Alabama v. North Carolina , 130 S. Ct. 2295 ( 2010 )


Menu:
  • (Slip Opinion)              OCTOBER TERM, 2009                                       1
    Syllabus
    NOTE: Where it is feasible, a syllabus (headnote) will be released, as is
    being done in connection with this case, at the time the opinion is issued.
    The syllabus constitutes no part of the opinion of the Court but has been
    prepared by the Reporter of Decisions for the convenience of the reader.
    See United States v. Detroit Timber & Lumber Co., 
    200 U. S. 321
    , 337.
    SUPREME COURT OF THE UNITED STATES
    Syllabus
    ALABAMA ET AL. v. NORTH CAROLINA
    ON EXCEPTIONS TO THE PRELIMINARY AND SECOND REPORTS
    OF THE SPECIAL MASTER
    No. 132, Orig. Argued January 11, 2010—Decided June 1, 2010
    In 1986, Congress granted its consent to the Southeast Interstate Low-
    Level Radioactive Waste Management Compact (Compact), which
    was entered into by Alabama, Florida, Georgia, Mississippi, North
    Carolina, South Carolina, Tennessee, and Virginia. The Compact is
    administered by a Commission, which was required, inter alia, to
    “identif[y] a host State for the development of a [new] regional
    disposal facility,” and to “seek to ensure that such facility is licensed
    and ready to operate . . . no . . . later than 1991.” Art. 4(E)(6), 
    99 Stat. 1875
    . The Commission designated North Carolina as a host
    State in 1986, thereby obligating North Carolina to take “appropriate
    steps to ensure that an application for a license to construct and op
    erate a [low-level radioactive waste storage facility] is filed with and
    issued by the appropriate authority.” Art. 5(C), 
    id., at 1877
    .
    In 1988, North Carolina asked the Commission for assistance with
    the costs of licensing and building a facility. The Commission
    adopted a resolution declaring it “appropriate and necessary” to pro
    vide financial assistance, and ultimately paid almost $80 million to
    North Carolina from 1988 through 1997. North Carolina also ex
    pended $34 million of its own funds. Yet by the mid 1990s, North
    Carolina was still many years—and many tens of millions of dol
    lars—away from obtaining a license.
    In 1997, the Commission notified North Carolina that absent a
    plan for funding the remaining licensing steps, it would not disburse
    additional funds to North Carolina. North Carolina responded that it
    could not continue without additional funding. After the parties
    failed to agree on a long-term financing plan, in December 1997 the
    Commission ceased its financial assistance to North Carolina, and
    North Carolina subsequently began an orderly shutdown of its pro
    2                   ALABAMA v. NORTH CAROLINA
    Syllabus
    ject.
    In June 1999, Florida and Tennessee filed a complaint with the
    Commission seeking monetary sanctions against North Carolina. In
    July 1999, North Carolina exercised its right under Article 7(G) to
    withdraw from the Compact. In December 1999, the Commission
    concluded that North Carolina had failed to fulfill its obligations un
    der the Compact and adopted a sanctions resolution demanding that
    the State repay approximately $80 million in addition to other mone
    tary penalties. North Carolina did not comply.
    In 2003, this Court granted Alabama, Florida, Tennessee, Virginia,
    and the Commission (Plaintiffs) leave to file a bill of complaint
    against North Carolina under this Court’s original jurisdiction, U. S.
    Const., Art. II, §2, cl. 2; 
    28 U. S. C. §1251
    (a). The complaint sets
    forth claims of violation of Plaintiffs’ rights under the Compact
    (Count I), breach of contract (Count II), unjust enrichment (Count
    III), promissory estoppel (Count IV), and money had and received
    (Count V), and requests monetary and other relief, including a decla
    ration that North Carolina is subject to sanctions and that the Com
    mission’s sanctions resolution is valid and enforceable.
    The Court assigned the case to a Special Master, who has con
    ducted proceedings and has filed two reports. The Preliminary Re
    port recommends denying without prejudice North Carolina’s motion
    to dismiss the Commission’s claims on sovereign immunity grounds;
    denying Plaintiffs’ motion for summary judgment on Count I, which
    sought enforcement of the Commission’s sanctions resolution; grant
    ing North Carolina’s cross-motion to dismiss Count I and other por
    tions of the complaint seeking such enforcement; and denying North
    Carolina’s motion to dismiss the claims in Counts II–V. The Master’s
    Second Report recommended denying Plaintiff’s motion for summary
    judgment and granting North Carolina’s motion for summary judg
    ment on Count II; and denying North Carolina’s motion for summary
    judgment on Plaintiffs’ remaining claims in Counts III–V. The par
    ties filed a total of nine exceptions to the Master’s Reports.
    Held:
    1. Plaintiffs’ seven exceptions are overruled. Pp. 7–21.
    (a) The terms of the Compact do not authorize the Commission to
    impose monetary sanctions against North Carolina. The Court’s con
    clusion is confirmed by a comparison of the Compact’s terms with
    three other interstate compacts concerning low-level radioactive
    waste storage approved by Congress contemporaneously with the
    Compact, all of which expressly authorize their commissions to im
    pose monetary sanctions against their party States. Pp. 7–9.
    (b) Plaintiffs’ exception that North Carolina could not avoid
    monetary sanctions by withdrawing from the Compact is moot, be
    Cite as: 560 U. S. ____ (2010)                    3
    Syllabus
    cause the Compact does not permit the Commission to impose mone
    tary sanctions in any event. The Court deems their exception that
    North Carolina forfeited its right to object to a monetary penalty by
    failing to participate at the sanctions hearing both abandoned and
    meritless. P. 10.
    (c) Because the express terms of the Compact do not make the
    Commission the “sole arbiter” of disputes arising under the Compact,
    Texas v. New Mexico, 
    462 U. S. 554
    , 569–570, the Court is not bound
    by the Commission’s conclusion that North Carolina breached its ob
    ligations under the Compact. Nor does the Court apply deferential
    administrative-law standards of review to the Commission’s conclu
    sion, but instead exercises its independent judgment as to both fact
    and law in executing its role as the “exclusive” arbiter of controver
    sies between the States, 
    28 U. S. C. §1251
    (a). Pp. 10–12.
    (d) North Carolina did not breach its contractual obligation to
    take “appropriate steps” toward the issuance of a license. Pp. 12–19.
    (1) The Compact requires North Carolina to take only those li
    censing steps that are “appropriate.” The parties’ course of perform
    ance establishes that it was not appropriate for North Carolina to
    proceed with the very expensive licensing process without external
    financial assistance. Nothing in the Compact’s text or structure re
    quires North Carolina to cover all licensing and building costs on its
    own. Plaintiffs’ assertion that it was understood that the host State
    would bear the up-front licensing and construction costs, but recoup
    those costs through its regional monopoly on radioactive waste dis
    posal, is not reflected in the Compact. Pp. 13–18.
    (2) Plaintiffs’ alternative argument that North Carolina repu
    diated its obligation to take appropriate steps when it announced it
    would take no further steps to obtain a license fails for the same rea
    sons their breach theory fails. Pp. 18–19.
    (e) North Carolina did not breach an implied duty of good faith
    and fair dealing when it withdrew from the Compact. The Compact
    by its terms imposes no limitation on North Carolina’s right to exer
    cise its statutory right under Article 7(G) to withdraw from the Com
    pact. A comparison between the Compact and other contemporane
    ously enacted compacts confirms the absence of a good-faith
    limitation in the Compact. Pp. 19–21.
    2. North Carolina’s two exceptions are overruled. Pp. 21–26.
    (a) It was reasonable for the Special Master to deny without
    prejudice North Carolina’s motion for summary judgment on the mer
    its of Plaintiffs’ equitable claims in Counts III–V. The Special Master
    concluded that those claims require further briefing, argument, and,
    possibly, discovery. The Court approves of the Special Master’s rea
    sonable exercise of his discretion to manage the proceedings. Pp. 21–
    4                   ALABAMA v. NORTH CAROLINA
    Syllabus
    22.
    (b) Under Arizona v. California, 
    460 U. S. 605
    , 614, the Commis
    sion’s claims are not barred by sovereign immunity so long as the
    Commission asserts the same claims and seeks the same relief as the
    plaintiff States. Nothing in the Court’s subsequent cases suggests
    that Arizona v. California has been implicitly overruled, and North
    Carolina does not ask the Court to overrule that decision. At least
    with respect to Counts I and II, the Commission’s claims under those
    Compact-related Counts are wholly derivative of the plaintiff States’
    claims. The summary judgment disallowing the claims in Counts I
    and II on their merits renders the sovereign immunity question with
    regard to any relief the Commission alone might have on those claims
    moot. Counts III–V are on a different footing. The Special Master
    concluded that further factual and legal development was necessary
    to determine whether the Commission’s claims under these Counts
    were identical to those of the plaintiff States. The Special Master’s
    case-management decision was reasonable. Pp. 22–26.
    Exceptions to Special Master’s Reports overruled, and Master’s recom
    mendations adopted; North Carolina’s motions to dismiss Count I
    and for summary judgment on Count II granted; Plaintiffs’ motions
    for judgment on Counts I and II denied; and North Carolina’s mo
    tions to dismiss the Commission’s claims on sovereign immunity
    grounds and for summary judgment on Counts III–V denied without
    prejudice.
    SCALIA, J., delivered the opinion of the Court, in which STEVENS,
    GINSBURG, and ALITO, JJ., joined, in which ROBERTS, C. J., joined in all
    but Parts II–D and III–B, in which KENNEDY and SOTOMAYOR, JJ.,
    joined in all but Part II–E, in which THOMAS, J., joined in all but Part
    III–B, and in which BREYER, J., joined in all but Parts II–C, II–D, and
    II–E. KENNEDY, J., filed an opinion concurring in part and concurring
    in the judgment, in which SOTOMAYOR, J., joined. ROBERTS, C. J., filed
    an opinion concurring in part and dissenting in part, in which THOMAS,
    J., joined. BREYER, J., filed an opinion concurring in part and dissent
    ing in part, in which ROBERTS, C. J., joined.
    Cite as: 560 U. S. ____ (2010)                              1
    Opinion of the Court
    NOTICE: This opinion is subject to formal revision before publication in the
    preliminary print of the United States Reports. Readers are requested to
    notify the Reporter of Decisions, Supreme Court of the United States, Wash­
    ington, D. C. 20543, of any typographical or other formal errors, in order
    that corrections may be made before the preliminary print goes to press.
    SUPREME COURT OF THE UNITED STATES
    _________________
    No. 132, Orig.
    _________________
    STATE OF ALABAMA, STATE OF FLORIDA, STATE OF
    TENNESSEE, COMMONWEALTH OF VIRGINIA, AND
    SOUTHEAST INTERSTATE LOW-LEVEL RADIO-
    ACTIVE WASTE MANAGEMENT COMMISSION,
    PLAINTIFFS v. STATE OF NORTH CAROLINA
    ON EXCEPTIONS TO THE PRELIMINARY AND SECOND REPORTS
    OF THE SPECIAL MASTER
    [June 1, 2010]
    JUSTICE SCALIA delivered the opinion of the Court.
    In this case, which arises under our original jurisdiction,
    U. S. Const., Art. III, §2, cl. 2; 
    28 U. S. C. §1251
    (a), we
    consider nine exceptions submitted by the parties to two
    reports filed by the Special Master.
    I
    In 1986, Congress granted its consent under the Com­
    pact Clause, U. S. Const., Art. I, §10, cl. 3, to seven inter­
    state compacts providing for the creation of regional facili­
    ties to dispose of low-level radioactive waste. Omnibus
    Low-Level Radioactive Waste Interstate Compact Consent
    Act, 
    99 Stat. 1859
    . One of those compacts was the South­
    east Interstate Low-Level Radioactive Waste Management
    Compact (Compact), entered into by Alabama, Florida,
    Georgia, Mississippi, North Carolina, South Carolina,
    Tennessee, and Virginia. 
    Id.,
     at 1871–1880. That Com­
    pact established an “instrument and framework for a
    cooperative effort” to develop new facilities for the long­
    2              ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    term disposal of low-level radioactive waste generated
    within the region. Art. 1, id., at 1872. The Compact was
    to be administered by a Southeast Interstate Low-Level
    Radioactive Waste Management Commission (Commis­
    sion), composed of two voting members from each party
    State. Art. 4(A), id., at 1874.
    A pre-existing facility in Barnwell, South Carolina was
    to serve as the initial facility for regional generators to
    dispose of their low-level radioactive waste. Art. 2(10), id.,
    at 1873. That facility was scheduled to close as the re­
    gional-disposal facility for the Compact by the end of 1992,
    ibid., and so the Compact required the Commission to
    develop “procedures and criteria for identifying . . . a host
    [S]tate for the development of a second regional disposal
    facility,” and to “seek to ensure that such facility is li­
    censed and ready to operate as soon as required but in no
    event later than 1991,” Art. 4(E)(6), id., at 1875. The
    Compact authorized the Commission to “designate” a
    party State as a host State for the facility. Art. 4(E)(7),
    ibid.
    In September 1986, the Commission designated North
    Carolina as the host for the second facility. North Caro­
    lina therefore became obligated to “take appropriate steps
    to ensure that an application for a license to construct and
    operate a [low-level radioactive waste storage facility] is
    filed with and issued by the appropriate authority.” Art.
    5(C), id., at 1877. In 1987, North Carolina’s General
    Assembly created the North Carolina Low-Level Radioac­
    tive Waste Management Authority (Authority) to fulfill
    the State’s obligation. N. C. Gen. Stat. §104G (1987), 1987
    N. C. Sess. Laws ch. 850.
    Although “[t]he Commission is not responsible for any
    costs associated with,” among other things, “the creation of
    any facility,” Art. 4(K)(1), 
    99 Stat. 1876
    , North Carolina
    asked the Commission for financial assistance with build­
    ing and licensing costs. The Commission responded by
    Cite as: 560 U. S. ____ (2010)           3
    Opinion of the Court
    adopting a resolution, which declared it was both “appro­
    priate and necessary” for the Commission “to provide
    financial assistance” to North Carolina. App. 63. To that
    end, the Commission created a “Host States Assistance
    Fund” to help North Carolina with the “financial costs and
    burdens” of “preliminary planning, the administrative
    preparation, and other pre-operational” activities. Id., at
    64.
    The estimate in 1989 was that it would cost approxi­
    mately $21 million and take two years to obtain a license
    for North Carolina’s regional-disposal facility.      That
    proved to be wildly optimistic. By 1990, the cost estimate
    had ballooned to $45.8 million, and the estimated date for
    obtaining a license now extended far into 1993. At the
    beginning of 1994 there still was no license, and the esti­
    mated cost had grown to $87.1 million. By end of 1994 the
    estimate was $112.5 million, and issuance of a license was
    not anticipated until 1997. And by December 1996 the
    estimated cost had increased by another $27 million and
    the projected date to receive a license had become August
    2000.
    North Carolina’s own appropriations—approximately
    $27 million from Fiscal Year 1988 through Fiscal Year
    (FY) 1995—did not cover the costs of the licensing phase.
    But during the same time period, the Commission pro­
    vided North Carolina with approximately $67 million.
    The funds came from surcharges and access fees collected
    for that purpose from generators disposing of low-level
    radioactive waste at the pre-existing Barnwell facility.
    Id., at 71–74, 145.
    In July 1995, however, South Carolina withdrew from
    the Compact, thereby depriving the Commission of contin­
    ued revenues from the Barnwell facility. In 1996, the
    Commission accordingly informed North Carolina that it
    would no longer be able to provide financial support for
    licensing activities. The Governor of North Carolina
    4              ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    responded that the State was not prepared to assume a
    greater portion of the project’s costs, and would not be able
    to proceed without continued Commission funding.
    Shortly thereafter the Commission adopted a resolution
    declaring that it was willing and able to provide additional
    funds, but calling on North Carolina to work with it to
    develop long-term funding sources for the facility. From
    FY 1996 through FY 1998, the Commission provided
    North Carolina approximately an additional $12.27 mil­
    lion in financial assistance. North Carolina, for its part,
    continued to provide its own funds toward licensing activi­
    ties—another $6 million during the same time period.
    In August 1997, the Commission notified North Caro­
    lina that absent a plan for funding the remaining steps of
    the licensing phase, it would not disburse additional funds
    to North Carolina after November 30, 1997. North Caro­
    lina responded that it would not be able to continue with­
    out additional guarantees of external funding. On Decem­
    ber 1, 1997, the parties having failed to agree upon a long­
    term financing plan, the Commission ceased financial
    assistance to North Carolina. By then it had provided
    almost $80 million.
    On December 19, 1997, North Carolina informed the
    Commission it would commence an orderly shutdown of its
    licensing project, and since that date has taken no further
    steps toward obtaining a license for the facility. But it did
    continue to fund the Authority for several more years, in
    the hope that the project would resume upon the restora­
    tion of external financial assistance. North Carolina
    maintained the proposed facility site, preserved the work
    it had completed to date, and retained the Authority’s
    books and records. It also participated in discussions with
    the Commission, generators of low-level radioactive waste,
    and other stakeholders regarding options to resolve the
    financing shortfall. From FY 1988 through FY 2000,
    North Carolina had expended almost $34 million toward
    Cite as: 560 U. S. ____ (2010)            5
    Opinion of the Court
    obtaining a license.
    In June 1999, after attempts to resolve the funding
    impasse had failed, Florida and Tennessee filed with the
    Commission a complaint for sanctions against North
    Carolina. It alleged that North Carolina had failed to
    fulfill its obligations under the Compact, and requested
    (among other things) return of the almost $80 million paid
    to North Carolina by the Commission, plus interest, as
    well as damages and attorney’s fees. The next month,
    North Carolina withdrew from the Compact by enacting a
    law repealing its status as a party State, see 1999 N. C.
    Sess. Laws ch. 357, as required by Article 7(G) of the
    Compact.
    More than four months later, in December 1999, the
    Commission held a sanctions hearing. North Carolina did
    not participate. After the hearing, the Commission con­
    cluded that North Carolina had failed to fulfill its obliga­
    tions under the Compact. It adopted a resolution demand­
    ing that North Carolina repay approximately $80 million,
    plus interest, to the Commission; pay an additional $10
    million penalty to compensate the Commission for the loss
    of future revenue (surcharges and access fees) it would
    have received had a facility been completed in North
    Carolina; and pay the Commission’s attorney’s fees. North
    Carolina did not comply.
    In July 2000, seeking to enforce its sanctions resolution,
    the Commission moved for leave to file a bill of complaint
    under our original jurisdiction. Southeast Interstate Low-
    Level Radioactive Waste Management Commission v.
    North Carolina, No. 131, Orig. North Carolina opposed
    the motion on the grounds that the Commission could not
    invoke this Court’s original jurisdiction, and we invited
    the Solicitor General to express the views of the United
    States. 
    531 U. S. 942
     (2000). The Solicitor General filed a
    brief urging denial of the Commission’s motion on the
    grounds that the Commission’s bill of complaint did not
    6              ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    fall within our exclusive original jurisdiction over “contro­
    versies between two or more States.” §1251(a). We denied
    the Commission’s motion. 
    533 U. S. 926
     (2001).
    In June 2002, the States of Alabama, Florida, Tennes­
    see, and Virginia, joined by the Commission (collectively
    Plaintiffs), moved for leave to file a bill of complaint
    against North Carolina. North Carolina opposed the
    motion, and we again sought the views of the Solicitor
    General. 
    537 U. S. 806
     (2002). The United States urged
    that we grant Plaintiffs’ motion, which we did. 
    539 U. S. 925
     (2003). The bill of complaint contains five counts:
    violation of the party States’ rights under the Compact
    (Count I); breach of contract (Count II); unjust enrichment
    (Count III), promissory estoppel (Count IV); and money
    had and received (Count V). Plaintiffs’ prayer for relief
    requests a declaration that North Carolina is subject to
    sanctions and that the Commission’s sanctions resolution
    is valid and enforceable, as well as the award of damages,
    costs, and other relief.
    We assigned the case to a Special Master, 
    540 U. S. 1014
     (2003), who has conducted proceedings and now has
    filed two reports. The Master’s Preliminary Report ad­
    dressed three motions filed by the parties. He recom­
    mended denying without prejudice North Carolina’s mo­
    tion to dismiss the Commission’s claims against North
    Carolina on the grounds of sovereign immunity. Prelimi­
    nary Report 4–14. He recommended denying Plaintiffs’
    motion for summary judgment on Count I, which sought
    enforcement of the Commission’s sanctions resolution. 
    Id.,
    at 14–33. He recommended granting North Carolina’s
    cross-motion to dismiss Count I and other portions of the
    bill of complaint that sought enforcement of the sanctions
    resolution. 
    Id.,
     at 33–34. And he recommended denying
    North Carolina’s motion to dismiss the claims in Counts
    II–V. 
    Id.,
     at 34–43.
    After the Special Master issued his Preliminary Report,
    Cite as: 560 U. S. ____ (2010)             7
    Opinion of the Court
    the parties engaged in partial discovery and subsequently
    filed cross-motions for summary judgment. The Special
    Master’s Second Report recommended denying Plaintiffs’
    motion for summary judgment on Count II, Second Report
    8–35, and granting North Carolina’s motion for summary
    judgment on Count II, 
    id.,
     at 35–40. Finally, he recom­
    mended denying North Carolina’s motion for summary
    judgment on Plaintiffs’ remaining claims in Counts III–V.
    
    Id.,
     at 41–45.
    II
    Plaintiffs present a total of seven exceptions to the
    Special Master’s two reports. We address them in turn.
    A
    Their first exception challenges the Special Master’s
    conclusion that the Commission lacked authority to im­
    pose monetary sanctions upon North Carolina. The terms
    of the Compact determine that question.
    Article 4(E) of the Compact sets forth the Commission’s
    “duties and powers.” Among its powers are the authority
    “[t]o revoke the membership of a party [S]tate that will­
    fully creates barriers to the siting of a needed regional
    facility,” Art. 4(E)(7), 
    99 Stat. 1875
    , and the authority “[t]o
    revoke the membership of a party [S]tate in accordance
    with Article 7(f),” Art. 4(E)(11), 
    ibid.
     Conspicuously ab­
    sent from Article 4, however, is any mention of the author­
    ity to impose monetary sanctions. Plaintiffs contend that
    authority may be found elsewhere—in the first paragraph
    of Article 7(F), which provides in relevant part:
    “Any party [S]tate which fails to comply with the
    provisions of this compact or to fulfill the obligations
    incurred by becoming a party [S]tate to this compact
    may be subject to sanctions by the Commission, in­
    cluding suspension of its rights under this compact
    and revocation of its status as a party [S]tate.” 
    Id.,
     at
    8              ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    1879.
    The sanctions expressly identified in Article 7(F)—
    “suspension” of rights and “revocation” of party-state
    status—flow directly from the Commission’s power in
    Articles 4(E)(7) and (11) to revoke a party State’s member­
    ship. That can fairly be understood to include the lesser
    power to suspend a party State’s rights. There is no simi­
    lar grounding in Article 4(E) of authority to impose mone­
    tary sanctions, and the absence is significant.
    According to Plaintiffs, however, the word “sanctions” in
    Article 7(F) naturally “includ[es]” monetary sanctions.
    Since the Compact contains no definition of “sanctions,”
    we give the word its ordinary meaning. A “sanction” (in
    the sense the word is used here) is “[t]he detriment loss of
    reward, or other coercive intervention, annexed to a viola­
    tion of a law as a means of enforcing the law.” Webster’s
    New International Dictionary 2211 (2d ed. 1957) (herein­
    after Webster’s Second); see Black’s Law Dictionary 1458
    (9th ed. 2009) (“A penalty or coercive measure that results
    from failure to comply with a law, rule, or order”). A
    monetary penalty is assuredly one kind of “sanction.” See
    generally Department of Energy v. Ohio, 
    503 U. S. 607
    ,
    621 (1992). But there are many others, ranging from the
    withholding of benefits, or the imposition of a nonmone­
    tary obligation, to capital punishment. The Compact
    surely does not authorize the Commission to impose all of
    them.
    Ultimately, context dictates precisely which “sanctions”
    are authorized under Article 7(F), and nothing in the
    Compact suggests that these include monetary measures.
    The only two “sanctions” specifically identified as being
    included within Article 7(F) are “suspension” of a State’s
    rights under the Compact and “revocation” of its status as
    a party State. These are arguably merely examples, and
    may not exhaust the universe of sanctions the Commission
    Cite as: 560 U. S. ____ (2010)           9
    Opinion of the Court
    can impose. But they do establish “illustrative applica­
    tion[s] of the general principle,” Federal Land Bank of St.
    Paul v. Bismarck Lumber Co., 
    314 U. S. 95
    , 100 (1941),
    which underlies the kinds of sanctions the Commission
    can impose. It is significant that both these specifically
    authorized sanctions are prospective and nonmonetary in
    nature.
    Moreover, Article 3 of the Compact provides: “The rights
    granted to the party [S]tates by this compact are addi­
    tional to the rights enjoyed by sovereign states, and noth­
    ing in this compact shall be construed to infringe upon,
    limit, or abridge those rights.” 
    99 Stat. 1873
    . Construing
    Article 7(F) to authorize monetary sanctions would violate
    this provision, since the primeval sovereign right is im­
    munity from levies against the government fisc. See, e.g.,
    Alden v. Maine, 
    527 U. S. 706
    , 750–751 (1999).
    Finally, a comparison of the Compact’s terms with those
    of “[o]ther interstate compacts, approved by Congress
    contemporaneously,” Texas v. New Mexico, 
    462 U. S. 554
    ,
    565 (1983), confirms that Article 7(F) does not authorize
    monetary sanctions. At the same time Congress consented
    to this Compact, it consented to three other interstate
    compacts that expressly authorize their commissions to
    impose monetary sanctions against the parties to the
    compacts. See Northeast Interstate Low-Level Radioac­
    tive Waste Management Compact, Art. IV(i)(14), 
    99 Stat. 1915
     (hereinafter Northeast Compact); Central Midwest
    Interstate Low-Level Radioactive Waste Compact, Art.
    VIII(f), 
    99 Stat. 1891
     (hereinafter Central Midwest Com­
    pact); Central Interstate Low-Level Radioactive Waste
    Compact, Art. VII(e), 
    99 Stat. 1870
     (hereinafter Central
    Compact). The Compact “clearly lacks the features of
    these other compacts, and we are not free to rewrite it” to
    empower the Commission to impose monetary sanctions.
    Texas v. New Mexico, 
    462 U. S., at 565
    .
    10              ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    B
    Because the Compact does not authorize the Commis­
    sion to impose monetary sanctions, Plaintiffs’ second
    exception—that North Carolina could not avoid monetary
    sanctions by withdrawing from the Compact—is moot.
    The third exception also pertains to the Commission’s
    sanctions resolution: that North Carolina forfeited its
    right to object to a monetary penalty by failing to partici­
    pate at the sanctions hearing. Plaintiffs have failed to
    argue this exception. They have merely noted that North
    Carolina refused to participate at the sanctions hearing,
    and have cited no law in support of the proposition that
    this was a forfeit. We deem the exception abandoned. It
    was wisely abandoned, because it is meritless. North
    Carolina opposed the sanctions resolution and denied that
    the Commission had jurisdiction to impose sanctions
    against it.
    C
    Plaintiffs next take exception to the Special Master’s
    recommendation that no binding effect or even deference
    be accorded to the Commission’s conclusion that North
    Carolina violated Article 5(C) of the Compact. We are
    bound by the Commission’s conclusion of breach only if
    there is “an explicit provision or other clear indicatio[n]” in
    the Compact making the Commission the “sole arbiter of
    disputes” regarding a party State’s compliance with the
    Compact. 
    Id.,
     at 569–570. Plaintiffs assert there is such a
    provision, the second sentence of Article 7(C), which
    states: “The Commission is the judge of the qualifications
    of the party [S]tates and of its members and of their com­
    pliance with the conditions and requirements of this com­
    pact and the laws of the party [S]tates relating to the
    enactment of this compact.” 
    99 Stat. 1879
    .
    Plaintiffs greatly overread this provision. The limited
    nature of the authority to “judge” that it confers upon the
    Cite as: 560 U. S. ____ (2010)           11
    Opinion of the Court
    Commission is clear from its context. The first sentence of
    Article 7(C) states that an eligible State “shall be de­
    clared” a party State “upon enactment of this compact into
    law by the [S]tate and upon [the] payment of” a $25,000
    fee, as “required by Article 4(H)(1).” 
    Ibid.
     The second
    sentence makes the Commission the “judge” of four mat­
    ters, all of which concern status as a party State or Com
    mission member. First, the Commission is the judge of the
    “qualifications” of a State to become a party State (the
    qualifications set forth in Article 7(A) for the initial party
    States and in Article 7(B) for States that subsequently
    petition to join). Second, the Commission is the judge of
    the qualifications of the members of the Commission,
    which are specified in Article 4(A). Third, the Commission
    is the judge of a party State’s compliance with the “condi­
    tions” and “requirements” of the Compact. The former
    term is an obvious reference to Article 7(B): “The Commis­
    sion may establish such conditions as it deems necessary
    and appropriate to be met by a [S]tate wishing . . . to
    become a party [S]tate to this [C]ompact.” 
    Id., at 1878
    .
    The accompanying term “requirements” also refers to
    Article 7’s prescriptions for prospective party States, such
    as paying the “fees required” under Article 7(C), 
    id., at 1879
    , and obtaining, as Article 7(B) requires, a two-thirds
    vote of the Commission in favor of admission. Finally, the
    Commission is the judge of the “laws of the party [S]tates
    relating to the enactment of this compact.” Art. 7(C), 
    ibid.
    Again, that concerns status as a party State, which re­
    quires that the State “enac[t] . . . this compact into law,”
    
    ibid.
     The Commission is the “judge” of only these specific
    matters.
    This is not to say the Commission lacks authority to
    interpret the Compact or to say whether a party State has
    violated its terms. That is of course implicit in its power
    to sanction under Article 7(F). But because “the express
    terms of the [Southeast] Compact do not constitute the
    12             ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    Commission as the sole arbiter” regarding North Caro­
    lina’s compliance with its obligations under the Compact,
    Texas v. New Mexico, 
    462 U. S., at 569
    , we are not bound
    to follow the Commission’s findings.
    Plaintiffs argue that we nonetheless owe deference to
    the Commission’s conclusion. But unless the text of an
    interstate compact directs otherwise, we do not review the
    actions of a compact commission “on the deferential model
    of judicial review of administrative action by a federal
    agency.” 
    Id.,
     at 566–567. The terms of this Compact do
    not establish that “this suit may be maintained only as
    one for judicial review of the Commission’s” determination
    of breach. 
    Id., at 567
    . Accordingly, we do not apply ad­
    ministrative-law standards of review, but exercise our
    independent judgment as to both fact and law in executing
    our role as the “exclusive” arbiter of controversies between
    the States, §1251(a).
    D
    Plaintiffs’ next two exceptions are to the Special Mas­
    ter’s recommendations to deny their motion for summary
    judgment on their breach-of-contract claims, and to grant
    North Carolina’s motion for summary judgment on those
    claims. In resolving motions for summary judgment in
    cases within our original jurisdiction, we are not techni­
    cally bound by the Federal Rules of Civil Procedure, but
    we use Rule 56 as a guide. This Court’s Rule 17.2; Ne
    braska v. Wyoming, 
    507 U. S. 584
    , 590 (1993). Hence,
    summary judgment is appropriate where there “is no
    genuine issue as to any material fact” and the moving
    party is “entitled to a judgment as a matter of law.” Fed.
    Rule Civ. Proc. 56(c); see Celotex Corp. v. Catrett, 
    477 U. S. 317
    , 322 (1986); Anderson v. Liberty Lobby, Inc., 
    477 U. S. 242
    , 248 (1986).
    Cite as: 560 U. S. ____ (2010)
    13
    Opinion of the Court
    1
    Plaintiffs claim North Carolina breached the Compact in
    December 1997, when (as it admits) it ceased all efforts
    toward obtaining a license. At that point, in their view,
    North Carolina was no longer “tak[ing] appropriate steps
    to ensure that an application for a license to construct and
    operate a [low-level radioactive waste storage facility] is
    filed with and issued by the appropriate authority,” Art.
    5(C), 
    99 Stat. 1877
    . North Carolina says that once the
    Commission ceased providing financial assistance on
    December 1, and once it became clear there was insuffi­
    cient funding to complete the licensing phase, there were
    no more “appropriate” steps to take. The Special Master
    concluded that the phrase “appropriate steps” in Article
    5(C) was ambiguous, and that the parties’ course of per­
    formance established that North Carolina was not re­
    quired to take steps toward obtaining a license once it was
    made to bear the remaining financial burden of the licens­
    ing phase. Second Report 10–24, 35–36. Plaintiffs take
    exception to that conclusion.
    Article 5(C) does not require North Carolina to take any
    and all steps to license a regional-disposal facility; only
    those that are “appropriate.” Plaintiffs contend that this
    requires North Carolina to take the steps set forth in the
    regulations of the Nuclear Regulatory Commission govern­
    ing the filing and disposition of applications for licenses to
    operate radioactive waste disposal facilities, 10 CFR pt. 61
    (1997). Those regulations set forth some, but certainly not
    all, of the “steps” the State would have to take to obtain a
    license. But Article 5(C) does not incorporate the regula­
    tions by reference, much less describe them as the appro
    priate steps.
    We could accept Plaintiffs’ contention if “appropriate”
    meant “necessary” (the steps set forth in the regulation
    are assuredly necessary to obtaining a license). But it
    does not. Whether a particular step is “appropriate”—
    14             ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    “[s]pecially suitable; fit; proper,” Webster’s Second 133—
    could depend upon many factors other than its mere in­
    dispensability to obtaining a license. It would not be
    appropriate, for example, to take a step whose cost greatly
    exceeded whatever benefits the license would confer, or if
    it was highly uncertain the license would ever issue.
    In determining whether, in terminating its efforts to
    obtain a license, North Carolina failed to take what the
    parties considered “appropriate” steps, the parties’ course
    of performance under the Compact is highly significant.
    See, e.g., New Jersey v. New York, 
    523 U. S. 767
    , 830–831
    (1998) (SCALIA, J., dissenting); Restatement (Second) of
    Contracts §§202(4), 203 (1979) (hereinafter Restatement).
    That firmly establishes that North Carolina was not ex­
    pected to go it alone—to proceed with the very expensive
    licensing process without any external financial assis­
    tance. The history of the Compact consists entirely of
    shared financial burdens. From the beginning, North
    Carolina made clear that it required financial assistance
    to do the extensive work required for obtaining a license.
    The Commission promptly declared it was “appropriate
    and necessary” to assist North Carolina with the costs.
    App. 63. It provided the vast majority of funding for li­
    censing-related activities—$80 million, compared to North
    Carolina’s $34 million. The Commission repeatedly noted
    the necessity (and propriety) of providing financial assis­
    tance to North Carolina, and reiterated its dedication to
    sharing the substantial financial burdens of the licensing
    phase. See, e.g., id., at 63, 71, 145. There is nothing to
    support the proposition that the other States had an obli­
    gation under the Compact to share the licensing costs
    through the Commission; but we doubt that they did so
    out of love for the Tarheel State. They did it, we think,
    because that was their understanding of how the Compact
    was supposed to work. One must take the Commission at
    its word, that it was “appropriate” to share the cost—
    Cite as: 560 U. S. ____ (2010)           15
    Opinion of the Court
    which suggests that it would not have been appropriate to
    make North Carolina proceed on its own.
    Nor was North Carolina required after December 19,
    1997, to continue to expend its own funds at the same
    level it had previously (which Plaintiffs concede had satis­
    fied North Carolina’s obligation to take “appropriate
    steps”). Once the Commission refused to provide any
    further financial assistance, North Carolina would have
    had to assume an unlimited financial commitment to cover
    all remaining licensing costs. Even if it maintained its
    prior rate of appropriations going forward, it would not
    have come close to covering the at least $34 million needed
    for the last steps of the licensing phase. And since the
    income from the South Carolina facility had been termi­
    nated, there was no apparent prospect of funding for the
    construction phase (expected to cost at least $75 million).
    In connection with its August 1997 refusal to provide
    further assistance, the Commission itself had said, “[I]t
    will be imprudent to continue to deplete Commission
    resources for this purpose if a source of funds is not estab­
    lished soon for the ultimate completion of the project.” Id.,
    at 306, 307; Joint Supp. Fact Brief App. 36, 37. And in
    March 1998, the Commission “strongly” reiterated that “it
    would be imprudent to spend additional funds for licens­
    ing activities if funds will not be available to complete the
    project.” Id., at 59. What was imprudent for the Commis­
    sion would surely have been imprudent (and hence inap­
    propriate) for North Carolina as well. The State would
    have wasted millions of its taxpayers’ dollars on what
    seemed to be a futile effort.
    JUSTICE BREYER would uphold Plaintiffs’ challenge on
    this point. He believes that the Compact obligated North
    Carolina to fund and complete the licensing and construc­
    tion of a nuclear waste facility. Post, at 2, 4–6 (opinion
    concurring in part and dissenting in part). In fact, how­
    ever, North Carolina was not even contractually required
    16                 ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    to “secur[e] a license,” post, at 2, but only to take “appro­
    priate steps” to obtain one, Art. 5(C), 
    99 Stat. 1877
    . And
    nothing in the terms of the Compact required North Caro­
    lina either to provide “adequate funding” for or to “beg[i]n
    construction” on a regional facility, post, at 2. Other con­
    temporaneously enacted interstate compacts expressly
    provide that the host State is “responsible for the timely
    development” of a regional facility, Central Midwest Com­
    pact, Art. VI(f), 
    99 Stat. 1887
    ; Midwest Compact,
    Art. VI(e), 
    id., at 1898
    , or “shall . . . [c]ause a regional
    facility to be developed on a timely basis,” Rocky Mountain
    Low-Level Radioactive Waste Compact, Art. III(d)(i), 
    id.,
    at 1903–1904. But the compact here before us has no such
    provision, and the contrast is telling.1 Texas v. New Mex
    ico, 
    462 U. S., at 565
    . Moreover, the Commission’s state­
    ments described in the preceding paragraph, that it would
    be imprudent to commit additional resources “ ‘if a source
    of funds is not established soon for the ultimate comple­
    tion of the project,’ ” or “ ‘if funds will not be available to
    complete the project,’ ” surely suggest that North Carolina
    is not committed to the funding by contract.
    JUSTICE BREYER asserts, post, at 4–5, that the rotating­
    ——————
    1 The Compact provides only that the host State is “responsible for
    the availability . . . of their regional facilities in accordance with”
    Article 5(B). Art. 3(C), 
    99 Stat. 1873
    –1874. The latter section makes
    clear that responsibility for “availability” does not mean that the host
    State will fund construction of the facility, but that it will keep it open
    and not impose unreasonable restrictions on its use. JUSTICE BREYER is
    correct that the Compact says the Commission is not “responsible” for
    the costs of “the creation” of a regional facility. Art. 4(K)(1), 
    id., at 1876
    . But what is important here is that it does not say that the host
    State is responsible—which (if it were true) would almost certainly
    have been joined with saying who was not responsible. What JUSTICE
    BREYER overlooks is the possibility that no one is responsible, and the
    licensing and construction of the facility is meant to depend upon
    voluntary funding by interested parties, such as the party States, the
    Commission, and low-level radioactive waste generators.
    Cite as: 560 U. S. ____ (2010)                   17
    Opinion of the Court
    host requirement in the Compact, see Art. 5(A), 
    99 Stat. 1873
    , necessarily implies that North Carolina is solely
    responsible for the licensing and construction costs of its
    facility. But all that requirement entails is that a party
    State “shall not be designated” as a host State for a second
    time before “each [other] party [S]tate” has taken a turn.
    
    Ibid.
     It can perfectly well envision that the States will
    take turns in bearing the lead responsibility for getting
    the facility licensed, supervising its construction, and
    operating the facility on its soil. In fact, that is just what
    its text suggests, since it describes the responsibility that
    is to be rotated as the host State’s “obligation . . . to have a
    regional facility operated within its borders.” 
    Ibid.
     Not to
    construct it, or pay for its construction, but to “have [it]
    operated within its borders.” As noted above, other con­
    temporaneously enacted compacts do spell out the obliga­
    tion of the host State to construct the facility. Still others
    at least provide that the host State will recoup its costs
    through disposal fees—which arguably suggests that the
    host State is to bear the costs. See, e.g., Central Compact,
    Art. III(d),    
    99 Stat. 1865
    ;     Northeast       Compact,
    Art. III(c)(2), 
    id., at 1913
    . The compact before us here
    does not even contain that arguable suggestion.
    What it comes down to, then, is JUSTICE BREYER’s intui­
    tion that the whole point of the Compact was that each
    designated host State would bear the up-front costs of
    licensing and construction, but would eventually recoup
    those costs through its regional monopoly on the disposal
    of low-level radioactive waste. Post, at 5–6. He can cite no
    provision in the Compact which reflects such an under­
    standing, and the behavior of the parties contradicts it.2 It
    ——————
    2 The course-of-dealing evidence that JUSTICE BREYER identifies, post,
    at 6–7, is not probative. The Commission’s statements that it is not
    legally responsible for costs and that at some point Commission funds
    will no longer be available, and North Carolina’s assurances that it will
    keep its commitments and honor its obligations, are perfectly compati­
    18                 ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    would, moreover, have been a foolish understanding, since
    the regional monopoly to recoup construction costs would
    not be a monopoly if South Carolina withdrew and contin­
    ued to operate its facility—which is exactly what hap­
    pened in 1995.3 Even leaving aside the principle, dis­
    cussed infra, at 21, that implied obligations are not to be
    read into interstate compacts, JUSTICE BREYER’s intuition
    fails to reflect the reality of what was implied.
    2
    Plaintiffs take exception to the Special Master’s rejec­
    tion of their alternative argument that North Carolina
    repudiated the Compact when it announced it would not
    take further steps toward obtaining a license. They argue
    that North Carolina’s announcement that it was shutting
    down the project constituted a refusal to tender any fur­
    ther performance under the contract.
    Plaintiffs’ repudiation theory fails for the same reasons
    their breach theory fails. A repudiation occurs when an
    obligor either informs an obligee “that the obligor will
    ——————
    ble with the proposition that North Carolina did not have to provide all
    funding for licensing the facility, and that it would be “inappropriate” to
    proceed toward obtaining a license for a facility that would never be
    needed or built.
    3 South Carolina’s withdrawal from the Compact not only “could”
    affect North Carolina’s ability to recoup its facility costs, as JUSTICE
    BREYER grudgingly concedes, post, at 5; it unquestionably would. With
    a regional competitor in the Barnwell facility and declining demand for
    waste disposal facilities due to technological and other factors, App.
    261, 263–264, North Carolina would receive significantly lower reve­
    nues from its facility, 
    id.,
     at 261–262, 265. The document attached to a
    1996 letter from North Carolina to the Commission trumpeting “$600
    million in cost savings” that would come from a new facility, post, at 5,
    proves precisely the opposite of what JUSTICE BREYER thinks. The cost
    savings were to accrue “to all generators” of waste, App. 266 (emphasis
    added)—that is, those who would use North Carolina’s facility. Those
    savings would come, of course, from lower costs for waste disposal,
    which means that North Carolina would be charging lower rates than
    the Barnwell facility (and thus receiving lower revenues).
    Cite as: 560 U. S. ____ (2010)            19
    Opinion of the Court
    commit a breach that would of itself give the obligee a
    claim for damages for total breach,” Restatement §250(a),
    or performs “a voluntary affirmative act which renders the
    obligor unable or apparently unable to perform without
    such a breach,” id., §250(b). Neither event occurred here.
    North Carolina never informed the Commission (or any
    party State) that it would not fulfill its Article 5(C) obliga­
    tion to take appropriate steps toward obtaining a license.
    Rather, it refused to take further steps that were not
    appropriate. Nor did North Carolina take an affirmative
    act that rendered it unable to perform. To the contrary, it
    continued to fund the Authority for almost two years; it
    maintained the records of the Authority; and it preserved
    the work completed to date while waiting for alternative
    funding sources that would enable resumption of the
    project. Plaintiffs further argue that a repudiation was
    effected by North Carolina’s refusal to take further steps
    toward licensing “except on conditions which go beyond”
    the terms of the Compact, Restatement §250, Comment b
    (internal quotation marks omitted)—i.e., the provision of
    external-financial assistance. But, as we have discussed,
    external-financial assistance was contemplated by the
    Compact.
    E
    Plaintiffs’ final exception is to the Special Master’s
    recommendation to deny their motion for summary judg­
    ment, and to grant North Carolina’s cross-motion for
    summary judgment, on their claim that North Carolina
    violated the implied duty of good faith and fair dealing
    when it withdrew from the Compact in July 1999. Plain­
    tiffs concede that North Carolina could withdraw from the
    Compact, but contend it could not do so in “bad faith.”
    And, they assert, its withdrawal after accepting $80 mil­
    lion from the Commission, and with monetary sanctions
    pending against it, was the epitome of bad faith.
    20                ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    We have never held that an interstate compact approved
    by Congress includes an implied duty of good faith and
    fair dealing. Of course “[e]very contract imposes upon
    each party a duty of good faith and fair dealing in its
    performance and enforcement.” Restatement §205. But
    an interstate compact is not just a contract; it is a federal
    statute enacted by Congress. If courts were authorized to
    add a fairness requirement to the implementation of
    federal statutes, judges would be potent lawmakers in­
    deed. We do not—we cannot—add provisions to a federal
    statute. See, e.g., Connecticut Nat. Bank v. Germain, 
    503 U. S. 249
    , 254 (1992). And in that regard a statute which
    is a valid interstate compact is no different. Texas v. New
    Mexico, 
    462 U. S., at 564, 565
    . We are especially reluctant
    to read absent terms into an interstate compact given the
    federalism and separation-of-powers concerns that would
    arise were we to rewrite an agreement among sovereign
    States, to which the political branches consented. As we
    have said before, we will not “ ‘order relief inconsistent
    with [the] express terms’ ” of a compact, “no matter what
    the equities of the circumstances might otherwise invite.”
    New Jersey v. New York, 
    523 U. S., at 811
     (quoting Texas
    v. New Mexico, 
    supra, at 564
    ).
    The Compact imposes no limitation on North Carolina’s
    exercise of its statutory right to withdraw. Under Article
    7(G), which governed North Carolina’s withdrawal,4 “any
    party [S]tate may withdraw from the compact by enacting
    a law repealing the compact.” 
    99 Stat. 1879
    . There is no
    restriction upon a party State’s enactment of such a law,
    ——————
    4 After North Carolina was designated as a host State, the Compact
    was amended to add Article 7(H), which restricted the ability of a party
    State to withdraw to within 30 days after a second regional-disposal
    facility opened. Southeast Interstate Low-Level Radioactive Waste
    Compact Amendments Consent Act of 1989, Pub. L. 101–171, §2, 
    103 Stat. 1289
    . That provision did not apply when North Carolina with­
    drew, because its facility had not been opened.
    Cite as: 560 U. S. ____ (2010)          21
    Opinion of the Court
    and nothing in the Compact suggests the parties under­
    stood there were “certain purposes for which the expressly
    conferred power . . . could not be employed.” Tymshare,
    Inc. v. Covell, 
    727 F. 2d 1145
    , 1153 (CADC 1984) (opinion
    for the court by Scalia, J.). Moreover, Article 3 ensures
    that no such restrictions may be implied, since it provides
    that the Compact shall not be “construed to infringe upon,
    limit or abridge” the sovereign rights of a party State.
    A comparison of the Compact with other, contemporane­
    ously enacted, compacts confirms there is no such limita­
    tion on North Carolina’s right to withdraw. See Texas v.
    New Mexico, 
    supra, at 565
    . In contrast to the Compact,
    several other compacts concerning the creation of regional
    facilities for the disposal of low-level radioactive waste
    contain express good-faith limitations upon a State’s
    exercise of its rights.      See, e.g., Central Compact,
    Art. III(f), 
    99 Stat. 1865
    ; Central Midwest Compact,
    Art. V(a), 
    id., at 1886
    ; Midwest Interstate Low-Level
    Radioactive Waste Management Compact, Art. V(a), 
    id., at 1897
    .
    III
    North Carolina submits two exceptions—one to the
    Special Master’s Second Report and one to his Preliminary
    Report.
    A
    North Carolina takes exception to the recommendation
    of the Second Report to deny without prejudice its motion
    for summary judgment on the merits of Plaintiffs’ equita­
    ble claims in Counts III–V. North Carolina’s motion was
    based on the ground that, as a matter of law, its obliga­
    tions are governed entirely by the Compact. The Special
    Master recommended denying the motion without preju­
    dice, because the claims in Counts III–V “requir[e] further
    briefing and argument, and possibly further discovery.”
    22                ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    Second Report 41. A threshold question for all claims in
    those Counts, for example, is whether they “belong to the
    Commission, the Plaintiff States, or both.” 
    Ibid.
     Perhaps
    the States can bring them in their capacity as parens
    patriae, but as the Special Master noted “the parties have
    not adequately briefed this issue, and its resolution in this
    case is unclear.” 
    Id.,
     at 42–43.
    We think it was reasonable for the Special Master to
    defer ruling. We granted the Special Master discretion to
    “direct subsequent proceedings” and “to submit such re­
    ports as he may deem appropriate.” 540 U. S., at 1014.
    He could have deferred filing any report until full factual
    discovery had been completed and all of the legal issues,
    many of which are novel and challenging, had been fully
    briefed, considered, and decided. Instead, he concluded
    that our immediate resolution of Counts I and II would
    facilitate the efficient disposition of the case; and in agree­
    ing to hear exceptions to his Preliminary Report and
    Second Report we implicitly agreed. His deferral of ruling
    on the merits of Counts III–V is part and parcel of the
    same case management, and we find no reason to upset it.
    B
    North Carolina takes exception to the Special Master’s
    recommendation in his Preliminary Report to deny with­
    out prejudice its motion to dismiss the Commission’s
    claims on the ground that they are barred by the Eleventh
    Amendment to the Constitution and by structural princi­
    ples of state sovereign immunity. The Special Master
    assumed for the sake of argument that a State possesses
    sovereign immunity against a claim brought by an entity,
    like the Commission, created by an interstate compact,5
    ——————
    5 We have held that an entity created through a valid exercise of the
    Interstate Compact Clause is not entitled to immunity from suit under
    the Eleventh Amendment, see Hess v. Port Authority Trans-Hudson
    Corporation, 
    513 U. S. 30
     (1994), but we have not decided whether such
    Cite as: 560 U. S. ____ (2010)                   23
    Opinion of the Court
    Preliminary Report 5. But he recommended denying
    North Carolina’s motion to dismiss “at this point in the
    proceedings.” 
    Ibid.
    The Special Master relied upon our decision in Arizona
    v. California, 
    460 U. S. 605
     (1983), which held that the
    Eleventh Amendment did not bar the participation of
    several Indian Tribes in an original action concerning the
    allocation of rights to the waters of the Colorado River.
    The United States had already intervened, in its capacity
    as trustee for several Indian Tribes; but the Tribes moved
    to intervene as well, and the States opposed. We granted
    the Tribes’ motion, stating that the States do not enjoy
    sovereign immunity against the United States, and “[t]he
    Tribes do not seek to bring new claims or issues against
    the States, but only ask leave to participate in an adjudi­
    cation of their vital water rights that was commenced by
    the United States.” 
    Id., at 614
    . Thus, “our judicial power
    over the controversy is not enlarged by granting leave to
    intervene, and the States’ sovereign immunity protected
    by the Eleventh Amendment is not compromised.” 
    Ibid.
    Relying on this holding, the Special Master held that
    sovereign immunity does not bar the Commission’s suit, so
    long as the Commission asserts the same claims and seeks
    the same relief as the other plaintiffs. Whether that is so,
    he said, “cannot be resolved without further factual and
    legal development[s],” Preliminary Report 6, and so North
    Carolina is free to renew its motion at a later point, 
    id.,
     at
    13–14. See Second Report 45–48.
    Assuming (as the Special Master did) that the Commis­
    sion’s claims against North Carolina implicate sovereign
    immunity, we agree with his disposition. North Carolina
    contends that making application of the Constitution’s
    waiver of sovereign immunity turn upon whether a
    nonsovereign party seeks to expand the relief sought is
    ——————
    an entity’s suit against a State is barred by sovereign immunity.
    24                ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    inconsistent with our decisions construing state sovereign
    immunity as a “personal privilege.” College Savings Bank
    v. Florida Prepaid Postsecondary Ed. Expense Bd., 
    527 U. S. 666
    , 675 (1999) (internal quotation marks omitted);
    see also Alden, 
    527 U. S., at 758
    . But nothing in those
    cases suggests that Arizona v. California has been implic­
    itly overruled.6 See Shalala v. Illinois Council on Long
    Term Care, Inc., 
    529 U. S. 1
    , 18 (2000). Neither of them
    arose under our original jurisdiction, and neither cited
    Arizona v. California or discussed—at all—the sovereign
    immunity issue that case addressed. That sovereign
    immunity is a personal privilege of the States says noth­
    ing about whether that privilege “is not compromised,”
    Arizona v. California, 
    supra, at 614
    , by an additional,
    nonsovereign plaintiff’s bringing an entirely overlapping
    claim for relief that burdens the State with no additional
    defense or liability.7
    North Carolina contends that Arizona v. California
    cannot apply to the Commission’s claims, because the
    Commission does not—indeed, cannot—assert the same
    claims or seek the same relief as the plaintiff States. We
    disagree. In the bill of complaint, the States and the
    Commission assert the same claims and request the same
    relief. Bill of Complaint ¶¶62–86 and Prayer for Relief.
    Their claim for restitution of $80 million cannot, given the
    ——————
    6 North Carolina has not asked us to overrule Arizona v. California,
    
    460 U. S. 605
     (1983). We decline to do so on our own motion and
    without argument. We therefore do not address the merits of THE
    CHIEF JUSTICE’s dissent.
    7 North Carolina also asserts that our decisions in Pennhurst State
    School and Hospital v. Halderman, 
    465 U. S. 89
     (1984), and County of
    Oneida v. Oneida Indian Nation of N. Y., 
    470 U. S. 226
     (1985), under­
    mine Arizona v. California, 
    supra, at 614
    . They do not. In neither case
    were there entirely overlapping claims for relief between sovereign and
    nonsovereign plaintiffs. See Pennhurst, 
    supra, at 103, n. 12
    . Indeed, in
    County of Oneida there was no sovereign plaintiff.
    Cite as: 560 U. S. ____ (2010)           25
    Opinion of the Court
    other allegations of the complaint, be thought to be $80
    million payable to each of the four plaintiff States and the
    Commission.
    North Carolina argues, however, that summary judg­
    ment in its favor is appropriate because it is clear that the
    Commission, and not the plaintiff States, provided $80
    million to North Carolina—wherefore, as a matter of law,
    only the Commission can claim entitlement to $80 million,
    either as a measure of damages for breach of the Compact
    under Counts I and II of the bill of complaint, see Re­
    statement §370, Comment a, and §373, or under the un­
    just enrichment, promissory estoppel, and money-had-and­
    received theories of recovery in Counts III, IV, and V, see,
    e.g., Restatement of Restitution §1, Comment a (1936).
    And, it contends, a stand-alone suit by the Commission is
    barred by sovereign immunity.
    With regard to Counts I and II, at least, we disagree.
    The Commission’s claims under those Compact-related
    Counts are wholly derivative of the States’ claims. See
    Arizona v. California, 
    supra, at 614
    . The Commission is
    “a legal entity separate and distinct from” the States that
    are parties to the Compact. Art. 4(M)(1), 
    99 Stat. 1877
    .
    Since it is not a party it has neither a contractual right to
    performance by the party States nor enforceable statutory
    rights under Article 5 of the Compact, see Bennett v.
    Spear, 
    520 U. S. 154
    , 162–163 (1997). The Compact does,
    however, authorize the Commission to “act or appear on
    behalf of any party [S]tate or [S]tates . . . as an intervenor
    or party in interest before . . . any court of law,” Art.
    4(E)(10), 
    99 Stat. 1875
    , and it is obviously in this capacity
    that the Commission seeks to vindicate the plaintiff
    States’ statutory and contractual rights in Counts I and II.
    Its Count I and Count II claims therefore rise or fall with
    the claims of the States. While the Commission may not
    bring them in a stand-alone action under this Court’s
    original jurisdiction, see §1251(a), it may assert them in
    26             ALABAMA v. NORTH CAROLINA
    Opinion of the Court
    this Court alongside the plaintiff States, see Arizona v.
    California, 
    460 U. S., at 614
    . The summary judgment
    disallowing the underlying claims on their merits renders
    the sovereign immunity question with regard to any relief
    the Commission alone might have on those claims moot.
    Counts III–V, which do not rely upon the Compact,
    stand on a different footing. As to them, while the Com­
    mission again seemingly makes the same claims and seeks
    the same relief as the States, it is conceivable that as a
    matter of law the Commission’s claims are not identical.
    The Commission can claim restitution as the party that
    paid the money to North Carolina; the other plaintiffs
    cannot claim it on that basis. Whether this means that
    the claims are not identical for Arizona v. California pur­
    poses, and that the Commission’s Counts III–V claims
    must be dismissed on sovereign immunity grounds, is a
    question that the Special Master declined to resolve until
    the merits issues were further clarified. We have ap­
    proved his deferral of those issues, and we likewise ap­
    prove his deferral of the related sovereign immunity issue.
    *    *    *
    We overrule the exceptions of Plaintiffs and North
    Carolina to the Special Master’s Reports, and we adopt the
    recommendations of the Special Master. We grant North
    Carolina’s motion to dismiss Count I. We grant North
    Carolina’s motion for summary judgment on Count II. We
    deny Plaintiffs’ motions for judgment on Counts I and II.
    And we deny without prejudice North Carolina’s motion to
    dismiss the Commission’s claims on the grounds of sover­
    eign immunity and its motion for summary judgment on
    Counts III–V.
    It is so ordered.
    Cite as: 560 U. S. ____ (2010)           1
    Opinion of KENNEDY, J.
    SUPREME COURT OF THE UNITED STATES
    _________________
    No. 132, Orig.
    _________________
    STATE OF ALABAMA, STATE OF FLORIDA, STATE OF
    TENNESSEE, COMMONWEALTH OF VIRGINIA, AND
    SOUTHEAST INTERSTATE LOW-LEVEL RADIO-
    ACTIVE WASTE MANAGEMENT COMMISSION,
    PLAINTIFFS v. STATE OF NORTH CAROLINA
    ON EXCEPTIONS TO THE PRELIMINARY AND SECOND REPORTS
    OF THE SPECIAL MASTER
    [June 1, 2010]
    JUSTICE KENNEDY, with whom JUSTICE SOTOMAYOR
    joins, concurring in part and concurring in the judgment.
    The Court is correct, in my view, to conclude that we
    may not “add provisions to a federal statute.” Ante, at 20.
    Plaintiffs do not request as much, however, in contending
    that North Carolina was required by the Compact to carry
    out its obligations in good faith. Rather, plaintiffs’ argu
    ment is that the Compact’s terms, properly construed,
    speak not only to the specific duties imposed upon the
    parties but also to the manner in which those duties must
    be carried out. This is an interpretive argument familiar
    to contract disputes. See, e.g., Restatement (Second) of
    Contracts §205 (1979) (hereinafter Restatement).
    As the opinion for the Court notes, congressional con
    sent to an interstate compact gives it the status of a fed
    eral statute. See ante, at 20. This is an apt and proper
    way to indicate that a compact has all the dignity of an
    Act of Congress. And that is surely what was meant in
    New Jersey v. New York, 
    523 U. S. 767
    , 811 (1998), where
    it was stated that the Court may not “ ‘order relief incon
    sistent with [the] express terms’ ” of a compact. Ante, at
    20 (quoting New Jersey; alteration in original; some inter
    2              ALABAMA v. NORTH CAROLINA
    Opinion of KENNEDY, J.
    nal quotation marks omitted); see also Cuyler v. Adams,
    
    449 U. S. 433
    , 438 (1981) (“[C]ongressional consent trans
    forms an interstate compact . . . into a law of the United
    States”).
    From this principle, however, it simply does not follow
    that a law’s nature and origin as a compact must be dis
    missed as irrelevant. Like a treaty, a compact represents
    an agreement between parties. See New Jersey, 
    supra, at 831
     (SCALIA, J., dissenting) (“[T]he Compact here is of
    course a treaty”). The Court’s duty in interpreting a com
    pact involves ascertaining the intent of the parties. See
    Sullivan v. Kidd, 
    254 U. S. 433
    , 439 (1921) (“[T]reaties are
    to be interpreted upon the principles which govern the
    interpretation of contracts . . . with a view to making
    effective the purposes of the high contracting parties”);
    Wright v. Henkel, 
    190 U. S. 40
    , 57 (1903) (“Treaties must
    receive a fair interpretation, according to the intention of
    the contracting parties”). Carrying out this duty may lead
    the Court to consult sources that might differ from those
    normally reviewed when an ordinary federal statute is at
    issue. That much is surely implicit in the Court’s refer
    ence to contract law principles elsewhere in its opinion in
    the instant case. See, e.g., ante, at 14 (“[T]he parties’
    course of performance under the Compact is highly signifi
    cant”); 
    ibid.
     (citing the Restatement); 
    id.,
     at 18–19 (same);
    see also New Jersey, 
    supra,
     at 830–831 (SCALIA, J., dis
    senting) (construing a compact in light of “hornbook con
    tracts law that the practical construction of an ambiguous
    agreement revealed by later conduct of the parties is good
    indication of its meaning”).
    That said, it is quite correct to hold here that the rea
    sonable expectations of the contracting States, as mani
    fested in the Compact, do not reveal an intent to limit
    North Carolina’s power of withdrawal. For purposes of
    rejecting this argument, it is sufficient to note—as the
    Court does—that the Compact permits any State to with
    Cite as: 560 U. S. ____ (2010)            3
    Opinion of KENNEDY, J.
    draw; imposes no limitation on this right; and explicitly
    provides that the Compact shall not be construed to
    abridge the sovereign rights of any party State. See ante,
    at 20–21. Federalism concerns also counsel reluctance to
    find that a State has implicitly restricted its sovereignty in
    such a manner.
    The Court is therefore correct to reject plaintiffs’ final
    exception. With these observations, I join the Court’s
    opinion with the exception of Part II–E.
    Cite as: 560 U. S. ____ (2010)            1
    Opinion of ROBERTS, C. J.
    SUPREME COURT OF THE UNITED STATES
    _________________
    No. 132, Orig.
    _________________
    STATE OF ALABAMA, STATE OF FLORIDA, STATE OF
    TENNESSEE, COMMONWEALTH OF VIRGINIA, AND
    SOUTHEAST INTERSTATE LOW-LEVEL RADIO-
    ACTIVE WASTE MANAGEMENT COMMISSION,
    PLAINTIFFS v. STATE OF NORTH CAROLINA
    ON EXCEPTIONS TO THE PRELIMINARY AND SECOND REPORTS
    OF THE SPECIAL MASTER
    [June 1, 2010]
    CHIEF JUSTICE ROBERTS, with whom JUSTICE THOMAS
    joins, concurring in part and dissenting in part.
    The parties to this case are Alabama, Florida, North
    Carolina, Tennessee, Virginia, and the Southeast Inter
    state Low-Level Radioactive Waste Management Commis
    sion. One of these things is not like the others: The Com
    mission is not a sovereign State. The Court entertains its
    suit—despite North Carolina’s sovereign immunity—
    because the Commission “asserts the same claims and
    seeks the same relief as the other plaintiffs.” Ante, at 23.
    Our Constitution does not countenance such “no harm, no
    foul” jurisdiction, and I respectfully dissent.
    The Court has made this mistake before. In Arizona v.
    California, 
    460 U. S. 605
     (1983), we allowed Indian Tribes
    that could not sue sovereign States to piggyback on the
    claims of the United States, which could. We reasoned
    that once the United States had initiated suit, the state
    defendants could “no longer . . . assert [their] immunity
    with respect to the subject matter of [the] action,” so the
    Tribes were free to pile on and join the suit. 
    Id., at 614
    .
    Today the Court retraces Arizona’s steps, quoting that
    case for the proposition that when private plaintiffs “ ‘do
    2              ALABAMA v. NORTH CAROLINA
    Opinion of ROBERTS, C. J.
    not seek to bring new claims or issues, . . . our judicial
    power over the controversy is not enlarged . . . , and the
    States’ sovereign immunity protected by the Eleventh
    Amendment is not compromised.’ ” Ante, at 23 (quoting
    Arizona, 
    supra, at 614
    ).
    That statement is contrary to the language of the Con
    stitution. The Eleventh Amendment provides:
    “The Judicial power of the United States shall not
    be construed to extend to any suit in law or equity,
    commenced or prosecuted against one of the United
    States by Citizens of another State, or by Citizens or
    Subjects of any Foreign State.”
    The immunity conferred is against the “commence[ment]
    or prosecut[ion]” of “any suit in law or equity.” There is no
    carve-out for suits “prosecuted” by private parties so long
    as those parties “ ‘do not seek to bring new claims or is
    sues.’ ” Ante, at 23 (quoting Arizona, supra, at 614).
    Understandably, the Court’s opinion leans heavily on
    Arizona, which has never been squarely overruled. Ante,
    at 23–24. But Arizona itself is built on sand. The relevant
    portion of that opinion is almost wholly unreasoned. It
    cites only a footnote in a prior case, the pertinent para
    graph of which failed even to discuss the State’s immunity
    from private suit. See 
    460 U. S., at
    614 (citing Maryland
    v. Louisiana, 
    451 U. S. 725
    , 745, n. 21 (1981)). That para
    graph addressed only intervention, not sovereign immu
    nity, and the two issues are distinct. See South Carolina
    v. North Carolina, 558 U. S. ___, ___, n. 5 (2010) (slip op.,
    at 10, n. 5).
    Most importantly, the subsequent development of our
    sovereign immunity jurisprudence has only undermined
    Arizona’s already weak foundations. We recognized in
    Alden v. Maine, 
    527 U. S. 706
    , 718 (1999), that the Consti
    tution left intact the States’ pre-existing “immunity from
    private suits”; as the Eleventh Amendment confirms, the
    Cite as: 560 U. S. ____ (2010)            3
    Opinion of ROBERTS, C. J.
    States did not “ ‘surrender . . . this immunity in the plan of
    the convention.’ ” 
    Id., at 717
     (quoting The Federalist No.
    81, p. 487 (C. Rossiter ed. 1961) (A. Hamilton)); see also
    Alden, 
    supra,
     at 718–722, 755–756. There is no reason to
    suppose that the States, at the founding, made an excep
    tion for private suits that happen to mimic other plaintiffs’
    claims—and neither Arizona nor the Court today suggests
    otherwise.
    Whether or not a plaintiff “seeks the same relief” or
    imposes any “additional defense or liability,” ante, at 23–
    24, simply does not matter in light of our recognition that
    sovereign immunity provides an “immunity from suit,” not
    a “defense to . . . liability.” Federal Maritime Comm’n v.
    South Carolina Ports Authority, 
    535 U. S. 743
    , 766 (2002).
    As we have explained, “the relief sought by a plaintiff
    suing a State is irrelevant to the question whether the suit
    is barred.” Seminole Tribe of Fla. v. Florida, 
    517 U. S. 44
    ,
    58 (1996). Indeed, we have suggested that private parties
    may not sue even if a court is “precluded . . . from award
    ing them any relief.” Federal Maritime Comm’n, supra, at
    766 (emphasis added) (dictum). It is the fact that a pri
    vate party is allowed to sue a sovereign State—not the
    burden of litigation or the relief sought—that infringes the
    immunity of the State. “The Eleventh Amendment is
    concerned not only with the States’ ability to withstand
    suit, but with their privilege not to be sued.” Puerto Rico
    Aqueduct and Sewer Authority v. Metcalf & Eddy, Inc.,
    
    506 U. S. 139
    , 147, n. 5 (1993).
    It is therefore impossible for the Court to hear private
    claims against a nonconsenting State without expanding
    “our judicial power over the controversy.” Arizona, 
    supra, at 614
    . Sovereign immunity is a limitation on that power.
    The similarity of claims may be relevant to joinder or
    intervention, but those are procedural means of processing
    claims, not fonts of judicial authority. See Henderson v.
    United States, 
    517 U. S. 654
    , 664 (1996).
    4                 ALABAMA v. NORTH CAROLINA
    Opinion of ROBERTS, C. J.
    Nor may the Court entertain private claims without
    “compromis[ing]” “the States’ sovereign immunity.” Ari
    zona, 
    460 U. S., at 614
    . As a party, the Commission enjoys
    legally enforceable rights against the defendant State: It
    may object to settlement, seek taxation of costs, advance
    arguments we are obliged to consider, and plead the
    judgment as res judicata in future litigation. If the Com
    mission truly sought nothing for itself—other than “a full
    exposition of the issues,” Preliminary Report of the Special
    Master 14—it could have participated as an amicus.
    The Commission and North Carolina know that more is
    at stake if the Commission is allowed to sue the State. It
    is precisely the Commission’s status as a party, its attempt
    to “prosecut[e]” a “suit in law or equity . . . against one of
    the United States,” U. S. Const., Amdt. 11, that sovereign
    immunity forbids.
    I would sustain North Carolina’s first exception to the
    Special Master’s reports.*
    ——————
    * I also join JUSTICE BREYER’s opinion and all of the Court’s opinion
    save Parts II–D and III–B. JUSTICE THOMAS joins all but Part III–B of
    the Court’s opinion.
    Cite as: 560 U. S. ____ (2010)            1
    Opinion of BREYER, J.
    SUPREME COURT OF THE UNITED STATES
    _________________
    No. 132, Orig.
    _________________
    STATE OF ALABAMA, STATE OF FLORIDA, STATE OF
    TENNESSEE, COMMONWEALTH OF VIRGINIA, AND
    SOUTHEAST INTERSTATE LOW-LEVEL RADIO-
    ACTIVE WASTE MANAGEMENT COMMISSION,
    PLAINTIFFS v. STATE OF NORTH CAROLINA
    ON EXCEPTIONS TO THE PRELIMINARY AND SECOND REPORTS
    OF THE SPECIAL MASTER
    [June 1, 2010]
    JUSTICE BREYER, with whom THE CHIEF JUSTICE joins,
    concurring in part and dissenting in part.
    I join Parts I, II–A, II–B, and III of the Court’s opinion.
    Unlike the Court, however, I believe that North Carolina
    breached the Southeast Interstate Low-Level Radioactive
    Waste Management Compact (Compact) when it sus­
    pended its efforts toward building a waste disposal facility.
    (THE CHIEF JUSTICE joins all but Parts II–D and III–B of
    the Court’s opinion.)
    Article 5(C) is the critical term of the Compact. It states:
    “Each party state designated as a host state for a re­
    gional facility shall take appropriate steps to ensure
    that an application for a license to construct and op­
    erate a facility . . . is filed with and issued by the ap­
    propriate authority.” Omnibus Low-Level Radioactive
    Waste Interstate Compact Consent Act (Consent Act),
    
    99 Stat. 1877
    .
    In September 1986, North Carolina was “designated as a
    host state for a regional” low-level nuclear waste disposal
    “facility.” Ibid.; see also App. 417, 432. Soon thereafter,
    North Carolina’s General Assembly enacted legislation
    2               ALABAMA v. NORTH CAROLINA
    Opinion of BREYER, J.
    authorizing a state agency to “site, finance, [and] build” a
    waste disposal facility. N. C. Gen. Stat. §104G–4 (1987)
    (repealed 2000). Pursuant to this legislation, a new facil­
    ity was to be completed by January 1, 1993. Ibid.
    From August 1987 until December 1997, North Carolina
    took a series of steps to prepare for the construction of the
    storage facility. See Brief for North Carolina in Support of
    Exceptions to Reports of the Special Master 6–8. And
    while doing so it continually assured its Compact partners
    that it “remain[ed] committed to fulfilling its obligations to
    the Compact to serve as the next host state.” App. 92
    (Letter from James G. Martin, Governor of North Caro­
    lina, to Carroll R. Campbell, Jr., Governor of South Caro­
    lina (October 25, 1990)); Statement of Undisputed Mate­
    rial Facts ¶¶24–26, 28, 33, 37, 39 (detailing press releases,
    gubernatorial letters, and other statements made by
    North Carolina expressing its commitment to its Compact
    obligations).
    But North Carolina never secured a license, never ob­
    tained adequate funding, and never began construction on
    a new facility. See Second Report of Special Master 2–3
    (hereinafter Second Report). Eventually, the State simply
    stopped trying: On December 19, 1997, North Carolina
    informed its fellow member States that it would “com­
    mence the orderly shutdown” of the waste disposal “pro­
    ject.” App. 319. After this point, North Carolina admit­
    tedly took no further steps toward obtaining a license or
    building a facility before withdrawing from the Compact in
    July 1999. Id., at 460 (North Carolina Admissions ¶11
    (North Carolina “did not [after 1997] take additional steps
    to . . . license a waste disposal facility”)); Second Report 10
    (“The parties do not dispute that North Carolina did not
    take additional steps to pursue a license for a waste facil­
    ity” after December 1997).
    Whatever one might think of the sufficiency of North
    Carolina’s activities during the previous decade, I do not
    Cite as: 560 U. S. ____ (2010)           3
    Opinion of BREYER, J.
    see how the Court can find that a year and a half of doing
    nothing—which North Carolina admits it did between
    December 1997 and July 1999—constitutes “tak[ing]
    appropriate steps.” If a student promises to “take appro­
    priate steps to ensure” that he will pass the bar and then
    refuses to study, has he not broken his promise? More to
    the point, if a builder promises that he will “take appro­
    priate steps to ensure” that a customer will be able to
    move into a new home in two years, and then does nothing
    at all, has the builder not broken his promise?
    As the majority notes, “[o]ther contemporaneously en­
    acted interstate compacts” delineated a host State’s obli­
    gations in more detail than the Southeast Compact does.
    Ante, at 16–17. But this fact may just as easily be read to
    indicate what the parties here intended, rather than, as
    the majority argues, what they did not intend. Regard­
    less, the language of the Compact and the context in which
    it was enacted—as part of a congressional effort to en­
    courage regional solutions to this Nation’s low-level radio­
    active waste problem, see Consent Act, 
    99 Stat. 1859
    ; Low-
    Level Radioactive Waste Policy Act, §4(a)(1), 
    94 Stat. 3348
    —both indicate that North Carolina was supposed to
    take “appropriate steps” to build a low-level radioactive
    waste disposal facility. And North Carolina’s General
    Assembly passed a state statute recognizing and accepting
    this responsibility. See N. C. Gen. Stat. §104G–4 (creating
    a state agency to “site, finance, [and] build” a waste dis­
    posal facility). How can it be that two years of inactivity
    followed by withdrawal satisfies this promise?
    The answer, says the Court, is that any further “appro­
    priate steps” would have cost a significant amount of
    money. Ante, at 14–15. In 1997, the Southeast Interstate
    Low-Level Radioactive Waste Management Commission
    (Commission), the entity responsible for administering the
    Compact, made clear that it would not advance North
    Carolina any more money toward building a facility. See
    4               ALABAMA v. NORTH CAROLINA
    Opinion of BREYER, J.
    App. 315. In response, North Carolina concluded that it
    was unwilling to fund the rest of the project itself. See id.,
    at 317–319. And the Court agrees that it would have been
    “imprudent” for North Carolina to spend further funds, in
    light of the Commission’s refusal to do so also. Ante, at
    15–16.
    But this is an odd excuse. If a builder promises to “take
    appropriate steps” to build me a house, the fact that he
    runs out of funds would not normally excuse his breaking
    his promise—at least if it is he, and not I, who is responsi­
    ble for financing the project. See 2 E. Farnsworth, Con­
    tracts §9.6, p. 638 (3d ed. 2004) (Farnsworth) (courts
    “generally” conclude that “additional expense” “does not
    rise to the level of impracticability” so as to excuse a party
    from performance). And here it is North Carolina, and not
    anyone else, who bears ultimate responsibility for finding
    the funds.
    The text, structure, and purpose of the Compact all
    demonstrate this fact. As the Court recognizes, ante, at 2,
    the Compact expressly provides that the Commission “is
    not responsible for any costs associated with . . . the crea­
    tion of any facility,” Art. 4(K)(1), 
    99 Stat. 1876
    . Rather,
    the Compact States determined that each “party state”
    should take a turn as the “host state,” during which time
    that State would be obligated to build a facility and then
    operate it for 20 years. See Art. 3(A), id., at 1873; Art.
    5(A), id., at 1877; Art. 5(C), ibid.; Art. 5(E), 
    103 Stat. 1289
    ;
    see also Art. 3(C), 
    99 Stat. 1873
    –1874 (“Host states are
    responsible for the availability, the subsequent post­
    closure observation and maintenance, and the extended
    institutional control of their regional facilities”). The host
    State would then recover its upfront construction expenses
    from the considerable fees and surcharges charged to the
    waste generators served by the facility. N. C. Gen. Stat.
    §§104G–15(a)–(b) (repealed 2000) (“It is the intent of the
    General Assembly that the cost of all activities [toward
    Cite as: 560 U. S. ____ (2010)            5
    Opinion of BREYER, J.
    siting, building, and operating a facility] be borne by the
    waste generators” who use it); Brief for Plaintiffs in Sur­
    reply to North Carolina’s Reply 1, n. 1 (noting that a dis­
    posal facility in South Carolina collected over $47 million
    in fees in 2008).
    Of course, as the majority notes, South Carolina’s with­
    drawal from the Compact could have affected North Caro­
    lina’s ability to “recoup” its “construction costs.” Ante, at
    18. But, as far as I am aware, North Carolina did not
    seriously seek to amend the Compact when South Caro­
    lina departed (even though the State had sought and
    obtained an amendment previously, see ante, at 20, n. 4;
    Brief for North Carolina in Reply to Exceptions By Plain­
    tiffs to Reports of the Special Master 27), nor has it argued
    to this Court that South Carolina’s departure voided its
    contractual obligations. Indeed, there is evidence in the
    record indicating that, even after South Carolina left the
    Compact, North Carolina continued to believe that the
    operation of a waste disposal facility presented a substan­
    tial financial opportunity. App. 255, 266 (Attachment to
    Letter from John H. MacMillan, Executive Director, North
    Carolina Low-Level Radioactive Waste Management
    Authority, to Richard S. Hodes, M. D., Chairman, South­
    east Compact Commission (Dec. 13, 1996) (enclosing a
    business plan identifying $600 million in cost savings that
    could provide a “substantial return” on the “investment
    needed to put the North Carolina facility into operation”)).
    I thus cannot conclude, as the majority does, that the
    Compact’s rotational design, as I understand it, is “fool­
    ish.” Ante, at 18. Rather, the Compact’s structure repre­
    sents what, in my view, was a understandable decision by
    the contracting States, all of whom needed a waste dis­
    posal facility, to bind themselves together so that each
    would take a turn “bear[ing] the cost of building” the
    necessary facility. Preliminary Report of Special Master
    21 (citing Art. 4(K), 
    99 Stat. 1876
    –1877); see Brief for
    6              ALABAMA v. NORTH CAROLINA
    Opinion of BREYER, J.
    Rocky Mountain Low-Level Radioactive Waste Compact
    Board et al. as Amici Curiae 16–18. This rotational ap­
    proach is surely a sensible solution to the problems caused
    by the widespread existence of low-level nuclear waste and
    the political unpopularity of building the necessary facili­
    ties to house it. See 
    id.,
     at 13–16; New York v. United
    States, 
    505 U. S. 144
    , 149–151 (1992).
    The only contrary evidence—i.e., that indicates that
    North Carolina did not bear ultimate funding responsibil­
    ity—consists of the fact that the Commission voluntarily
    advanced North Carolina nearly $80 million between 1988
    and 1998 in order to help it defray its costs. Second Re­
    port 16. The Court believes that this “course of perform­
    ance” demonstrates that, once the Commission turned off
    its monetary spigot, North Carolina was no longer re­
    quired to do anything further. Ante, at 14–15. But why?
    If I advance my builder half the cost of a building, I have
    not thereby promised to advance him the whole cost. This
    is particularly true when the contract says I am responsi­
    ble for none of the cost of the building. At the very least,
    something more in the circumstances would have to show
    that additional expenditure had become a reasonable
    expectation.
    In this case, nothing suggests that North Carolina could
    reasonably expect further financing assistance. Indeed, I
    can find nothing in the majority’s opinion, or the record,
    that suggests that the Commission or the other Compact
    States intended to let North Carolina off the hook. And
    numerous documents indicate precisely the opposite—that
    despite the Commission’s funding assistance, North Caro­
    lina was still responsible for funding the project. See, e.g.,
    App. 63 (Resolution (Feb. 9, 1988) (“The Commission,
    although not obligated to do so under the Compact,” pro­
    vides funding for North Carolina)); 
    id., at 215
     (Letter from
    Richard S. Hodes, M. D., Chairman, Southeast Compact
    Commission, to James B. Hunt, Governor of North Caro­
    Cite as: 560 U. S. ____ (2010)             7
    Opinion of BREYER, J.
    lina (Jan. 5, 1996) (“At some point, Commission funds will
    no longer be available to North Carolina . . . , and North
    Carolina will need to make alternate plans . . .”)); id., at 75
    (Press Release by James G. Martin, Governor of North
    Carolina (Nov. 8, 1989) (“ ‘The task of siting and operating
    a low-level radioactive waste disposal facility is a com­
    mitment the state of North Carolina has made and one
    which I am personally committed to keeping’ ”)); id., at 92
    (Letter from Governor of North Carolina, to Governor of
    South Carolina (“North Carolina remains committed to
    fulfilling its obligations to the Compact to serve as the
    next host state”); id., at 183 (Letter from James B. Hunt,
    Jr., Governor of North Carolina, to David M. Beasley,
    Governor of South Carolina (Mar. 14, 1995) (“Let me
    assure you that North Carolina is committed to honoring
    its obligation to the Compact”)); Statement of Undisputed
    Material Facts ¶¶28, 33, 39 (other public statements about
    North Carolina’s commitment to building a facility).
    Without better evidence of a reallocation of funding
    responsibility, I can only conclude that North Carolina
    remained under an obligation to “take appropriate steps”
    at all times relevant to this case. And North Carolina
    admittedly took no steps towards building a disposal facil­
    ity from December 1997 and July 1999: It did no in-depth
    study of the further financing that might be necessary; it
    made no serious effort to look for alternative funding; the
    Executive of the State did not ask its legislature for any
    appropriation. Rather, North Carolina simply withdrew
    from the Compact. Ante, at 5.
    Of course, North Carolina was free to withdraw from the
    Compact. Art. 7(G), 
    99 Stat. 1879
    –1880. But that fact
    does not repair what, in my view, was a breach of a key
    contractual provision. See Franconia Associates v. United
    States, 
    536 U. S. 129
    , 142–143 (2002) (“Failure by the
    promisor to perform . . . establishes an immediate breach”);
    Restatement (Second) of Contracts §235(2) (1979) (“When
    8             ALABAMA v. NORTH CAROLINA
    Opinion of BREYER, J.
    performance of a duty under a contract is due any non
    performance is a breach” (emphasis added)); 2 Farnsworth
    §8.8, at 471.
    With respect, I dissent.
    

Document Info

Docket Number: 132, Orig.

Citation Numbers: 176 L. Ed. 2d 1070, 130 S. Ct. 2295, 560 U.S. 330, 2010 U.S. LEXIS 4381

Judges: Breyer, Kennedy, Roberts, Scalia

Filed Date: 6/1/2010

Precedential Status: Precedential

Modified Date: 8/3/2023

Authorities (28)

Tymshare, Inc. v. William J. Covell. William J. Covell v. ... , 727 F.2d 1145 ( 1984 )

Alden v. Maine , 119 S. Ct. 2240 ( 1999 )

Henderson v. United States , 116 S. Ct. 1638 ( 1996 )

Wright v. Henkel , 23 S. Ct. 781 ( 1903 )

Sullivan v. Kidd , 41 S. Ct. 158 ( 1921 )

Federal Land Bank of St. Paul v. Bismarck Lumber Co. , 62 S. Ct. 1 ( 1941 )

United States v. Detroit Timber & Lumber Co. , 26 S. Ct. 282 ( 1906 )

New Jersey v. New York , 118 S. Ct. 1726 ( 1998 )

College Savings Bank v. Florida Prepaid Postsecondary ... , 119 S. Ct. 2219 ( 1999 )

Shalala v. Illinois Council on Long Term Care, Inc. , 120 S. Ct. 1084 ( 2000 )

Federal Maritime Commission v. South Carolina State Ports ... , 122 S. Ct. 1864 ( 2002 )

Texas v. New Mexico , 103 S. Ct. 2558 ( 1983 )

Pennhurst State School and Hospital v. Halderman , 104 S. Ct. 900 ( 1984 )

Countyof Oneida v. Oneida Indian Nation of NY , 105 S. Ct. 1245 ( 1985 )

New York v. United States , 112 S. Ct. 2408 ( 1992 )

Puerto Rico Aqueduct and Sewer Authority v. Metcalf & Eddy, ... , 113 S. Ct. 684 ( 1993 )

Nebraska v. Wyoming , 113 S. Ct. 1689 ( 1993 )

Hess v. Port Authority Trans-Hudson Corporation , 115 S. Ct. 394 ( 1994 )

Franconia Associates v. United States , 122 S. Ct. 1993 ( 2002 )

Arizona v. California , 103 S. Ct. 1382 ( 1983 )

View All Authorities »

Cited By (80)

North American Landscaping, Construction and Dredge, Co., ... ( 2018 )

United States v. Pleau ( 2012 )

ENERGYSOLUTIONS, LLC v. Utah , 625 F.3d 1261 ( 2010 )

Search Market v. Jubber , 685 F.3d 1160 ( 2012 )

Cejka v. Vectrus Systems Corporation ( 2020 )

Trinet Group, Inc. v. United States ( 2020 )

George Koynok v. Thomas Lloyd , 405 F. App'x 679 ( 2011 )

New York State Citizens' Coalition for Children v. Poole ( 2019 )

UAW v. Kelsey-Hayes Co. , 854 F.3d 862 ( 2017 )

Council Tree Investors Inc v. FCC , 863 F.3d 237 ( 2017 )

Oneida Indian Nation v. County of Oneida , 617 F.3d 114 ( 2010 )

New York State Citizens' Coalition for Children v. Poole ( 2019 )

James H. Fischer v. Sandra F. Forrest ( 2020 )

United States v. Smith ( 2021 )

United States v. Nkajlo Vangh ( 2021 )

Steven Hammer v. Sam's East, Inc. , 754 F.3d 492 ( 2014 )

Confederated Tribes of the Chehalis Reservation v. Thurston ... , 724 F.3d 1153 ( 2013 )

United States v. Rico Williams , 836 F.3d 1 ( 2016 )

Todd Crabtree v. Daniel McDermott ( 2017 )

Masters Pharmaceutical, Inc. v. DEA , 861 F.3d 206 ( 2017 )

View All Citing Opinions »