Horbach, Eugene v. Kaczmarek, Alvis , 288 F.3d 969 ( 2002 )


Menu:
  • In the
    United States Court of Appeals
    For the Seventh Circuit
    No. 99-3102
    EUGENE HORBACH, individually and
    as assignee of TYRREE CORPORATION,
    a dissolved Illinois corporation,
    and EUGENE HORBACH, on behalf of
    TYRREE CORPORATION, a dissolved
    Illinois corporation,
    Plaintiff-Appellant,
    v.
    ALVIS KACZMAREK and One Three Six, Inc.,
    Defendants-Appellees.
    Appeal from the United States District Court
    for the Northern District of Illinois, Eastern Division.
    No. 95 C 5180--Elaine E. Bucklo, Judge.
    ARGUED MAY 14, 2001--DECIDED April 30, 2002
    Before BAUER, ROVNER, and DIANE P. WOOD,
    Circuit Judges.
    ROVNER, Circuit Judge. In 1989, TyrRee
    Corporation agreed to purchase a tire
    pyrolysis system (a series of machines
    that shred, heat, and convert old tires
    into commercially viable by-products)
    from Shred Pax Corporation. TyrRee
    allegedly paid Shred Pax more than $1.7
    million for the assembly and storage of
    the machinery but ultimately did not
    accept delivery, concluding that it had
    not gotten what it had paid for. In 1995,
    following TyrRee’s dissolution, Eugene
    Horbach, TyrRee’s majority shareholder
    and assignee, filed suit against Shred
    Pax (which by then had changed its name
    to One Three Six, Inc., but for the sake
    of convenience we will ignore the name
    change), and its majority shareholder and
    president, Alvis Kaczmarek./1 In
    pertinent part, Horbach’s complaint
    sought relief on theories of contractual
    breach, fraud, rescission, constructive
    trust/ unjust enrichment, and conversion.
    The district court dismissed these
    claims, finding that the allegations did
    not support a claim for conversion and
    that the other claims were untimely. We
    affirm.
    I.
    Because the district court dismissed
    this case at the pleading stage, we
    accept the allegations in Horbach’s
    complaint as true. E.g., Johnson v.
    Rivera, 
    272 F.3d 519
    , 520 (7th Cir.
    2001).
    Horbach and Aaron Gellman formed TyrRee,
    an Illinois corporation, in August of
    1989 with the goal of owning and
    operating tire pyrolysis plants. Horbach,
    a citizen of the State of Washington,
    subscribed to 71 percent of TyrRee’s
    stock. Gellman later assigned to Horbach
    his 21 percent interest in TyrRee, making
    Horbach the owner of approximately 92
    percent of TyrRee’s outstanding shares.
    On September 5, 1989, TyrRee entered
    into a preliminary letter agreement with
    Shred Pax for the purchase of a tire
    pyrolysis system. That agreement
    contemplated the subsequent execution of
    a formal purchase order for the
    equipment, which the parties completed
    and signed on September 26, 1989. The
    purchase order provided that Shred Pax
    would design and manufacture the
    equipment in accordance with
    specifications attached to the order and
    have it ready for delivery and testing on
    or before February 1, 1990. The order
    gave TyrRee the right to inspect, test,
    and approve the equipment before it
    accepted delivery. The testing envisioned
    by the purchase order involved "full and
    continuous operation" of the equipment
    over a period of seven days. R. 20 Ex. 4
    para. 7.
    At a meeting which took place on or
    about February 9, 1990, Shred Pax
    informed TyrRee that the equipment was
    ready for testing and installation.
    TyrRee had not yet located a suitable
    site at which it could engage in full-
    scale testing of the system, however, so
    the parties agreed that Shred Pax would
    continue to hold the equipment in
    exchange for a monthly storage fee until
    TyrRee was able to locate such a site.
    TyrRee also wanted Shred Pax to make
    certain modifications to the pyrolysis
    system that would take additional time to
    complete.
    On April 6, 1990, Shred Pax sent a
    letter to TyrRee confirming that the
    pyrolysis system, as modified, was ready
    for testing. This letter purported to
    constitute the formal "Equipment Notice"
    contemplated by the purchase agreement,
    entitling Shred Pax to a specified
    installment payment from TyrRee. TyrRee
    subsequently advised Shred Pax that it
    would not be able to conduct acceptance
    testing of the equipment prior to July
    and suggested that Shred Pax should
    conduct the testing itself at a place and
    time of its own choosing. Apparently,
    however, Shred Pax opted to wait for
    TyrRee and continue collecting a storage
    fee while it did so. Further
    modifications to the equipment were
    ordered in September 1990.
    TyrRee dissolved on September 9, 1990.
    All of the company’s rights under the
    initial letter agreement and purchase
    order were assigned to Horbach.
    On or about February 5, 1991, an agent
    for Horbach visited the facility in
    Portland, Oregon, where the pyrolysis
    equipment was being stored. Instead of a
    completed system, however, the agent
    discovered only scattered components that
    did not appear to have been manufactured
    in compliance with the purchase order.
    Shred Pax subsequently explained to
    Horbach that not all of the equipment
    was, in fact, located in Portland, and
    that it would take 60 days to assemble
    the pyrolysis system for acceptance
    testing. That testing never took place.
    On April 18, 1991, Horbach’s attorney
    notified Shred Pax that the purchase
    order was cancelled because Shred Pax had
    failed to manufacture and deliver the
    equipment in accordance with the terms of
    the order. By this time, Horbach had
    already paid more than $1.76 million
    toward the purchase and storage of the
    equipment and related items. Horbach
    demanded the return of his money, but
    Shred Pax refused.
    Horbach filed suit against Shred Pax and
    Kaczmarek in 1995. As we noted at the
    outset, the district court subsequently
    dismissed each of the claims that arose
    from the purchase order. Horbach v.
    Kaczmarek, 
    915 F. Supp. 18
    (N.D. Ill.
    1996); Horbach v. Kaczmarek, 
    934 F. Supp. 981
    (N.D. Ill. 1996)./2
    The court found the breach of contract
    claim 
    untimely. 915 F. Supp. at 22-23
    .
    The court noted at the outset that the
    Illinois Commercial Code specifies a
    four-year limitations period for such a
    claim. See 810 ILCS 5/2-725(1). The
    defendants argued that the limitations
    had begun to run on February 1, 1990, the
    date that the purchase order had
    specified for delivery of the equipment.
    At the latest, the period began to run on
    February 5, 1991, when Horbach’s agent
    inspected the equipment and realized that
    it had not been completed in conformance
    with the terms of the purchase order.
    Horbach, however, had waited until
    September 11, 1995, to bring suit--too
    long under even the most generous
    calculation of the four-year limitations
    period. Horbach asserted that Shred Pax
    had fraudulently concealed its breach of
    the purchase order and that he should
    therefore have the benefit of the longer,
    five-year limitations period applicable
    to cases of fraudulent concealment. See
    735 ILCS 5/13-215. But, as the district
    court pointed out, the Illinois Supreme
    Court has held that this limitations
    period governs only when the defendant’s
    concealment has left the plaintiff with
    less than a reasonable time to sue under
    the otherwise-applicable statute of
    limitations. See Anderson v. Wagner, 
    402 N.E.2d 560
    , 573 (Ill. 1979), appeal
    dismissed sub nom. Woodward v. Burnham
    City Hosp., 
    449 U.S. 807
    , 
    101 S. Ct. 54
    (1980); see also, e.g., Morris v.
    Margulis, 
    754 N.E.2d 314
    , 319-20 (Ill.
    2001); Barratt v. Goldberg, 
    694 N.E.2d 604
    , 609 (Ill. App. 1998). Here, Horbach
    had at least three years left in which to
    bring suit as of February 1991, when the
    inspection of the equipment revealed that
    it was not ready for delivery. The
    district court found three years to
    constitute a reasonable period of time in
    which to bring suit and for that reason
    found the limitations period for claims
    of fraudulent concealment not to 
    apply. 915 F. Supp. at 22
    . Horbach suggested
    that Anderson and its progeny were
    inconsistent with the express language of
    the fraudulent concealment statute, but
    the district court observed that it was
    "not at liberty to ignore clear state law
    authority." 
    Id. The court
    dismissed the equitable claims
    for rescission and constructive trust
    pursuant to the doctrine of laches. 
    Id. at 23.
    That doctrine applies when the
    plaintiff has waited for an unreasonable
    length of time to assert his claim and
    the defendant has been prejudiced by the
    delay. People v. Wells, 
    696 N.E.2d 303
    ,
    312 (Ill. 1998); Van Milligan v. Board of
    Fire & Police Commissioners of Village of
    Glenview, 
    630 N.E.2d 830
    , 833 (Ill.
    1994). "The doctrine is grounded in the
    equitable notion that courts are
    reluctant to come to the aid of a party
    who has knowingly slept on his rights to
    the detriment of the opposing party."
    Tully v. State, 
    574 N.E.2d 659
    , 662 (Ill.
    1991). Illinois courts follow the general
    rule that where the limitations period
    governing claims at law has expired,
    laches will bar the equitable claims,
    even if the defendant has not shown
    prejudice. See Meyers v. Kissner, 
    594 N.E.2d 336
    , 340-41 (Ill. 1992); see also,
    e.g., Golden v. McDermott, Will & Emery,
    
    702 N.E.2d 581
    , 589 (Ill. App. 1998).
    Thus, because Horbach had waited to file
    suit until the statute of limitations on
    his breach of contract claim had already
    run, laches demanded the dismissal of the
    accompanying equitable claims. 915 F.
    Supp. at 23.
    Although the fraud claim was subject to
    a longer, five-year period of
    limitations, see 735 ILCS 5/13-205, the
    court found that claim to be untimely as
    well. Pursuant to the discovery rule,
    commencement of the pertinent limitations
    period may be delayed until such time as
    the plaintiff knew or should have known
    that he was wrongfully injured. See
    generally Hermitage Corp. v. Contractors
    Adjustment Co., 
    651 N.E.2d 1132
    , 1135
    (Ill. 1995). Illinois courts have applied
    this rule to torts arising out of
    contractual relationships. See 
    id. at 1136
    (collecting cases). Horbach argued
    that the limitations period began to run
    no sooner than February 5, 1991, relying
    on the complaint’s allegation that he
    remained ignorant of Shred Pax’s
    wrongdoing until his agent inspected the
    equipment on that date. However, the
    complaint also revealed that Shred Pax
    had informed TyrRee in April of 1990 that
    the equipment was ready for delivery and
    testing; and notwithstanding Shred Pax’s
    efforts to schedule inspection and
    testing of the system, TyrRee and Horbach
    had waited for more than ten months to
    look at the equipment. Horbach had
    alleged no reason for this delay. Had
    Horbach inspected the equipment promptly
    after Shred Pax had announced that it was
    ready, the court observed, he would have
    discovered his injury. The court
    therefore concluded that the statute of
    limitations began to run sometime before
    September of 1990 and that Horbach’s
    fraud claim, filed in September 1995, was
    too 
    late. 915 F. Supp. at 24
    .
    Following the dismissal of these claims,
    Horbach obtained the court’s permission
    to file a second amended complaint which
    set forth additional allegations that
    Horbach believed would resuscitate the
    fraud claim and which also asserted a new
    claim for conversion./3 In the district
    court’s eyes, however, the second amended
    complaint fared no better than the first.
    With respect to the fraud claim, the
    court found the new allegations
    insufficient to justify Horbach’s delay
    in discovering the alleged fraud. 934 F.
    Supp. at 985-86. Horbach alleged that the
    pyrolysis equipment was highly complex
    and that he lacked the technical
    knowledge and skill to assess the quality
    of that equipment himself. The only way
    to determine whether the system met the
    requirements of the purchase order,
    Horbach asserted, was to test it, which
    he could not reasonably have done before
    September of 1990. But the court noted
    that when Horbach’s agent finally
    inspected the equipment in February 1991,
    its shortcomings (and thus Shred Pax’s
    alleged fraud) were readily apparent. In
    fact, the complaint revealed that there
    was no integrated "system" at all, but
    only scattered components. This was
    something that any qualified inspector--
    if not a lay person like Horbach himself-
    -would have readily determined upon
    examining the equipment. The court again
    found no plausible basis for inferring
    that the injury could not have been
    discovered prior to September of 1990.
    
    Id. at 985.
    Horbach also suggested that
    it was not unreasonable for him to
    postpone inspection of the system until
    February of 1991 because he had requested
    modifications to the system after
    February 1990. However, the court pointed
    out that Shred Pax had completed these
    modifications by the time it announced in
    April 1990 that the equipment was ready
    for testing and delivery, and TyrRee did
    not request additional changes until late
    September 1990. For that five-month
    period, then, TyrRee believed the
    equipment was ready for testing. Horbach
    offered no reasonable excuse for not hav
    ing inspected the equipment during that
    time. 
    Id. Finally, Horbach
    asserted that
    his inspection of the equipment was
    delayed by his ongoing search for a site
    where the equipment could not only be
    tested but permanently installed.
    However, as the district court pointed
    out, the complaint indicated that on
    April 6, 1990, in its letter announcing
    the readiness of the equipment, Shred Pax
    informed TyrRee that it would proceed
    with testing of the equipment at a site
    of its own choosing in the event TyrRee
    was unable to locate a site within
    fourteen days. The parties understood,
    then, that inspection and testing of the
    equipment was not to be postponed any
    longer based on Horbach’s search for a
    permanent installation site. In fact, as
    we noted earlier, Shred Pax did not test
    the equipment--a fact, the district court
    added, that might have tipped off TyrRee
    that something was amiss. Even so,
    Horbach postponed his inspection for ten
    months--a delay that the court believed
    was not justifiable. 
    Id. at 986.
    Accordingly, the court dismissed the
    fraud claim for a second time.
    The court found no basis in the
    allegations of the complaint for a
    conversion claim. 
    Id. The theory
    underlying this claim was that Shred Pax
    and Kaczmarek had improperly converted
    Horbach’s money to their own use by
    accepting his periodic payments for the
    completion and storage of the pyrolysis
    system all the while knowing that they
    were not entitled to those payments due
    to the inadequate state of the equipment.
    The court found this rationale defective
    for two reasons. First, because the
    purchase order entitled the defendants to
    periodic advance payments, Horbach could
    not show that the money he had paid
    belonged at all times to him. Horbach’s
    remedy, upon discovery that the equipment
    had not been completed, was to sue for
    breach of contract rather than
    conversion. 
    Id. Second, in
    order to
    establish the conversion of money under
    Illinois law, a plaintiff must show that
    he had "a ’right to a specific fund or
    specific money in coin or bills.’"
    Sutherland v. O’Malley, 
    882 F.2d 1196
    ,
    1200 (7th Cir. 1989), quoting Mid-
    American Fire & Marine Ins. Co. v.
    Middleton, 
    468 N.E.2d 1335
    , 1339 (Ill.
    App. 1984). Horbach, however, was not
    claiming entitlement to a specific fund
    or account (let alone specific coins or
    bills), but rather a particular amount of
    money. His claim thus did not meet this
    particular criterion of a conversion
    
    claim. 934 F. Supp. at 986
    .
    II.
    Horbach challenges four aspects of the
    district court’s judgment. First, he
    contends that the longer limitations
    period for fraudulent concealment should
    apply to his breach of contract claim.
    Second, assuming that his breach of
    contract claim is timely, Horbach
    contends that his equitable claims are
    timely as well, and that the court erred
    in invoking laches to dispose of them.
    Third, Horbach maintains that one cannot
    say as a matter of law that he should
    have known of the defendants’ alleged
    fraud earlier, and that, consequently,
    the district court should not have
    dismissed his fraud claim as untimely.
    Finally, Horbach asserts that his
    complaint states a valid claim for
    conversion. As this case was dismissed at
    the pleading stage, our review is of
    course de novo. E.g., Vorhees v. Naper
    Aero Club, Inc., 
    272 F.3d 398
    , 401 (7th
    Cir. 2001).
    A. Timeliness of the Breach of Contract
    Claim
    Horbach contends that the district court
    erred in applying the four-year
    limitations period to his claim for
    breach of contract rather than the longer
    five-year period that the Illinois
    legislature has specified for cases in
    which the defendant has fraudulently
    concealed a cause of action from the
    person to whom that cause belongs. See
    735 ILCS 5/13-215. As we noted above, the
    district court applied the four-year
    period based on the Illinois Supreme
    Court’s opinion in Anderson, 
    402 N.E.2d 560
    . Anderson construed the fraudulent
    concealment statute to apply only when
    the defendant’s concealment has deprived
    the plaintiff of a reasonable amount of
    time in which to bring suit under the
    statute of limitations that would
    ordinarily apply. 
    Id. at 573.
    In this
    case, when Horbach discovered in February
    1991 that the pyrolysis system was not
    complete as Shred Pax had represented,
    Horbach still had three years in which to
    bring suit before the four-year
    limitations period specified for
    contractual claims expired. The district
    court thought that three years was more
    than enough time in which to bring suit
    and so, pursuant to Anderson and its
    progeny, declined to apply the longer
    limitations period for cases of
    fraudulent concealment. See, e.g., 
    id. at 573
    (seven to sixteen months following
    discovery of fraudulent concealment is a
    reasonable amount of time in which to
    bring suit). Horbach does not suggest
    that the district court misinterpreted
    Anderson but argues instead that
    Anderson’s holding is inconsistent with
    the language of the fraudulent
    concealment statute. Horbach Br. 12.
    Horbach believes that given the
    opportunity, the Illinois Supreme Court
    would reconsider and overrule its holding
    in Anderson, and on that basis he
    contends that this court should not
    consider itself bound by this precedent.
    See West v. American Tel. & Tel. Co., 
    311 U.S. 223
    , 236, 
    61 S. Ct. 179
    , 183 (1940)
    ("When [state’s highest court] has
    spoken, its pronouncement is to be
    accepted by federal courts as defining
    state law unless it has later given clear
    and persuasive indication that its
    pronouncement will be modified, limited
    or restricted.") (emphasis supplied).
    We discern no basis for ignoring the
    Illinois Supreme Court’s opinion in
    Anderson, however. Sitting in diversity,
    this court must look to state law on
    matters of substance, Erie R.R. Co. v.
    Tompkins, 
    304 U.S. 64
    , 
    58 S. Ct. 817
    (1938), including the relevant statute of
    limitations, e.g., Doe v. Roe No. 1, 
    52 F.3d 151
    , 154 (7th Cir. 1995). The
    parties agree that in this case, the law
    of Illinois governs. Anderson embodies
    the Illinois Supreme Court’s
    interpretation of the fraudulent
    concealment statute and leaves no doubt
    that the statute does not apply where, as
    here, the plaintiff discovers his injury
    in plenty of time to file suit within the
    limitations period that would otherwise
    apply.
    Horbach suggests that the Illinois
    Supreme Court’s subsequent opinion in
    Hermitage Corp. v. Contractors Adjustment
    
    Co., supra
    , 
    651 N.E.2d 1132
    , signals a
    retreat from Anderson, but we disagree.
    In Hermitage, the court was concerned
    with the discovery rule, which, as we
    noted earlier, delays the commencement of
    the statute of limitations in certain
    cases until such time as the plaintiff
    knew or should have known that he had
    been injured. See 
    id. at 1135.
    The
    defendant urged the Illinois Supreme
    Court to hold, as some lower courts had
    done, that the discovery rule would not
    postpone the start of the limitations
    period past the date of injury so long as
    the plaintiff still had a reasonable
    amount of time to bring suit once he
    became aware (or should have become
    aware) that he had been injured. The
    defendant cited the court’s holding in
    Anderson in support of this argument. But
    the court noted that it had already
    covered this ground in Sharpe v. Jackson
    Park Hosp., 
    441 N.E.2d 645
    (1982), where
    it had rejected the notion that
    Anderson’s construction of the fraudulent
    concealment statute created any exception
    to or limitation upon the discovery rule.
    
    Id. at 646-47;
    see 
    Hermitage, 651 N.E.2d at 1137-38
    . The discovery rule, the court
    re-emphasized in Hermitage, delays the
    start of the limitations period, whereas
    the fraudulent concealment statute
    extends the limitations period. 
    Id. at 1137.
    Anderson’s "reasonable time" rule
    applies only in the latter situation. See
    
    id. "[B]ecause this
    case does not involve
    a fraudulent concealment issue that might
    extend the statute of limitations,"
    Hermitage concluded, "we do not address
    Anderson." 
    Id. at 1138.
    In short, Hermitage does not signal a
    retreat from Anderson. The court merely
    recognized that the discovery rule and
    the fraudulent concealment statute
    operate in two different ways, and that
    consequently it would be inappropriate to
    engraft Anderson’s "reasonable time"
    limitation onto the discovery rule. See
    also Highsmith v. Chrysler Credit Corp.,
    
    18 F.3d 434
    , 442 n.7 (7th Cir. 1994). Any
    notion that the court is on the verge of
    abandoning Anderson is put to rest by the
    court’s decision just last year in Morris
    v. 
    Margulis, supra
    , in which it applied
    the "reasonable time" rule without
    
    reservation. 754 N.E.2d at 319-20
    .
    B. Timeliness of the Equitable Claims
    Relying on the fact that the statute of
    limitations had run on Horbach’s claim
    for breach of contract, the district
    court found that his equitable claims
    ought to be dismissed on the basis of
    laches. Horbach does not quarrel with the
    court’s application of the laches
    doctrine, but rather reiterates his
    contention that his breach of contract
    claim was timely. But we have rejected
    that argument, and so have no need to
    further consider the dismissal of his
    equitable claims.
    C. Timeliness of the Fraud Claim
    Horbach had five years from the date he
    knew or reasonably should have known that
    the defendants had perpetrated a fraud
    upon him in which to file suit. 735 ILCS
    5/13-205. Horbach did not actually
    discover the alleged fraud until February
    1991, when his agent inspected the
    pyrolysis equipment. He filed suit within
    five years of that date; but the question
    presented here is whether he should have
    known of his injury sooner. Specifically,
    we must ask whether Horbach should have
    discovered his injury sooner than
    September 1990 (five years before he
    brought suit). The district court thought
    that he should have done so, given that
    Shred Pax had informed Horbach that the
    equipment was ready for testing in April
    1990 and a simple inspection would have
    revealed that the system had not been
    completed. Horbach contends that the
    district court was not entitled to make
    this determination as a matter of law. He
    suggests that in view of the complexity
    of the equipment, his own lack of
    expertise, and the modifications he had
    asked Shred Pax to make, the only way to
    determine whether the system met the
    specifications set forth in the purchase
    order was to test it, and this he was not
    in a position to do before September of
    1990. The mere fact that a visual
    inspection would have identified the
    alleged fraud does not mean that he was
    obligated to conduct such an inspection,
    Horbach argues.
    We agree with the district court,
    however, that Horbach’s own allegations
    reveal that he could and should have
    discovered his injury prior to September
    of 1990. Although Horbach makes much of
    the complexity of the pyrolysis system,
    his own lack of expertise, and the need
    for testing (which imposed its own set of
    demands) to determine whether the
    machinery conformed to the purchase
    order, the complaint makes clear that
    Shred Pax’s purported fraud was readily
    apparent to the naked, non-expert eye.
    When Horbach’s agent visited the Portland
    facility, he found no pyrolysis system at
    all, but only scattered components, and
    the components that he could see did not
    conform to specifications. R. 20 para.
    80. Thus, the complexity of the machinery
    did nothing to cloak Shred Pax’s
    purported fraud. Shred Pax’s alleged
    misrepresentation--that the system was
    complete and ready for testing--would
    have been immediately apparent to anyone
    conducting an inspection. Under these
    circumstances, Horbach’s delay in making
    such inspection was not reasonable. Shred
    Pax had announced the completion of the
    equipment, both parties apparently
    assumed that testing of the equipment was
    imminent, Horbach had already paid well
    in excess of $1 million for the
    equipment, and Shred Pax was charging
    TyrRee and Horbach a monthly storage fee
    for the equipment pending the selection
    of a permanent installation site. For all
    of these reasons, we believe that Horbach
    should have discovered Shred Pax’s
    alleged fraud prior to September of 1990.
    The district court correctly dismissed
    the fraud claim as untimely.
    D. The Conversion Claim
    Horbach alleges in his second amended
    complaint that between April 1 and
    September 10, 1990, he deposited some
    $56,800 with the defendants in reliance
    upon their representation that the
    pyrolysis equipment was complete and in
    consideration for defendants’ agreement
    to hold the equipment. In fact, Horbach
    alleges, the equipment was far from ready
    and as a result the defendants were not
    entitled to those payments; yet, the
    defendants refused his demand for the
    return of his money. Horbach contends
    that these allegations are sufficient to
    establish a viable claim for conversion.
    "’The essence of conversion is the
    wrongful deprivation of one who has a
    right to the immediate possession of the
    object unlawfully held.’" In re Thebus,
    
    483 N.E.2d 1258
    , 1260 (Ill. 1985),
    quoting Bender v. Consolidated Mink
    Ranch, Inc., 
    441 N.E.2d 1315
    , 1320 (Ill.
    App. 1982); see also National Union Fire
    Ins. Co. of Pittsburgh, Pa. v. Wilkins-
    Lowe & Co., 
    29 F.3d 337
    , 340 (7th Cir.
    1994) (per curiam). An asserted right to
    money normally will not support a claim
    for conversion. Only if the money at
    issue can be described as "specific
    chattel," 
    Thebus, 483 N.E.2d at 1260
    --in
    other words, "a specific fund or specific
    money in coin or bills," Mid-America Fire
    & Marine Ins. Co. v. 
    Middleton, supra
    ,
    468 N.E.2d at 1339--will conversion lie.
    Moreover, the plaintiff’s right to the
    money must be absolute. See 
    Thebus, 483 N.E.2d at 1260
    , quoting Jensen v. Chicago
    & W. Ind. R.R. Co., 
    419 N.E.2d 578
    , 593
    (Ill. App. 1981). "It must be shown that
    the money claimed, or its equivalent, at
    all times belonged to the plaintiff and
    that the defendant converted it to his
    own use." 
    Thebus, 483 N.E.2d at 1261
    (emphasis supplied); see also National
    Union Fire Ins. 
    Co., 29 F.3d at 340
    .
    The district court correctly dismissed
    Horbach’s conversion claim. Even if we
    assume that the money Horbach paid to
    defendants for the completion and storage
    of the pyrolysis equipment properly could
    be characterized as specific chattel,
    Horbach cannot show that his right to
    possession of that money was absolute. As
    his complaint reveals, Horbach made the
    payments in question to the defendants by
    agreement in exchange for their
    commitment to complete and store the
    equipment while he continued the search
    for an appropriate testing and
    installation site. The incomplete state
    of the equipment, and its failure to
    conform to the agreed-upon
    specifications, may have given rise to an
    obligation on the defendants’ part to
    return of some or all of the money that
    he had paid to them. But Horbach cannot
    show that the money at all times belonged
    unconditionally to him. His agreement
    with the defendants obligated him to pay
    them that money; and the defendants’
    receipt of that money thus cannot be
    described as unauthorized or wrongful in
    the sense that a claim for conversion
    requires.
    III.
    For the reasons we have discussed, we
    AFFIRM the district court’s decision to
    dismiss Horbach’s claims for breach of
    contract, rescission, constructive
    trust/unjust enrichment, fraud, and
    conversion.
    FOOTNOTES
    /1 Although Horbach named One Three Six as a defen-
    dant below, the company has opted not to appear
    in this appeal.
    /2 Horbach asserted a number of other claims based
    on an alleged agreement with Kaczmarek to pur-
    chase approximately 80 percent of Shred Pax’s
    stock. The disposition of those claims is not at
    issue in this appeal.
    /3 The second amended complaint additionally at-
    tempted to assert a new claim for breach of
    contract based on Shred Pax’s agreement to store
    the pyrolysis equipment pending acceptance test-
    ing. The district court determined that this
    agreement amounted to no more than a modification
    of the purchase order and thus was likewise
    barred by the four-year statute of 
    limitations. 934 F. Supp. at 984-85
    . Horbach does not chal-
    lenge this reasoning on appeal.
    

Document Info

Docket Number: 99-3102

Citation Numbers: 288 F.3d 969

Judges: Per Curiam

Filed Date: 4/30/2002

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (24)

Kelvin Highsmith, Marcita Highsmith, and Joseph Villasenor ... , 18 F.3d 434 ( 1994 )

national-union-fire-insurance-company-of-pittsburgh-pa-a-delaware-stock , 29 F.3d 337 ( 1994 )

Shaun R. Johnson v. Officer Ruben Rivera, Officer Matthew ... , 272 F.3d 519 ( 2001 )

Kimberly A. Sutherland v. Paul R. O'Malley and O'Malley & O'... , 882 F.2d 1196 ( 1989 )

Doe v. Roe No. 1, and Roe No. 2 , 52 F.3d 151 ( 1995 )

charles-m-vorhees-as-of-the-last-will-and-testament-of-helen-brach-a , 272 F.3d 398 ( 2001 )

People v. Wells , 182 Ill. 2d 471 ( 1998 )

In Re Thebus , 108 Ill. 2d 255 ( 1985 )

Anderson v. Wagner , 79 Ill. 2d 295 ( 1979 )

Sharpe v. Jackson Park Hospital , 92 Ill. 2d 232 ( 1982 )

Morris v. Margulis , 197 Ill. 2d 28 ( 2001 )

Hermitage Corp. v. Contractors Adjustment Co. , 166 Ill. 2d 72 ( 1995 )

Van Milligan v. BD. OF FIRE & POLICE COM'RS OF VILLAGE OF ... , 158 Ill. 2d 84 ( 1994 )

Tully v. State , 143 Ill. 2d 425 ( 1991 )

Barratt v. Goldberg , 296 Ill. App. 3d 252 ( 1998 )

Golden v. McDermott, Will & Emery , 299 Ill. App. 3d 982 ( 1998 )

Meyers v. Kissner , 149 Ill. 2d 1 ( 1992 )

Mid-America Fire & Marine Insurance v. Middleton , 127 Ill. App. 3d 887 ( 1984 )

Jensen v. Chicago & Western Indiana RR Co. , 94 Ill. App. 3d 915 ( 1981 )

Bender v. Consolidated Mink Ranch, Inc. , 110 Ill. App. 3d 207 ( 1982 )

View All Authorities »