract. Thompson
    filed an unsuccessful motion for summary judgment, which argued that D2
    bore the risk that the site might be unbalanced. At the conclusion of a bench
    2
    D2 sued both Thompson and Fidelity and Deposit Company of Maryland, which
    had issued an indemnity bond. Fidelity’s damages are limited to its bond of $581,605.50.
    4
    Case: 19-40745         Document: 00515550522              Page: 5      Date Filed: 09/02/2020
    No. 19-40745
    trial, the district court held in D2’s favor on all claims. It ordered Thompson
    to pay D2 $81,068.00 for unpaid work under the contract and $257,588.53
    for “excess” excavating work. Interest of 1.5%/month was added to those
    awards starting in May 2016, when payment became due under the Texas
    prompt payment law. The biggest award of all was for attorneys’ fees:
    $356,080.91.
    II.
    We review the district court’s findings of fact for clear error, but this
    appeal largely turns on legal issues of contract interpretation, which we
    review de novo. Lyda Swinerton Builders, Inc. v. Okla. Sur. Co., 
    903 F.3d 435
    ,
    450 (5th Cir. 2018).
    One of those questions of law is the focus of the appeal: whether D2
    could recover beyond the contract price for “excavation of unanticipated
    excess soil.” 3 The district court concluded D2 could recover under either a
    contract or quantum meruit theory.
    A.
    Thompson challenges the contract ruling on the ground that D2 bore
    the risk that the site might be unbalanced and thus cannot recover beyond the
    contract price for any “excess” excavation work. A party to a Texas
    3  Texas courts use the term “extra work” to mean work “which, by definition is
    work ‘arising outside and independent of the contract, something not required in its
    performance.’” Joe F. Canterbury, Jr. & Robert J. Shapiro, Texas
    Construction Law Manual § 1:28 (3d ed. 2019) (quoting Brown-McKee, Inc. v.
    Western Beef, Inc., 
    538 S.W.2d 840
    , 844 (Tex. Civ. App.—Amarillo 1976, writ refused
    n.r.e.). In contrast, “additional work” is “that required in the performance of the contract
    and without which it could not be carried out.”
    Id. § 8:8 (quoting
    City of Houston v. L.J.
    Fuller, Inc., 
    311 S.W.2d 285
    , 290 (Tex. Civ. App.—Houston 1958, no writ)). We use the
    different term “excess,” as that is how the district court and the parties describe the
    excavation work for the unanticipated dirt removal. In the Texas parlance, we conclude
    that this was “additional work” because it was required under the contract.
    5
    Case: 19-40745      Document: 00515550522          Page: 6     Date Filed: 09/02/2020
    No. 19-40745
    construction project is liable for breach of contract when it provides
    inadequate construction plans and the contract allocates to that party the risk
    of inaccurate plans. See Interstate Contracting Corp. v. City of Dallas, 
    407 F.3d 708
    , 720–21 (5th Cir. 2005). Thompson asserted the site was balanced,
    which the district court rightly found was not true. 4
    The remaining question is which party bore the risk that the site might
    be unbalanced. The default rule in Texas, dating back to a case interpreting
    an 1899 contract to construct a building in San Antonio, is that the party
    doing the work bears the risk that it will end up being more difficult than
    anticipated unless the contract shifts that risk to the buyer of the services.
    Lonergan v. San Antonio Loan & Tr. Co., 
    104 S.W. 1061
    , 1065–66 (Tex. 1907);
    see also Interstate 
    Contracting, 407 F.3d at 720
    –21 (“In order for an owner to
    breach a contract by supplying inadequate plans to a contractor, [Texas law]
    require[s] that the contract evidence an intent to shift the burden of risk of
    inadequate plans to the owner.”). This default rule flows from the basic
    contract principle that “where one agrees to do, for a fixed sum, a thing
    possible to be performed, he will not be excused or become entitled to
    additional compensation, because unforeseen difficulties are encountered.”
    El Paso Field Servs., L.P. v. MasTec N. Am., Inc., 
    389 S.W.3d 802
    , 811 (Tex.
    2012) (citation omitted). If a factory agrees to manufacture 100 widgets for
    $500, it cannot later charge $600 if it ends up taking more labor or materials
    to produce the widgets than expected.
    The default rule applies here because the excavation contract does not
    allocate to Thompson the risk that the site would be unbalanced. If anything,
    it placed that risk on D2. D2 agreed that it had “visited the Project site,
    become familiar with local conditions under which the Work is to be
    4
    D2 did not, however, bring claims for breach of warranty or fraudulent
    inducement based on misrepresentation.
    6
    Case: 19-40745      Document: 00515550522          Page: 7     Date Filed: 09/02/2020
    No. 19-40745
    performed and correlated personal observations with requirements of the
    Contract Documents.” It further represented that it would “evaluate and
    satisfy itself” about a number of conditions, including “the location,
    condition, layout, and nature of the Project site and surrounding areas.” As
    a result, D2 would not be “entitled to an adjustment in the Contract Price or
    an extension of time resulting from [its] failure to fully comply” with those
    conditions. That agreement to verify the topography of the site put the risk
    on D2. “Someone has to bear the loss of additional costs,”
    id. at 811,
    and the
    excavation contract did not shift those costs to Thompson.             Compare
    Dall./Fort Worth Int’l Airport Bd. v. INET Airport Sys., Inc., 
    819 F.3d 245
    , 252
    (5th Cir. 2016) (contractor did not assume all risks when the contract
    contained no provision on point and a mixture of provisions allocating risks
    of defects to both parties), with Interstate 
    Contracting, 407 F.3d at 721
    –23
    (contractor assumed risk when the written instrument obligated contractor
    to independently investigate work site and explicitly allocated “[a]ll risks of
    differing subsurface conditions” to the contractor).
    D2’s attempt to distinguish MasTec and Interstate Contracting because
    they involved different contractual language fails on two levels. First, there
    must be language shifting the burden to Thompson. So even if the language
    we just cited does not assign the risk to D2, the contract must say that
    Thompson assumed the risk that the project would require removing more
    dirt than the plans predicted. It does not. Second, the difference in language
    is only a matter of degree. To be sure, the language in MasTec was about as
    clear an assumption of risk as possible: “[MasTec] assumes full and complete
    responsibility for any such conditions pertaining to the Work, the site of the
    Work or its surroundings and all risks in connection 
    therewith.” 389 S.W.3d at 806
    (alteration in original). The contract in Interstate Contracting similarly
    stated: “All risks of differing subsurface conditions shall be borne solely by
    the 
    [contractor].” 407 F.3d at 721
    . But just because stronger language
    7
    Case: 19-40745        Document: 00515550522          Page: 8    Date Filed: 09/02/2020
    No. 19-40745
    existed in other cases does not mean that “the parties’ intentions as
    expressed in [this] writing” are different. 
    MasTec, 389 S.W.3d at 805
    . D2
    knew it had an obligation to confirm the site’s topography because it tried to
    do so—but gave up—when Thompson resisted further delay. See Granite
    Constr. Co. v. Tex. Dep’t of Transp., 
    2012 WL 5974085
    , at *8 (Tex. App.—
    Austin Nov. 20, 2012, no pet.) (discussing contractual language obligating a
    party to examine a work site and stating that “[c]ourts interpreting similar
    contractual provisions have consistently held that this type of language
    precludes a contractor from maintaining a claim for varying site
    conditions.”).
    Although all along its contract claim has relied on the notion that
    Thompson mispresented that the site was balanced, D2 now tries to
    distinguish Interstate Contracting and Lonergan by arguing this is not a
    “defective plans and specifications case.” Metaphysically distinguishing
    between “defective plans and specifications” on the one hand and a mere
    representation that a site is balanced on the other is inconsistent with Texas
    law, as Texas cases largely reason that “plans and specifications . . .
    constitute an affirmative representation on which a contractor could rely.”
    Interstate 
    Contracting, 407 F.3d at 718
    ; see also
    id. at 716–720
    (collecting
    cases).
    Of course, a valid modification of the contract via a change order could
    render Thompson liable. But change orders, like any modification, must
    satisfy the normal requirements of a contract: “a meeting of the minds
    supported by consideration.” Hathaway v. Gen. Mills, Inc., 
    711 S.W.2d 227
    ,
    228 (Tex. 1986); see also 
    INET, 819 F.3d at 252
    (“[A]ny change order to
    adjust for the defects discovered by INET required the assent of both
    parties.”). Critically, “[a] promise to fulfill a pre-existing obligation cannot
    serve as new consideration for an amendment to a contract.” In re OSG Ship
    Mgmt., 
    514 S.W.3d 331
    , 338 (Tex. App.—Houston [14th Dist.] 2016, no pet.).
    8
    Case: 19-40745     Document: 00515550522            Page: 9   Date Filed: 09/02/2020
    No. 19-40745
    The oral change order lacked that consideration. D2 acknowledges that the
    alleged consideration was its exporting excess soil. The original contract
    already obligated D2 to do so without any compensation beyond the contract
    price. Hauling the dirt, therefore, cannot serve as consideration. The oral
    change order is void.
    If the contract had required less excavation work than the parties
    expected, Thompson would not be able to get a refund on the $630,000 it
    agreed to pay. Likewise, when the work turned out to involve more work
    than the parties expected, D2 cannot recover more than the $630,000.
    Thompson did not breach its contract with D2 when the site turned out to be
    unbalanced. Accordingly, we vacate the $257,588.53 breach-of-contract
    award for “excavation of unanticipated excess soil.”
    B.
    The district court concluded that quantum meruit was an alternative
    remedy “[i]n the event that the extra excavation work associated with the
    excess soil falls outside the scope of the contract.” We have just held that
    the contract required excavation of all the soil, however much it turned out
    to be. So by its own terms, the quantum meruit ruling does not stand because
    this work was within, not outside, the contract.
    The district court properly understood that quantum meruit was
    available only if the excess soil work was not covered by the contract. Black
    Lake Pipe Line Co. v. Union Constr. Co., 
    538 S.W.2d 80
    , 86 (Tex. 1976)
    (recognizing that contractor could recover quantum meruit “for the
    reasonable value of services rendered and accepted which are not covered by
    the contract” (emphasis added)), overruled on other grounds by Sterner v.
    Marathon Oil Co., 
    767 S.W.2d 686
    (Tex. 1989). “Quantum meruit is an
    equitable theory of recovery which is based on an implied agreement to pay
    for benefits received.” Heldenfels Bros., Inc. v. City of Corpus Christi, 832
    9
    Case: 19-40745      Document: 00515550522         Page: 10     Date Filed: 09/02/2020
    No. 19-40745
    S.W.2d 39, 41 (Tex. 1992). It is generally unavailable if a valid contract
    covers the goods or services a plaintiff furnished. In re Kellogg Brown & Root,
    Inc., 
    166 S.W.3d 732
    , 740 (Tex. 2005). Quantum meruit corrects an injustice
    when a promise to pay was implied. If the parties reached an express
    agreement allocating payments, services, and risks—that is, a contract—then
    a court should not step in and impose its view of what would constitute an
    equitable arrangement.
    Texas recognizes an exception to this general rule in the construction
    context. A plaintiff that does not substantially perform a construction
    contract, and thus cannot “recover[] under the express contract,” may
    pursue quantum meruit for the value of its services. See Murray v. Crest
    Constr., Inc., 
    900 S.W.2d 342
    , 345 (Tex. 1995). Unlike the goods or services
    provided under many contracts, partial work done on a construction project
    cannot be transferred to another buyer. So it would be unjust to allow the
    party receiving the partial construction to not pay anything for it. See Vortt
    Exploration Co. v. Chevron U.S.A., Inc., 
    787 S.W.2d 942
    , 944 (Tex. 1990)
    (noting that “quantum meruit is founded on unjust enrichment”). If there
    is no free lunch, then certainly there is no free house. As a result, when a
    breaching contractor cannot recover the contract price, it nonetheless may
    be able to recover in quantum meruit. 
    Murray, 900 S.W.2d at 345
    ; cf. WARD
    FARNSWORTH, RESTITUTION: CIVIL LIABILITY FOR UNJUST
    ENRICHMENT 89–90 (2014) (recognizing that the related equitable claim of
    restitution may be available when a breaching party no longer has a contract
    claim but should recover for benefits conferred).
    That “partial performance” exception does not fit this case. D2 seeks
    a quantum meruit recovery despite having substantially performed its
    contractual duties and, therefore, being able to collect on the contract. In
    other words, D2 wants quantum meruit plus the contract price. That is not
    allowed. See Balfour Beatty Rail, Inc. v. Kan. City S. Ry. Co., 
    173 F. Supp. 3d 10
    Case: 19-40745      Document: 00515550522          Page: 11     Date Filed: 09/02/2020
    No. 19-40745
    363, 451 (N.D. Tex. 2016) (denying quantum meruit when the work was
    within the scope of the contract); Bright Excavation, Inc. v. Pogue Constr. Co.,
    
    2020 WL 1921681
    , at *7 (Tex. App.—Dallas April 21, 2020, no pet.) (same);
    see also 
    FARNSWORTH, supra, at 90
    (explaining that the contract price
    remains “a ceiling” on what a breaching party can recover from the
    defendant on an equitable claim). It would override the parties’ agreement
    to allow the plaintiff to recover more than the contract price for work the
    contract required. Excess Underwriters at Lloyd’s, London v. Frank’s Casing
    Crew & Rental Tools, Inc., 
    246 S.W.3d 42
    , 50 (Tex. 2008) (“[W]hen a valid
    agreement already addresses the matter, recovery under an equitable theory
    is generally inconsistent with the express agreement.” (quoting Fortune Prod.
    Co. v. Conoco, Inc., 
    52 S.W.3d 671
    , 684 (Tex. 2000))).            Because the
    unanticipated excavation work was D2’s responsibility under the contract,
    quantum meruit is not a vehicle for recovering more than the contract price.
    Neither breach of contract nor quantum meruit allows D2 to recover
    for “excavation of unanticipated excess soil.”
    III.
    We have emphasized the sanctity of the agreement the parties reached
    in rejecting any remedy beyond the contract price. Recall, though, that the
    district court awarded $81,068 to ensure that Thompson paid that full
    contract price. That figure included the unpaid amounts to D2, reduced by
    the $20,000 it cost Thompson to complete the work once D2 stopped
    performing.
    Thompson also challenges this award. This argument is part of its
    appeal of the district court’s rejection of its counterclaim for breach of
    contract. Thompson contends that, because D2 stopped performing before
    it completed the work, Thompson does not owe the $81,068 in outstanding
    charges to D2 and instead should have received damages from D2 for the
    11
    Case: 19-40745      Document: 00515550522          Page: 12      Date Filed: 09/02/2020
    No. 19-40745
    costs of completing the work. D2 argues that Thompson did not adequately
    brief this issue. Forfeiture presents a close call, which we avoid making
    because the deference we owe the district court’s findings allows us to readily
    reject the argument on the merits.
    The district court found that D2 did not breach the contract, and even
    if it did, Thompson’s prior breach and its failure to manage the construction
    site excused D2’s failure to perform.         The district court found that
    management of the site was so deficient that D2 had to regrade the same areas
    as many as six times and was unable to complete its work in other parts of the
    site, justifying D2’s cessation of work. That finding is not clear error. It is a
    bedrock principle of contract law that “the conduct of one party to a contract
    which prevents the other from performing his part is an excuse for non-
    performance.” United States v. Peck, 
    102 U.S. 64
    , 65 (1880); see also Hearne
    v. Garrett, 
    49 Tex. 619
    , 624–25 (1878) (“Where one is employed to perform
    some stipulated work . . . and, after part performance of the contract on his
    part, he is wrongfully prevented from completing the work contracted for, or
    laboring for the full period of time stipulated, it seems fully settled that the
    employee may treat the contract as abandoned . . . .”). As a result, we affirm
    the damage award for $81,068 and the rejection of Thompson’s
    counterclaim.
    IV.
    Thompson also challenges the rulings that it violated the Texas
    prompt pay statute, which results in annual interest of 18% on the unpaid
    claims, and that D2 could foreclose on statutory and constitutional liens to
    recover its judgment. Its only argument is that these remedies require an
    underlying breach of contract and that it has no contractual liability. We
    agreed in part with Thompson’s appeal of the contract claims, so it also
    enjoys only partial success on these claims. For the contractual recovery we
    12
    Case: 19-40745      Document: 00515550522        Page: 13      Date Filed: 09/02/2020
    No. 19-40745
    have reversed, obviously there can be no interest or lien. But for the
    contractual recovery we affirmed, these other remedies still attach.
    ***
    We AFFIRM the judgment for the $81,068 in unpaid work and the
    related prompt payment statute and lien remedies for that breach of contract.
    We REVERSE the judgment of $257,588.53 for the “excavation of
    unanticipated excess soil” and RENDER judgment for Thompson on those
    breach of contract and quantum meruit claims.           We REMAND for
    modification of the judgment consistent with this opinion.
    13