Eagle Supply & Mfg. v. Bechtel Jacobs Co. , 868 F.3d 423 ( 2017 )


Menu:
  •                          RECOMMENDED FOR FULL-TEXT PUBLICATION
    Pursuant to Sixth Circuit I.O.P. 32.1(b)
    File Name: 17a0185p.06
    UNITED STATES COURT OF APPEALS
    FOR THE SIXTH CIRCUIT
    EAGLE SUPPLY AND MANUFACTURING, L.P.,                 ┐
    Plaintiff-Appellee,      │
    │
    >      No. 16-6428
    v.                                             │
    │
    │
    BECHTEL JACOBS COMPANY, LLC,                          │
    Defendant-Appellant.       │
    ┘
    Appeal from the United States District Court
    for the Eastern District of Tennessee at Knoxville.
    No. 3:10-cv-00407—Pamela Lynn Reeves, District Judge.
    Argued: August 3, 2017
    Decided and Filed: August 17, 2017
    Before: SUTTON, McKEAGUE, and THAPAR, Circuit Judges.
    _________________
    COUNSEL
    ARGUED: Lochlin B. Samples, SMITH, CURRIE & HANCOCK, LLP, Atlanta, Georgia, for
    Appellant. Brian G. Corgan, KILPATRICK TOWNSEND & STOCKTON, LLP, Atlanta,
    Georgia, for Appellee. ON BRIEF: Lochlin B. Samples, Karl Frederick Dix, SMITH, CURRIE
    & HANCOCK, LLP, Atlanta, Georgia, for Appellant. Brian G. Corgan, Ian M. Goldrich,
    Reginald A. Williamson, KILPATRICK TOWNSEND & STOCKTON, LLP, Atlanta, Georgia,
    for Appellee.
    _________________
    OPINION
    _________________
    THAPAR, Circuit Judge.      During World War II, the United States launched the
    Manhattan Project—the military’s effort to build the world’s first atomic bomb. Building the
    No. 16-6428                  Eagle Supply & Mfg. v. Bechtel Jacobs Co.                     Page 2
    bomb was a big project. Cleaning up afterward turned out to be a big one, too. Since the mid-
    1980s, the Project’s original uranium-enrichment facilities in Oak Ridge, Tennessee, have been
    inactive, and the Department of Energy (“DOE”) has worked to clean up the hazardous waste left
    behind.
    This case arises out of that cleanup. To manage its effort, DOE hired Bechtel Jacobs
    Company (“Bechtel”), a global engineering and construction firm. Bechtel, in turn, hired Eagle
    Supply & Manufacturing (“Eagle”) to help decontaminate the complex. Circumstances changed,
    and litigation ensued. Now, years after the work finished, Eagle and Bechtel continue to fight
    over the payment owed for Eagle’s work, over the meaning of certain contractual provisions, and
    even over what happened at the site. The district court found for Eagle, and Bechtel appealed.
    We now affirm the district court’s award of damages and attorney’s fees to Eagle, but remand so
    that the court can recalculate the interest to which Eagle is entitled under the Tennessee Prompt
    Pay Act.
    I.
    DOE hired Bechtel to clean up the uranium-enrichment site at Oak Ridge, with plans to
    convert the area into a commercial industrial park. That required not only the demolition of
    buildings and equipment across the 2,200-acre complex but also the careful removal of
    radioactive nuclear waste. After removing the waste, the team would need to decontaminate the
    soil and groundwater to ensure that the site would be safe for redevelopment. In short, the Oak
    Ridge project was a massive undertaking. Accordingly, Bechtel sought additional manpower
    and requested bids from potential subcontractors.
    Eagle submitted one of those bids. Eagle relied on Bechtel’s forecasts for the project but
    also factored in administrative costs and profit. As it turned out, one of Eagle’s competitors
    submitted a cheaper bid, and another received a higher technical rating. But Bechtel determined
    that Eagle promised the right balance of merit and price.              Bechtel also considered it
    “advantageous” that Eagle was a federally certified small business and a Historically
    Underutilized Business Zone contractor. Still Bechtel haggled after deciding that it would likely
    award the subcontract to Eagle. Bechtel convinced Eagle to accept a price reduction of over
    No. 16-6428                 Eagle Supply & Mfg. v. Bechtel Jacobs Co.                      Page 3
    $444,000, implying that Eagle would otherwise lose the bid. The two companies eventually
    agreed to a fixed-price subcontract for the full cost of performing the demolition and
    decontamination work.
    Unfortunately, things did not go as planned. Soon after the work began, the parties
    realized that the project would be much more challenging and costly than they had anticipated.
    At the first set of facilities, Eagle discovered that it would need to remove a lot more sediment
    than expected. More sediment meant more employees. And to get more employees, Eagle had
    to reallocate employees from another area of the project. This staffing adjustment forced Eagle
    to abandon its original plan to tackle multiple areas simultaneously and resulted in delays and
    increased costs.
    Shortly after the sediment setback, Bechtel announced a change to the security clearance
    requirements for the main facility at issue in this case—the K-1004-L facility. Workers at K-
    1004-L would now have to carry a higher security clearance and contend with an additional
    security perimeter. This caused two problems: (1) increased congestion meant the work took
    longer, and (2) increased security meant that Eagle had to hire new workers and subcontractors
    with the requisite security clearance. Not surprisingly, Eagle soon exceeded its projected costs.
    The problems were not over. When Eagle began work on K-1004-L, it discovered
    substantial amounts of asbestos and fluorine gas. These unanticipated hazards sidelined Eagle’s
    crews while the company hired remediation experts.            And the new dangers meant more
    protective gear, which in turn slowed down Eagle’s work.
    Meanwhile, over an eight-month period, Bechtel made over sixty modifications to the
    subcontract’s mandatory contractor procedures.        These modifications affected nearly every
    aspect of Eagle’s work—from environmental-health-and-safety requirements to personnel-
    change procedures. Apart from Bechtel’s modifications, Eagle catalogued thirty-nine separate
    incidents of site conditions that differed from the initial forecast. All in all, Eagle’s work proved
    significantly more challenging and expensive than either party had anticipated.
    Changes happen—especially in long-term construction projects.                   Bechtel and
    Eagle planned for that eventuality by including a “Changes” provision in their contract (GC-18).
    No. 16-6428                        Eagle Supply & Mfg. v. Bechtel Jacobs Co.                                     Page 4
    GC-18 allowed Bechtel to make changes. But if those changes caused Eagle’s costs to increase,
    GC-18 required Bechtel to make appropriate “equitable adjustment[s]” in price and time for
    performance.
    So when the changes occurred, Eagle requested equitable adjustments. Bechtel, however,
    dragged its feet on compensating Eagle for the overruns. When the financial burden became too
    great, Eagle objected to continuing the project. Bechtel, in turn, threatened to terminate Eagle,
    but ultimately agreed to pay Eagle’s immediate labor and materials costs for the duration of the
    project. This preliminary payment only covered Eagle’s labor and materials—not overhead,
    administrative expenses, or profit. So Eagle submitted another two requests for adjustment to its
    bid price to cover these outstanding expenses. Eight years after completing its work at K-1004-
    L—and still waiting to be paid for its requested price adjustments—Eagle filed this suit.
    Eagle alleges breach of contract and seeks compensation for its extra work on the Oak
    Ridge project.         Specifically, Eagle seeks damages for the two “Requests for Equitable
    Adjustment” that it submitted to Bechtel. The first addressed the additional costs that Eagle
    incurred at the K-1004-L site (the parties call this the “Combined Changes REA”). Bechtel
    conceded some equitable adjustment for these additional costs, but the parties were unable to
    settle upon an appropriate figure. The second request sought a price adjustment for excess waste
    that Eagle removed across the project (the parties call this “Waste Generation REA”). Bechtel
    contests liability for this excess waste.
    The district court awarded Eagle the full amount of each request, plus interest and
    attorney’s fees. Bechtel now appeals.
    II.
    A.
    Both parties agree that some amount is due to Eagle for cost overruns at the K-1004-L
    site; the question is how much.1 In general, a court’s determination of the amount of an
    1
    In its reply brief, Bechtel suggests for the first time that it “is relieved of liability” for the cost overruns at
    K-1004-L because Eagle failed to provide notice under SC-37. Reply Br. 8. Bechtel contends that SC-37 required
    Eagle to provide notice when the subcontract work reached 75% of allocated funds. But the reply brief contradicts
    No. 16-6428                      Eagle Supply & Mfg. v. Bechtel Jacobs Co.                                   Page 5
    equitable adjustment is one of fact. See United States v. Callahan Walker Constr. Co., 
    317 U.S. 56
    , 61 (1942). So we review an equitable adjustment for clear error, while we review any
    conclusions of law de novo. Pressman v. Franklin Nat. Bank, 
    348 F.3d 182
    , 185 (6th Cir. 2004).
    Moreover, where a district court’s findings of fact involve credibility determinations about
    witness testimony, we accord even greater deference. Anderson v. City of Bessemer, 
    470 U.S. 564
    , 575 (1985). Such a credibility finding, “if not internally inconsistent, can virtually never be
    clear error.” 
    Id. (emphasis added).
    Here, the district court heard four days of testimony and combed through hundreds of
    exhibits before finding that Eagle was entitled to the full payment it requested. Among other
    evidence, the court relied upon payroll reports from Eagle’s accounting system, copies of
    invoices for every payment Eagle now claimed, and equipment logs reflecting use and resulting
    charges. Substantial evidence in the record supported the district court’s factual findings, and
    thus, the K-1004-L damages award was not clearly erroneous.
    Bechtel insists that the district court’s award was too large and that the court unduly
    relied on the testimony of two Eagle witnesses. Bechtel first complains that the court should
    have disregarded the testimony of an Eagle employee who was not involved in reconstructing the
    company’s costs.         But who prepared the estimates is not material to the court’s holistic
    assessment of the amount due. Bechtel’s next target is a competitor of Eagle—who, interestingly
    enough, testified on Eagle’s behalf—and who Bechtel complains produced a “technically
    inferior” bid proposal. Why it matters that the competitor’s proposal was “inferior” is anybody’s
    guess. Just because Bechtel did not like the competitor’s bid does not mean that its testimony is
    irrelevant or incorrect. Indeed, one thing is clear: A competitor has little incentive to overstate
    Eagle’s costs. In any event, neither gripe demonstrates that the damages award was clearly
    erroneous.
    Bechtel’s statement in its opening brief that “Eagle provided notice pursuant to SC-37” for the K-1004-L work, and
    it is inconsistent with Bechtel’s concession throughout this litigation that it owed some amount for these cost
    overruns. Appellant Br. 10; R. 166, PgID #1802. Regardless, Bechtel did not raise this argument until its reply
    brief, and thus it is waived. Kuhn v. Washtenaw County, 
    709 F.3d 612
    , 623 (6th Cir. 2013) (“This court does not
    usually consider issues raised for the first time on appeal in a reply brief, whether or not they were previously raised
    in the district court.”).
    No. 16-6428                  Eagle Supply & Mfg. v. Bechtel Jacobs Co.                   Page 6
    Finally, Bechtel questions why the district court did not reduce the K-1004-L damages
    award to account for Eagle’s “inefficiencies.” According to Bechtel, (1) Eagle’s subcontractor
    cross-contaminated the project with asbestos and (2) missing equipment delayed Eagle’s work.
    And, Bechtel says, these mistakes increased Eagle’s costs by 10%. But Bechtel’s only evidence
    of cross-contamination is testimony from one Bechtel employee—and that testimony conflicts
    with another Bechtel employee’s praise for Eagle’s performance throughout the same incident.
    Yet another Bechtel employee contradicted the equipment-delay claim: He testified that, in each
    instance, alternate equipment was available or the absent equipment was unnecessary at that
    point in the project. The district judge was present for this evidence. She reached a conclusion
    based on it. And Bechtel’s mere distaste for that conclusion does not make it clearly erroneous.
    B.
    Bechtel disclaims any liability to Eagle for excess waste on two grounds. First, Bechtel
    argues that Eagle did not give adequate notice that it was handling excess waste. Second,
    Bechtel challenges the district court’s method of calculating the cost of the excess waste
    equitable adjustment.
    1. Notice
    In general, a subcontractor cannot bring an adjustment claim if it fails to adhere to a
    contractual notice requirement. Big Chief Drilling Co. v. United States, 
    15 Cl. Ct. 295
    , 303
    (1988).     But Bechtel has not identified any applicable notice requirement in the parties’
    subcontract. Sure, the provision on “Changes,” GC-18, required Eagle to promptly request any
    equitable adjustment arising from a Bechtel-imposed change order. See Ex. J-1 (Subcontract) at
    10 (“Subcontractor must assert its right to an adjustment under this clause in writing within 10
    days from the date of receipt of the written order.”). But the excess-waste adjustment request
    was not a response to a Bechtel-change order—it addressed cost overruns caused by higher-than-
    expected waste volumes at the work site. So GC-18 is out, and we are left without a clause in
    which to anchor Bechtel’s notice requirement. This omission speaks volumes: Even Bechtel
    cannot find that obligation in the subcontract. Perhaps general principles of contract law might
    No. 16-6428                       Eagle Supply & Mfg. v. Bechtel Jacobs Co.                                   Page 7
    have filled the gap; Bechtel just does not tell us how. Instead, it offers a conclusory assertion
    that Eagle breached an obligation that does not appear to exist; hardly a winning proposition.
    Moreover, Bechtel must prove both that Eagle failed to provide timely notice and that
    Bechtel suffered prejudice as a result.2 Big Chief Drilling 
    Co., 15 Cl. Ct. at 303
    . Bechtel says
    that Eagle’s untimely notice prevented it from tracking the actual amount of waste Eagle
    removed and limited its options for minimizing the associated costs. But Bechtel refers to
    nothing in the record that supports either assertion. The burden of showing prejudice cannot be
    satisfied with such conclusory statements. It takes evidence. Cf. Bowerman v. UAW Local No.
    12, 
    646 F.3d 360
    , 370 (6th Cir. 2011) (explaining that “[m]ere conclusory statements” do not
    satisfy a party’s burden of proof). Bechtel provides none.
    2. Calculation of Damages for Excess Waste
    Bechtel also challenges the district court’s method of calculating Eagle’s excess-waste
    damages. Calculation of damages is a determination of fact, subject to “the discretion and good
    judgment of the fact finder as guided by the facts of the particular case.” Canderm Pharmacal,
    Ltd. v. Elder Pharms., Inc., 
    862 F.2d 597
    , 606 (6th Cir. 1988) (citation omitted). We thus review
    damages awards for clear error. 
    Id. The district
    court failed to specify which method it used to calculate Eagle’s damages for
    clearing excess waste. Courts generally have two options for calculating damages for equitable
    adjustments where the actual costs cannot be documented: the “total-cost” method and the “jury-
    verdict” method. Cavalier Clothes, Inc. v. United States, 
    51 Fed. Cl. 399
    , 417 (2001). Although
    the court did not specify its methodology, both parties addressed the total-cost method in their
    briefs. So we will too.
    2
    Bechtel suggests that, for contracts (like this one) with limitation-of-funds clauses, the subcontractor bears
    the burden of proving that the contractor was not prejudiced by the untimely notice. The authority that Bechtel cites
    does not support its position. Titan Corporation v. West never mentions the prejudice requirement. 
    129 F.3d 1479
    (Fed. Cir. 1997). And International Science and Technology Institute, Inc. v. United States discusses whether
    failure to provide notice can be excused if the government would likely have allowed the work to continue after
    receiving notice. 
    53 Fed. Cl. 798
    , 807 (2002). But Bechtel never suggests that the government (or Bechtel) would
    have directed Eagle to stop working, so this exception does not apply here. And the law is established that, outside
    of that exception, the burden of proving prejudice sits with the contractor. See Big Chief Drilling 
    Co., 15 Cl. Ct. at 303
    (citing cases).
    No. 16-6428                 Eagle Supply & Mfg. v. Bechtel Jacobs Co.                     Page 8
    Under the total-cost method, damages are estimated according to “the difference between
    [the] total costs incurred in performance of the contract and [the] bid price.” 
    Id. Because this
    is
    only an approximation, courts “require[] four indicia of reliability to be present before a
    contractor may recover.” 
    Id. at 418.
    The plaintiff must prove that “(1) the nature of the
    particular losses make it impossible or highly impractical to determine them with a reasonable
    degree of accuracy; (2) the plaintiff’s bid or estimate was realistic; (3) its actual costs are
    reasonable; and (4) it was not responsible for the added expenses.” 
    Id. (citation omitted).
    Bechtel argues that Eagle came up short on each measure.
    First, Eagle had to show that it is “impossible or highly impractical” to prove the actual
    amount of its losses. Throughout the project, Bechtel prescribed the waste-volume tracking
    procedures. Initially, those procedures did not require Eagle to record actual waste volumes, so
    Eagle did not. Later, Bechtel modified the procedures to require that Eagle track actual waste
    volumes, so Eagle did. As a result, when it came time to calculate damages, Eagle could only
    supply averages—not the actual volumes of waste that it removed throughout the project.
    Bechtel suggests that Eagle theoretically could have tracked its actual volumes by employing a
    different tracking method. But it is hard to fault Eagle for following the tracking procedures that
    Bechtel prescribed. The district court apparently did not. And neither will we.
    Second, Eagle had to show that its original bid for the subcontract was realistic. The
    purpose of this factor is to prevent a subcontractor from “get[ting] the benefit of increased
    damages merely because it submitted an unreasonably low bid[.]” 
    Id. Courts therefore
    assess
    whether a bid is realistic by comparing it with its competition. 
    Id. Here, Eagle’s
    bid was higher
    than the lowest—and slightly higher than the government’s estimate for the project. It is true, as
    Bechtel notes, that Eagle relied on Bechtel’s Waste General Forecasts, which Bechtel warned
    bidders were provided for informational purposes only. But Eagle’s bid still fell comfortably
    within the range of its competitors’. It was therefore not unrealistic.
    Third, Eagle had to show that its actual costs were reasonable. Eagle provided the district
    court with substantial evidence to support its costs, including affidavits from truck loaders,
    invoices, and employee timesheets.        Bechtel challenges Eagle’s calculation as “inherently
    inaccurate,” because it relied in part on Eagle’s previous visual estimates of waste volume.
    No. 16-6428                 Eagle Supply & Mfg. v. Bechtel Jacobs Co.                       Page 9
    Appellant Br. 47. But the district court needed only a “reasonable basis for computation,” even
    if “approximate.” Hi-Shear Tech. Corp. v. United States, 
    356 F.3d 1372
    , 1381 (Fed. Cir. 2004)
    (citation omitted). And the records Eagle provided were more than sufficient for that purpose.
    Bechtel’s challenge is again little more than a disagreement with the district court’s conclusion.
    Finally, Eagle had to show that it was not responsible for the added expenses. The
    district court found that increased performance costs were solely attributable to changed site
    conditions, and it noted that one of Bechtel’s own employees praised Eagle for overcoming those
    conditions. Bechtel, on the other hand, cites no evidence suggesting that Eagle contributed to the
    excess waste or the costs associated with it.
    Neither of Bechtel’s challenges to the excess-waste damages holds water. Substantial
    evidence supported the district court’s award, and we have no reason to displace it now.
    III.
    Along with the two equitable adjustments, the district court awarded Eagle interest and
    attorney’s fees under the Tennessee Prompt Pay Act. Under the Prompt Pay Act, a court must
    award interest on overdue contractual payments. Tenn. Code. Ann. § 66-34-601. The Act also
    permits a court to award attorney’s fees where one party acts in bad faith. 
    Id. § 66-34-602(b).
    Bechtel challenges the district court’s award of interest, the interest calculation, and the award of
    attorney’s fees.
    A.
    The Tennessee Prompt Pay Act requires a court to award interest on overdue payments
    under a contract. Tenn. Code. Ann. § 66-34-601. This interest accrues from the date the
    payment came due until the date the offending party finally pays up. 
    Id. Bechtel challenges
    the
    interest rate that the district court applied. Unless a contract requires the use of a different rate,
    the Tennessee Prompt Pay Act instructs courts to apply the interest rate specified in Tennessee
    Code § 47-14-121. 
    Id. Neither party
    disputes that the statutory interest rate applies here. But in
    the years between the formation of the parties’ subcontract and the start of this litigation,
    Tennessee amended that rate. The question is therefore whether the original or amended rate
    No. 16-6428                     Eagle Supply & Mfg. v. Bechtel Jacobs Co.                                Page 10
    applies. We review this statutory-interpretation question de novo. United States v. Parrett,
    
    530 F.3d 422
    , 429 (6th Cir. 2008).
    From the time that the parties contracted until the commencement of this litigation,
    the statutory interest rate was 10%.             Pre-amendment, the statute provided that “[i]nterest
    on judgments, including decrees, shall be computed at the effective rate of ten percent (10%)
    per annum, except as may be otherwise provided or permitted by statute[.]” Tenn. Code Ann.
    § 47-14-121 (1979). Tennessee amended the Prompt Pay Act in the middle of this litigation.
    Tenn. Code Ann. § 47-14-121 (2012).                  The amended statute created a new formula for
    calculating the applicable interest rate. Under the amended formula, the interest rate depends on
    the date of the judgment’s entry. 
    Id. § 47-14-121(a).
    The question here is how to determine the
    interest on claims that accrued in the pre-amendment period when judgment was entered in the
    post-amendment period. No Tennessee court has squarely addressed this question.3
    In general, “statutes are presumed to operate prospectively and not retroactively.” Kee v.
    Shelter Ins., 
    852 S.W.2d 226
    , 228 (Tenn. 1993). But under Tennessee law, there is an exception
    to this general rule for procedural and remedial statutes. 
    Id. Such statutes
    apply retrospectively
    both “to causes of action arising before such acts become law” and “to all suits pending when the
    legislation takes effect.” 
    Id. So if
    the Prompt Pay Act is remedial, it applies retrospectively.
    Remedial statutes provide a “means or method whereby causes of action may be
    effectuated, wrongs redressed and relief obtained[.]” In re D.A.H., 
    142 S.W.3d 267
    , 273 (Tenn.
    2004) (quoting State Dep’t of Human Servs. v. Defriece, 
    937 S.W.2d 954
    , 958 (Tenn. Ct. App.
    1996)).       Simply put, remedial statutes provide a way to “redress injuries.”                     Black’s Law
    Dictionary (10th ed. 2014) (found within definition of “remedial statutes”). Here, the Act’s
    interest provision falls under the statutory heading of “Remedies for Delinquent Payment or
    Nonpayment,” suggesting that Tennessee legislators considered the provision to be remedial.
    Tenn. Code Ann. § 66-34-601. And the interest provision’s purpose is to redress the wrong of
    3
    Only one Tennessee case mentions the question of which interest rate applies when there is a post-
    amendment judgment concerning a pre-amendment contract. There, the trial court applied the post-amendment
    interest rate, reasoning that “allowance of prejudgment interest is an equitable measure to make the prevailing party
    whole.” Classical City Mech., Inc. v. Potter S. E., LLC, No. E2015-01890-COA-R3-CV, 
    2016 WL 5956616
    , at *16
    (Tenn. Ct. App. Oct. 14, 2016) (quoting from the trial court order). On appeal, however, the Tennessee Court of
    Appeals did not address whether the pre-amendment or post-amendment rate applied.
    No. 16-6428                       Eagle Supply & Mfg. v. Bechtel Jacobs Co.                                 Page 11
    delayed payment and set out the method for obtaining relief. So the Prompt Pay Act is properly
    read as remedial.
    The district court therefore erred in applying the pre-amendment interest rate of 10%.
    Since the district court entered judgment on August 19, 2016, the applicable interest rate should
    have been 5.5%. See Tenn. Judgment Interest Rates, July 1, 2012 - July 1, 2017.
    Eagle offers two responses.             First, Eagle argues it had a vested right in the pre-
    amendment interest rate. While vested rights cannot be taken away retrospectively, see 
    Kee, 852 S.W.2d at 228
    , Eagle provides no legal support for its claim that its right to collect the pre-
    amendment interest is a “vested right.” Nor have we found a Tennessee case suggesting that
    these types of “rights” can vest at all.
    Second, Eagle believes that applying the amended Act retrospectively would be unjust.
    Eagle offers no legal support for that argument. Nor does Eagle explain why a 5.5% interest
    payment would not adequately redress the wrong of Bechtel’s overdue payments. Eagle is thus
    entitled to interest on both damages awards, but only at a rate of 5.5%.
    B.
    The Tennessee Prompt Pay Act also provides for the recovery of “[r]easonable attorney’s
    fees” from a non-prevailing party who “has acted in bad faith.” Tenn. Code Ann. § 66-34-
    602(b). A party acts in bad faith when it acts with “knowing or reckless disregard for contractual
    rights or duties.” Madden Phillips Constr., Inc. v. GGAT Dev. Corp., 
    315 S.W.3d 800
    , 829
    (Tenn. Ct. App. 2009). The district court found that Bechtel acted with “knowing or reckless
    disregard” for Eagle’s contractual rights and awarded Eagle attorney’s fees. We review this
    award for abuse of discretion but the underlying finding of bad faith for clear error. Griffin
    Indus., Inc. v. U.S. E.P.A., 
    640 F.3d 682
    , 686 (6th Cir. 2011). Here, four grounds cited by the
    district court support the award.4
    4
    In its bad-faith analysis, the district court relied in part on the parties’ pre-contract negotiations. R. 198,
    PgID #3058. Bechtel argues that its behavior in negotiations preceding the existence of the subcontract cannot be
    relied upon as evidence of bad faith in its later contractual dealings. Appellant Br. 50. This argument need not
    detain us here, because the district court’s determination was not clearly erroneous on the weight of the remaining
    evidence.
    No. 16-6428                 Eagle Supply & Mfg. v. Bechtel Jacobs Co.                      Page 12
    Ground one:      The court found Bechtel’s response to Eagle’s requests for equitable
    adjustment to be “riddled with bad faith.”          R. 198, PgID #3059.         Even after Bechtel
    acknowledged overruns of about $4.6 million at the K-1004-L site, Bechtel refused to pay Eagle,
    bickering over the precise allocation of responsibility. Eagle repeatedly responded to Bechtel’s
    gripes with revised requests, only to have Bechtel demand that Eagle compile data differently or
    make additional revisions. Despite Bechtel’s “nitpicking,” its subcontract administrator admitted
    he admonished Eagle for failing to provide comprehensive data without even reviewing the
    documents that Eagle submitted.
    Ground two: When Eagle tried to modify the subcontract to ensure payment for its out-
    of-scope work, Bechtel responded with a letter that the district court determined conveyed a
    thinly veiled threat of termination. Bechtel quibbles with the district court’s reading of the letter.
    But the district court had a vantage point we do not; it had the ability to hear witnesses on both
    sides and see them testify. After the hearing, the district court agreed with Eagle—the letter
    contained a threat of termination. That determination was reasonable based on the testimony at
    the hearing. Madden v. Chattanooga City Wide Serv. Dept., 
    549 F.3d 666
    , 674 (6th Cir. 2008).
    Ground three: Bechtel assigned an employee to the project with the express task of
    reducing subcontractor costs by $100 million. This employee, Eugene Glasbergen, repeatedly
    interfered with Eagle’s ability to do its work. Glasbergen held frequent meetings with Eagle’s
    subcontractors without Eagle’s knowledge or permission, causing confusion and tension. His
    antics so interfered with Eagle’s ability to conduct its work and manage its own subcontractors
    that Eagle sent several formal notices to Bechtel objecting to his conduct. One of Bechtel’s own
    employees testified that he had never witnessed someone treat a subcontractor the way that
    Glasbergen treated Eagle. At one point, Glasbergen even bragged that Eagle would not be paid
    “a dime” for cost overruns, and that, if he had his way, Eagle would end up paying Bechtel. R.
    168, PgID #2111.        The district court questioned Glasbergen’s motives, noting that his
    compensation was directly tied to his ability to reduce Eagle’s requests for equitable adjustment.
    Bechtel argues that the district court erroneously considered inadmissible testimony about
    Glasbergen when making these findings. But Bechtel did not object to the testimony, so Bechtel
    has waived that objection. See United States v. Martin, 
    757 F.2d 770
    , 771 (6th Cir. 1985).
    No. 16-6428                 Eagle Supply & Mfg. v. Bechtel Jacobs Co.                     Page 13
    Ground four: In an episode that the district court described as the “most disturbing,”
    Bechtel instigated a DOE investigation of Eagle by suggesting that Eagle had defrauded the
    government through overbilling. R. 198, PgID ##3058-59. The investigation required Eagle to
    respond to a grand jury subpoena and further delayed Eagle’s efforts to collect from Bechtel.
    DOE ultimately declined to take any action against Eagle. On appeal, Bechtel attempts to recast
    its failed arguments about facts in the record, suggesting that the district court misunderstood the
    events surrounding the DOE investigation. But again, the district court heard the testimony and
    made a reasonable determination—one that was not clearly erroneous.
    Bechtel offers still more attacks on the district court’s finding of bad faith. First, Bechtel
    suggests that it only refused to pay Eagle in order to comply with a government directive.
    During DOE’s investigation into Eagle’s allegedly fraudulent billing, the government issued a
    “Stop Payment Directive” that instructed Bechtel not to pay Eagle until further notice. Bechtel
    now claims that this DOE directive remains in effect and that its failure to pay Eagle was
    therefore justified.   Bechtel ignores the fact that DOE issued this directive during its
    investigation into Eagle—an investigation that concluded years ago without any finding of
    wrongdoing.     Moreover, Bechtel has paid Eagle for other settled claims in the interim,
    contradicting its claim that it felt the government’s stop-payment order prevented it from paying
    Eagle for its past work.
    Second, Bechtel argues that the district court applied the wrong standard, finding mere
    “lack of good faith,” instead of the requisite “bad faith.” Appellant Br. 49. To be sure, the
    district court’s order uses the phrase “lack of good faith.” But it also describes Bechtel’s conduct
    as evincing “bad faith” three times, including once in a section header (“BJC’s Acts of Bad
    Faith”). R. 198, PgID ##3058-59, 3068. Read in context, the phrase “lack of good faith” is
    simply shorthand for “bad faith.”
    Finally, Bechtel argues that it was engaged in a dispute over the amount it owed to Eagle,
    and courts have said that such disputes are not themselves evidence of bad faith. See Sun Splash
    Painting, Inc. v. Homestead Vill., Inc., No. M2002-00853-COA-R3-CV, 
    2003 WL 22345482
    , at
    *2 (Tenn. Ct. App. Oct. 15, 2003). Fair enough. But it is how Bechtel conducted itself during
    No. 16-6428                 Eagle Supply & Mfg. v. Bechtel Jacobs Co.                     Page 14
    this dispute that led the district court to its finding of bad faith. A dispute over billing is not a
    license to treat the other side however you want.
    In sum, Bechtel fails to demonstrate that the district court’s finding of bad faith was
    clearly erroneous or that the district court abused its discretion in awarding attorney’s fees to
    Eagle.
    IV.
    Finally, Bechtel offers two affirmative defenses to its nonpayment under the subcontract.
    Bechtel first argues that the subcontract contains a “pay-if-paid” provision conditioning its
    payment to Eagle on first receiving funds from the government. Bechtel also argues that Eagle
    failed to comply with the Truth in Negotiations Act’s requirements for federal subcontractors.
    The district court correctly rejected both defenses.
    A.
    First, Bechtel argues that the subcontract includes a “pay-if-paid” provision, which
    required Bechtel to pay Eagle only if and when the government paid Bechtel. Pay-if-paid
    conditions shift the risk of nonpayment from the contractor to the subcontractor by requiring the
    subcontractor to wait for payment until the contractor has been paid. Thos. J. Dyer Co. v. Bishop
    Int’l Eng’g Co., 
    303 F.2d 655
    , 661 (6th Cir. 1962). In legalese, pay-if-paid clauses are a type of
    condition precedent: One party is not obligated to perform until some condition is satisfied.
    Both parties agree that Tennessee law governs our interpretation of the contract in this
    case. Tennessee has said little about pay-if-paid clauses, but some of its cases address a similar
    type of condition: “pay-when-paid.” In form, there is a subtle difference. While pay-if-paid
    clauses say the contractor does not have to pay unless it is paid, pay-when-paid clauses delay the
    payment until the contractor is paid. Of course, practically they are the same: the contractor only
    pays the subcontractor when and if it receives payment. Thus, we anticipate that Tennessee
    would treat the clauses identically. And we know that Tennessee strongly disfavors pay-when-
    paid clauses, only enforcing such conditions when “there is clear language to support them.”
    Koch v. Constr. Tech., Inc., 
    924 S.W.2d 68
    , 71 (Tenn. 1996). Add the rule that the risk of
    No. 16-6428                  Eagle Supply & Mfg. v. Bechtel Jacobs Co.                   Page 15
    nonpayment normally lies with the prime contractor, 
    Dyer, 303 F.2d at 661
    (applying Ohio and
    Kentucky law), and Bechtel has a steep hill to climb.
    A pay-if-paid clause seems simple enough to write: “I will not pay you unless and until I
    first get paid.” And the subcontract here does contain some language that sounds like a pay-if-
    paid condition. For example, Clause GC-6 requires that Bechtel make payments “from funds
    advanced by the Government” and “not from its own assets.” Ex. J-1 at 10. Likewise, SC-37
    provides that Bechtel must perform its obligations only if the government first appropriates
    funds. 
    Id. at 53-54.
    That provision further provides that Eagle may stop any work that would
    cause it to incur costs above the appropriated funds, rather than continuing on “at its own risk.”
    
    Id. at 54.
    In context, however, both provisions are ambiguous. The relevant language of GC-6 is
    sandwiched between two sentences that describe the process by which the government can
    assume the subcontract from Bechtel. 
    Id. at 10.
    The position of this language makes it unclear
    whether this condition applies to the entire contract or is triggered only if the government
    assumes the subcontract.          And although SC-37 contains some language suggesting
    conditionality, it mentions neither DOE nor the government generally—only Bechtel’s
    obligations under the subcontract. Plus, Bechtel seeks to establish an unambiguous pay-if-paid
    provision by combining isolated clauses from disparate sections of the contract. That is not the
    natural way to read this. We therefore cannot say that GC-6 and SC-37 are “clear,” 
    Koch, 924 S.W.2d at 71
    , or “express,” 
    Dyer, 303 F.2d at 661
    —let alone “unambiguous,” as Bechtel
    claims.
    Even if GC-6 and SC-37 contain some conditional language, the subcontract’s provision
    on “Invoicing and Payment,” SC-15, does not. Ex. J-1 at 41-43. This provision lists several
    situations under which Bechtel can withhold payment, but the exceptions do not include
    unavailability of funds or nonpayment by the government. 
    Id. If the
    subcontract contains a pay-
    if-paid condition, it seems odd not to mention it in the clause specifically addressing payment.
    Furthermore, SC-15 explicitly creates a different “condition precedent” that requires Eagle to
    waive claims against Bechtel prior to being paid. 
    Id. at 42.
    The fact that the parties relied on the
    phrase “condition precedent” there indicates that they knew how to create an explicit condition
    No. 16-6428                 Eagle Supply & Mfg. v. Bechtel Jacobs Co.                     Page 16
    precedent when they wanted to. So if the parties had intended to condition Eagle’s payment on
    the government’s appropriation of funds, they could have made that intention clear.
    Bechtel argues that SC-15 “has no bearing on the current dispute” because Eagle did not
    invoice its two equitable adjustment requests. Reply Br. 11. Bechtel contends that SC-15 would
    have become operative only if the parties had agreed upon a price, DOE had provided funding,
    and Eagle had submitted an invoice. But even if SC-15 was not implicated here, the provision is
    still relevant for interpretive purposes. This court must construe the parties’ contract as a whole.
    In re Baxter, 
    104 F.2d 318
    , 320 (6th Cir. 1939) (“It is a settled rule in the construction of a
    contract that the interpretation must be upon the entire instrument. It cannot be disjointed or
    particular parts separated from the balance[.]”). So SC-37 and GC-6 must be read against the
    backdrop of the entire subcontract, which includes SC-15.
    Regardless, this court has made clear that pay-if-paid conditions require absolute
    precision of language. In Dyer, the contract provided that “no part of [the price to be paid to
    Subcontractor] shall be due until five (5) days after Owner shall have paid Contractor 
    therefor[.]” 303 F.2d at 656
    (internal quotation marks omitted). That language was more explicit than the
    subcontract here, yet this court determined that it was not “express” enough to create a pay-if-
    paid condition. 
    Id. at 661.
    If Dyer’s language was insufficient, the provision here proves even
    more so.
    Read as a whole, the subcontract is unclear as to how it allocates the risk of nonpayment.
    And under Tennessee law, ambiguity must be construed against Bechtel, the undisputed drafter
    of the subcontract. Allstate Ins. Co. v. Watson, 
    195 S.W.3d 609
    , 612 (Tenn. 2006). Thus, the
    district court rightly concluded that the subcontract contains no pay-if-paid condition.
    B.
    Bechtel also defends its nonpayment by arguing that Eagle failed to comply with the
    federal Truth in Negotiations Act. Specifically, it suggests that Eagle failed to provide current,
    complete, and accurate data at all times through trial and subsequent briefing.
    No. 16-6428                 Eagle Supply & Mfg. v. Bechtel Jacobs Co.                  Page 17
    The Truth in Negotiations Act requires federal contractors and subcontractors to make
    full disclosure to the government during negotiations. Bechtel argues that Eagle violated these
    disclosure requirements by failing to submit a signed “Certificate of Current Cost or Pricing
    Data” to Bechtel when Eagle sought an adjustment to the subcontract. Reply Br. 12. Indeed, the
    Act requires subcontractors to “submit cost or pricing data before the pricing of a change or
    modification to [a] subcontract[.]” 41 U.S.C. § 3502(a)(4). But the subcontractor needs to
    certify the data “[a]s soon as practicable after agreement on price[.]” 48 C.F.R. § 52.215-
    20(b)(2) (emphasis added). In other words, the certification requirement does not apply until
    after the parties conclude negotiations and reach a price agreement, 48 C.F.R. § 15.406-2 n.**, as
    Bechtel concedes, Reply Br. 13. The record shows that Eagle and Bechtel never reached an
    agreement on either of Eagle’s equitable adjustment requests. So Eagle could not have violated
    the Act—the certification rule did not apply yet.
    Bechtel also argues that Eagle’s revisions to its equitable adjustment requests are
    evidence of its noncompliance with the Act. But the district court found that Eagle provided
    most of these revisions in response to Bechtel’s “nitpicking”—“nitpicking” that Bechtel offered
    without reading Eagle’s initial requests. R. 198, PgID #3053. Bechtel cannot spin the revisions
    it requested—and that Eagle provided in an effort to cooperate—into evidence that Eagle flouted
    a federal disclosure law. Thus, Bechtel has failed to show that Eagle violated the Truth in
    Negotiations Act.
    V.
    For the foregoing reasons, we affirm in part and reverse in part. We affirm the district
    court’s damages award, as well as the award of attorney’s fees, but remand for the district court
    to recalculate the interest owed to Eagle.