TN v. Chattanooga , 403 F.3d 392 ( 2005 )


Menu:
  •                             RECOMMENDED FOR FULL-TEXT PUBLICATION
    Pursuant to Sixth Circuit Rule 206
    File Name: 05a0164a.06
    UNITED STATES COURT OF APPEALS
    FOR THE SIXTH CIRCUIT
    _________________
    X
    -
    STATE OF TENNESSEE ex rel. WIRELESS INCOME
    Plaintiff-Appellant, -
    PROPERTIES, LLC,
    -
    -
    No. 03-6608
    ,
    v.                                           >
    -
    -
    -
    CITY OF CHATTANOOGA and WILLIAM C.
    -
    MCDONALD, in his capacity as Administrator of
    Defendants-Appellees. -
    Public Works,
    -
    N
    Appeal from the United States District Court
    for the Eastern District of Tennessee at Chattanooga.
    No. 02-00372—R. Allan Edgar, Chief District Judge.
    Argued: August 11, 2004
    Decided and Filed: April 7, 2005
    Before: SILER, MOORE, and COLE, Circuit Judges.
    _________________
    COUNSEL
    ARGUED: James T. Williams, MILLER & MARTIN, Chattanooga, Tennessee, for Appellants.
    Michael A. McMahan, NELSON, McMAHAN & NOBLETT, Chattanooga, Tennessee, for
    Appellees. ON BRIEF: James T. Williams, MILLER & MARTIN, Chattanooga, Tennessee,
    Camden Ballard Scearce, Jr., HUSCH & EPPENBERGER, LLC, Chattanooga, Tennessee, for
    Appellants. Michael A. McMahan, NELSON, McMAHAN & NOBLETT, Chattanooga, Tennessee,
    for Appellees.
    ______________________
    AMENDED OPINION
    ______________________
    KAREN NELSON MOORE, Circuit Judge. Plaintiff-Appellant Wireless Income Properties,
    LLC (“Wireless”) appeals the decision of the district court, which granted in part and denied in part
    both its and Defendant-Appellee City of Chattanooga’s (“City”) respective motions for summary
    judgment.     Wireless, a company engaged in the construction and management of
    telecommunications towers, filed applications with the City for permits to construct monopole
    communication towers. The City then called for a moratorium on the issuing of such permits to
    consider amendments to the pertinent zoning ordinances. After the moratorium was lifted,
    1
    No. 03-6608                 State of Tennessee et al. v. City of Chattanooga et al.                               Page 2
    Wireless’s applications no longer complied with the newly amended zoning ordinances. Wireless
    brought suit in federal court seeking mandamus relief requiring the City to issue the permits, and
    also asserting that the City had committed violations of the Telecommunications Act of 1996
    (“TCA”) and 42 U.S.C. § 1983. Both sides filed motions for summary judgment, which the district
    court granted in part and denied in part. Among other things, the district court ordered the City to
    act on the pending applications within sixty days of the judgment.
    Wireless makes three arguments on appeal: (1) the district court erred when it ordered the
    City to act upon Wireless’s permit applications within sixty days of the judgment; (2) the district
    court erred when it held that the City was not required to apply the zoning ordinances in effect at
    the time Wireless filed its applications for building permits; and (3) the district court erred when it
    held that a violation of the TCA does not give rise to a cause of action under 42 U.S.C. § 1983.
    For the reasons explained below, we REVERSE the district court’s sixty-day order; instead
    the district court should issue appropriate injunctive relief compelling the City to grant Wireless the
    requested permits. We AFFIRM the district court’s dismissal of Wireless’s § 1983 claims in light
    of the Supreme Court’s recent decision in City of Rancho Palos Verdes v. Abrams, No. 03-1601, –
    S. Ct. –, 
    2005 WL 645209
    (March 22, 2005).
    I. BACKGROUND
    Wireless constructs, owns, and manages telecommunications towers in the Southeastern
    United States. Between December 14, 2001 and January 15, 2002, Wireless filed seven Land
    Disturbing Activity Permit Applications (“applications”) with the Public Works Department of the
    City, seeking approval for the construction of monopole communication towers. At the time each
    application was filed, Wireless or the company’s principal, G. Larry Wells (“Wells”), either owned
    or leased the underlying property, or had an agreement with the owner of the property to file the
    applications. In addition, the property  underlying each application conformed to the particular
    zoning ordinances then in effect.1
    On January 15, 2002, the Chattanooga City Council (“City Council”) passed a resolution
    which declared a moratorium on the issuance      of building permits for communication towers in
    certain zones effective until March 13, 2002.2 The purpose of the moratorium was “to allow [for]
    consideration of amendments to the provisions of the Zoning Ordinance for communication towers
    in [the cited] zones by the City Council,” due to concern that the then-effective ordinances failed
    sufficiently to “protect the public welfare.” Joint Appendix (“J.A.”) at 112. A second resolution
    was passed on February 12, 2002, extending the moratorium until April 5, 2002.
    On March 19, 2002, the City Council passed Ordinance No. 11253, which changed the
    standards for the location of communication towers. The changes were not to take effect until
    April 3, 2002. One of the changes was a new requirement mandating that all applications   be
    approved by the Board of Appeals for Variances and Special Permits (“Variance Board”).3 On
    1
    Each of the properties “was zoned appropriately for the construction of a communications tower of the type
    and height as identified on each individual site plan attached to each of the Applications.” Appellant’s Br. at 6-7. Five
    of the properties were zoned C-2 (convenience commercial), one was zoned M-3 (warehouse and wholesale), and one
    was zoned M-1 (manufacturing). In addition, at the time of the filings, construction of monopole communication towers
    was designated a permitted use in these zones pursuant to the City’s then-effective zoning ordinances.
    2
    Wireless was aware of the impending moratorium and filed the last of its two applications on January 15, 2002.
    3
    Wells was aware of this new requirement. In fact, he had attended and participated in some of the City Council
    Legal and Legislative Committee meetings on the subject.
    No. 03-6608               State of Tennessee et al. v. City of Chattanooga et al.                             Page 3
    March 26, 2002, the City Council passed another resolution setting April 3, 2002 as the termination
    date of the moratorium.
    As a result of the amendments to the zoning ordinances, all of Wireless’s applications were
    rendered defective in various ways such that they did not qualify for issuance of the permits.
    Wireless asserts that the City never served it with any type of written documentation signaling either
    the approval or denial of its applications. The City concedes that its only communication with
    Wireless regarding the allegedly now-inadequate applications was a telephone call on March 20,
    2002, between Perry Mayo (“Mayo”), the city employee primarily responsible for processing
    applications, and Wireless. During this phone call, Mayo informed Wireless that the applications
    could not be approved absent a “special exceptions permit.” Appellees’ Br. at 4; J.A. at 104-05
    (Mayo Dep. at 37-38). Mayo believed that the applications were therefore “on hold” at this point,
    and accordingly, took no further action. J.A. at 104-05 (Mayo Dep. at 37-38). Wireless never took
    the steps necessary to cure the defects in its applications   by satisfying the new requirements and
    taking the applications before the Variance Board.4
    On December 10, 2002, Wireless filed suit in federal court against the City and William C.
    McDonald in his capacity as Administrator of Public Works, seeking mandamus relief “requiring
    the City to issue the requested permits, and asserted [that] the City had engaged in certain violations
    of the TCA, violations of 42 U.S.C. § 1983 and violations of Wireless’ substantive due process
    rights.” Appellant’s Br. at 3. On February 6, 2003, Wireless filed a motion for partial summary
    judgment on the basis of the City’s violations of the TCA, and requested a writ of mandamus that
    would force the City to issue the requested permits. The City filed a cross-motion for summary
    judgment on June 30, 2003, asking the court to conclude that it had committed no violations of the
    TCA, and asking that Wireless’s claims be dismissed.
    On October 20, 2003, the district court issued an opinion, granting in part and denying in part
    both of the motions for summary judgment. The court found that the City’s failure to act upon
    Wireless’s filed applications constituted a violation of the TCA and ordered the City either to grant
    or to deny the applications within sixty days from the date of judgment. The court also denied
    Wireless’s motion to the extent that it asked the court “to compel the City to apply zoning laws in
    effect before April 3, 2002.” J.A. at 168 (D. Ct. Op. at 12). Finally, regarding Wireless’s § 1983
    claim, the district court, after lengthy analysis, concluded that a violation of the TCA did not give
    rise to a cause of action under § 1983. Accordingly, the court granted summary judgment in favor
    of the City on this issue. Wireless filed a timely notice of appeal on November 18, 2003 from the
    district court’s final judgment.
    II. ANALYSIS
    A. Standard of Review
    This court reviews a grant of summary judgment de novo. Walls v. Amerisure Mut. Ins. Co.,
    
    343 F.3d 881
    , 884 (6th Cir. 2003). “Although the denial of a motion for summary judgment is
    usually an interlocutory order that is not immediately appealable, where ‘an appeal from a denial
    of summary judgment is presented in tandem with a grant of summary judgment, this court has
    jurisdiction to review the propriety of the district court’s denial of summary judgment.’” 
    Id. (quoting Hamad
    v. Woodcrest Condo. Ass’n, 
    328 F.3d 224
    , 235 (6th Cir. 2003)). While the denial
    of a motion for summary judgment “on purely legal grounds” is reviewed de novo, 
    id., a denial
    based on the finding of a genuine issue of material fact is reviewed for an abuse of discretion.
    4
    Wells asserted in his deposition that although he knew that his pending applications would be deficient after
    passage of the amendments to the ordinance, he did not amend the applications, as he thought that they would be
    grandfathered, i.e., that they would be approved under the old ordinance.
    No. 03-6608           State of Tennessee et al. v. City of Chattanooga et al.                    Page 4
    McMullen v. Meijer, Inc., 
    355 F.3d 485
    , 489 (6th Cir. 2004). A grant of summary judgment is
    proper when, taking the facts in the light most favorable to the non-movant, there exists no genuine
    issue of material fact and “the moving party is entitled to a judgment as a matter of law.” 
    Walls, 343 F.3d at 884
    . Finally, the decision of a district court to grant injunctive relief is reviewed for abuse
    of discretion. United States v. City of Detroit, 
    329 F.3d 515
    , 520 (6th Cir. 2003) (en banc); New Par
    v. City of Saginaw, 
    301 F.3d 390
    , 394 (6th Cir. 2002).
    B. Sixty-Day Order
    On appeal Wireless contends that the district court erred when it ordered the City to either
    grant or deny Wireless’s permit applications within sixty days. Specifically, Wireless contends that
    the proper remedy for the City’s violations of the TCA would be to require the City to issue the
    requested permits. In response, the City contends that Wireless’s claim is not ripe for review under
    the TCA. For the reasons set out below, we reject the City’s ripeness claim and agree with Wireless
    that the district court erred in failing to require the City to issue the requested permits.
    The TCA, codified at 47 U.S.C. § 332, provides in subsection (c)(7)(B) the following:
    (ii)    A State or local government or instrumentality thereof shall act on any
    request for authorization to place, construct, or modify personal wireless
    service facilities within a reasonable period of time after the request is duly
    filed with such government or instrumentality, taking into account the nature
    and scope of such request.
    (iii)   Any decision by a State or local government or instrumentality thereof to
    deny a request to place, construct, or modify personal wireless service
    facilities shall be in writing and supported by substantial evidence contained
    in a written record.
    ***
    (v)     Any person adversely affected by any final action or failure to act by a State
    or local government or any instrumentality thereof that is inconsistent with
    this subparagraph may, within 30 days after such action or failure to act,
    commence an action in any court of competent jurisdiction. The court shall
    hear and decide such action on an expedited basis. . . .
    47 U.S.C. § 332(c)(7)(B).
    At the outset, the City argues that Wireless’s claim is not ripe for review. The City contends
    that because Wireless has failed to comply with the requirements of the amended ordinance its
    applications are still pending, and the City has yet to take final action on the applications as is
    required by 47 U.S.C. § 332(c)(7)(B)(v). Accordingly, the City argues that because “no final action
    ha[s] been taken, as contemplated by the TCA, prior to a valid cause of action being pursued under
    that statute, . . . no legal injury could have been sustained by [Wireless] due to the City’s alleged
    inaction.” Appellees’ Br. at 10.
    The City relies on Nextel Partners Inc. v. Kingston Township, 
    286 F.3d 687
    (3d Cir. 2002),
    in support of its argument. However, that case is not on point. There, Nextel brought suit against
    the township, alleging that the latter had violated the TCA because the ordinance in place
    “prohibit[ed] the provision of personal wireless service.” 
    Id. at 690.
    The plaintiff wanted to
    construct a wireless communications tower on private property within the township, and had
    negotiated with the township, but had never filed an application for a building permit.
    On appeal, the Third Circuit construed Nextel’s complaint as asserting a claim that the
    township’s failure to approve Nextel’s proposed facility violated the TCA. The court noted that the
    No. 03-6608                State of Tennessee et al. v. City of Chattanooga et al.                                  Page 5
    language of 47 U.S.C. § 332(c)(7)(B)(v), which “permit[s] an aggrieved party to commence an
    action to challenge a ‘failure to act’ must be read in conjunction with” 47 U.S.C. § 332(c)(7)(B)(iii),
    which “requir[es] state and local governments and instrumentalities to act within a reasonable time
    on ‘any request for authorization to place, construct, or modify [a] personal wireless service
    facilit[y].’” 
    Id. at 692
    (citations omitted). Accordingly, the court stated that in order for
    § 332(c)(7)(B)(v) to be triggered, there must have been a request made as referenced in
    § 332(c)(7)(B)(iii). The court noted that because Nextel had never filed an application for a building
    permit with the township, or made any other request for the placement or construction of a wireless
    facility, the township’s failure to approve the facility did not constitute a “failure to act” within the
    language of 47 U.S.C. § 332(c)(7)(B)(v). Thus, Nextel’s claims under the TCA were not actionable
    in court. “In the absence of a request to approve the construction of a facility, the failure to approve
    the facility is not a ‘failure to act’ within the meaning of this provision.” 
    Id. Here, by
    contrast, there
    is no dispute that Wireless made the appropriate     request when it filed its applications with the City.
    Accordingly, Nextel is distinguishable.5 Even if there was no action upon Wireless’s applications,
    as the City contends, there was a “failure to act” under § 332(c)(7)(B)(v) satisfying ripeness
    concerns.
    The district court found that the City had violated the TCA by failing to act on Wireless’s
    filed applications, as the TCA mandates that such requests be acted on “within a reasonable period
    of time after the request is duly filed.” 47 U.S.C. § 332(c)(7)(B)(ii). Because the district court
    concluded that the City neither denied Wireless’s applications nor took any action on the
    applications during the nine months that passed after the lifting of the moratorium and before the
    lawsuit was filed, the court deemed this inaction a violation of both the TCA’s timing and writing
    requirements. See 47 U.S.C. § 332(c)(7)(B)(ii-iii). Citing New Par v. City of Saginaw for the
    proposition “that injunctive relief is an appropriate remedy for such 
    violations,” 301 F.3d at 399
    , the
    district court ordered the City to act upon Wireless’s applications within sixty days of the judgment.
    Under the circumstances of this case, we conclude that the City’s actions during the nine
    months following the expiration of the moratorium amounted not simply to a failure to act but rather
    constituted a functional denial of Wireless’s applications. As Mayo, the City employee in charge
    of processing permit applications, stated in his deposition, it was not the City’s practice to comply
    with the substantive and procedural mandates of the TCA when it determined that an application
    ought to be denied. Instead when the City received an application which Mayo believed did not
    comply with the City’s regulations, his practice was to telephone the applicant and inform the
    applicant of the defects in the application. J.A. at 108 (Mayo Dep. at 52). Mayo would then hold
    the application until the applicant submitted the necessary amendments to bring the application into
    compliance with City regulations. J.A. at 105 (Mayo Dep. at 38). If the applicant did not amend
    his application within a several-year period, Mayo would discard the faulty application. 
    Id. A formal
    denial of the permit application, as required by the TCA, would never occur.
    This is exactly the procedure adhered to by the City when it reviewed Wireless’s permit
    applications. Following the passage of the City’s new regulations and the expiration of the City’s
    moratorium, Mayo telephoned Wireless and informed Wireless that its applications did not comply
    with the new ordinance. J.A. at 104 (Mayo Dep. at 37). Mayo also informed Wireless of the
    changes that would need to be made to the applications in order for permits to be granted and
    indicated that no further action would be taken on the applications unless these changes were made.
    J.A. at 104-105 (Mayo Dep. at 37-38). Consistent with Mayo’s statements to Wireless, no further
    5
    The City also relies on APT Tampa/Orlando, Inc. v. Orange County & Bd. of Comm’rs, No. 97-891-CIV-ORL-
    22, 
    1997 WL 33320573
    (M.D. Fla. Dec. 10, 1997). However, again, in that case, the court determined that in order for
    there to have been a final action or failure to act such that 47 U.S.C. § 332(c)(7)(B)(v) would be implicated, the plaintiffs
    in the case had to have applied for a tower permit. Absent an application for a permit, their “claims [were] not yet ripe.”
    
    Id. at *4.
    Accordingly, that case has no application to the present controversy.
    No. 03-6608           State of Tennessee et al. v. City of Chattanooga et al.                    Page 6
    action was taken by the City on Wireless’s applications in the nine months following the expiration
    of the moratorium.
    These actions by the City constituted an informal denial of Wireless’s applications. Mayo’s
    telephone call informed Wireless that its applications, absent amendment, would not be granted.
    Following this telephone call, no written decision as to the status of Wireless’s applications was
    provided by the City. While such an informal procedure might be sufficient in another context under
    state law, such a procedure directly contravenes the substantive and procedural requirements of the
    TCA.
    The TCA does not preempt all authority of state or local governments over the regulation
    of wireless towers. See 47 U.S.C. § 332(c)(7)(A). Instead, it merely imposes several substantive
    and procedural requirements upon the state or local government’s consideration of permit
    applications. See generally 47 U.S.C. § 332(c)(7)(B). Among those requirements, the TCA
    mandates that the state or local governments: (1) act on any permit application “within a reasonable
    period of time after” the application is filed; and (2) provide a decision on the application “in writing
    and supported by substantial evidence contained in a written record.” 47 U.S.C. § 332(c)(7)(B)(ii)-
    (iii).
    We agree with the district court’s assessment that the City’s informal decision-making
    process violated the mandates of the TCA. Because we conclude, however, that an informal denial
    was issued by the City, we disagree with the district court as to the provisions of the TCA that were
    violated by the City’s actions. First, we conclude that City’s decision violated the TCA requirement
    that a decision be “in writing.” 47 U.S.C. § 332(c)(7)(B)(ii). We have held that for a decision to
    meet the “in writing” requirement, the written denial must: “(1) be separate from the written record;
    (2) describe the reasons for the denial; and (3) contain a sufficient explanation of the reasons for the
    denial to allow a reviewing court to evaluate the evidence in the record that supports those reasons.”
    New 
    Par, 301 F.3d at 395-396
    . The City’s rejection of Wireless’s applications did not meet the “in
    writing” requirement for the simple reason that no written documentation of the City’s decision was
    ever provided to Wireless. Instead, Wireless merely received a telephone call indicating that its
    applications were not in compliance with the City’s regulations.
    Additionally we conclude, unlike the district court, that the City’s decision violated the
    TCA’s requirement that a decision to deny a permit application must be “supported by substantial
    evidence contained in a written record.” 47 U.S.C. § 332(c)(7)(B)(iii). “Substantial evidence is
    ‘more than a mere scintilla. It means such relevant evidence as a reasonable mind might accept as
    adequate to support a conclusion.’” New 
    Par, 301 F.3d at 396
    (quoting Richardson v. Perales, 
    402 U.S. 389
    , 401 (1971)). In this case, the City provided no written record supporting its decision to
    deny Wireless’s application. Given that the City failed to provide written documentation in support
    of its decision, we must conclude that the City’s decision was not supported by substantial evidence,
    in violation of the TCA.
    Having determined that the City’s informal denial of Wireless’s applications violated the
    TCA’s requirements that such decisions be “in writing” and “supported by substantial evidence,”
    we must now determine what is the appropriate relief for such a violation. See 47 U.S.C.
    § 332(c)(7)(B)(v). We agree with the district court that, pursuant to New Par, “injunctive relief is
    an appropriate remedy for [TCA] 
    violations.” 301 F.3d at 399
    . We disagree with the district court,
    however, as to the nature of appropriate injunctive relief in this case. The district court concluded
    that an order requiring the City to act on Wireless’s applications within sixty days was the
    appropriate remedy. This order failed to recognize that the City had already effectively denied
    Wireless’s applications in violation of the TCA. The district court’s sixty-day order would therefore
    only result in the inevitable occurring, namely a reaffirmance of the City’s informal decision that
    the applications ought to be denied under the new regulations. See New 
    Par, 301 F.3d at 400
    (noting
    No. 03-6608               State of Tennessee et al. v. City of Chattanooga et al.                               Page 7
    that generally where the defendant has already provided a decision in violation of the TCA, remand
    would serve no useful purpose). The City has recognized that under the amended zoning ordinances
    Wireless’s applications are inadequate. See J.A. at 66 (Answer) (noting that “the proposed site in
    each [Wireless] application did not and does not meet the setback requirements” in the amended
    zoning ordinance). Given that the sixty-day order would serve no useful purpose, we conclude that
    the proper remedy is injunctive relief compelling the City to grant the requested permits.
    Although the TCA does not specify a particular remedy for violations of its provisions, see
    47 U.S.C. § 332(c)(7)(B)(v), we have repeatedly concluded that where the defendant denied a permit
    application, and that denial violated the TCA’s “in writing” and “substantial evidence” requirements,
    the proper remedy is injunctive relief compelling the defendant to issue the requested permit. See,
    e.g., New 
    Par, 301 F.3d at 399-400
    ; Telespectrum v. Pub. Serv. Comm’n, 
    227 F.3d 414
    , 419, 424
    (6th Cir. 2000); see also Preferred Sites, LLC v. Troup County, 
    296 F.3d 1210
    , 1222 (11th Cir.
    2002); Omnipoint Corp. v. Zoning Hearing Bd. of Pine Grove Township, 
    181 F.3d 403
    , 410 (3d Cir.
    1999); Cellular Tel. Co. v. Town of Oyster Bay, 
    166 F.3d 490
    , 497 (2d Cir. 1999). In New Par we
    recognized that an injunction requiring the issuance of a permit ordinarily is a proper remedy when
    a governmental body has denied a permit without substantial evidence supporting the denial. In
    support of this proposition, we cited numerous cases from various circuits, including National
    Tower, LLC v. Plainville Zoning Board of Appeals, 
    297 F.3d 14
    , 21-22 (1st Cir. 2002), which stated
    that:
    The statutory requirements [of the TCA] that the board act within “a reasonable
    period of time,” and that the reviewing court hear and decide the action “on an
    expedited basis,” indicate that Congress did not intend multiple rounds of decisions
    and litigation, in which a court rejects one reason and then gives the board the
    opportunity, if it chooses, to proffer another. Instead, in the majority of cases the
    proper remedy for a zoning board decision that violates the Act will be an order, like
    the one the district court issued in this case, instructing the board to authorize
    construction.
    
    Id. Were we
    to affirm the district court’s order giving the City sixty days to act upon the permit
    applications, we would subject the parties to further litigation. On remand the City would inevitably
    again reject Wireless’s applications, albeit likely in a formal written decision. See J.A. at 66
    (Answer) (The City “aver[s] that the applications as submitted would be inadequate to a obtain a
    building permit under the applicable Zoning Ordinance.”). Wireless would then challenge this
    decision in federal court. Given the Congressional intent embodied in the TCA to avoid multiple
    rounds of litigation, we conclude that the proper remedy    in this case is injunctive relief compelling
    the City to grant Wireless’s permit applications.6 Given that our past cases such as New Par and
    Telespectrum indicate that this is the proper remedy, we conclude that the district court abused its
    discretion by failing to issue this form of injunctive relief.
    6
    We are mindful that such a result might be seen as a windfall for Wireless, given that the City has the power
    under the TCA and Tennessee law generally to alter its regulations. See 47 U.S.C. § 332(c)(7)(A) (“Except as provided
    in this paragraph, nothing in this chapter shall limit or affect the authority of a State or local government or
    instrumentality thereof over decisions regarding the placement, construction, and modification of personal wireless
    facilities.”); Schneider v. Lazarov, 
    390 S.W.2d 197
    , 200 (Tenn. 1965) (noting that under state law the filing of a permit
    application does not generally “confer[] any right in the applicant or permittee against a change in the zoning ordinance
    which imposes further limitations”). The City’s fatal flaw here was that it failed to issue a written decision supported
    by substantial evidence. Instead, the City effectively denied Wireless’s applications through the City’s moratoria and
    Mayo’s telephone call. Under these circumstances, the City must bear the consequences of its failure to comply with
    the TCA.
    No. 03-6608           State of Tennessee et al. v. City of Chattanooga et al.                 Page 8
    C. § 1983 Claim
    As part of its complaint, Wireless asserted a claim pursuant to 42 U.S.C. § 1983. The district
    court granted the City’s motion for summary judgment on this claim on the grounds that the TCA’s
    remedial scheme was sufficiently comprehensive to preclude a § 1983 cause of action. Wireless
    argues this conclusion was erroneous. The Supreme Court’s recent decision in City of Rancho Palos
    Verdes v. Abrams, No. 03-1601, – S. Ct. –, 
    2005 WL 645209
    (March 22, 2005), is dispositive of this
    issue. In Rancho Palos Verdes, the Supreme Court concluded that enforcement of the TCA’s
    substantive provisions “through § 1983 would distort the scheme of expedited judicial review and
    limited remedies created by” the TCA’s remedial provisions. 
    Id. at *9.
    The Court therefore held
    “that the TCA — by providing a judicial remedy different from § 1983 in [the statute] itself —
    precluded resort to § 1983.” 
    Id. Given the
    Supreme Court’s conclusion that Congress foreclosed
    a § 1983 cause of action for violations of the TCA, we affirm the district court’s grant of the City’s
    motion for summary judgment on this claim.
    III. CONCLUSION
    For the foregoing reasons, we REVERSE the district court’s sixty-day order and REMAND
    so that the district court can issue appropriate injunctive relief ordering the City to grant Wireless
    the requested permits. We AFFIRM the district court’s dismissal of Wireless’s § 1983 claims in
    light of the Supreme Court’s recent decision in Rancho Palos Verdes.