N J Collins Inc v. Pacific Leasing Inc ( 2000 )


Menu:
  •                           UNITED STATES COURT OF APPEALS
    For the Fifth Circuit
    No. 99-31128
    N.J. COLLINS, INC.,
    Plaintiff-Appellant,
    VERSUS
    PACIFIC LEASING, INC.,
    Defendant-Appellee.
    Appeal from the United States District Court
    For the Eastern District of Louisiana
    (97-CV-2379-N)
    October 16, 2000
    Before REAVLEY, BENAVIDES, and DENNIS, Circuit Judges.
    DENNIS, Circuit Judge:*
    N.J.     Collins,      Inc.,     (“NJC”)       sued    Pacific      Leasing,       Inc.,
    (“Pacific”) for an alleged breach of a sale contract whereby
    Pacific was to sell the tugboat FRANCES J to NJC for $700,000.
    Pacific filed a counter-claim, contending NJC breached the contract
    by failing to make required advance deposits.                          The district court
    *
    Pursuant to 5TH CIR. R. 47.5, the Court has determined that this opinion should not be
    published and is not precedent except under the limited circumstances set forth in 5TH CIR. R.
    47.5.4.
    1
    granted partial summary judgment to Pacific upon determining that
    Pacific had not modified the contract or waived the provisions
    requiring advance deposits of $70,000, that NJC had not relied to
    its detriment on Pacific’s actions, and that NJC breached the
    contract’s advance deposit requirements by failing to make the
    payments.     Trial was conducted solely on the issue of damages.                NJC
    requested that the court instruct the jury regarding Pacific’s duty
    to mitigate its damages. The district court instructed the jury on
    the duty imposed on Pacific by the Uniform Commercial Code (“UCC”)
    to   resell   the     tugboat     in   good    faith    and   in   a   commercially
    reasonable manner, but the court refused to instruct the jury
    separately     on    the   duty   to   mitigate,       reasoning   that    the   jury
    instruction given subsumed the duty to mitigate in the UCC context.
    The jury returned a verdict in favor of Pacific, and the court
    entered judgment awarding $210,000 in damages to Pacific.                         On
    appeal, NJC contends that the district court made two errors: (1)
    in granting partial summary judgment to Pacific on the issues of
    contract breach, contract modification, and waiver and reliance,
    and (2) in not separately instructing the jury on the issue of
    Pacific’s     duty    to   mitigate.      We    affirm    the   district    court’s
    judgment.
    I.    Factual Background
    Pacific and NJC executed the sale contract on July 26, 1996.
    2
    Because the tugboat was located in Guam and NJC was located in New
    Orleans, the contract required Pacific to deliver the boat from
    Guam to Balboa, Panama, where NJC would pay the balance of the
    contract and take possession of the boat.          The terms of the
    contract obligated NJC to make an advance deposit of $35,000 by
    August 2; NJC failed to do so.        Pacific made demands on NJC to
    fulfill its obligation to pay the deposit; a draft purchase/sale
    agreement sent to NJC by Pacific on August 6 maintained the August
    2 deposit requirement.    In the meantime, seeking to salvage the
    sale and to transfer the boat to the United States before the
    typhoon season, Pacific notified NJC on August 8 that the boat
    would depart Guam on August 13.   According to the terms of the July
    26 contract and the August 6 draft purchase/sale agreement, NJC was
    obligated to deposit another $35,000 in Pacific’s bank account
    within three days of being notified of the intent to sail from
    Guam.    NJC failed to make that payment.
    Pacific persisted in demanding that NJC make the required
    deposits, and continued to move the boat across the Pacific in
    hopes of salvaging the sale.    One day prior to the arrival of the
    boat in Los Angeles, Pacific informed NJC by fax that it would
    allow prospective buyers to inspect the boat there.2    Pacific sold
    another boat in Los Angeles that NJC had contracted to purchase and
    informed NJC by fax on October 8 that it was moving the FRANCES J
    2
    NJC claimed to have not received the fax transmission.
    3
    on to Balboa, Panama.3    Having received no response from NJC after
    September 23, Pacific did not contact NJC when the boat arrived in
    Balboa.   Instead, Pacific moved the boat through the Panama Canal
    to New Orleans and sold it to an alternate buyer for the reduced
    price of $527,000.     NJC never received financing approval for the
    sale and never made any of the deposits required by the contract.
    II.   Analysis
    A.    Contract modification and waiver
    We review the grant of summary judgment de novo, employing the
    same standards used by the district court.         Alton Ochsner Med.
    Found. v. Allendale Mut. Ins. Co., 
    219 F.3d 501
    , 504 (5th Cir.
    2000).
    This dispute is governed by the UCC, as adopted by Guam.
    According to section 2201 of the Guam UCC, for a contract for the
    sale of a good more than $500 in value to be enforceable, it must
    be in writing and signed by the party against whom its enforcement
    is being sought.     13 GUAM CODE ANN. § 2201(1) (2000).   Section 2209
    provides that a modification must also be in writing when the sale
    price as modified exceeds the $500 threshold of Section 2201.       Id.
    § 2209(3).   The section also provides, however, that:
    Although an attempt at modification or rescission does
    not satisfy the requirements of subdivision (2) or (3),
    it can operate as a waiver.... A party who has made a
    3
    NJC again claimed that it did not receive the fax
    transmission.
    4
    waiver affecting an executory portion of the contract may
    retract the waiver by reasonable notification received by
    the other party that strict performance will be required
    of any term waived, unless the retraction would be unjust
    in view of a material change of position in reliance on
    the waiver.
    Id. § 2209(4) and (5).
    NJC argues that Pacific’s performance of the contract by
    moving the boat across the ocean to Balboa, despite the lack of
    advance payments by NJC, in effect modified the contract to not
    include the advance deposit requirements.                According to the above-
    quoted sections of the Guam UCC, however, such a modification was
    required to be in writing.4          NJC is unable to identify any writings
    that are modifications of the contract.              Indeed, the only writings
    of record from Pacific to NJC indicate the opposite; Pacific’s
    communications demanding that the deposits be made as required by
    the contract, and the purchase/sale agreement of August 6 referring
    to the advance deposit requirements of the July 26 contract, all
    indicate that the contract had not been modified.
    NJC next argues that Pacific’s movement of the boat across the
    ocean     despite   NJC’s    nonpayment      of    the     deposits     were   actions
    constituting an attempted modification and were therefore a waiver
    of the advance deposit requirements in the contract, according to
    Guam UCC section 2209(4).           Courts interpreting this section of the
    UCC   have    reasoned      that,   because       waiver    is   “the    intentional
    4
    This is true whether the value is calculated as the value
    of the full contract–$700,000–or the value of the deposits
    affected by the alleged modification–$70,000.
    5
    relinquishment of a right,” waiver must be proven either by showing
    that the actions were so unequivocal that they induced reliance on
    the alleged waiver by the other party or the waiver must be
    “clearly inferable from the circumstances.”                Bank v. Truck Ins.
    Exchange, 
    51 F.3d 736
    , 739 (7th Cir. 1995); see also American Suzuki
    Motor Corp. v. Bill Kummer, Inc., 
    65 F.3d 1381
    , 1387 (7th Cir. 1995)
    (finding that actions evidencing a waiver must be “unequivocal,”
    and that a waiver can only occur if the other party “reasonably
    relied” on it).          The attorney for Pacific testified that he
    directed the movement of the boat across the ocean to make it
    available to a market before the Pacific typhoon season, but also
    in   hopes   of    salvaging     Pacific’s      contract    with   NJC.      His
    communications with NJC consistently noted NJC’s failure to make
    the advance deposits, demanded that the payments be made, and asked
    NJC to inform Pacific why the payments had not been made.                  These
    actions   did     not   constitute     an    unequivocal   relinquishment     of
    Pacific’s    right      to   collect   the    advance   deposit    of   $70,000;
    therefore, they cannot be construed as an “attempted modification”
    and waiver of Pacific’s right to the advance deposits.                  Moreover,
    NJC fails to point to any disadvantage it suffered from reliance on
    Pacific’s movement of the boat across the ocean despite NJC’s
    default upon the advance deposits.               NJC was unable to secure
    financing, so it did not incur debt in an attempt to complete the
    purchase.       Because NJC failed to provide proof from which a
    6
    reasonable     trier   of   facts   could      have   found     an   attempted
    modification or detrimental reliance, we conclude that the district
    court was correct in granting summary judgment to Pacific.
    B.   Mitigation of damages
    In reviewing a trial court’s instructions to the jury, we
    reverse only “[i]f the charge as a whole leaves us with substantial
    and ineradicable doubt whether the jury has been properly guided in
    its deliberations.”     McCullough v. Beech Aircraft Corp., 
    587 F.2d 754
    , 759 (5th Cir. 1979).
    The district court instructed the jury that Pacific was
    obliged to give NJC reasonable notice of its intent to resell the
    FRANCES J and to act in good faith and in a commercially reasonable
    manner.   These instructions are in accord with the seller’s duty
    when reselling a good under the Guam UCC.                13 GUAM CODE ANN. §
    2706(1) (2000) (“Where the resale is made in good faith and in a
    commercially    reasonable    manner     the    seller    may    recover   the
    difference between the resale price and the contract price together
    with any incidental damages allowed under the provisions of this
    division (Section 2710), but less expenses saved in consequence of
    the buyer’s breach.”).      The seller’s damages in case of breach are
    reduced, or mitigated, by the amount of a resale conducted in good
    faith and in a commercially reasonable manner.             See id.     Section
    2706(1)   encompasses   the   seller’s    requirement     to    mitigate   his
    7
    damages under the UCC.           See 5 ROBERT L. HAIG, BUSINESS & COMMERCIAL
    LITIGATION   IN   FEDERAL COURTS § 74.8, at 704 (1998) (observing that
    “[t]he[] terms [of UCC § 2-706(1)] require seller to mitigate
    damages wherever possible”). NJC failed to show that Pacific could
    have taken any additional mitigating action consistent with the
    UCC.   Therefore, we find that the jury instruction here adequately
    informed     the    jury   of   Pacific’s    duty   to   mitigate.    To     have
    instructed the jury as to an additional mitigation duty would have
    been redundant and possibly misleading.             In any event, under the
    circumstances of the present case, the lack of an additional
    instruction       on   mitigation   does    not   create   a   substantial   and
    ineradicable doubt that the jury was misled.               See, e.g., Beckman
    Cotton Co. v. First Nat’l Bank of Atlanta, 
    666 F.2d 181
    , 183-84 (5th
    Cir. 1982) (measuring the duty to mitigate by the UCC’s commercial
    reasonableness standard).
    III. Conclusion
    For the foregoing reasons, we AFFIRM the district court’s
    grant of summary judgment in favor of Pacific and against NJC on
    the issue of liability for breach of contract and fraud and AFFIRM
    the district court’s final judgment awarding damages to Pacific.
    8