Sierra Club v. United States Forest Serv. , 828 F.3d 402 ( 2016 )


Menu:
  •                         RECOMMENDED FOR FULL-TEXT PUBLICATION
    Pursuant to Sixth Circuit I.O.P. 32.1(b)
    File Name: 16a0151p.06
    UNITED STATES COURT OF APPEALS
    FOR THE SIXTH CIRCUIT
    _________________
    SIERRA CLUB,                                         ┐
    Plaintiff-Appellant,   │
    │
    │
    v.                                              >      No. 15-2457
    │
    │
    UNITED STATES FOREST SERVICE,                        │
    Defendant-Appellee,       │
    │
    │
    ENBRIDGE ENERGY, LIMITED PARTNERSHIP,                │
    Intervenor-Appellee.      │
    ┘
    Appeal from the United States District Court
    for the Eastern District of Michigan at Bay City.
    No. 1:15-cv-10154—Thomas L. Ludington, District Judge.
    Argued: June 16, 2016
    Decided and Filed: June 30, 2016
    Before: MOORE, SUTTON, and DONALD, Circuit Judges.
    _________________
    COUNSEL
    ARGUED: Marianne G. Dugan, Eugene, Oregon, for Appellant. Lane N. McFadden, UNITED
    STATES DEPARTMENT OF JUSTICE, Washington, D.C., for Federal Appellee. David H.
    Coburn, STEPTOE & JOHNSON LLP, Washington, D.C., for Appellee Enbridge Energy. ON
    BRIEF: Marianne G. Dugan, Eugene, Oregon, for Appellant. Lane N. McFadden, UNITED
    STATES DEPARTMENT OF JUSTICE, Washington, D.C., for Federal Appellee. David H.
    Coburn, Joshua Runyan, STEPTOE & JOHNSON LLP, Washington, D.C., for Appellee
    Enbridge Energy.
    1
    No. 15-2457                   Sierra Club v. U.S. Forest Serv. et al.               Page 2
    _________________
    OPINION
    _________________
    KAREN NELSON MOORE, Circuit Judge. Plaintiff-Appellant Sierra Club appeals from
    the district court’s decision granting summary judgment in favor of Defendants-Appellees
    United States Forest Service (“USFS”) and Enbridge Energy Limited Partnership (“Enbridge”).
    Sierra Club argues that the USFS violated the National Environmental Policy Act (“NEPA”), 
    42 U.S.C. § 4332
    (2)(C), in failing to prepare an Environmental Impact Statement (“EIS”) or an
    Environmental Assessment (“EA”) prior to reissuing a permit to Enbridge to operate and
    maintain an oil pipeline on federal land. In granting summary judgment, the district court
    concluded that the USFS appropriately found that the reissuance of Enbridge’s permit fell within
    a “categorical exclusion” and thus the agency was not required to prepare an EIS or an EA. For
    the reasons discussed below, we AFFIRM the judgment of the district court.
    I. BACKGROUND
    A. Factual Background
    The federal government may grant a right-of-way through federal land “for pipeline
    purposes for the transportation of oil.” 
    30 U.S.C. § 185
    (a). Beginning in 1953, the USFS issued
    a “special use permit” to Lakehead Pipeline Company, Inc. (“Lakehead”), permitting the
    company to use an 8.10 mile strip of government land within the Lower Michigan National
    Forest “for the purpose of[] [c]onstructing, operating and maintaining a pipeline to transport
    crude oil.” R. 20-8 (1954 Permit at 1) (Page ID #1639). The pipeline (“Line 5”) extends from
    Superior, Wisconsin to Sarnia, Ontario. 
    Id.
    In 1992, Lakehead changed its name to Lakehead Pipe Line Company, Limited
    Partnership, and the USFS reissued the special-use permit to this entity. R. 17-24 (1992 Permit
    at 1) (Page ID #1323). The 1992 permit authorized the use of the right-of-way until December
    31, 2012, and noted that the USFS “shall renew the authorization” for a reasonable term “[i]f the
    right-of-way project or facility is still being used for the purpose(s) previously authorized and is
    No. 15-2457                   Sierra Club v. U.S. Forest Serv. et al.               Page 3
    being operated and maintained in accordance with all the provisions of the authorization” and
    other applicable laws and resource-management plans. 
    Id. at 6
     (Page ID #1328).
    The 1992 permit was amended in 2002 when Lakehead changed its name to Enbridge
    Energy, Limited Partnership.     R. 17-26 (2002 Amendment at 1) (Page ID #1337).               The
    amendment noted that “only the name of the company has changed not the ownership” and that
    “[a]ll other conditions of the permit as amended, remain unchanged.” 
    Id.
     In 2011 and 2012,
    after a different Enbridge pipeline ruptured and spilled oil into the Kalamazoo River, Enbridge
    sought and received amendments to the 1992 permit in order to install “emergency flow release
    device[s]” on Line 5.     R. 18-1 (2011 Amendment) (Page ID #1394); see R. 18-3 (2012
    Amendment) (Page ID #1407).
    In September 2012, Enbridge requested that the USFS renew the special-use permit for
    Line 5. See R. 14-14 (Decision Memo at 1) (Page ID #336); R. 14-16 (9/26/12 Email at 1) (Page
    ID #400). The USFS reviewed Enbridge’s request in 2013 and conducted field studies on the
    potential impact on certain wildlife and vegetation in the area. See R. 17-12 (4/2/13 Letter at 1–
    2) (Page ID #1219–20); R. 14-14 (Decision Memo at App’x C) (Page ID #354); 
    id.
     at App’x D
    (Page ID #377). In 2014, the USFS contacted the United States Department of Transportation’s
    (“DOT”) Pipeline and Hazardous Materials Safety Administration (“PHMSA”) in order to
    confirm that Enbridge and Line 5 were in compliance with state and federal pipeline regulations.
    See R. 15-32 (2/28/14 Email at 1) (Page ID #1007).
    On January 29, 2014, the USFS began a public comment period for the proposed renewal
    of Enbridge’s special-use permit. See R. 14-2 (Public Notice at 1–3) (Page ID #228–30). The
    USFS proposed that a categorical exclusion to the documentation required by an EIS or EA
    applied. 
    Id. at 2
     (Page ID #229). Specifically, the USFS proposed that the renewal fell into
    category 15 (“CE-15”), which applies to the
    [i]ssuance of a new special use authorization for a new term to replace an existing
    or expired special use authorization when the only changes are administrative,
    there are not changes to the authorized facilities or increases in the scope or
    intensity of authorized activities, and the applicant or holder is in full compliance
    with the terms and conditions of the special use authorization.
    
    Id. at 2
     (Page ID #229) (quoting 
    36 C.F.R. § 220.6
    (e)(15)).
    No. 15-2457                    Sierra Club v. U.S. Forest Serv. et al.               Page 4
    The USFS received comments from the public in response, including a letter from
    Marvin Roberson, a Sierra Club Forest Ecologist, sent on behalf of Sierra Club. See R. 14-9
    (Roberson Letter at 1–3) (Page ID #318–20). Sierra Club’s letter objected to the application of
    CE-15 for three reasons. 
    Id. at 1
     (Page ID #318). First, Sierra Club stated that no EA or EIS had
    ever been completed for Line 5 because the original permit was issued “prior to the enactment of
    NEPA.” 
    Id. at 2
     (Page ID #319). Second, Sierra Club argued that intensity of activities along
    the pipeline had increased over the past two years because oil flow within the pipeline had
    “increased by over 10%,” and thus the exclusion did not apply. 
    Id.
     Finally, Sierra Club
    contended that Enbridge’s prior permit expired on December 31, 2012; because Enbridge was
    therefore not “renew[ing]” its prior permit request, Sierra Club asserted that the USFS must treat
    the application as a new permit request and prepare an EA or EIS. 
    Id.
    The USFS responded on March 31, 2014. See R. 15-40 (3/31/14 Letter) (Page ID
    #1023). The USFS explained that Enbridge’s renewal “made no request to change the pipeline
    operations” as authorized by the existing permit, and that the existing “permit is for the operation
    and maintenance of the pipeline,” not for any particular oil flow through the pipeline, which “is
    regulated by the [PHMSA] of the [DOT] and outside the scope of this project.” 
    Id.
     at 1–2 (Page
    ID #1023–24). The USFS also noted that the language of CE-15 explicitly referred to expired
    permits. 
    Id. at 3
     (Page ID #1025).
    On December 10, 2014, the USFS issued a “Decision Memo,” concluding that Enbridge
    should be reissued a permit to continue its existing operations and “that this decision qualifies for
    categorical exclusion from documentation in an [EIS] or [EA]” under CE-15.                 R. 14-14
    (Decision Memo at 13) (Page ID #348). In reaching this conclusion, the memo evaluated
    whether any “extraordinary circumstances” applied such that an EA or EIS was necessary
    regardless of the otherwise applicable exclusion. 
    Id. at 5
     (Page ID #340). Accordingly, the
    memo discussed the impact that the reissuance would have on certain flora and fauna in the area,
    and specifically, whether the reissuance would affect the Kirtland’s warbler, an endangered
    songbird. 
    Id.
     at 5–6 (Page ID #340–41). The USFS concluded that the reissuance “[w]ould have
    no effect on the Kirtland’s warbler.” 
    Id. at 6
     (Page ID #341). The USFS attached the biological
    assessment reports prepared by a biologist and a botanist. See 
    id.
     at App’x C (Page ID #354–
    No. 15-2457                   Sierra Club v. U.S. Forest Serv. et al.              Page 5
    68); 
    id.
     at App’x D (Page ID #377–80).           The memo concluded that “no extraordinary
    circumstances which may result in significant individual or cumulative effects on the quality of
    the environment” existed. 
    Id. at 13
     (Page ID #348).
    The USFS subsequently re-issued Enbridge’s special-use permit. R. 51-2 (2015 Permit)
    (Page ID #2385).
    B. Procedural History
    The Sierra Club filed suit against the USFS in the United States District Court for the
    Eastern District of Michigan on January 14, 2015, alleging that the USFS violated NEPA by not
    preparing an EA or EIS. R. 1 (Compl. at 1, 7–13) (Page ID #1, 7–13). Enbridge intervened as a
    defendant on February 25, 2015. R. 7 (Order Granting Mot. to Intervene) (Page ID #116). The
    parties filed cross-motions for summary judgment, see R. 27 (Pl. Mot. for Summ. J.) (Page ID
    #1970); R. 37 (USFS Cross-Mot. for Summ. J.) (Page ID #2092); R. 40 (Enbridge Cross-Mot.
    for Summ. J.) (Page ID #2214), and each party also filed a response. See R. 36 (USFS Resp. to
    Pl. Mot. for Summ. J.) (Page ID #2051); R. 39 (Enbridge Resp. to Pl. Mot. for Summ. J.) (Page
    ID #2137); R. 44 (Pl. Resp. to Cross-Mot. for Summ. J.) (Page ID #2301).
    The district court granted the defendants’ cross-motions for summary judgment on
    September 30, 2015, concluding that the USFS properly applied CE-15 in reissuing Enbridge’s
    permit without conducting an EIS or EA. See R. 52 (09/30/15 D. Ct. Order at 12–21) (Page ID
    #2673–82). Judgment was entered in favor of the USFS and Enbridge, R. 53 (Judgment) (Page
    ID #2684), and Sierra Club timely appealed. R. 54 (Notice of Appeal) (Page ID #2685).
    II. DISCUSSION
    A. Standard of Review
    The Administrative Procedure Act (“APA”) provides for judicial review of final agency
    actions. 
    5 U.S.C. § 702
    . “When a district court upholds on summary judgment an administrative
    agency’s final decision under the APA,” this Circuit reviews the district court’s decision de novo
    but reviews the agency’s action under the APA’s arbitrary or capricious standard.             Ky.
    Waterways All. v. Johnson, 
    540 F.3d 466
    , 473 (6th Cir. 2008). “The APA directs courts to ‘hold
    No. 15-2457                    Sierra Club v. U.S. Forest Serv. et al.               Page 6
    unlawful and set aside agency action, findings, and conclusions found to be arbitrary, capricious,
    an abuse of discretion, or otherwise not in accordance with law.’” Ky. Riverkeeper, Inc. v.
    Rowlette, 
    714 F.3d 402
    , 407 (6th Cir. 2013) (quoting 
    5 U.S.C. § 706
    (2)(A)). A decision is
    arbitrary or capricious under the APA if the agency
    has relied on factors which Congress had not intended it to consider, entirely
    failed to consider an important aspect of the problem, offered an explanation for
    its decision that runs counter to the evidence before the agency, or is so
    implausible that it could not be ascribed to a difference in view or the product of
    agency expertise.
    Nat’l Ass’n of Home Builders v. Defs. of Wildlife, 
    551 U.S. 644
    , 658 (2007) (quoting Motor
    Vehicle Mfrs. Ass’n, Inc. v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983)).
    B. Statutory and Regulatory Framework
    Congress enacted NEPA “to reduce or eliminate environmental damage.” Dep’t of
    Transp. v. Pub. Citizen, 
    541 U.S. 752
    , 756 (2004). “NEPA itself does not mandate particular
    results in order to accomplish these ends,” but rather “imposes only procedural requirements on
    federal agencies with a particular focus on requiring agencies to undertake analyses of the
    environmental impact of their proposals and actions.” 
    Id.
     at 756–57 (internal quotation marks
    omitted). NEPA’s “‘action-forcing’ procedures . . . require that agencies take a ‘hard look’ at
    environmental consequences.” Robertson v. Methow Valley Citizens Council, 
    490 U.S. 332
    , 350
    (1989) (internal quotations omitted).
    In forcing agencies to “take a ‘hard look’ at environmental consequences,” 
    id.
     (internal
    quotations omitted), NEPA requires federal agencies to prepare an EIS when the agency
    proposes “‘major Federal actions significantly affecting the quality of the human environment.’”
    Pub. Citizen, 
    541 U.S. at 757
     (quoting 
    42 U.S.C. § 4332
    (2)(C)). An EIS must detail, among
    other things, “the environmental impact of the proposed action,” “any adverse environmental
    effects which cannot be avoided” in implementing the proposal, and any available alternatives.
    
    42 U.S.C. § 4332
    (2)(C).      Under regulations promulgated by the Council of Environmental
    Quality (“CEQ”) an agency may “prepare a more limited document, an Environmental
    Assessment (EA),” in some circumstances. Pub. Citizen, 
    541 U.S. at 757
    . An EA “is a highly
    significant ‘first step’ that determines whether the next step will or will not be the preparation of
    No. 15-2457                   Sierra Club v. U.S. Forest Serv. et al.              Page 7
    a fully polished, high-budget environmental impact statement.” Friends of Fiery Gizzard v.
    Farmers Home Admin., 
    61 F.3d 501
    , 504 (6th Cir. 1995). If the EA demonstrates “that the
    project will have no significant adverse environmental consequences,” then the agency is not
    required to prepare an EIS but “must publish a finding of no significant impact.” 
    Id.
     at 504–05
    (internal quotation marks omitted); see also 
    40 C.F.R. §§ 1501.4
    (e), 1508.13.
    “In some cases, however, neither an EA nor an EIS is required.” West v. Sec’y of Dep’t
    of Transp., 
    206 F.3d 920
    , 927 (9th Cir. 2000). CEQ regulations allow an agency to adopt a
    “categorical exclusion” for a “category of actions which do not individually or cumulatively
    have a significant effect on the human environment and which have been found to have no such
    effect in procedures adopted by a Federal agency in implementation of these regulations.’” 
    Id.
    (quoting 
    40 C.F.R. § 1508.4
    ). The procedures adopted by an agency to establish a categorical
    exclusion, however, must “provide for extraordinary circumstances in which a normally
    excluded action may have a significant environmental effect” and thus require further action.
    
    40 C.F.R. § 1508.4
    ; see also Ctr. for Biological Diversity v. Salazar, 
    706 F.3d 1085
    , 1096 (9th
    Cir. 2013); California v. Norton, 
    311 F.3d 1162
    , 1168 (9th Cir. 2002).
    “Pursuant to CEQ regulations, each agency develops criteria to determine the appropriate
    level of environmental review for different types of actions,” West, 
    206 F.3d at
    927 (citing
    
    40 C.F.R. § 1507.3
    (b)(2)), and the USFS has accordingly established several CEs. See 
    36 C.F.R. § 220.6
    (a), (d)–(e). The USFS has promulgated nineteen categories of agency action, such as
    CE-15, for which the agency must prepare “a project or case file and decision memo,” but not an
    EA or EIS. 
    36 C.F.R. § 220.6
    (e). A decision memo must include the agency’s reason for
    invoking the CE as well as “[a] finding that no extraordinary circumstances exist.” 
    36 C.F.R. § 220.6
    (f)(2)(iii). “To determine whether extraordinary circumstances exist,” USFS regulations
    direct the agency to “consider if the proposed action may have a potentially significant impact on
    certain ‘resource conditions.’” Utah Envtl. Cong. v. Bosworth, 
    443 F.3d 732
    , 741 (10th Cir.
    2006); see 
    36 C.F.R. § 220.6
    (b).       These “resource conditions” include the presence of
    “[f]ederally listed threatened or endangered species or designated critical habitat.” 
    36 C.F.R. § 220.6
    (b)(1)(i). USFS regulations specify, however, that “[t]he mere presence of one or more
    of these resource conditions does not preclude use of a categorical exclusion,” but rather the
    No. 15-2457                    Sierra Club v. U.S. Forest Serv. et al.               Page 8
    agency must consider whether “a cause-effect relationship between a proposed action” and these
    resource conditions exists and, if so, “the degree of the potential effect.”             
    36 C.F.R. § 220.6
    (b)(2).
    Agencies engage in a “scoping” process to identify significant issues.             
    40 C.F.R. § 1501.7
    . USFS regulations on CEs require that the agency prepare an EA if an “official
    determines, based on scoping, that it is uncertain whether the proposed action may have a
    significant effect on the environment,” and the agency must prepare an EIS if “the proposed
    action may have a significant environmental effect.” 
    36 C.F.R. § 220.6
    (c).
    C. The USFS Did Not Arbitrarily Apply CE-15 in Reissuing Enbridge’s Permit
    Sierra Club argues that the USFS acted arbitrarily in applying CE-15 and not conducting
    an EA or EIS. Sierra Club’s objections can be grouped into two sets of arguments: first, those
    that contend that the reissuance of Enbridge’s permit falls outside of the plain language of CE-
    15, and second, those that assert that “extraordinary circumstances” apply such that an EA and
    EIS were required even if the action might normally be excluded from documentation.
    1.     The Renewal of Enbridge’s Permit Falls Within the Text of CE-15
    Sierra Club contends that the plain language of CE-15 does not apply to the reissuance of
    Enbridge’s permit because (1) Enbridge has increased the oil flow on Line 5 and (2) Enbridge’s
    1992 permit expired prior to the issuance of the 2015 permit. Neither of these arguments are
    persuasive.
    Sierra Club first asserts that Enbridge has dramatically increased “the scope and intensity
    of use of the pipeline within the past two years.” See Appellant Br. at 14. CE-15 applies to the
    reissuance of a permit “when the only changes are administrative” and “there are not changes to
    the authorized facilities or increases in the scope or intensity of authorized activities.” 
    36 C.F.R. § 220.6
    (e)(15). Accordingly, Sierra Club argues, the USFS cannot invoke CE-15 here. Contrary
    to Sierra Club’s assertions, however, there have been no “increases in the scope or intensity” of
    activities authorized by Enbridge’s 1992 permit. 
    Id.
     The 2015 permit grants Enbridge an 8.10
    mile right-of-way through the Huron-Manistee National Forest to “operat[e] and maintain[] a . . .
    No. 15-2457                         Sierra Club v. U.S. Forest Serv. et al.                         Page 9
    steel pipeline . . . and associated facilities.” R. 51-2 (2015 Permit) (Page ID #2385).1 This is the
    same use authorized by the original permit, which granted Lakehead Pipeline an 8.10 mile right-
    of-way “for the purpose of[] [c]onstructing, operating and maintaining a pipeline to transport
    crude oil across Government owned land within the Lower Michigan National Forest.” R. 20-8
    (1953 Permit at 1) (Page ID #1639). Although Sierra Club contends that Enbridge has increased
    the volume of oil flow within the pipes, “[t]he Forest Service does not and never has regulated
    the flow of oil inside the pipeline.” USFS Appellee Br. at 22. The PHMSA has authority to
    regulate oil pipeline flow and pressure. See, e.g., 
    49 C.F.R. § 195.106
    . Accordingly, Enbridge
    has not varied the “scope or intensity of authorized activities,” 
    36 C.F.R. § 220.6
    (e)(15), between
    the earlier permit and the 2015 permit because the permit only authorizes use of a right-of-way
    and the scope of the right-of-way has not changed.
    Next, Sierra Club contends that the 2015 permit is not an administrative continuation of
    the 1992 permit because “[t]he previous permit expired December 31, 2012” and the new permit
    “was issued to a new company, not to the original permittee.” Appellant Br. at 17. This is not
    persuasive. First, the plain language of CE-15 refers to the “[i]ssuance of a new special use
    authorization . . . to replace an existing or expired special use authorization.”                         
    36 C.F.R. § 220.6
    (e)(15) (emphasis added); see USFS Appellee Br. at 33. Accordingly, it is irrelevant that
    the 1992 permit may have “expired” two years earlier, because CE-15 applies to expired permits.
    Second, as the USFS points out, “[t]he APA provides that ‘[w]hen the licensee has made timely
    and sufficient application for a renewal or a new license in accordance with agency rules, a
    license with reference to an activity of a continuing nature does not expire until the application
    has been finally determined by the agency.’” USFS Appellee Br. at 34 (quoting 
    5 U.S.C. § 558
    (b)). The record shows that Enbridge applied for a renewal prior to the expiration of the
    1992 permit and Enbridge continued to pay fees for the right-of-way during the time that the
    USFS was considering their application. See, e.g., R. 14-16 (9/26/12 Email) (Page ID #400); R.
    1
    Sierra Club asserts that the new permit provides a larger, 61.09 acre or 8.4 mile, right-of-way. Appellant
    Br. at 15. In support of this statement, Sierra Club cites a final draft of the special-use permit in the record that
    provides the “permit covers 61.09 acres . . . or 8.4 miles,” R. 14-18 (Final Permit Draft at 1) (Page ID #409), but the
    other documents attached to this draft state that the permit covers only 58.98 acres or 8.1 miles. 
    Id. at 12
     (Page ID
    #420). The USFS later issued the permit to Enbridge, see R. 51 (Notice at 1–2) (Page ID #2381–82), and this final
    permit document states that the right-of-way is 58.98 acres or 8.1 miles. See R. 51-2 (2015 Permit at 1) (Page ID
    #2385). According to the USFS, the discrepancy was a typographical error. USFS Appellee Br. at 25.
    No. 15-2457                   Sierra Club v. U.S. Forest Serv. et al.               Page 10
    19-55 (02/01/2013 Bill) (Page ID #1576). Enbridge’s 1992 permit was thus not “expired” under
    the APA. Lastly, Sierra Club is also incorrect in asserting that the new permit “was issued to a
    new company.” Appellant Br. at 17. The 1992 permit was issued to Lakehead, but the USFS
    amended the 1992 permit in 2002 when Lakehead changed its name to Enbridge. See R. 17-26
    (2002 Amendment) (Page ID #1337). The 2002 amendment states that “only the name of the
    company has changed not the ownership” and “[a]ll other conditions of the permit as amended,
    remain unchanged.”     Id.; see also USFS Appellee Br. at 36.           Accordingly, Sierra Club’s
    arguments that the 2015 permit “is a brand-new permit to a new permittee” are without merit.
    Appellant Br. at 17.
    2.   The USFS Did Not Act Arbitrarily in Determining That No
    “Extraordinary Circumstances” Existed
    Sierra Club also advances several arguments that relate to whether the USFS
    appropriately determined that no “extraordinary circumstances” exist precluding the use of CE-
    15. These arguments are similarly unavailing.
    Sierra Club first argues that the USFS cannot utilize CE-15 because “[t]he project may
    impact an endangered species, Kirtland’s warbler.” Appellant Br. at 16. As discussed above,
    even if a proposed agency action would normally fall within a CE, the USFS is required to
    consider whether “extraordinary circumstances related to the proposed action” preclude the use
    of the CE. See 
    36 C.F.R. § 220.6
    (a). To make this determination, USFS regulations require the
    agency to consider certain “[r]esource conditions,” including whether there are “[f]ederally listed
    threatened or endangered species” in the area. 
    36 C.F.R. § 220.6
    (b)(1)(i). Although it is
    undisputed that Kirtland’s warbler, an endangered songbird, is “known to occur” in the area of
    national forest where Line 5 is located, see R. 14-14 (Decision Memo at App’x C, p.5) (Page ID
    #358), this does not preclude the USFS from applying CE-15. Under USFS regulations, the
    “mere presence” of an endangered species does not preclude the use of a CE. 
    36 C.F.R. § 220.6
    (b)(2). Rather, the USFS must consider whether there is “a cause-effect relationship
    between a proposed action” and the species, and if so, “the degree of the potential effect” of the
    agency action on the species. 
    Id.
     Here, the USFS’s decision memo on the 2015 permit includes
    a biologist’s report that unambiguously concludes that “the Enbridge Special Use Authorization
    No. 15-2457                   Sierra Club v. U.S. Forest Serv. et al.              Page 11
    would have no effect on Kirtland’s warbler.” R. 14-14 (Decision Memo at App’x D, p.9) (Page
    ID #362). The reasons behind this conclusion are documented in the biologist’s report and
    summarized in the agency’s decision memo. Sierra Club has not raised any arguments that
    undermine the biologist’s report, and it has not demonstrated that the agency acted arbitrarily in
    relying on the biologist’s conclusion in determining that no “extraordinary circumstances”
    existed such that CE-15 could not apply. Accordingly, Sierra Club is not entitled to relief on the
    basis of this argument.
    Sierra Club advances two final arguments.         In its opening brief, Sierra Club cites
    
    40 C.F.R. § 1508.25
    (a) for the proposition that the USFS was required to assess the “cumulative
    impacts” of its actions prior to applying the CE. Appellant Br. at 18. Section 1508.25, however,
    relates to the types of actions that an agency must consider “[t]o determine the scope of
    environmental impact statements.” 
    40 C.F.R. § 1508.25
    (a). As discussed above, a categorical
    exclusion is defined as “a category of actions which do not individually or cumulatively have a
    significant effect on the human environment,” and thus no EIS is required. 
    40 C.F.R. § 1508.4
    (emphasis added). Because a categorical exclusion defines a type of agency action that has no
    cumulative significant effect on the environment, courts have “conclude[d] that section
    1508.25’s requirements do not apply to [an agency’s] categorical exclusion analysis.” See, e.g.,
    Ctr. for Biological Diversity, 706 F.3d at 1097; Utah Envtl. Cong., 
    443 F.3d at 741
    . Rather, in
    order to comply with NEPA, the agency must determine whether a CE applies and whether an
    “extraordinary circumstance” exists that precludes the use of a CE; the agency is not required to
    independently evaluate cumulative impacts because this process already takes cumulative
    impacts into account. See Ctr. for Biological Diversity, 706 F.3d at 1097; Utah Envtl. Cong.,
    
    443 F.3d at
    741–42.
    Relatedly, Sierra Club argues that the agency must independently consider the factors set
    forth in 
    40 C.F.R. § 1508.27
    (b) in determining whether an EIS is required. See Appellant Br. at
    22–25. Section 1508.27 defines “significantly” for the purposes of NEPA. The regulation states
    that “[s]ignificantly as used in NEPA requires considerations of both context and intensity” and
    the regulation directs agencies to consider several factors in evaluating the “intensity” of an
    action, including “[t]he degree to which the proposed action affects public health or safety” and
    No. 15-2457                   Sierra Club v. U.S. Forest Serv. et al.              Page 12
    “[t]he degree to which the effects on the quality of the human environment are likely to be highly
    controversial.” 
    40 C.F.R. § 1508.27
    (a)–(b). Sierra Club asserts that the USFS failed to discuss
    these factors in applying CE-15, but, as with the “cumulative impact” analysis discussed above,
    the USFS was not required independently to evaluate these factors. As stated above, a CE is
    defined as a category of agency action that has no “significant effect on the human
    environment.” 
    40 C.F.R. § 1508.4
    . And, in order for the agency to establish CEs, agencies must
    “provide for extraordinary circumstances in which a normally excluded action may have a
    significant environmental effect.” 
    Id.
     The USFS has promulgated CE regulations that require
    the USFS to consider certain “[r]esource conditions” in determining whether an extraordinary
    circumstance exists. 
    36 C.F.R. § 220.6
    (b). Accordingly, USFS regulations—which set forth the
    agency’s CEs and how the agency must determine whether an extraordinary circumstance
    exists—necessarily take into account the NEPA-wide definition of “[s]ignificantly” provided in
    § 1508.27. Because Sierra Club does not challenge the substance of USFS’s regulations here,
    the question is whether the record demonstrates that the USFS appropriately evaluated the
    present facts against its regulations and whether the USFS reached a non-arbitrary conclusion.
    See, e.g., Ctr. for Biological Diversity, 706 F.3d at 1097–98; U.S. v. Coal. for Buzzards Bay,
    
    644 F.3d 26
    , 34–35 (1st Cir. 2011); Utah Envtl. Cong., 
    443 F.3d at
    741–42.
    The USFS did so here. The USFS publicly promulgated its intent to apply CE-15,
    accepted public comments, and responded to the comments that it received. See R. 14-2 (Public
    Notice at 1–3) (Page ID #228–30); R. 15-40 (3/31/14 Letter) (Page ID #1023). The USFS
    determined that Enbridge was in compliance with pipeline regulations, see R. 15-32 (2/28/14
    Email at 1) (Page ID #1007), and evaluated whether any “resource conditions” existed such that
    an extraordinary circumstance may apply. See, e.g., R. 14-14 (Decision Memo at 5–6) (Page ID
    #340–341). It set forth this discussion in its Decision Memo and attached evaluations from both
    a biologist and a botanist that concluded that reissuing the permit would not have an impact on
    sensitive flora or fauna populations in the area, including Kirtland’s warbler. Id. at 13; App’x C;
    App’x D (Page ID #348, 354–80). This is not a case in which the agency “failed entirely to
    consider the potential environmental consequences of its decision at the time the decision was
    made” and instead used a CE as a “post-hoc rationalization” for the agency’s actions. See, e.g.,
    Norton, 
    311 F.3d at
    1175–76; Jones v. Gordon, 
    792 F.2d 821
    , 828–29 (9th Cir. 1986). Rather,
    No. 15-2457                  Sierra Club v. U.S. Forest Serv. et al.            Page 13
    the record demonstrates that the USFS followed the appropriate decision-making process and
    reached a non-arbitrary conclusion.
    III. CONCLUSION
    For the reasons set forth above, we AFFIRM the judgment of the district court.