Kiewit Offshore Services, LTD v. Dresser-Rand Glob ( 2018 )


Menu:
  •      Case: 17-20438      Document: 00514671684         Page: 1    Date Filed: 10/08/2018
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    No. 17-20438                    United States Court of Appeals
    Fifth Circuit
    FILED
    October 8, 2018
    KIEWIT OFFSHORE SERVICES, LIMITED,
    Lyle W. Cayce
    Plaintiff - Appellee                                           Clerk
    v.
    DRESSER-RAND GLOBAL SERVICES, INCORPORATED,
    Defendant - Appellant
    Appeal from the United States District Court
    for the Southern District of Texas
    USDC No. 4:15-CV-1299
    Before HIGGINBOTHAM, DENNIS, and COSTA, Circuit Judges.
    PER CURIAM:*
    This case involves a dispute between two contracting parties about
    whether one must pay the other approximately $10 million. Dresser-Rand
    Global Services, Inc. (Dresser-Rand) contends that Kiewit Offshore Services,
    Ltd. (Kiewit) changed the contract’s scope of work without complying with the
    contract’s required procedures and is therefore not entitled to payment from
    Dresser-Rand for work reflected in several invoices. The district court granted
    * Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH
    CIR. R. 47.5.4.
    Case: 17-20438       Document: 00514671684       Page: 2   Date Filed: 10/08/2018
    No. 17-20438
    summary judgment in favor of Kiewit. Dresser-Rand appealed. Because we
    conclude the district court correctly held that there were no genuine fact issues
    and Kiewit was entitled judgment as a matter of law, we AFFIRM.
    I
    In 2012, Dresser-Rand solicited a bid from Kiewit to design, engineer,
    and fabricate two large litoral compression modules, ultimately for use by
    Dresser-Rand’s customer, PEMEX Exploration and Production (PEMEX), on
    an existing offshore oil-drilling platform in the Gulf of Mexico. 1 Dresser-Rand
    accepted Kiewit’s bid and, in 2013, the parties entered into a contract. Kiewit
    subcontracted separately with Excel Engineering (Excel) to assist with
    engineering the modules. The completed modules were delivered to Dresser-
    Rand in 2014, and Dresser-Rand accepted them.
    Several provisions of Dresser-Rand’s contract with Kiewit are relevant
    on appeal. Appendix E to the contract set forth the contract’s “scope of work”
    for equipment and services. Article 303 required the parties to propose change
    orders for any changes to the contract’s scope of work. Appendix A set forth
    the completion date, contract price, payment schedule, and notes regarding
    reimbursement procedures. Article 701 of Appendix A set forth a total “target
    estimate” of the contract price before any change orders of $27,271,336. The
    same article also set forth documentation and timekeeping requirements for
    work compensated by reimbursable rates.                The contract contained no
    maximum or “not-to-exceed” price.
    Kiewit submitted eight invoices to Dresser-Rand, reflecting a total price
    of $42,792,860.      Dresser-Rand paid the first four invoices, which totaled
    $33,265,588, but refused to pay the remaining four invoices, DR-04b, 05, 06,
    and 07, totaling $9,486,588. The parties agree that Kiewit did not submit any
    1   Kiewit was not a party to the agreement between Dresser-Rand and PEMEX.
    2
    Case: 17-20438      Document: 00514671684       Page: 3    Date Filed: 10/08/2018
    No. 17-20438
    change orders for work reflected in Invoices DR-04b, 05, and 06, which are the
    subject of this appeal. 2
    In May 2015, Kiewit filed suit against Dresser-Rand, alleging breach of
    contract,   promissory      estoppel,   and    unjust   enrichment     and    seeking
    compensatory damages in the amount listed in the remaining four invoices.
    Dresser-Rand counter-claimed, alleging breach of contract and seeking to
    recover over $2.3 million in damages, including liquidated damages assessed
    to Dresser-Rand by PEMEX for late delivery of the modules. The parties cross-
    moved for summary judgment, and the district court granted Kiewit’s motion,
    dismissing all of Dresser-Rand’s counterclaims and awarding Kiewit damages
    for nonpayment of Invoices DR-04b, 05, and 06.
    II
    We review a district court’s grant of summary judgment de novo. Howell
    v. Town of Ball, 
    827 F.3d 515
    , 521 (5th Cir. 2016). Summary judgment is
    appropriate where “there is no genuine dispute as to any material fact and the
    movant is entitled to judgment as a matter of law.” FED. R. CIV. P. 56(a). The
    function of the judge at the summary judgment stage is not to weigh the
    evidence and determine the truth of the matter, but to determine whether
    there is a genuine issue for trial. Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    ,
    249 (1986). A genuine dispute of material fact exists when, based on the
    evidence, “a reasonable jury could return a verdict for the nonmoving party.”
    Id. at 248. The non-movant’s evidence “is to be believed, and all justifiable
    inferences are to be drawn in his favor.” Id. at 255. We may affirm a district
    court’s grant of summary judgment on any ground supported by the record and
    raised below. See Windham v. Harris Cty., 
    875 F.3d 229
    , 234 (5th Cir. 2017).
    2 Invoice DR-07, totaling $41,031, was the subject of a separate summary judgment
    motion. Dresser-Rand does not appeal the district court’s order as to DR-07.
    3
    Case: 17-20438      Document: 00514671684    Page: 4   Date Filed: 10/08/2018
    No. 17-20438
    A party asserting a genuine factual dispute must support that “assertion
    by citing to particular parts of materials in the record.”       FED. R. CIV. P.
    56(c)(1)(A).     “If the evidence is merely colorable, or is not significantly
    probative, summary judgment may be granted.” Anderson, 477 U.S. at 249–
    50 (internal citations omitted). Conclusional allegations are insufficient to
    defeat a motion for summary judgment. Rushing v. Kan. City S. Ry. Co., 
    185 F.3d 496
    , 513 (5th Cir. 1999). Nor can the non-moving party satisfy its burden
    by establishing “some metaphysical doubt as to the material facts,” or by
    putting forth “unsubstantiated assertions” or a “scintilla” of evidence. Little v.
    Liquid Air Corp., 
    37 F.3d 1069
    , 1075 (5th Cir. 1994) (internal citations
    omitted).      In deciding issues of contractual interpretation, we “apply the
    contract law of the particular state that governs the agreement,” which the
    parties here agree is Texas. Al Rushaid v. Nat’l Oilwell Varco, Inc., 
    757 F.3d 416
    , 419 (5th Cir. 2014) (quoting Wash. Mut. Fin. Grp., LLC v. Bailey, 
    364 F.3d 260
    , 264 (5th Cir. 2004)).
    III
    The district court determined that “it is undisputed that Kiewit did not
    submit [c]hange [o]rders for the work reflected in Invoices DR-04B, 05, and 06
    and that the invoices accurately reflect the costs Kiewit incurred.”
    Accordingly, the court proceeded to consider a single question: whether the
    costs reflected in the invoices constituted a change in the contract’s “scope of
    work” such that Kiewit was required to submit a change order pursuant to
    Article 303 of the contract. Finding that Dresser-Rand’s summary judgment
    evidence was insufficient to establish any changes to the contract’s scope of
    work, the court denied Dresser-Rand’s motion for summary judgment with
    4
    Case: 17-20438     Document: 00514671684    Page: 5   Date Filed: 10/08/2018
    No. 17-20438
    respect to the invoices, and granted Kiewit’s corresponding motion for
    summary judgment.
    On appeal, Dresser-Rand raises three arguments that the district court
    erred by granting summary judgment in favor of Kiewit. First, that it raised
    a genuine issue of material fact that Kiewit changed the contract’s scope of
    work by building modules with three decks instead of two. Second, that Kiewit
    did not comply with the contract’s condition precedent to repayment. Third,
    that Kiewit submitted insufficient, conclusory summaries of the work
    underlying the invoices, preventing the district court from determining how
    Kiewit derived its damages claim. We address each of these arguments in turn.
    A
    Dresser-Rand first contends that the district court improperly
    disregarded summary judgment evidence that it claims raised a genuine fact
    issue as to whether Kiewit changed the contract’s scope of work without
    complying with Article 303.    Dresser-Rand specifically argues that Kiewit
    created two non-identical, three-deck modules, even though the contract’s
    scope-of-work provision specified that the two modules should be identical and
    have two decks.      In response, Kiewit argues that no change orders were
    necessary because the increased costs in the invoices were reflective of changes
    within the original scope of work resulting from substantial design evolution,
    and therefore did not constitute changes to the contract’s overall scope.
    According to Kiewit, the contract’s scope, as defined in Appendix E, was a
    “black box,” granting it broad discretion to design and engineer the modules,
    so long as it incorporated certain performance requirements provided by
    PEMEX. For the following reasons, we find Kiewit’s arguments persuasive
    and affirm the district court’s judgment.
    It is indisputable that Kiewit ultimately furnished modules with three
    decks. However, on the plain language of the contract, it is ambiguous whether
    5
    Case: 17-20438      Document: 00514671684        Page: 6     Date Filed: 10/08/2018
    No. 17-20438
    this constituted a change to the contract’s scope of work. 3 In construing a
    written contract, Texas courts first attempt to determine the parties’ true
    intentions as expressed in the instrument. Valence Operating Co. v. Dorsett,
    
    164 S.W.3d 656
    , 662 (Tex. 2005). Texas courts consider a contract in its
    entirety, harmonizing and giving effect to all provisions and rendering none
    meaningless. Id. Extraneous evidence may be considered to determine the
    true meaning of the contract only if the contract is ambiguous. David J. Sacks,
    P.C. v. Haden, 
    266 S.W.3d 447
    , 450–51 (Tex. 2008) (citing Nat’l Union Fire Ins.
    Co. v. CBI Indus., Inc., 
    907 S.W.2d 517
    , 520 (Tex. 1995)). “Whether a contract
    is ambiguous is a question of law that must be decided by examining the
    contract as a whole in light of the circumstances present when the contract was
    entered.” Columbia Gas Transmission Corp. v. New Ulm Gas, Ltd., 
    940 S.W.2d 587
    , 589 (Tex. 1996). If a contract, on its face, can be given a “definite certain
    legal meaning,” courts may not look to extrinsic evidence to render it
    ambiguous. EOG Res., Inc. v. Killam Oil Co., 
    239 S.W.3d 293
    , 298 (Tex. App.
    2007).    Ambiguity exists where “the contract is subject to two or more
    reasonable interpretations after applying the pertinent rules of construction.”
    Columbia Gas Transmission Corp., 940 S.W.2d at 589.
    Article 303 of the contract states that Kiewit must submit a change order
    to Dresser-Rand for any change to the contract’s scope of work:
    At any time during the progress of the Work, either Company or
    Contractor may propose Change Orders. . . . Contractor shall be
    entitled to a Change Order making necessary and reasonable
    adjustments to the Contract Price . . . solely and to the extent
    reasonably necessary resulting from impacts to the Work resulting
    3 Neither party claims on appeal that the contract is ambiguous; indeed, both parties
    consistently maintained that it was unambiguous below. However, “even when both parties
    agree that their contract is unambiguous and merely disagree as to its unambiguous
    meaning, [we] may independently conclude that the contract is ambiguous.” 14 TEX. JUR. 3D
    CONTRACTS § 229 (2018) (citing Plotkin v. Joekel, 
    304 S.W.3d 455
     (Tex. App. 2009)).
    6
    Case: 17-20438       Document: 00514671684         Page: 7    Date Filed: 10/08/2018
    No. 17-20438
    from events beyond Contractor’s control including without
    limitation: Changes in the Scope of Work.
    Additionally, Dresser-Rand is correct that Appendix E, setting forth the
    contract’s scope of work, refers generally to a “2 deck module.” 4 However,
    Appendix E also states that “the module(s) layout will be set by control
    parameters,” including allowable space, safety and allowances for exit access,
    construction, maintenance, operation, weight restrictions, and third-party
    certification. Additionally, the scope-of-work provision specifies that “[t]he
    ultimate goal of the module layout is to minimize space and weight
    requirements        without      compromising         on     safety,     constructability,
    maintainability and operability.” Viewed in its entirety, Appendix E’s plain
    language could reasonably support two different readings: the first, that
    Kiewit was required to build modules with two decks; the second, that the
    layout of the modules, including the number of decks per module, was flexible
    and intended ultimately to yield to other considerations if necessary. See
    Valence Operating Co., 164 S.W.3d at 662. Thus, the plain language of the
    contract does not definitively answer whether, by designing and building
    modules with three decks instead of two, Kiewit changed the contract’s scope
    of work and was therefore required to comply with Article 303’s change-order
    requirement.
    The circumstances existing at the time the parties entered into the
    contract do not clarify this ambiguity. See Columbia Gas Transmission Corp.,
    940 S.W.2d at 589; Kachina Pipeline Co. v. Lillis, 
    471 S.W.3d 445
    , 450 (Tex.
    2015) (considering “the commercial or other setting in which the contract was
    negotiated and other objectively determinable factors that give context to the
    parties’ transaction” to determine whether a contract is ambiguous) (quoting
    4We have not found similar support within Appendix E for Dresser-Rand’s contention
    that Kiewit changed the contract’s scope of work by building modules that were not identical.
    7
    Case: 17-20438       Document: 00514671684         Page: 8     Date Filed: 10/08/2018
    No. 17-20438
    Americo Life, Inc. v. Myer, 
    440 S.W.3d 18
    , 22 (Tex. 2014)). Stephen Shupak,
    Commercial Support Director for Dresser-Rand, testified that PEMEX,
    Dresser-Rand’s customer that would ultimately use the modules, provided a
    “performance spec” focused on module output and that the contract
    consequently left the design of the modules to Kiewit. Dresser-Rand’s General
    Projects Manager, Daniel Simpson, similarly stated that Kiewit had discretion
    to design the modules if they complied with end-game performance
    requirements and “the basic data sheet spec” provided by PEMEX, detailing
    the “material to use on the internals of the compressors, the pressures you’re
    dealing with, that kind of thing.” Likewise, Jerry Walker, Dresser-Rand’s
    Executive Vice President, testified that PEMEX provided “a very open-ended
    spec . . . we referred to it as kind of a black box. It allowed the fabricator to do
    what it needed to have a—more of a functional performance.” Such evidence
    could reasonably support a conclusion that the contract’s scope of work focused
    primarily on Kiewit meeting PEMEX’s performance expectations, rather than
    the specific design of the modules. Even so, this does not preclude a conclusion
    that Kiewit was required to submit a change order to Dresser-Rand before
    altering the number of decks per module.               Because we conclude that the
    contract is ambiguous in this respect, we examine extrinsic evidence to
    determine the parties’ intention. See Haden, 266 S.W.3d at 450–51.
    Considering all relevant evidence in the summary judgment record, 5 we
    conclude that the district court was correct to hold that no reasonable jury
    5  The bulk of Dresser-Rand’s summary judgment evidence consists of documents
    referencing changes to Excel’s scope of work. We agree with the district court that “‘Scope of
    Work’ is a defined term with a particular meaning” within each contract. Excel’s subcontract
    with Kiewit contained a distinct “scope of work” provision with a proposal for basic and
    detailed engineering and design, including a multi-page list of specific design deliverables.
    The subcontract also broadly required “an approved change order” for “[a]ny and all changes
    to th[e] Agreement.” Thus, changes to Excel’s detailed engineering and design proposal, as
    outlined in the subcontract, were not necessarily indicative of changes to the scope of work
    8
    Case: 17-20438      Document: 00514671684         Page: 9    Date Filed: 10/08/2018
    No. 17-20438
    could find that Kiewit’s design and construction of the modules constituted a
    change in the contract’s scope of work, and Kiewit was entitled to summary
    judgment. See Jhaver v. Zapata Off-Shore Co., 
    903 F.2d 381
    , 384 (5th Cir.
    1990) (recognizing that summary judgment is appropriate if extrinsic evidence
    of the parties’ intent does not present a genuine issue of material fact); see also
    United States v. Tracts 31a, Lots 31 & 32, 
    852 F.3d 385
    , 390 n.5 (5th Cir. 2017)
    (citing Jhaver for the same proposition). Extrinsic evidence supports Kiewit’s
    argument that the increased costs in Invoices DR-04b, 05, and 06 reflected
    design changes within the original scope of work. Simpson testified that the
    original scope of the project was “two compression modules” and “the scope of
    supply didn’t change.” He also stated that what Dresser-Rand balked at was
    not a scope change, but rather the number of hours Kiewit took to complete the
    modules:
    Effectively, we contracted to build two modules. You know, we had
    two modules that were built. It wasn’t like there was extra
    compression—compression put in and extra scrubbers and extra
    lube oil consoles. The scope did not materially change, but yet
    engineering spent three times more money engineering the module
    than what they were contracted to do in the beginning. . . . The
    item—the issue is not with the scope of what they produced. The
    issue is with the amount of hours and what they charged to
    produce it. That’s the issue that we have.
    Significantly, Kenneth DeVito, Dresser-Rand’s Project Manager, testified that
    Kiewit was not required to submit change orders for increased costs,
    quantities, or manhours incurred during Kiewit’s performance of the original
    scope of work. Thus, the record demonstrates that Dresser-Rand understood
    Kiewit’s scope of work to comprise building two compression modules that
    set forth in Appendix E. Dresser-Rand’s assertion that “a scope change for Excel has to be a
    scope change for Kiewit” is “conclusory,” “unsubstantiated,” and thus insufficient to defeat
    summary judgment. See Rushing, 185 F.3d at 513; Little, 37 F.3d at 1075.
    9
    Case: 17-20438       Document: 00514671684        Page: 10    Date Filed: 10/08/2018
    No. 17-20438
    complied with the general performance requirements specified in the contract.
    The increased costs above the contract’s target estimate for building the
    modules, which resulted from Kiewit’s evolving design process, thus did not
    require Kiewit to request a change order under Article 303. 6 Though Dresser-
    Rand undoubtedly came to owe Kiewit more than it expected it would, we agree
    with the district court that Dresser-Rand assumed the risk of the increased
    costs reflected in the invoices by failing to include a limiting, “not-to-exceed”
    price in the contract.
    Dresser-Rand’s most compelling evidence that there was a scope
    change—the language in Appendix E referring to a two-deck module—is
    “merely colorable” and “is not significantly probative,” in light of the parties’
    intent that Kiewit should have broad design discretion. See Anderson, 477 U.S.
    at 249–50.     Because Dresser-Rand has failed to raise a genuine issue of
    material fact that the costs reflected in the invoices were for work outside of
    the contract’s original scope of work, Kiewit was entitled to summary
    judgment.
    B
    Dresser-Rand next contends that Article 701 of Appendix A to the
    contract required Kiewit to receive advanced authorization from Dresser-Rand
    as a condition precedent to repayment for all reimbursable rates-driven scope
    work. Under Texas law, a condition precedent requires that an event occur or
    be performed before a right accrues and can be enforced. Centex Corp. v.
    Dalton, 
    840 S.W.2d 952
    , 956 (Tex. 1992). Whether a condition exists, rather
    than a covenant or promise, must be gathered from the contract as a whole and
    6  By contrast, the parties executed a change order when Dresser-Rand asked Kiewit
    to provide engineering analysis related to PEMEX’s decision to use a different lift-rigging
    system for setting the modules than originally planned. Because analysis for the new lift-
    rigging system fell outside of Kiewit’s original scope of work under the contract, a change
    order was necessary.
    10
    Case: 17-20438    Document: 00514671684      Page: 11   Date Filed: 10/08/2018
    No. 17-20438
    from the intent of the parties. Citizens Nat’l Bank v. Tex. & Pac. Ry. Co., 
    150 S.W.2d 1003
     (Tex. 1941). Conditions precedent are normally created through
    use of language such as “if,” “provided that,” “on condition that,” or other
    similar conditional phrases. Criswell v. European Crossroads Shopping Ctr.,
    Ltd., 
    792 S.W.2d 945
    , 948 (Tex. 1990). While the inclusion of such language is
    not necessary, its absence is probative of an intent to make a promise, rather
    than impose a condition, and the terms will be construed as a covenant to
    prevent unfairness from nonpayment for completed work. Id. Courts avoid
    finding a condition precedent where another reasonable reading of the contract
    is possible, where the intent of the parties is doubtful, or where a condition
    would impose an absurd or impossible result. Schwarz-Jordan, Inc. v. Delisle
    Constr., 
    569 S.W.2d 878
    , 881 (Tex. 1978); Hohenberg Bros. v. George E. Gibbons
    & Co., 
    537 S.W.2d 1
    , 3 (Tex. 1976). Texas courts do not favor conditions due to
    “their harshness in operation.” Sirtex Oil Indus. v. Erigan, 
    403 S.W.2d 784
    ,
    787 (Tex. 1966).
    In Dresser-Rand and Kiewit’s contract, Article 701, Note (v) to Appendix
    A states:
    Amounts for work compensated by Reimbursable Rates are
    factored into the milestone payments and shall be spread
    throughout multiple milestones. Reimbursable Rates-driven scope
    will be supported by weekly time sheets/time sheet summaries,
    each authorized in advance by Company and confirmed as
    accepted for payment by signature of a duly authorized Company
    representative.
    The plain language of Article 701, Note (v) uses imperatives such as “shall”
    and “will” instead of the conditional language traditionally associated with the
    creation of conditions precedent, suggesting that the parties intended to make
    a promise. See Criswell, 792 S.W.2d at 948. Moreover, the contract as a whole
    appears to support this interpretation; other provisions of the contract employ
    explicitly conditional language, suggesting that Dresser-Rand knew how to
    11
    Case: 17-20438       Document: 00514671684          Page: 12     Date Filed: 10/08/2018
    No. 17-20438
    create a condition precedent and chose not to do so in Article 701. Accordingly,
    we construe Article 701 as a covenant and not a condition precedent. See
    Schwarz-Jordan, Inc., 569 S.W.2d at 881. Doing so is in line with Texas courts’
    aversion to finding conditions precedent and avoids an unfair result here, as
    Kiewit completed the work reflected in the invoices and Dresser-Rand accepted
    it. See Sirtex Oil Indus., 403 S.W.2d at 787; Criswell, 792 S.W.2d at 948.
    C
    Finally, Dresser-Rand contends, for the first time on appeal, that Kiewit
    submitted insufficient, conclusory summaries of the work reflected in Invoices
    DR-04b, 05, and 06, preventing the district court from verifying the total
    amount of damages Kiewit claimed.                  Dresser-Rand failed to raise this
    argument below, and we therefore decline to consider it here. 7 See Vogel v.
    Veneman, 
    276 F.3d 729
    , 733 (5th Cir. 2002) (“Except in cases of extraordinary
    circumstances, we do not consider issues raised for the first time on appeal.”)
    (internal quotations and citations omitted); AG Acceptance Corp. v. Veigel, 
    564 F.3d 695
    , 700 (5th Cir. 2009) (“Extraordinary circumstances exist when the
    issue involved is a pure question of law and a miscarriage of justice would
    result from our failure to consider it.”) (internal quotations and citations
    omitted).
    ***
    For these reasons, we AFFIRM the district court’s judgment.
    7 The district court noted that it was undisputed that the invoices accurately reflected
    actual costs incurred by Kiewit for work performed and accepted by Dresser-Rand.
    12