Frey, Sarah E. v. EPA , 403 F.3d 828 ( 2005 )


Menu:
  •                             In the
    United States Court of Appeals
    For the Seventh Circuit
    ____________
    No. 03-3877
    SARAH E. FREY, KEVIN ENRIGHT,
    and PROTECT OUR WOODS, INC.,
    Plaintiffs-Appellants,
    v.
    ENVIRONMENTAL PROTECTION AGENCY,
    STEPHEN L. JOHNSON, Acting
    Administrator, and VIACOM, INC.,
    Defendants-Appellees.
    ____________
    Appeal from the United States District Court for the
    Southern District of Indiana, Indianapolis Division.
    No. IP 00-0660-C-Y/F—Richard L. Young, Judge.
    ____________
    ARGUED MAY 25, 2004—DECIDED APRIL 6, 2005
    ____________
    Before EASTERBROOK, WOOD, and WILLIAMS, Circuit
    Judges.
    WOOD, Circuit Judge. In this successive appeal, we con-
    front another chapter in the long history of certain
    Superfund sites located near Bloomington, Indiana. The sites
    are contaminated with polychlorinated biphenyls (PCBs),
    dioxin, and other toxic chemicals. Sarah Frey, Kevin Enright,
    and the organization Protect Our Woods (to whom we refer
    2                                                No. 03-3877
    collectively as “Frey”) are before us once again, trying to
    invoke the citizen suit provision of the Comprehensive
    Environmental Response, Compensation, and Liability Act
    of 1980 (CERCLA). That law, in general, permits a plaintiff
    to challenge cleanup efforts at Superfund sites once the
    Environmental Protection Agency (EPA) and other responsi-
    ble parties proclaim their work to be completed. 42 U.S.C.
    § 9613(h)(4); Frey v. EPA, 
    270 F.3d 1129
    , 1133 (7th Cir. 2001)
    (Frey I). Frey argues that her suit meets the statutory cri-
    teria, because EPA has completed the excavation of PCBs
    and has not yet selected further remedies. The district court
    saw matters differently; it found that Frey’s action was
    (still) premature because EPA has made it clear that it is
    studying further cleanup options for the three sites chal-
    lenged in this lawsuit: Lemon Lane Landfill, Neal’s Land-
    fill, and Bennett’s Dump. We conclude, however, that
    because EPA has failed to provide any objective referent by
    which to measure its progress, Frey is finally entitled to her
    day in court. We reverse.
    I
    On January 4, 1983, the United States initiated a civil
    action under CERCLA, 42 U.S.C. §§ 9601 et seq., against
    Viacom (formerly the Westinghouse Electric Corporation and
    then the CBS Corporation, until it merged into Viacom) to
    clean up two PCB contaminated dump sites in Bloomington,
    Indiana. After the City of Bloomington sued Viacom in con-
    nection with two other contaminated sites, the cases were
    consolidated and an additional two sites were added, bringing
    the total to six. In 1985, the parties entered into a consent
    decree that directed Viacom to excavate fully (meaning
    literally down to bedrock) and incinerate the PCBs at the
    six sites. This plan proved to be controversial, because it
    required Viacom to construct an incinerator. In 1988, Frey
    filed suit to challenge the proposed incineration remedy; we
    No. 03-3877                                                 3
    dismissed that action for lack of subject matter jurisdiction.
    Schalk v. Reilly, 
    900 F.2d 1091
    , 1096-97 (7th Cir. 1990).
    Although Frey’s lawsuit was unsuccessful, the Indiana
    State Legislature acted in 1991 to block construction of the
    incinerator. This forced the parties to the consent decree
    into further negotiations to find alternative remedies for the
    contaminated sites. In the course of these discussions, EPA
    and Viacom came to an impasse. Viacom believed that it
    should be required only to excavate highly contaminated
    soil (known as “hot spots”), while EPA took the position that
    hot spots excavation would be appropriate only if water
    treatment and sediment removal were included as part of
    the alternative remedy. In 1997, the district court issued an
    order stating that the sites had to be remediated by 1999.
    To assist the parties in breaking the deadlock in time for
    the 1999 deadline, the court appointed a special master
    “to see that the aims of the consent decree are carried out
    expeditiously and to resolve possible disputes between the
    parties.” The special master’s report recommended that the
    remediation deadline be moved back one year to 2000. It
    noted that the parties had reached agreement on some
    alternative methods of PCB excavation and that they had
    also agreed to complete the source control (excavation) work
    by the end of 2000. While the excavation work was under-
    way, Viacom agreed to investigate water treatment and sedi-
    ment remediation solutions at the three sites. According to
    the schedule proposed by the special master, the parties were
    to “engage in further settlement negotiations regarding water
    treatment and sediment removal aspects of remediation at
    Neal’s Landfill and Lemon Lane Landfill, including nego-
    tiations for permanent water treatment solutions for these
    sites, approximately one year following the completion of
    source control activities at each site.” The district court
    adopted the special master’s report and recommendations
    on February 1, 1999, noting in its order that the schedule
    required that excavation work at Neal’s Landfill and
    4                                                No. 03-3877
    Bennett’s Dump be completed by the end of 1999 and that
    the work at Lemon Landfill be completed by the end of
    2000. It instructed the parties to engage in further set-
    tlement negotiations regarding the water treatment and
    sediment removal phases of the remediation.
    After the incinerator option was abandoned, EPA took
    steps to select a new source control remedy for excavation
    of PCBs at the three sites. The National Oil and Hazardous
    Substances Pollution Contingency Plan (NCP), 40 C.F.R. Pt.
    300, establishes the criteria and procedures to be followed
    in comparing remedial alternatives and choosing a re-
    sponse. This regulatory process requires EPA to develop a
    list of effective remedial alternatives and to assess their
    feasibility. 
    Id. at §
    300.430(d) & (e) (describing the Remedial
    Investigation/Feasibility Study phase). After each alterna-
    tive is evaluated against nine established criteria, EPA
    selects a preferred remedy and presents it to the public in
    a proposed plan for review and comment. Following a period
    of public comment, including the possibility of a public
    meeting, EPA selects a final remedy and memorializes it in
    a public document called a Record of Decision (ROD). 
    Id. at §
    300.430(f)(3)(F).
    On March 29, 1999, EPA issued an amendment of the ROD
    for the “source control operable unit” for Neal’s Landfill.
    This document explained that the original remedy for
    Neal’s Landfill called for the excavation of 320,000 cubic
    yards of PCB contaminated landfill material and treatment
    through construction of an approved waste-fired inciner-
    ator. The modified remedy called for the excavation and
    removal of material with a high level contamination (the
    hot spots) to be followed by the construction of a landfill
    cap. Prior to adopting the hot spots excavation remedy, EPA
    considered alternatives, including the total excavation of
    the landfill. It concluded that the hot spots remedy was
    superior to total excavation in light of the nine regulatory
    criteria. As required by the regulations, EPA took public
    No. 03-3877                                                  5
    comment and held a hearing in Bloomington on the pro-
    posed remedies. This ROD Amendment dealt only with the
    source control component. It stipulated that “[s]ubsequent
    actions are planned to address fully the principal threats
    posed by this site. Future remedial decisions will be made
    regarding additional interim and final water treatment and
    sediment removal.”
    On May 12, 2000, EPA issued a ROD Amendment for
    Lemon Lane Landfill. EPA again adopted the hot spots
    excavation technique for PCB removal after considering
    other alternatives, including total excavation. It explained
    that the new ROD Amendment “only addresses source con-
    trol measures, and future remedial decisions will be made
    regarding treatment of contaminated groundwater . . . .”
    When Frey brought the present suit, the materials we
    have been discussing were presented to the district court.
    EPA also offered an affidavit and testimony from Thomas
    Alcamo, the Remedial Project Manager responsible for di-
    recting and overseeing the cleanup activities at the three
    sites. Alcamo also oversaw the development of the specific
    remedial approaches adopted by EPA. Alcamo’s affidavit
    establishes that water and sediment investigations are “in
    progress” at all three sites. He confirmed that all of the work
    in connection with the bureaucratically dubbed “source con-
    trol operable unit” at Neal’s Landfill was completed in
    November 1999, including the excavation and off-site dis-
    posal of 41,747 tons of PCB contaminated material. He
    further explained that, pursuant to the 1985 consent decree,
    Viacom had constructed a water treatment plant at Neal’s
    Landfill that became operational in 1990. EPA was still
    “evaluating the need based upon risk for expanding the
    Viacom water treatment plan including increasing the vol-
    ume of spring water to be captured and treated, storage of
    storm water and adding additional water processing equip-
    ment to decrease the PCB concentrations in the effluent.”
    He also indicated that EPA was “concurrently evaluating
    6                                               No. 03-3877
    based upon risk to both human and ecological receptors the
    need to remove PCB contaminated sediments from [sur-
    rounding creeks].”
    Turning to Lemon Lane Landfill, Alcamo’s affidavit rep-
    resented that the “source control operable unit” correspond-
    ing to that site was completed in November 2000. It in-
    volved the excavation and off-site disposal of 80,096 tons of
    PCB contaminated material. After EPA determined that the
    landfill had contaminated the Illinois Central Spring (ICS),
    EPA funded the construction of an interim water treatment
    plant that became operational in May 2000. With respect to
    what Alcamo described as the water operable unit, he said
    that EPA was still “evaluating the need to increase storm
    water storage, the need to add additional process equipment
    based upon discharge criteria developed by the Indiana
    Department of Environmental Management to reduce the
    PCBs from the water treatment plant effluent, the need
    based upon risk to human and ecological receptors to treat
    additional springs near the Lemon Lane site, and the
    ability to capture and treat PCB contaminated water closer
    to the Lemon Lane site.” As with Neal’s Landfill, EPA is
    concurrently evaluating the need to remove PCB contami-
    nated sediments from nearby streambeds.
    The soil and excavation activities at Bennett’s Dump,
    which involved excavation and off-site disposal of 36,157
    tons of PCB contaminated material, were completed in
    November 1999. Although contaminated sediment was re-
    moved from the banks of a nearby creek, EPA discovered
    that PCBs have continued to leak from the site into an ad-
    jacent creek. Alcamo stated that “Viacom is implementing
    a groundwater investigation plan to allow EPA to better
    understand the site’s hydrology,” and that EPA intended to
    take further action once Viacom gives it whatever informa-
    tion the new investigation reveals. Alcamo testified that
    groundwater investigations generally take a longer period
    of time than excavation activities.
    No. 03-3877                                                  7
    Dorothy Alke serves as the Project Manager for Viacom’s
    cleanup efforts in Bloomington. According to Alke, when the
    parties to the consent decree considered alternative excava-
    tion remedies, EPA had not yet decided on water treatment
    or sediment remedies for the three sites. At this time, Viacom
    and EPA disputed Viacom’s liability for various cleanup
    costs. This impasse was resolved by the special master’s re-
    port, and Viacom then implemented the negotiated exca-
    vation remedies at the three sites. Alke claimed that when
    EPA first proposed the concept of additional water treat-
    ment, Viacom was willing to investigate and negotiate about
    such remedies, and to consider including them as part of an
    overall solution. She confirmed that Viacom was under-
    taking a series of groundwater investigations.
    The record establishes that the hot spots were excavated
    at Neal’s Landfill by November 1999 and at Lemon Lane
    Landfill by November 2000. PCB contaminated soils and
    sediments were excavated from Bennett’s Dump in the fall
    of 1999, and again in September 2000. Water and sediment
    contamination has not yet been fully addressed at any of
    the sites, although investigation and testing continue. Frey
    is before us again, alleging that the excavation remedy se-
    lected by EPA has failed to bring the sites into compliance
    with CERCLA and other environmental statutes. Her abil-
    ity to litigate this question, however, is limited by the “Tim-
    ing of review” provision set out in CERCLA § 113(h), 42
    U.S.C. § 9613(h), which we have twice interpreted as
    requiring a citizen seeking to challenge a remediation action
    to wait for the selected action to be completed. Frey 
    I, 270 F.3d at 1133-34
    ; 
    Schalk, 900 F.2d at 1095
    . We elaborated
    on this point in our prior opinion when we explained that
    the time limits in § 113(h) are “geared to concrete, existing,
    remedial measures; not measures that might be devised at
    some future date.” Frey 
    I, 270 F.3d at 1134
    (distinguishing
    between “active steps designed to clean up a site” and “hypo-
    thetical” future possibilities).
    8                                                No. 03-3877
    Contending that concrete and existing remedial measures
    are still underway at all three sites, EPA moved for sum-
    mary judgment on the ground that Frey’s action is barred by
    § 113(h). Frey responded that EPA’s only “selected” remedy,
    the hot spots excavation, has been completed and no further
    remedies have been “selected” pursuant to federal regula-
    tions. The district court found that “the targeted excavation
    has been completed at each site. To date, the EPA has not
    selected a remedy for water treatment and sediment
    removal for any of the sites at issue.” Nonetheless, the
    district court concluded that Frey’s action was premature
    because “active remedial planning” was underway. It
    granted EPA’s motion for summary judgment. Frey appeals.
    II
    The parties agree on little in this case, including the basic
    question of what standard of review applies. Frey contends
    that we should apply a de novo standard because the case
    presents a question of statutory interpretation decided on
    summary judgment. EPA urges us to apply the “clearly
    erroneous” standard, on the theory that the case at bottom
    involves the application of facts to a legal rule. Jurcev v.
    Cent. Comm. Hosp., 
    7 F.3d 618
    , 623 (7th Cir. 1993), cert.
    denied, 
    511 U.S. 1081
    (1994).
    In our view, Frey has the better of the argument. Al-
    though it is true that Jurcev held that the clearly erroneous
    standard may be applied to cases in which “(1) the facts are
    undisputed, (2) the trial court is merely applying the law to
    the facts, and (3) the nonmoving party has made no request
    for a jury trial,” 
    id. at 623,
    this case does not fit that
    pattern. The trial court was not merely applying undisputed
    legal principles to agreed facts. Rather, this case raises a
    question of statutory interpretation, and thus the proper
    standard of review is de novo. Zambrano v. Reinert, 
    291 F.3d 964
    , 968 (7th Cir. 2002).
    No. 03-3877                                                   9
    III
    CERCLA provides the statutory framework that guides
    cleanup of hazardous waste sites. To ensure that cleanup
    efforts would not be impeded by litigation, Congress enacted
    § 113(h), which provides in relevant part:
    No Federal court shall have jurisdiction . . . to review
    any challenges to removal or remedial action selected
    under section 9604 of this title, or to review any order
    issued under section 9606(a) of this title, in any action
    except one of the following: . . . .
    (4) An action under section 9659 of this title (relating
    to citizens suits) alleging that the removal or reme-
    dial action taken under section 9604 of this title or
    secured under section 9606 of this title was in violation
    of any requirement of this chapter. Such an action
    may not be brought with regard to a removal where
    a remedial action is to be undertaken at the site.
    42 U.S.C. § 9613(h) (emphasis added). Frey has offered a
    straightforward interpretation of this language for our con-
    sideration: a citizen may bring suit once a “selected” remedy
    has been completed. She contends that EPA’s only “selected”
    remedy, the excavation of PCBs adopted in the ROD
    Amendments, is now complete. Since EPA has not yet “se-
    lected” a remedy (through a ROD Amendment) to address
    the groundwater or sediment contamination, there is no
    remedial action that remains to be completed. Accordingly,
    Frey reasons, her suit may now go forward.
    EPA has failed to offer an alternative interpretation of
    the statutory language. Instead, it hangs its hat on lan-
    guage from Frey I that says that a citizen suit may not go
    forward when only one stage of a broader remediation plan
    has been completed. In our prior opinion, we said that “[t]he
    statute does not say ‘a remedial action,’ or ‘a stage of a
    remedial plan.’ Instead, it calls flatly for restraint from suit
    when ‘remedial action’ (period) remains to be done.” 270
    10                                               No. 03-3877
    F.3d at 1134 (emphasis added). EPA contends that the
    excavation of PCBs is simply one stage of its proposed plan,
    and that Frey’s suit is therefore prohibited until all phases,
    including water and soil remediation, have been completed.
    But EPA’s position avoids the real question here, which
    is whether the record shows that only a stage has been com-
    pleted, or if it shows that an entire remedial measure has
    been completed. At oral argument, EPA’s counsel asserted
    that the agency’s ongoing investigation and testing of
    groundwater and soil contamination precludes review under
    the statute. But what if EPA decides to study the contamina-
    tion for an indeterminate period of time without taking any
    remedial action? Counsel had no response when asked
    whether the statute precludes review if EPA claims that it
    will take action, after further study, at some point before
    the sun becomes a red giant and melts the earth. We then
    asked counsel whether a reviewing court could invoke the
    Administrative Procedures Act (APA), 5 U.S.C. § 706(1), to
    compel agency action unlawfully withheld or unreasonably
    delayed, if EPA dragged its feet for decades. Counsel informed
    us that a court could not act under these circumstances
    because CERCLA’s rules governing judicial review override
    the APA. See 5 U.S.C. § 702 (stating that Administrative
    Procedures Act review is not available when “any other
    statute that grants consent to suit expressly or impliedly
    forbids the relief which is sought”); 
    Schalk, 900 F.2d at 1097
    . We can only conclude from this exchange that EPA
    considers itself protected from review under CERCLA
    § 113(h) as long as it has any notion that it might, some day,
    take further unspecified action with respect to a particular
    site.
    There is no support in the statute for such an open-ended
    prohibition on a citizen suit. Frey I spoke of “active steps
    designed to clean up a site” and held that “the time limits
    in § 113(h) are geared to concrete, existing, remedial mea-
    sures; not measures that might be devised at some future
    No. 03-3877                                               11
    
    date.” 270 F.3d at 1134
    . For EPA to delay Frey’s suit, it
    must point to some objective referent that commits it and
    other responsible parties to an action or plan. No such ob-
    jective evidence exists in this record. There is no timetable
    or other objective criterion by which to assess when EPA’s
    amorphous study and investigation phase may end. The
    special master’s report, adopted in 1999 by the district
    court, instructed EPA and Viacom to negotiate permanent
    water treatment solutions for the sites “approximately one
    year following the completion of source control activities at
    each site.” Source control activities were completed in 1999
    and 2000, yet EPA concedes in its brief on appeal that no
    permanent water or soil treatment remedies have been
    adopted to date. At argument, EPA’s counsel alluded to the
    possibility of further measures in 2005 or 2006. We are un-
    impressed with this vague reference, unsupported by any
    timetable in the record.
    In its ROD Amendments, EPA referred to future “operable
    units” that will be implemented to address the contaminated
    groundwater and sedimentation once excavation has been
    completed. See 40 C.F.R. § 300.430(a)(1)(ii)(A) (discussing
    use of “operable units” in remediating contaminated sites).
    We recognize that environmental regulations may call for
    a phased approach in expediting total site cleanup. 
    Id. And it
    is quite clear that EPA is entitled to gather data and as-
    sess alternatives before selecting an appropriate response.
    But the data collection and analysis must proceed with
    some level of transparency. EPA cannot preclude review by
    simply pointing to ongoing testing and investigation, with
    no clear end in sight.
    Frey offers one solution to this problem. She asks us to
    read the text of § 113(h) narrowly to preclude review only
    when EPA has selected a remedy through its Record of
    Decision process. Frey concedes that if EPA had selected a
    final remedy for all three operable phases (excavation,
    12                                               No. 03-3877
    water treatment, sediment treatment) through a ROD, she
    could not bring suit until all three remedies had been fully
    implemented. But it did not do so. In this case, she contends,
    plans for groundwater and sediment remediation cannot
    reasonably be characterized as later stages of the excava-
    tion remedy that EPA has already selected.
    Frey is correct insofar as there is no evidence of any kind
    that EPA will be doing anything specific in the future with
    this site. We do not go so far as to hold that EPA must have
    issued either a ROD or a ROD Amendment before it obtains
    the breathing room afforded by § 113(h). We conclude only
    that there must be some objective indicator that allows for
    an external evaluation, with reasonable target completion
    dates, of the required work for a site. (Although we are sure
    that EPA would not try to avoid the statute by submitting
    a 100-year plan, we note that such a target date would
    obviously be unreasonable.) Neither the consent decree nor
    the special master’s report serves as an objective measure
    here. Instead, we see only a desultory testing and investiga-
    tion process of indefinite duration.
    We address one final point. Section 113(h)(4) bars suit “with
    regard to a removal where a remedial action is to be under-
    taken at the site.” The district court noted that § 113(h)(4)
    bars lawsuits when “the process of investigation and anal-
    ysis—by definition a ‘removal’ action—is underway in order
    to determine what ‘remedial’ action is to be taken.” Thus,
    the district court found that Frey’s complaint was prema-
    ture. This language might be read to suggest that the
    district court thought that Frey was challenging a removal,
    rather than a remedial, action. This, in any event, is a
    theme that Viacom has advanced on appeal: it argues that
    its ongoing investigations are part of a removal action
    under the statute. It is incorrect.
    CERCLA response actions fall into two categories: removal
    and remedial actions. Removal refers to a short-term action
    No. 03-3877                                               13
    taken to halt risks posed by hazardous wastes immediately.
    Remedial actions involve permanent solutions, taken instead
    of or in addition to removal, such as the destruction of haz-
    ardous materials. 42 U.S.C. § 9601(23) & (24); 
    Schalk, 900 F.2d at 1092
    n.1; State of Alabama v. EPA, 
    871 F.2d 1548
    ,
    1551 n.1 (11th Cir. 1989). This case concerns a challenge to
    a remedial action, because it deals with “actions consistent
    with permanent remedy” including excavation and destruc-
    tion of hazardous materials. 42 U.S.C. § 9601(24). Further-
    more, EPA’s Remedial Project Manager stated unequivocally
    that this is a remedial action.
    Viacom points out that the following phrase in the defini-
    tion of removal encompasses the testing and investigation
    of water and sediment contamination: “such actions as may
    be necessary to monitor, assess, and evaluate the release or
    threat of release of hazardous substances.” A reading of the
    full definition, however, indicates that removal is concerned
    with minimizing and mitigating damage from the “threat of
    release” of a hazardous substance through measures such as
    “security fencing”, “temporary evacuation” and “emergency
    assistance.” 42 U.S.C. § 9601(23). This does not describe the
    decades-long study and excavation of the PCBs and other
    toxins that have contaminated the Bloomington environ-
    ment.
    We recognize that Congress intended for remedial action
    to be complete before permitting judicial review. Frey 
    I, 270 F.3d at 1133
    ; 
    Schalk, 900 F.2d at 1095
    . Congress did not,
    however, intend to extinguish judicial review altogether.
    North Shore Gas Co. v. EPA, 
    930 F.2d 1239
    , 1245 (7th Cir.
    1991). After a very long wait, the citizens of Bloomington
    are finally entitled to their day in court.
    IV
    For these reasons, we REVERSE the judgment of the
    district court and REMAND for proceedings consistent with
    this opinion.
    14                                       No. 03-3877
    A true Copy:
    Teste:
    ________________________________
    Clerk of the United States Court of
    Appeals for the Seventh Circuit
    USCA-02-C-0072—4-6-05