Developers Surety and Indemnity v. Renaissance/Valley Farms, LLC , 614 F. App'x 805 ( 2015 )


Menu:
  •                 NOT RECOMMENDED FOR FULL-TEXT PUBLICATION
    File Name: 15a0400n.06
    Case No. 14-6400
    FILED
    UNITED STATES COURT OF APPEALS                        Jun 02, 2015
    FOR THE SIXTH CIRCUIT                        DEBORAH S. HUNT, Clerk
    RENAISSANCE/VALLEY FARMS, LLC,                       )
    DKCD, INC., & DONALD J. COOK,                        )
    )
    Plaintiffs-Appellants,
    )       ON APPEAL FROM THE
    )       UNITED STATES DISTRICT
    v.
    )       COURT FOR THE WESTERN
    )       DISTRICT OF KENTUCKY
    T&C CONTRACTING, INC.,
    )
    )
    Defendant-Appellee.
    )
    )                 OPINION
    BEFORE: McKEAGUE and DONALD, Circuit Judges; MATTICE, District Judge.
    MATTICE, District Judge. Renaissance/Valley Farms, LLC, DKCD, Inc., and Donald
    J. Cook (hereinafter, “Appellants” or “the Renaissance parties”) raised claims under Kentucky
    law for breach of contract, negligence, and contractual and common law indemnity against T&C
    Contracting, Inc., (hereinafter, “T&C” or “Appellee”) arising out of T&C’s subcontract with
    DKCD to perform certain roadway construction work. On cross motions for summary judgment,
    the district court denied the motion of the Renaissance parties and granted T&C’s motion as to
    all claims against T&C. The Renaissance parties timely appealed, and we now affirm the district
    court’s decision.
    
    The Honorable Harry S. Mattice, Jr., District Judge of the United States District Court
    for the Eastern District of Tennessee, sitting by designation.
    I. Background
    Although the procedural history of this action is complex, this matter comes before this
    Court solely for a review of the district court’s judgment as to Appellants’ claims against
    Appellee for breach of contract, negligence, and indemnification. The parties did not below, and
    do not now, dispute the vast majority of the basic facts underlying this action.
    In 2004, Renaissance/Valley Farms, LLC (hereinafter, “R/V”) commenced construction
    of a subdivision on the north side of Valley Station Road in Louisville, Kentucky. The project
    required certain road construction to be completed in order to accommodate the increase in
    traffic that would stem from the new subdivision, including the widening of a curved stretch of
    Valley Station Road and the construction of additional lanes of traffic. R/V – the “owner” of the
    project – contracted with DKCD, Inc., doing business as Renaissance Development, to serve as
    construction manager of the project (hereinafter, the “original contract”).1                DKCD retained
    Heritage Engineering, LLC to prepare engineering plans for the roadway construction project.
    Because Valley Station Road is a state-owned right of way that is under the control of the
    Kentucky Transportation Cabinet (hereinafter, “KYTC”), R/V was required to apply for an
    encroachment permit in order to perform construction on the roadway.                     R/V submitted its
    application for such a permit, including the initial engineering site design plan prepared by
    Heritage (hereinafter, the “original plan”). In February 2005, the KYTC issued an encroachment
    permit to R/V to complete the construction as requested. The permit states:
    THE PERMITTEE AGREES THAT ALL WORK WITHIN THE EXISTING
    RIGHT-OF-WAY SHALL BE DONE IN ACCORDANCE WITH THE PLANS
    AS APPROVED AND PERMITTED BY AN ENCROACHMENT PERMIT.
    ANY CHANGES OR VARIANCES MADE AT THE TIME OF
    CONSTRUCTION WITHOUT WRITTEN APPROVAL FROM THE
    DEPARTMENT OF HIGHWAYS SHALL BE REMOVED BY THE
    1
    Donald J. Cook is the principal and manager of R/V and the principal and president of DKCD. Where appropriate,
    R/V, DKCD, and Cook will collectively be referred to as “the Renaissance parties” and “Appellants.”
    -2-
    PERMITTEE AT NO EXPENSE TO THE DEPARTMENT OF HIGHWAYS
    AND SHALL BE REDONE TO CONFORM WITH THE APPROVED PLANS.
    The permit incorporates by reference the May 26, 2004 design plan prepared by Heritage, and
    states that “[t]he permittee agrees as a condition to the issuance of the permit to construct and
    maintain such facilities in accordance with said plan . . . .”
    Steven Tucker, the engineer with KYTC who approved of R/V’s encroachment permit,
    confirmed that KYTC would have to review any revisions to plans upon which a permit had been
    issued before such revised plans could be used to construct or complete a project. Tucker
    confirmed that such revisions are done by the engineer or the permittee, not by the construction
    company.2
    In August 2005, DKCD entered into a subcontract with T&C to perform the construction
    work on Valley Station Road.3 The relevant portions of the subcontract are as follows:
    SECTION FOUR
    PERFORMANCE OF WORK
    A.      Subcontractor shall . . . perform all labor required for the completion of
    the above-described work in accordance with all provision of the original contract
    [between R/V and DKCD] and of the specifications, plans, and addenda referred
    to in the original contract, all of which are hereby made a part of this agreement,
    and to the satisfaction of owner and contractor.
    ...
    SECTION FOURTEEN
    CHANGES, EXTRA WORK, AND DISPUTES
    A.      Changes in Original Contract.        Construction Manager is not an
    insurer or guarantor of the work or any part of the work; of the performance by
    owner of the original contract; or of plans and specifications furnished by owner.
    2
    Tucker also testified that, when issuing such permits, the State does not “approve” of the specific plans; rather, the
    State reviews the plans and issues a permit if it appears that the plans meet state guidelines. Tucker stated that the
    State relies “strictly on the engineer” for the plan specifics, such as elevations.
    3
    The subcontract was apparently not signed until September 12, 2005; however, the “effective date” of the contract
    was August 25, 2005.
    -3-
    Subcontractor shall be bound by any changes or alterations made by owner to the
    original contract specifications or plans, or in the amount or character of the work
    or any part of the work, to the same extent that contractor is bound by any such
    change or alteration.
    B.      Notice of Change Order.      Subcontractor will be notified of any change
    order requested by or of owner with respect to subcontract work and will be
    consulted with respect to the proposed terms of any such change order, but
    subcontractor shall be bound by the terms of any change order negotiated in good
    faith by Construction Manager with owner. . . .
    ...
    SECTION TWENTY-FOUR
    SPECIAL PROVISIONS
    Subcontractors shall comply with all federal, state, territorial, and local codes and
    statutes of the area involved and shall indemnify Construction Manager against
    any and all claims or liens as a result of acts or omissions on part of subcontractor
    with respect to any noncompliance with such codes and statutes.
    It is undisputed that, at some point in 2005, Heritage prepared a revised site design plan
    for the Valley Station Road construction (hereinafter, “the revised plan”).4 Both the original and
    existing plans included a “typical section” providing for the road to be constructed with a cross
    slope of “2% minimum or continue existing grade” of the roadway. The revised plans also
    contained “spot elevations” that were to be used to grade the slope of the roadway construction
    because the drainage ditch would not allow for a continuous matching slope of the existing
    grade. It is undisputed that no one involved in the project – that is, the Renaissance parties,
    Heritage, or T&C – submitted the revised plans to the KYTC.
    4
    The timeline of these events is not entirely clear from a review of the record. It appears that T&C had an
    opportunity to review the original engineering plans prior to signing its subcontract. According to T&C’s president,
    Donald Thornberry, he reviewed the original site design plan and advised the Renaissance parties that those plans
    “would not work” due to the presence of a drainage ditch. The plans were then re-engineered by Heritage, and the
    revised plans were then given to T&C before it officially entered into its subcontract with DKCD.
    -4-
    According to T&C’s president, Donald Thornberry, Les Gatrost – the project
    superintendent appointed by the Renaissance parties – brought T&C a copy of the revised plans.5
    It is undisputed that T&C used the revised engineering plans, rather than the original plans, to
    complete the construction work on Valley Road Station. Gatrost was present on the site for the
    duration of the construction work “almost on a daily basis” as the construction representative for
    the Renaissance parties.
    T&C completed the construction as detailed in the revised plans prepared by Heritage.
    Specifically, it used the spot elevations specified in the revised plans – rather than the typical
    section regarding slope included in both the original and revised plans – to construct the
    roadway. The typical section is the default for construction work. However, where more
    specific instructions – such as spot elevations – are provided, the specific instructions will
    supersede the typical section. As constructed using the spot elevations, the turning lane on
    Valley Station Road had a “break” in the slope, with a cross slope of approximately two percent,
    as compared to the other lanes which had slopes of approximately six percent. Heritage intended
    there to be such a break in order to account for a drainage ditch at the site and therefore designed
    its revised plans to have such slopes.
    However, when Tucker inspected the construction on behalf of KYTC upon its
    completion, he saw the break in the slope and immediately determined that the construction was
    not acceptable because it created a “flat lane going up against a superelevation.” On July 24,
    2008, KYTC issued an Encroachment Inspection notice to R/V, stating that KYTC was rejecting
    the roadway for several reasons, including that the turning lane did not have the correct cross
    5
    Below, the Renaissance parties generally disputed T&C’s contention that they had given the revised plans to T&C;
    however, the district court correctly found that the Renaissance parties failed to present any evidence to refute
    T&C’s evidence that Gatrost provided the revised plans to Thornberry on behalf of the Renaissance parties, and
    indeed, they have failed to point to any such contradictory evidence on appeal.
    -5-
    slope and that there was a “[d]angerous edge drop off” between the edge of the roadway and a
    paved ditch. Subsequently, remediation work was completed by another construction company
    in order to bring R/V into compliance with its encroachment permit.6
    After the Renaissance parties asserted their claims against T&C for breach of contract,
    negligence, and indemnification, T&C filed a motion for summary judgment before the district
    court. It argued that the work was not rejected due to any breach by T&C, but rather, because
    Renaissance failed to submit the revised plans to KYTC for approval; it further argued that the
    fact that the work was rejected is not proof that the work violated applicable codes and
    regulations. It argued that there was no breach of contract because its subcontract with DKCD
    required it to complete the construction in conformance with the plans designed by Heritage and
    provided by the Renaissance parties and because Renaissance supervised the construction project
    in conformance with the revised plans.            Similarly, it argued that it was not negligent in
    performing the construction work pursuant to the revised plans because Kentucky law indicates
    that a contractor will not be deemed negligent when it does work in compliance with the
    instructions given to it. Finally, T&C argued that there was no negligent act or omission on its
    part to trigger the indemnity clause of the contract.
    The Renaissance parties filed a cross motion for summary judgment, arguing that T&C
    was in breach of Section 24 of the subcontract because it agreed to accept “all risk of loss” in the
    event that its work did not comply with state codes or statutes, and KYTC’s inspection notice
    was proof that T&C’s work did not comply with all applicable codes and statutes. Specifically,
    they argued that T&C violated: (1) Section 177.106 of the Kentucky Revised Statutes (“KRS”)
    6
    The remediation work was completed upon payment from a bond secured from Developers Surety and Indemnity
    Company by DKCD. Developers commenced the underlying action in the district court; however, the Renaissance
    parties reached a settlement agreement with Developers in 2012, wherein they agreed to pay Developers damages
    and interest for Developers’ required performance under the surety bond.
    -6-
    by creating an encroachment that interfered “with the safe, convenient and continuous use and
    maintenance” of Valley Station Road; (2) 603 Ky. Admin. Reg. 5:150 (“KAR 5:150”) because
    the cross slope was below the acceptable cross-slope level as defined by the relevant engineering
    standards and incorporated by reference into Kentucky’s regulations; and (3) 603 Ky. Admin.
    Reg. 1:020 (“KAR 1:020”) because the work was not done as shown on the permits and
    approved plans. The Renaissance parties also argued that T&C was liable for negligence per se
    based on its violation of KRS 177.106(1).
    The district court found that T&C neither breached its subcontract nor acted negligently,
    and that it was not required to indemnify the Renaissance parties. The district court noted that
    the Renaissance parties had failed to present any evidence to contradict T&C’s evidence that it
    received the revised plans from Renaissance and constructed the roadway in accordance with
    those revised plans. The district court then found that T&C could not be found to have violated
    KRS § 177.106(1) because “the Renaissance Parties have not raised a genuine factual dispute as
    to whether T&C failed to remove an encroachment from the road in violation of the statutory
    language,” noting that R/V was the permit holder as discussed in the statute. It further noted that
    no court had ever “applied the statute to impose liability on a contractor engaged in road
    construction.” The district court similarly rejected the argument that T&C had violated KAR
    5:150, finding that any violation with respect to errors in the cross slope as constructed was
    attributable to “Heritage, the design engineer, or the Renaissance Parties, as the party who
    contracted with Heritage to design the plans.” The district court noted that the undisputed record
    evidence confirmed that contractors such as “T&C are expected to follow the engineering plans
    provided to them,” and that T&C fulfilled its duty “to construct the roadway according to the
    plans it received from the Renaissance parties”; it thus concluded that the Renaissance parties
    -7-
    had failed to create a “genuine factual dispute as to whether T&C was required to apply
    independent judgment or engineering principles in its construction of the road.” The district
    court then found no violation by T&C as to KAR 1:020, finding that T&C had no responsibility
    for submitting the revised plans to KYTC and that the responsibility for any violation of this
    subsection would lie with the permittee – R/V – or the engineer – Heritage. The district court
    further noted that T&C was required by its subcontract “to complete the roadwork in accordance
    with the plans and specifications provided by the Renaissance parties,” and that the Renaissance
    parties failed to present any evidence to contradict T&C’s evidence that it complied with this
    requirement. Because the Renaissance parties failed to create any issue of fact that T&C’s work
    “was substandard or technically unsound,” the district court concluded that any “deficiencies” in
    the construction work were “more appropriately attributed to the Renaissance Parties for failing
    to submit, or in not instructing Heritage to submit, the revised plans to the KYTC.” Finding no
    violation of codes or regulations on the part of T&C, the district court found that T&C was
    entitled to judgment as to the Renaissance parties’ claim for breach of contract.
    Based on these same findings, the district court concluded that the Renaissance parties
    failed to establish that T&C violated any statutes or regulations in order to establish negligence
    per se or that it breached the standard of care applicable to its performance under the
    subcontract. The district court accordingly found that T&C was also entitled to judgment as to
    the issue of negligence and that it was not required to indemnify the Renaissance parties for any
    loss, and it granted T&C’s motion for summary judgment and denied the motion for summary
    judgment filed by the Renaissance parties.
    -8-
    II. Standard of Review
    We review de novo the district court’s summary judgment determination, but we review
    “the court’s findings of specific facts for clear error.” Keck v. Graham Hotel Sys., 
    566 F.3d 634
    ,
    636 (6th Cir. 2009). Summary judgment is proper when, viewing the evidence in the light most
    favorable to the nonmoving party, “there is no genuine dispute as to any material fact and the
    movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a); Matsushita Elec.
    Indus. Co. v. Zenith Radio Corp., 
    475 U.S. 574
    , 587 (1986). If, however, sufficient probative
    evidence supports a claim that disputes over material facts remain, summary judgment is not
    appropriate, and the case must be resolved by a judge or jury at trial. Anderson v. Liberty Lobby,
    Inc., 
    477 U.S. 242
    , 248-49 (1986); see also White v. Wyndham Vacation Ownership, Inc.,
    
    617 F.3d 472
    , 475-76 (6th Cir. 2010). “We review cross motions for summary judgment under
    this standard as well, evaluating each motion on its own merits.” La Quinta Corp. v. Heartland
    Props., LLC, 
    603 F.3d 327
    , 335 (6th Cir. 2010).
    Questions of statutory interpretation are questions of law subject to de novo review.
    Vander Boegh v. EnergySolutions, Inc., 
    772 F.3d 1056
    , 1059 (6th Cir. 2014). In Kentucky, the
    interpretation of a contract is also a question of law subject to de novo review. Cogent Solutions
    Grp., LLC v. Hyalogic, LLC, 
    712 F.3d 305
    , 309 (6th Cir. 2013).
    III. Discussion
    On appeal, the Renaissance parties argue that the district court erred in finding that T&C
    did not violate the cited statutes and regulations and in finding that the construction work was
    rejected based on failure to comply with the original plans submitted to KYTC, rather than
    because the work performed by T&C was deficient and dangerous.7 The Renaissance parties
    7
    This Court may review the district court’s denial of a motion for summary judgment when the appeal from that
    denial “is presented together with an appeal from a grant.” McMullen v. Meijer, Inc., 
    355 F.3d 485
    , 489 (6th Cir.
    -9-
    argue for the first time that T&C also breached Section 4 of the subcontract by working from the
    revised plans, rather than from the “original” plans incorporated by reference into that Section;
    that is, Renaissance argues that T&C had an affirmative duty under [S]ections 4 and 24 of its
    subcontract “not to follow the [revised] plans.” Alternatively, they argue that, even if Section 4
    did require T&C to follow the revised plans, the doctrine of repugnant clauses required the
    district court to enforce “the more essential” provision of the contract – Section 24. They
    reassert their argument that T&C is liable for negligence per se based on its violation of the cited
    statutes and also argue that T&C was negligent in failing to recognize and/or to call to
    Appellants’ attention that “the plans from which it worked called for the creation of unsafe and
    dangerous conditions.”
    In response, T&C reiterates its position that it was bound by the subcontract to complete
    the construction work according to the revised plans provided by the Renaissance parties – either
    under Section 4 because the revised plans were the original set of plans given to T&C upon the
    signing of the subcontract or under Section 14(A) because that provision bound T&C to any
    revisions to the plans approved by the Renaissance parties. It further argues that the doctrine of
    repugnant clauses was not properly asserted by the Renaissance parties before the district court
    and is thus not properly before this Court. Regardless, T&C argues that the doctrine is not
    applicable in this case because Sections 4 and 24 are not inherently “repugnant” or, to the extent
    that they are, Section 24 is not more essential to the contract than Section 4. T&C also reasserts
    its arguments that: it lacked discretion or responsibility to reassess the engineering principles
    relied upon by Heritage in creating the revised plans; it was not negligent in performing its work
    pursuant to and in conformance with the revised plans; the Renaissance parties have failed to
    2004) (per curiam). Accordingly, the Appellants’ appeal is properly before this Court as to both the denial of their
    own motion for summary judgment and as to the grant of T&C’s Motion.
    - 10 -
    establish that any violation of statute or regulations led to their losses; and regardless, it does not
    bear the responsibility for any alleged violations of statutes or regulations.
    A. Breach of Contract
    The Court will first consider Appellants’ claim that T&C breached its subcontract. In
    Kentucky, the complaining party must establish the following three elements to prove a claim for
    breach of contract: (1) the existence of a contract; (2) breach of that contract; and (3) damages
    flowing from that breach. Metro. Louisville/Jefferson Cnty. Gov’t v. Abma, 
    326 S.W.3d 1
    , 8
    (Ky. Ct. App. 2009).
    Appellants pled their claim for breach of contract relying solely upon Section 24 of the
    subcontract, which provided that T&C “shall comply with all federal, state, territorial, and local
    codes and statutes of the area involved and shall indemnify Construction Manager against any
    and all claims or liens as a result of acts or omissions on part of subcontractor with respect to any
    noncompliance with such codes and statutes.” Appellants have repeatedly argued that the fact
    that T&C complied with the revised engineering plans is “irrelevant” to the consideration of
    whether T&C breached Section 24 of the subcontract. However, a contract “must be construed
    as a whole, giving effect to all parts and every word in it if possible.” City of Louisa v. Newland,
    
    705 S.W.2d 916
    , 919 (Ky. 1986); see also Ky. Spirit Health Plan, Inc. v. Commonwealth Fin. &
    Admin. Cabinet, Nos. 2013-CA-001050-MR, 2013-CA-001201-MR, 
    2015 WL 510852
    , at *4
    (Ky. Ct. App. Feb. 6, 2015) (“[W]e attempt to divine intent from the scope of the entire
    agreement, not by relying simply on individual terms or phrases examined in isolation.”). The
    Court thus rejects Appellants’ contention that Section 24 of the subcontract must be analyzed in
    a vacuum, without consideration to the parties’ complete set of obligations under the contract.
    - 11 -
    In this case, the Court’s de novo review of Appellants’ claim for breach of contract leads
    to the same conclusion reached by the district court: that T&C’s construction work on Valley
    Station Road did not constitute a breach of contract. Appellants first contend that T&C violated
    KRS § 177.106(1), which provides:
    Before any person shall proceed to cause or continue or allow to remain in
    existence any encroachment under, on or over any part of the right-of-way of a
    state highway he shall first obtain from the Department of Highways a permit so
    to do. Any encroachment heretofore or hereafter placed or allowed to continue or
    remain under, on or over any road which is found by the Department of Highways
    to be interfering in any way with the safe, convenient and continuous use and
    maintenance of such road shall upon thirty (30) days[’] notice to the person or to
    his chief agent by the Department of Highways be removed or relocated by such
    person at his own expense.
    Appellants argue that T&C violated this statute by constructing the roadway in such a manner as
    to trigger the violation notice from the KYTC pursuant to R/V’s encroachment permit.
    Appellants’ reading of this statute is, however, untenable. By its plain language, Section
    177.106(1) applies to the encroachment permit holder, as it speaks only to the permitee’s
    obligations to obtain a permit and to remediate any encroachment found by the KYTC to violate
    the terms of the permit. There is no dispute that (1) T&C was not required to obtain an
    encroachment permit, (2) T&C had no encroachment permit, (3) KYTC did not issue a notice to
    T&C regarding a violation of any encroachment permit, and (4) T&C was not required to – nor
    was it asked to – remove the encroachment. Because Section 177.106(1) speaks only to a
    permittee’s obligations and T&C was not a permittee, the statute does not apply to T&C in its
    role as a subcontractor construction company, and T&C thus had no obligations under the
    statute. Appellants have failed to establish not only that T&C did not comply with this statute,
    but that it was required to comply with this statute at all. Accordingly, Section 177.106(1)
    cannot serve as a basis for finding in Appellants’ favor as to breach of contract.
    - 12 -
    Appellants also argue that T&C is in breach of Section 24 of the subcontract for violating
    KAR 1:020 and 5:150. Section 1:020 provides, in relevant part, that,
    The owner or occupant of property . . . who desires to construct new or additional
    driveway entrance approaches, to relocate, or make other changes in existing
    driveway entrance approaches thereto, shall make application for a permit to the
    District Engineer of the Department of Highways upon standard forms furnished
    by the Transportation Cabinet. . . .
    All work involved is to be done wholly at the expense of the permittee and in
    accordance with the approved permit and plans. . . .
    ...
    . . . To insure the safety of the highway user and to protect highway facilities
    against damage, the entrance approach shall be constructed or installed as shown
    on the permit, documents and plans approved by the Department of Highways.
    603 Ky. Admin. Reg. 1:020 § 1(2)(a)-(b), (3)(b).8 Section 5:150 incorporates by reference
    KYTC’s “Permits Manual” to apply to work done pursuant to encroachment permits; the Permits
    Manual itself adopts the American Association of State Highway Transportation Officials’
    Policy of Geometric Design of Highways and Streets (hereinafter, “the Green Book”), which
    provides engineering standards for roadway projects. Appellants argue that, because T&C did
    not construct the road pursuant to the plans on file with KYTC in connection with R/V’s
    encroachment permit, and because it did not construct the road with a 4.3 percent cross slope
    called for by the Green Book, T&C violated both of these regulations in breach of its promise to
    comply with all state codes.
    It is undisputed that the road work, as completed, did not comply with Section 1:020, as
    the construction was completed in accordance with the revised plans, rather than in accordance
    with the original engineering plans on file with KYTC. It is also undisputed that T&C did not
    construct the road with a 4.3 percent cross slope but instead constructed the road with an
    8
    It is undisputed that the construction on Valley Station Road qualifies as a “driveway entrance approach” under
    this regulation.
    - 13 -
    approximately 2 percent cross slope as called for by the spot elevations provided in the revised
    plans. Nonetheless, the Court simply cannot find that T&C breached its subcontract.
    First, the regulations that Appellants complain were violated relate directly to the process
    of obtaining and complying with encroachment permits issued by the State of Kentucky. In this
    case, R/V obtained such a permit, the terms of which required R/V to ensure that all work “be
    done in accordance with the plans as approved and permitted,” and to obtain prior written
    approval of “any changes or variances” to those plans. Indeed, R/V “agree[d] as a condition to
    the issuance of the permit to construct and maintain such facilities in accordance with said
    plan[.]” Nonetheless, Appellants provided T&C with a revised set of plans that varied from the
    plans that had been authorized by the KYTC when the permit was issued and failed to obtain
    prior written approval of those revised plans. Appellants then supervised the construction of the
    Valley Station Road project utilizing the revised plans, rather than the original, permitted plans.
    The revised plans were created by Appellants’ retained engineer, Heritage, whose representatives
    have testified that the work was completed in precisely the manner intended by Heritage when it
    prepared the revised plans.
    Appellants have attempted to construe the language of various statutes and regulations in
    a manner that would allow it to shift the blame for the deficiency notice onto its subcontractor,
    T&C. But none of Appellants arguments compel the Court to conclude that T&C’s subcontract
    relieved R/V of its obligations pursuant to its permit from the KYTC or shifted the responsibility
    for engineering and design principles from the retained engineer, Heritage, to the construction
    subcontractor, T&C. To the extent that any act or omission resulted in a violation of the cited
    regulations, such act or omission was on the part of the Renaissance parties and/or Heritage.
    - 14 -
    Appellants argue that such a conclusion ignores the plain language of the contract, as
    T&C agreed in Section 24 of its subcontract to comply with, and therefore be liable for all
    violations of, all state codes and statutes. However, Section 4 of the contract required T&C to
    “perform all labor required for the completion of the [construction project] in accordance with all
    provisions of the original contract and of the specifications, plans, and addenda referred to in the
    original contract.” Section 14 further required T&C to be “bound by any changes or alterations
    made by owner to the original contract specifications or plans, or in the amount or character of
    the work or any part of the work[.]”9 If Appellants’ broad reading of Section 24 is correct, T&C
    was in a classic catch-22: it could comply with the work requirements of the contract, by
    constructing the roadway pursuant to the revised plans provided by the Renaissance parties, but
    in doing so risk being in breach of Section 24 of its contract, or it could instead comply with the
    original plans approved of by KYTC, but then risk being in breach of the work provisions of the
    contract for not complying with the revised plans.10
    However, a complete reading of Section 24 undermines Appellants’ position and affirms
    the conclusion reached by the district court. Section 24 requires T&C to comply with all laws
    9
    On appeal, T&C has argued that the contract required it to comply with the revised engineering plans, either
    because they were part of the original contract referenced in Section 4 or because the revised plans constituted a
    change or alteration of the original contract by the owner that T&C was bound to follow as described in Section 14.
    The district court did not consider the specific issue of whether Section 4 or Section 14 required T&C to follow the
    revised plans; instead, it simply found that the contract required T&C to work from the plans provided to it by the
    Renaissance parties.
    Upon consideration of the arguments and evidence, the Court agrees with the Renaissance parties that Section 4
    required T&C to perform its work pursuant to the “original contract” – that is, the contract between R/V and DKCD
    that included the original engineering plans. However, the Court further finds that, by providing the revised
    engineering plans to T&C and by supervising T&C’s construction work using those revised plans, the Renaissance
    parties invoked Section 14 of the subcontract which “bound” T&C to “any changes or alterations made by owner to
    the original contract specifications or plans.” Thus, T&C was contractually obligated to perform its construction
    work in conformance with the revised engineering plans and was not, as Appellants argue, obligated by its
    subcontract to ignore the revised plans and proceed with construction based on the original plans.
    10
    Indeed, Appellants have noted that “[a] builder usually can comply with both plans and codes and statutes at the
    same time. Section 4(A) and Section 24 come into conflict only if plans call for construction in violation of codes
    and statutes.”
    - 15 -
    “of the area involved” and to indemnify Appellants “against any and all claims or liens as a
    result of acts or omissions on part of the subcontractor.” In interpreting this provision, we rely –
    as did the district court – upon City of Louisville v. Padgett, 
    457 S.W.2d 485
    (Ky. Ct. App.
    1970):
    [T]he contractor should be relieved from checking every order given it . . . . The
    [entity] for whom the contractor works does the engineering, stakes out the
    project, tells the contractor what to grade and what to do and so long as the
    contractor complies with these instructions by its superior then the contractor is
    fulfilling its obligation. If the contractor was required, at its peril, to check and
    double check all plans given it and required to keep an engineering force for the
    purpose of interpreting these plans, and was not permitted to follow the orders of
    the engineering force of its superior, then the costs of public improvement would
    be so increased as to make them almost prohibitive. . . . The contractor’s work is
    not the engineering job of laying out the project but is merely in doing what it is
    instructed to do. So long as it does this work as it is instructed to do by its
    superior in a workman like manner, not negligently, then the contractor is not
    liable.
    
    Id. at 490
    (quoting Wood v. Foster & Creighton Co., 
    235 S.W.2d 1
    , 3 (Tenn. 1950)).11
    The Court concludes that the statutes and regulations relied upon by Appellants, which
    pertain to the rights and obligations of permit holders, as well as to engineering design
    principles, are not “of the area involved” by subcontractor T&C – that is, those statutes and
    regulations are not binding on or relevant to a subcontracting construction company. The
    undisputed evidence demonstrates that T&C’s area of expertise was construction based on plans
    that had been prepared by engineers – not the area of engineering itself. T&C’s contract required
    it to perform the construction work pursuant to the plans provided and did not afford it any
    11
    The parties argued at length regarding the applicability and relevance of Padgett to this case. The Court notes
    that material factual distinctions exist between the instant case and Padgett, which involved the issue of whether a
    contractor who contracted with a public agency may be liable for personal injury arising from oral changes to the
    work order. Nonetheless, the Court finds persuasive the discussion in Padgett regarding the role and responsibility
    of construction subcontractors that are provided engineering plans for their projects.
    - 16 -
    discretion in the execution of those plans.12 T&C complied with the engineering plans provided
    to it by the Renaissance parties, as required by the work provisions of its contract. 13 Appellants
    have failed to demonstrate that T&C failed to comply with any codes or statutes in its area of
    involvement or that any “act or omission on part of subcontractor” led to the complained of
    violations.14 For these reasons, the Court concludes that T&C did not breach its subcontract and
    that the district court’s grant of summary judgment on behalf of T&C was proper.15
    B. Negligence
    We next turn to Appellants’ claim against T&C for negligence. In Kentucky, a plaintiff
    must prove the following elements in order to establish negligence: “(1) the defendant owed a
    duty of care to the plaintiff, (2) breach of that duty, (3) injury to the plaintiff, and (4) legal
    causation between the defendant’s breach and the plaintiff’s injury.” Osborne v. Keeney, 
    399 S.W.3d 1
    , 17 (Ky. 2012).
    Below, Appellants framed their negligence claim as one for negligence per se based on
    T&C’s purported violation of KRS § 177.106. A claim for “[n]egligence per se ‘is merely a
    12
    Appellants argue that such a reading of the contract would render Section 24 completely moot. However, this
    argument presupposes that the statutes and regulations cited by the Renaissance parties are the only “federal, state,
    territorial, and local codes and statutes” relevant to such a project.
    13
    Appellants also argue on appeal that T&C is in breach of contract because it failed to complete its work “to the
    satisfaction of owner and contractor,” as provided by Section 4 of the subcontract. However, Appellants failed to
    timely raise this argument below, and the Court will not consider the argument for the first time on appeal. See, e.g.,
    Scottsdale Ins. Co. v. Flowers, 
    513 F.3d 546
    (6th Cir. 2008). The Court nonetheless notes that Appellants’ claim for
    breach of contract was premised solely upon a violation of Section 24 of the subcontract, not on Section 4.
    Furthermore, any argument that T&C’s work was not completed “to the satisfaction of owner and contractor”
    because it was performed pursuant to the revised plans but resulted in a deficiency notice is fatally circular, in that
    Appellants could have argued that the work was not satisfactory because T&C did comply with the revised plans
    and because it did not comply with the revised plans.
    14
    This reading of Section 24 allows the Court to give meaning to all of the provisions and terms of the subcontract.
    In doing so, the Court has found no repugnancy between Section 24 and the work provisions of the subcontract, and
    it accordingly need not address the parties’ arguments regarding the applicability of the doctrine of repugnant
    clauses.
    15
    The Court’s holding does not undermine the well-settled principle that parties may, by contract, allocate risk and
    liability; the Court merely holds that, under this contract and these circumstances, T&C is not liable for the statutory
    violations alleged by the Renaissance parties.
    - 17 -
    negligence claim with a statutory standard of care substituted for the common law standard of
    care.’” Young v. Carran, 
    289 S.W.3d 586
    , 588-89 (Ky. Ct. App. 2008) (quoting Real Estate
    Mktg, Inc. v. Franz, 
    885 S.W.2d 921
    , 926-27 (Ky. 1994)). The Court has previously discussed
    Section 177.106 and has found that it applies only to encroachment permit holders and not to
    subcontracting construction companies, such as T&C. The Court has also found that T&C did
    not have any obligations pursuant to that statute and that it did not – and indeed could not –
    violate the statute. For these same reasons, Appellants’ claim for negligence per se must fail,
    and we affirm the district court’s holding to that effect.
    On appeal, Appellants have reframed their negligence claim, arguing that T&C breached
    its duty of care to Appellants by failing to recognize and/or call to Appellants’ attention that “the
    plans from which it worked called for the creation of unsafe and dangerous conditions,” arguing
    that they “reasonably relied upon T&C’s experience and expertise” regarding the cross slope and
    drop off. However, Appellants have nonetheless failed to create a genuine issue of material fact
    with regard to the issue of negligence. Appellants failed to point to any evidence in the record
    that contradicts T&C’s evidence that construction companies working pursuant to subcontracts
    have a duty to comply with the engineering plans provided by the owner. Appellants have also
    failed to present any evidence or authority suggesting that subcontractors have a common law
    duty to second guess or reevaluate the engineering plans provided to them. Indeed, the Court
    finds that, quite to the contrary, Padgett holds that there is no such duty. See 
    Padgett, 457 S.W.2d at 490
    . Having breached no duty to the Renaissance parties, T&C was entitled to
    judgment as to the claim for negligence.
    - 18 -
    C. Indemnification
    Finally, Appellants maintain that they are entitled to indemnity from T&C for the cost of
    the ameliorative construction work. We have now determined that the district court’s findings
    that T&C did not breach its contract and did not act negligently should be affirmed. Because we
    have concluded that T&C is not liable to the Renaissance parties – at common law or under the
    terms of the subcontract – we must also conclude that the Renaissance parties are not entitled to
    indemnity as “one cannot be required to indemnify if one is not liable.” York v. Petzl Am., Inc.,
    
    353 S.W.3d 349
    , 354-55 (Ky. Ct. App. 2010); see also Clark v. Hauck Mfg. Co., 
    910 S.W.2d 247
    , 253 (Ky. 1995) overruled on other grounds by Martin v. Ohio Cnty. Hosp. Corp., 
    295 S.W.3d 104
    (Ky. 2009).
    IV. Conclusion
    In this case, all of the parties involved could have – and perhaps should have – taken
    different actions that would have prevented the need for remedial construction. But the Court’s
    job is not to determine, with the benefit of hindsight, the ideal course of action for each party to
    this project. Instead, the Court is tasked with analyzing the contract, interpreting the relevant
    statutes and regulations, and determining the parties’ duties, obligations, and liabilities. Here,
    T&C had a duty to comply with the terms of its subcontract and to complete the construction
    work it was tasked with pursuant to the plans provided to it by the Appellants. There is no
    genuine dispute that it did so, and Appellants have failed to present a compelling argument that
    T&C was obligated – contractually or at common law – to do more.
    For these reasons, we AFFIRM the judgment of the district court in all respects.
    - 19 -