Environmental Barrie v. Slurry Systems Inc ( 2008 )


Menu:
  •                               In the
    United States Court of Appeals
    For the Seventh Circuit
    ____________
    No. 06-3910
    E NVIRONMENTAL B ARRIER C O ., LLC,
    Plaintiff-Appellee,
    v.
    S LURRY S YSTEMS, INC.,
    Defendant-Appellant.
    ____________
    Appeal from the United States District Court
    for the Northern District of Illinois, Eastern Division.
    No. 06 C 0212—Rebecca R. Pallmeyer, Judge.
    ____________
    A RGUED S EPTEMBER 17, 2007—D ECIDED A UGUST 29, 2008
    ____________
    Before F LAUM, R IPPLE, and W OOD , Circuit Judges.
    W OOD , Circuit Judge. After an arbitration hearing to
    resolve a construction contract dispute between Environ-
    mental Barrier Company (“EBC”) and Slurry Systems, Inc.
    (“SSI”), Arbitrator Franklin I. Kral issued an award in
    favor of EBC in the amount of $388,919.88. When SSI did
    not pay, EBC filed suit in Illinois court to confirm the
    award, and SSI responded by removing the case to the
    U.S. District Court for the Northern District of Illinois. SSI
    2                                               No. 06-3910
    urged the district court to vacate the arbitral award, or
    in the alternative, to modify it. The district court did
    neither: instead, it confirmed the award entered by Arbitra-
    tor Kral. In the course of doing so, the court held that EBC
    had “standing” to enforce the arbitration clause in the
    contract and that the arbitrator had not exceeded his
    powers. On appeal, SSI is now urging us to find that EBC
    never obtained the right to enforce the contract’s arbitra-
    tion clause. SSI’s appellate briefs present this argument
    as a challenge to arbitrability, based on the fact that SSI
    agreed to arbitrate only with EBC’s predecessor-in-interest,
    not with EBC itself. This is a major shift from the way
    SSI presented its case first to the arbitrator and later to
    the district court, where it framed the issue in terms of
    EBC’s standing to pursue this arbitration. The difference
    is crucial—indeed, on these facts, fatal—to SSI’s claim.
    I
    On February 29, 2000, the U.S. Army Corps of Engineers
    entered into a contract with SSI for work on a project to
    reduce flooding during heavy rains. The McCook Reservoir
    Project, as it was called, involved the construction of a
    multibillion-gallon reservoir; SSI won the right to build
    the overburden cutoff wall. SSI in turn subcontracted part
    of its work to an entity called Geo-Con, Inc., using a form
    contract that the parties signed in April 2000. The parties’
    briefs recount in detail the progress of SSI’s and Geo-Con’s
    work from 2000 to 2003; we include only the facts pertinent
    to this appeal.
    No. 06-3910                                                3
    Attachment A to the SSI/Geo-Con subcontract elaborated
    on Article 8.1 of the text, specifying that “Contractor and
    Subcontractor shall jointly work together to perform all of
    the work together [sic] to minimize the overall cost of the
    work.” Attachment A also included a longer version of
    Article 10.1, which described how the parties would
    allocate revenues, costs, profits, and loss and gave guid-
    ance for a final settling-up based on the actual distribution
    of costs. The subcontract also contained an exclusivity
    clause, Article 1.3; a broad arbitration clause covering
    “[a]ny claim arising out of or related to this Subcon-
    tract,”Article 6.2; and a clause restricting assignment or
    sub-subcontracting, Article 7.4.2.
    The project’s scope and methodology changed as the
    work proceeded, requiring the Corps at one point to
    suspend operations while it figured out an alternative
    way to finish the project. Once the modifications to the
    Prime Contract were in place, SSI and Geo-Con resumed
    their joint effort to complete their portion of the work. By
    April 2003, they were finished with their construction
    work. What remained to be done was the final reckoning
    of who owed whom how much; this proved to be more
    difficult. There were, for instance, several pending change
    orders, and it was unclear how costs and profits would
    be shifted among the parties. To the extent that these
    financial details are relevant, we return to them later.
    EBC entered the picture in September 2003, when Geo-
    Con, for reasons unrelated to the McCook project, filed
    for bankruptcy in the U.S. Bankruptcy Court for the
    Southern District of New York. During Geo-Con’s reorga-
    4                                                No. 06-3910
    nization, EBC (through two intermediary entities) acquired
    substantially all of Geo-Con’s assets for a purchase price
    of $2.1 million. The bankruptcy court found that EBC was
    the only qualified purchaser of Geo-Con’s assets. In an
    order dated April 16, 2004, the court approved the sale
    in accordance with the terms set forth in a letter from
    the intermediaries. Part II of the offer letter addressed the
    Geo-Con acquisition and set forth a list of “excluded
    assets.” The exclusions included “[a]ll contracts for services
    to be performed by Geo-Con, except . . . P90099 McCook,
    IL” (emphasis added). In other words, the McCook contract
    was acquired by the intermediary, and then passed along
    to EBC. There was a Schedule A to the offer letter that
    listed equipment loans and leases. This was the “Schedule
    A” to which the bankruptcy court referred when it said
    in its order that the contracts listed in Schedules A and C
    were executory.
    The sale of the McCook contract was later reflected on
    Schedule D to the April 29, 2004, bill of sale between Geo-
    Con and EBC that carried out the bankruptcy court’s
    order. The bill of sale provided that Geo-Con was selling
    “all of Seller’s accounts receivable (including without
    limitation the accounts set forth on Schedule A hereto),”
    and “contracts” specified as the “Assumed Contracts.” This
    was a different “Schedule A” than the one attached to
    the offer letter mentioned in the bankruptcy court’s
    April 16 order. Schedule A to the bill of sale lists accounts
    receivable and contracts that EBC was acquiring, and it
    includes the McCook project. Thus, the fact that the
    bankruptcy court had described the contracts listed in
    Schedules A and C as executory has little bearing on this
    case.
    No. 06-3910                                                 5
    SSI asserts that it was not aware of Geo-Con’s bank-
    ruptcy proceedings as they were taking place. It learned
    about them, however, no later than June 17, 2004, when
    EBC notified SSI by letter that EBC had succeeded to Geo-
    Con’s rights under the subcontract. The letter contained a
    demand that SSI pay EBC the balance due to Geo-Con
    for the work that Geo-Con had performed under the
    subcontract. At the time, EBC believed that this balance
    was $711,000. (It later found out that SSI had received two
    additional payments from the Corps that it had not
    disclosed, totaling $425,951.38; the discrepancy is im-
    material for our purposes.)
    EBC’s June 2004 letter also noted that the “subcontract
    between Geo-Con and Slurry Systems calls for mediation
    and arbitration of disputes,” but it added that
    EBC’s preference is to resolve its claim against Slurry
    Systems amicably, if possible, without the expenditure
    of mediation fees and expenses which, pursuant to the
    contract, are to be shared equally by the parties.
    Accordingly, we request an opportunity to meet with
    you within the next two weeks to discuss and hope-
    fully resolve EBC’s claim. If you are unwilling to meet
    with us within that time, EBC will commence media-
    tion and arbitration proceedings.
    SSI did not respond positively to EBC’s letter. On July 7,
    2004, SSI’s attorneys sent a letter to EBC’s counsel, express-
    ing the opinion that “all disputes between Geo-Con and
    Slurry Systems have been resolved,” and adding that, “[a]s
    a matter of fact, Geo-Con actually owes Slurry Systems, but
    because of Geo-Con’s liquidation, there is no point in
    6                                               No. 06-3910
    Slurry pursuing the matter.” SSI’s letter noted EBC’s
    statement that the subcontract between Geo-Con and
    SSI “calls for the mediation and arbitration of disputes,”
    and requested that EBC provide SSI “with a copy of the
    subcontract if you still plan to pursue this matter[.]”
    EBC did pursue the matter. After mediation efforts
    failed, EBC’s counsel called SSI’s counsel to discuss
    arbitration. The following week, in a letter dated March 16,
    2005, counsel for SSI wrote the following note to EBC’s
    attorney:
    As I stated on the phone, while I am pleased to resolve
    potential procedural issues by agreement, the first
    order of business is to determine whether your client,
    [EBC,] has any standing to arbitrate its claim against
    our client, [SSI].
    You have agreed that invoking the arbitration
    clause in [Geo-Con’s] subcontract with SSI goes hand-
    in-hand with EBC fully assuming that subcontract.
    That requires EBC to perform fully all obligations
    imposed upon Geo-Con by the subcontract, which it
    has not yet done. Additionally, SSI has not even
    consented to EBC’s assumption of the subcontract, and
    is unaware of EBC’s technical expertise or level of
    capitalization, or its ability to perform work under
    the subcontract. Under these circumstances, SSI may
    be excused from accepting performances from EBC
    under 11 U.S.C. § 365(c) and other applicable laws.
    The letter went on to state that it was “therefore essential
    that EBC provide SSI with adequate assurances that it
    can perform its obligations under the subcontract before
    No. 06-3910                                                7
    EBC can assume the subcontract.” Specifically, it de-
    manded (1) that EBC confirm that it “is in the construc-
    tion business and can handle any remedial work neces-
    sary under the subcontract”; (2) that EBC “provide SSI
    with the insurance and performance bond required by
    the subcontract”; and (3) that EBC give SSI its “financial
    data and biographical information,” so that SSI could
    “make an informed decision regarding whether or not
    to withhold SSI’s consent from the proposed assumption.”
    It added that “[t]hese issues need to be resolved now,
    and not in the context of an arbitration.” The letter closed
    by warning that if it should turn out that Geo-Con’s
    work was “defective in any way, SSI will hold EBC ac-
    countable.”
    The issues were not resolved, and instead EBC filed its
    demand for arbitration a month later, on April 20, 2005.
    The demand briefly explained the background of the
    parties’ dispute and the basis for EBC’s claim against SSI.
    EBC argued that SSI owed EBC “at least $657,273.50” and
    that SSI had “breached the Subcontract by failing to pay
    that amount.”
    At that critical juncture, SSI said nothing about the basic
    arbitrability of the dispute. Instead, it filed an Answering
    Statement on May 9, 2005. In the box on the Answering
    Statement form labeled “RESPONDENT ANSWERS
    CLAIMANT DEMAND FOR ARBITRATION AS FOL-
    LOWS,” SSI wrote: “EBC seeks additional moneys under
    a subcontract which has been paid in full; Respondent
    [SSI] denies any money is due and seeks return of
    overpayments and declaratory relief.” The “DOLLAR
    8                                               No. 06-3910
    AMOUNT OF CLAIM” was listed as “To be determined,”
    and in the box labeled “OTHER RELIEF SOUGHT,” SSI
    stated its claim for “A declaration that EBC assumed the
    subcontract and is in breach of its non-monetary terms;
    an accounting of money to be paid under the subcon-
    tract and a return of any over payments.” Notably, SSI did
    not merely answer EBC’s claim; it also filed a counterclaim.
    SSI elaborated on its position in a supplementary letter to
    Arbitrator Kral on June 20, 2005. The letter, which SSI sent
    “[i]n order to facilitate our June 21, 2005 preliminary
    hearing,” first explained that the disputes “center around
    a construction subcontract” between SSI and Geo-Con to
    build a slurry wall for the Corps. It then launched directly
    into the dispute over payment, providing Arbitrator Kral
    with SSI’s version of how the parties had agreed to
    allocate the costs and profits. Next, the letter stated that
    “Geo-Con abandoned the Project before it was over,” and
    so while “EBC now seeks an additional $657,274 . . ., strict
    application of the payment terms does not require SSI
    to pay the unearned windfall EBC seeks. Instead, it re-
    quires EBC to pay SSI several hundred thousand dollars
    in overpayments.” The remaining three paragraphs
    expanded on why EBC owed money to SSI. There is not
    even a passing reference to a defense of lack of
    arbitrability.
    Three days after the preliminary hearing, on June 24,
    2005, SSI wrote another letter to Arbitrator Kral, this time
    to “follow up on the subject of ‘non-monetary breaches.’ ”
    SSI reiterated its position that “Geo-Con left the job before
    it was finished” and noted that by virtue of the April 16,
    No. 06-3910                                                  9
    2004, bankruptcy order, “EBC was allowed to assume Geo-
    Con’s Subcontract with SSI.” SSI then argued that the
    bankruptcy court directed EBC, as the purchaser of Geo-
    Con’s asserts, “to make such cure payments as are re-
    quired by Section 365 of the [Bankruptcy] Code and
    agreed to among the Debtors and respective contracting
    parties.” SSI and Geo-Con had not agreed to EBC’s as-
    sumption of the contract, SSI continued, nor had Geo-Con
    even informed SSI of its bankruptcy. “Nevertheless,” the
    letter contended, “section 365 required Geo-Con/EBC to
    do the following in order to assume the contract” (referring
    to the list of three items in SSI’s letter of March 16, 2005,
    to EBC). Until EBC satisfied those conditions, SSI con-
    cluded, “EBC cannot have assumed the contract, and
    lacks standing to pursue this arbitration case.”
    At the end of the letter, SSI noted its concern that should
    the Corps raise a future claim involving Geo-Con’s work,
    EBC might try to evade its responsibility by “contending
    it is not Geo-Con. Part of SSI’s relief sought in this arbitra-
    tion is a declaration that EBC has in fact assumed all of
    Geo-Con’s obligations under the Subcontract.” Thus, in
    the same letter, SSI both argued that EBC had not
    properly assumed the subcontract (through its reference
    to alleged outstanding duties under Bankruptcy Code
    § 365 that prevented assumption) and argued that EBC
    had assumed the contract. Perhaps unsure of the
    latter point, SSI asked in its Answering Statement for a
    declaration that EBC had assumed the contract. It seems
    that what SSI was looking for was a ruling from the
    arbitrator that before EBC should be permitted to enforce
    Geo-Con’s rights under the subcontract, it had to assure
    10                                              No. 06-3910
    that it also would fulfill Geo-Con’s remaining contractual
    obligations. Once again, this was not a challenge to
    arbitrability; it was a position premised on a procedural
    question of standing and on the merits of the dispute.
    Each party to the arbitration filed a position paper on
    July 18, 2005. In response to SSI’s argument that it had
    never consented to the assignment of Geo-Con’s rights
    to EBC, EBC argued that the subcontract did not
    require SSI’s consent under these circumstances. Article
    7.4.2 of the subcontract provides:
    [1] The Subcontractor shall not assign the Work of this
    Subcontract without the written consent of the Con-
    tractor, nor [2] subcontract the whole of this Sub-
    contract without the written consent of the Contractor,
    nor [3] further subcontract portions of this Subcon-
    tract without written notification to the Contractor
    when such notification is requested by the Contractor.
    Only the first clause restricts assignment; the second and
    third restrict further subcontracting. Moreover, the restric-
    tion on assignment only requires the subcontractor to
    obtain the contractor’s written consent before assigning
    “the Work” of the subcontract. The work was completed
    by April 2003, a full year before the bankruptcy court
    issued its order approving EBC’s assumption of Geo-Con’s
    assets. The arbitrator took note of that timing in an
    express finding that “the Work” of the subcontract was
    complete before Geo-Con assigned the contract to EBC.
    In its position paper, SSI reiterated its belief that Geo-
    Con had “repudiated” the parties’ agreement, and that it
    “had continuing obligations to SSI to maintain insurance
    No. 06-3910                                               11
    coverage, provide a warranty for its work, and provide
    SSI with a performance bond to cover those obligations.”
    SSI maintained its position that EBC must “comply with
    its outstanding obligations under the Contract,” and that
    SSI therefore “seeks: (1) declaratory judgment confirming
    that EBC has assumed the contract; (2) a declaratory
    judgment that EBC is in breach on non-monetary terms
    of the Subcontract (e.g., insurance), and that EBC cure
    those defaults as previously ordered by the courts; (3) an
    accounting of the moneys to be paid between the parties
    on the Subcontract; and (4) an order requiring EBC to
    return to SSI the overpayments made to Geo-Con, believed
    to be in excess of $500,000” (footnotes omitted). SSI’s
    argument further stated that according to the bill of sale
    attached to the bankruptcy order, “EBC did, in fact,
    assume the Subcontract.” SSI added that “[w]hat Geo-Con
    could not do, and therefore what EBC cannot do, is to
    selectively accept the benefits of the Subcontract while
    rejecting the obligations.” Until EBC fulfilled those obliga-
    tions (as required by § 365), the argument concluded, “EBC
    lacks standing to invoke the Arbitration Clause in the
    Subcontract.” The rest of the argument explained why
    and to what extent Geo-Con was overpaid for its work
    and concluded by stating that “EBC must cure all non-
    monetary defaults before getting anything from SSI. But
    applying the Subcontract, Geo-Con/EBC was vastly
    overpaid, and that money must be returned.”
    Discovery ensued, followed by a two-day arbitration
    hearing on August 23-24, 2005. The transcripts from the
    hearing reveal that the only issues addressed were who
    owed what and to whom. There was no discussion of
    12                                              No. 06-3910
    standing or of arbitrability. Even so, in a post-hearing
    brief filed by EBC on October 19, 2005 (SSI did not file a
    post-hearing brief), EBC addressed the “standing” defense
    presented in SSI’s position paper:
    SSI claims that EBC lacks standing to compel SSI to
    arbitrate EBC’s claim because SSI did not agree to the
    assignment of the Subcontract to EBC, and because
    certain alleged “cure” payments were not made.
    Generally speaking, issues of standing are for the
    arbitrator to decide in the first instance.
    Arbitrator Kral’s award was issued on November 21,
    2005. He recognized that “a threshold issue was raised
    by SSI as to the standing of EBC to arbitrate this dispute
    under Subcontract Article 6.2 [the arbitration clause]. EBC
    agreed that it had assumed the Subcontract as evidenced
    by the Bankruptcy Court filings.” He also noted that
    SSI’s standing defense was premised on its position that
    EBC had not assumed the subcontract properly. EBC’s
    response was that “GEO’s performance of its work on
    the Project ended in December, 2002 and thereby the
    consent of SSI to the assumption is not required.” The
    arbitrator resolved the standing question by stating that
    he “agree[d] with EBC’s position.” He went on to reject
    the entirety of SSI’s counterclaim and awarded a total
    recovery, including contract interest, of $388,919.86 to EBC.
    II
    On January 6, 2006, EBC filed an action to confirm its
    award in the Circuit Court of Cook County; SSI promptly
    No. 06-3910                                                 13
    removed the case to federal court. As the district court
    described SSI’s position, SSI argued “first, that the arbitra-
    tor exceeded his powers by entering an award in favor
    of EBC, who was not a party to the original Agreement.
    Further, SSI contends, even if EBC were a party to the
    Agreement, it lacks standing to invoke the arbitration
    clause because it was in default of the contract.” We
    comment first on the standing argument, and then turn
    to the more troublesome arbitrability point.
    We begin with a word about terminology. We are
    reminded of Justice Scalia’s observation in Steel Co. v.
    Citizens for a Better Environment, 
    523 U.S. 83
    (1998), that
    “[j]urisdiction . . . is a word of many, too many, mean-
    ings[.]” 
    Id. at 90
    (internal quotation marks omitted). The
    same, unfortunately, can be said for “standing.” Every-
    thing from the fundamental requirement imposed by
    Article III that there must be a “case or controversy”
    between the parties seeking relief in federal court, to
    various prudential doctrines such as the restrictions on
    invoking the rights of third parties, to the inquiry
    whether a statute is designed to protect the rights of the
    person before the court, has been swept into the word
    “standing.” There is no reason to suppose that arbitrators
    are bound to the case-or-controversy requirement that
    circumscribes the judicial power of the United States.
    Indeed, some state courts are authorized to give advisory
    opinions. See, e.g., M ASS. C ONST. pt. II, ch. 3, art. 2; R.I.
    C ONST . art. 10, § 3. See generally Jonathan D. Persky,
    “Ghosts That Slay”: A Contemporary Look at State Advisory
    Opinions, 37 C ONN. L. R EV. 1155 (2005). In the context of
    arbitration, the term “standing” addresses the entitle-
    14                                               No. 06-3910
    ment of the party to raise a given point before the arbitra-
    tor. This is more like the concept of standing described
    by the Supreme Court in Associated General Contractors of
    California, Inc. v. California State Council of Carpenters,
    
    459 U.S. 519
    (1983), in which the Court considered the
    question whether a union was a proper party to sue for
    treble damages under the antitrust laws when it was
    neither a consumer nor a competitor in the market in
    which trade was restrained. In the course of rejecting the
    union’s right to sue, the Court commented that “[h]arm
    to the antitrust plaintiff is sufficient to satisfy the con-
    stitutional standing requirement of injury in fact, but the
    court must make a further determination whether the
    plaintiff is a proper party to bring a private antitrust
    action.” 
    Id. at 535
    n.31.
    That is the sense in which standing to arbitrate should
    be understood: is the petitioner a proper party to raise a
    particular claim in the arbitration? This explains why
    courts have not hesitated to hold that standing is a matter
    for the arbitrator to resolve, even though (as we note in a
    moment) arbitrability is usually an issue for the court. John
    Wiley & Sons, Inc. v. Livingston, 
    376 U.S. 543
    , 557-58 (1964);
    Chi. Typographical Union No. 16 v. Chi. Sun-Times, Inc., 
    860 F.2d 1420
    , 1424 (7th Cir. 1988) (“Procedural issues, in-
    cluding the standing of a party to the arbitration, . . . are
    for the arbitrator, so long as the subject matter of the
    dispute is within the arbitration clause.”) (emphasis
    omitted); United Steelworkers of Am., AFL-CIO-CLC v.
    Smoke-Craft, Inc., 
    652 F.2d 1356
    , 1360 (9th Cir. 1981)
    (“Whether the Steelworkers had standing as a party to
    the arbitration to proceed with that arbitration, which
    No. 06-3910                                                 15
    had been properly commenced, was a procedural matter
    for the determination of the arbitrator.”). SSI submitted
    the standing question to the arbitrator on its own
    initiative, and it was proper for the arbitrator to decide it.
    Focusing particularly on standing, the district court noted
    that “SSI’s . . . objection to EBC’s standing to enforce the
    arbitration clause relates to EBC’s alleged breach of other
    contract provisions.” Reiterating that this kind of issue
    is for the arbitrator, the court found that “[t]he arbitrator’s
    conclusion . . . is thus subject to deferential review,
    which it easily survives.”
    The harder question is whether an agreement to
    arbitrate existed between the parties. It is difficult, how-
    ever, not for the reasons the district court identified, but
    instead for a more fundamental reason. There is not a hint
    in the record that SSI ever called this issue to the arbitra-
    tor’s attention or sought to enjoin the arbitration on the
    ground that there was no agreement to arbitrate. Thus,
    even though the ordinary rule is that the question whether
    an agreement to arbitrate exists is one for the court, see
    AT&T Techs., Inc. v. Commc’ns Workers of Am., 
    475 U.S. 643
    ,
    649 (1986); Flender Corp. v. Techna-Quip Co., 
    953 F.2d 273
    ,
    277 (7th Cir. 1992), the right to a judicial determination
    of arbitrability is, like many rights, one that can be waived.
    As our detailed explanation above of the arbitration
    proceedings in this case demonstrates, SSI never told the
    arbitrator that it thought this dispute was nonarbitrable.
    To the contrary, it voluntarily submitted to the
    arbitrator’s authority, filed a counterclaim, and confined
    its objections to EBC’s standing to arbitrate. Only after
    16                                               No. 06-3910
    the arbitrator issued an award unfavorable to SSI and the
    case wound up in court did SSI raise an objection to
    the arbitrator’s authority to decide the dispute. SSI has
    stressed before this court that “[f]rom the outset, SSI
    contended that no agreement to arbitrate existed (and no
    contract of any kind existed) unless and until EBC com-
    plied with the requirements imposed by 11 U.S.C. § 365
    for assignment and assumption of executory contracts.”
    The problem is that SSI never said anything of the sort
    to the arbitrator. Not until it reached the district court
    did it recast its prior argument about standing as a chal-
    lenge to arbitrability.
    This is not a tactic we can accept, for sound policy
    reasons. It is terribly wasteful of the arbitrator’s time, the
    parties’ time, and the court’s time. Anyone who wants
    to object to arbitrability is entitled to make her position
    known to the arbitrator and the other party; the other
    party may then, if it wishes, respond with a petition for
    an order to compel arbitration under the Federal Arbitra-
    tion Act (“FAA”), 9 U.S.C. § 4, and obtain a judicial deter-
    mination on arbitrability. See, e.g., Moses H. Cone Hosp. v.
    Mercury Constr. Corp., 
    460 U.S. 1
    (1983). In addition,
    keeping the arbitrability card close to the chest would
    allow a party like SSI to take a wait-and-see approach: if
    it had liked Arbitrator Kral’s decision, it would have
    remained silent, but since it did not, it is now com-
    plaining about arbitrability.
    This court has already disapproved this method of
    proceeding. In AGCO Corp. v. Anglin, 
    216 F.3d 589
    (7th Cir.
    2000), for example, we stated:
    No. 06-3910                                                 17
    We first consider whether the Anglins waived any
    objection to the arbitrability of the Retail Obligations
    when they consented to arbitration and agreed to
    participate in the arbitration hearing. If a party will-
    ingly and without reservation allows an issue to be
    submitted to arbitration, he cannot await the out-
    come and then later argue that the arbitrator lacked
    authority to decide the matter. See Jones Dairy Farm
    v. Local No. P-1236, United Food & Commercial Workers
    Int’l Union, AFL-CIO, 
    760 F.2d 173
    , 175-76 (7th Cir.
    1985). If, however, a party clearly and explicitly re-
    serves the right to object to arbitrability, his participa-
    tion in the arbitration does not preclude him from
    challenging the arbitrator’s authority in court. Int’l
    Ass’n of Machinists & Aerospace Workers, Lodge No. 1777
    v. Fansteel, Inc., 
    900 F.2d 1005
    , 1009 (7th Cir. 1990). The
    record suggests that the Anglins have followed the
    latter 
    course. 216 F.3d at 593
    . It was “undisputed that counsel for the
    Anglins objected to arbitration” of the parties’ dispute, 
    id., on the
    ground that “the Anglins could not have contem-
    plated that their arbitration clause with AGCO would
    encompass a dispute with a nonsignatory party,” 
    id. at 596.
    We accordingly reversed the district court’s confirma-
    tion of AGCO’s award.
    Unlike the Anglins, SSI failed at any time during the
    arbitration proceedings to raise or reserve an objection
    to arbitrability. Instead, it freely accepted the arbitrator’s
    authority to decide the dispute and, indeed, submitted
    its own counterclaim for resolution. Only after the arbitra-
    tion outcome displeased SSI did it restyle its “standing”
    18                                               No. 06-3910
    and “executory contract” arguments as encompassing
    a challenge to the existence of an agreement to arbitrate
    between SSI and the nonsignatory EBC. As we noted
    in Jones Dairy Farm:
    Jones Dairy Farm did not make [arbitrability] an issue.
    It did not, while agreeing to participate in the arbitra-
    tion, challenge the arbitrator’s jurisdiction, and make
    clear that it was preserving its challenge for eventual
    presentation to a court if the arbitrator ruled in the
    union’s favor . . . . The company never questioned
    the arbitrator’s 
    authority. 760 F.2d at 175
    . “If a party voluntarily and unreservedly
    submits an issue to arbitration, he cannot later argue that
    the arbitrator had no authority to resolve it.” 
    Id. (citing cases
    from the Ninth, Fifth, and Second Circuits); see
    also CUNA Mut. Ins. Soc’y v. Office and Prof’l Employees
    Int’l Union, Local 39, 
    443 F.3d 556
    , 563 (2006) (“[T]here was
    not a true question of arbitrability in this case. Instead,
    CUNA dresses up its arguments about the scope of the
    arbitrator’s authority in arbitrability clothing.” (internal
    quotation marks omitted)); cf. 
    Flender, 953 F.2d at 278
    (“We
    reiterate ‘this circuit’s caution against allowing a party
    to use issues of the arbitrator’s authority as a ruse to
    obtain judicial review of the merits of an arbitral
    award.’ ” (quoting Burkart Randall v. Lodge No. 1076, 
    648 F.2d 462
    , 467 (7th Cir. 1981))). SSI’s professed challenge
    to arbitrability comes too late. By freely submitting to
    the arbitration of its claims without preserving a chal-
    lenge to the arbitrator’s authority, SSI missed the chance
    to come back later, before a court, and deny that an agree-
    ment to arbitrate existed.
    No. 06-3910                                                 19
    III
    With SSI’s challenge to arbitrability off the table, we have
    no trouble rejecting its remaining arguments. First, it is
    clear that Arbitrator Kral based his award on the con-
    tract and that he did not exceed his powers in any other
    respect when fashioning his award. The district court’s
    opinion contains a thorough analysis of these points, see
    No. 06 C 212, 
    2006 WL 2853830
    (N.D. Ill. Sept. 29, 2006).
    We see no need to repeat everything it said here, particu-
    larly given the level of deference that we apply to an
    arbitrator’s award. See IDS Life Ins. Co. v. Royal Alliance
    Assocs., Inc., 
    266 F.3d 645
    , 650-51 (7th Cir. 2001) (“[N]either
    error nor clear error nor even gross error is a ground for
    vacating an award[;] if the district judge is satisfied that
    the arbitrators resolved the entire dispute and can figure
    out what that resolution is, he must confirm the award.”);
    Baravati v. Josephthal, Lyon & Ross, Inc., 
    28 F.3d 704
    , 706
    (7th Cir. 1994) (“Judicial review of arbitration awards is
    tightly limited; perhaps it ought not be called ‘review’
    at all.”).
    Nor did the district court abuse its discretion in denying
    SSI’s motion for reconsideration under F ED. R. C IV. P. 59.
    See Zivitz v. Greenberg, 
    279 F.3d 536
    , 539 (7th Cir. 2002). The
    motion argued that EBC had concealed an affidavit that
    contradicted the testimony of EBC’s sole witness at the
    arbitration hearing, and that this “newly discovered
    evidence” tended to show that EBC’s award had been
    “procured by fraud, corruption or other means,” which
    is one ground for vacating or amending an award under
    the FAA. See 9 U.S.C. § 10(a)(1).
    20                                               No. 06-3910
    To succeed on a motion under Rule 59, a party must
    show that: (1) it has evidence that was discovered post-
    trial; (2) it had exercised due diligence to discover the
    new evidence; (3) the evidence is not merely cumulative
    or impeaching; (4) the evidence is material; and (5) the
    evidence is such that a new trial would probably produce
    a new result. See Matter of Chi., Milwaukee, St. Paul & Pac.
    R.R. Co., 
    78 F.3d 285
    , 293-94 (7th Cir. 1996). SSI argues that
    in this case, however, the court should not have relied on
    the normal criteria for a Rule 59 motion, because the
    FAA “provides the exclusive grounds for challenging an
    arbitration award within its purview,” LaFarge Conseils
    et Etudes, S.A. v. Kaiser Cement & Gypsum Corp., 
    791 F.2d 1334
    , 1338 (9th Cir. 1986). Section 10(a)(1) of the FAA calls
    for the court to consider whether EBC’s alleged fraud
    was (1) not discoverable upon the exercise of due
    diligence prior to the arbitration; (2) materially related to
    an issue in the arbitration; and (3) established by clear
    and convincing evidence. Gingiss Int’l, Inc. v. Bormet, 
    58 F.3d 328
    , 333 (7th Cir. 1995).
    We need not decide which was the proper standard to
    apply in this case, because we do not think the district
    court abused its discretion under either of them. Under
    both Rule 59 and 9 U.S.C. § 10(a)(1), the materiality of the
    evidence is critical. At the hearing on SSI’s Rule 59 motion,
    the district court concluded that “nothing in the so-called
    newly discovered document . . . bears any relationship to
    the award, and it’s simply not material or outcome deter-
    minative.” SSI argues that under the FAA standard, the
    evidence must be material not necessarily to the outcome
    of the arbitration, but simply to some issue in the arbitra-
    No. 06-3910                                                21
    tion. SSI cites only Gingiss 
    International, supra
    , in support
    of this distinction, but Gingiss drew no such line. The
    question there was whether a district court erred by
    refusing to set aside an arbitration award under 9 U.S.C.
    § 10(a)(1); it had nothing to do with the standard of
    review that applies to a post-trial motion in a case to
    confirm an arbitral award. Moreover, Gingiss does not
    stand for the odd proposition that something might be
    material to an issue in an arbitration, but immaterial to
    the outcome. Without stronger support for this notion,
    we decline to adopt it. Finally, as EBC points out, § 10(a)(1)
    provides for vacatur only if the award itself was procured
    by “corruption, fraud, or undue means.” In other
    words, even if SSI is correct and we should be relying
    exclusively on the FAA, we must find a nexus between
    the purported fraud and the arbitrator’s final decision.
    The district court found no such nexus, nor do we.
    We mention briefly several other reasons why SSI cannot
    meet even the FAA standard. It is debatable at best
    whether the affidavit in question was concealed fraudu-
    lently; indeed, EBC denied that it withheld the docu-
    ment intentionally, and SSI offers no evidence to the
    contrary. The FAA also requires that the complaining
    party act with due diligence, yet the district court ex-
    pressed doubt that SSI had done so, since it had been
    aware of the issue for at least a month before the
    district court’s initial decision. Finally, even assuming
    that SSI had acted with due diligence and that the evi-
    dence of fraudulent withholding was clear and con-
    vincing, the fact remains that the district court found the
    “so-called newly discovered evidence” to be both cumula-
    22                                              No. 06-3910
    tive and immaterial. Both the district judge and the arbitra-
    tor were already aware of everything contained in the
    supposedly concealed document when they made their
    respective decisions. Under either Rule 59 or §10(a)(1), this
    finding supports a denial of SSI’s motion.
    IV
    The district court’s judgment confirming the arbitrator’s
    award is A FFIRMED.
    8-29-08
    

Document Info

Docket Number: 06-3910

Judges: Wood

Filed Date: 8/29/2008

Precedential Status: Precedential

Modified Date: 9/24/2015

Authorities (19)

Ahmad Baravati v. Josephthal, Lyon & Ross, Incorporated, ... , 28 F.3d 704 ( 1994 )

Chicago Typographical Union No. 16 v. Chicago Sun-Times, ... , 860 F.2d 1420 ( 1988 )

Burkart Randall, a Division of Textron, Inc. v. Lodge No. ... , 648 F.2d 462 ( 1981 )

Jones Dairy Farm v. Local No. P-1236, United Food and ... , 760 F.2d 173 ( 1985 )

Ids Life Insurance Company and American Express Financial ... , 266 F.3d 645 ( 2001 )

Cuna Mutual Insurance Society v. Office and Professional ... , 443 F.3d 556 ( 2006 )

Robert Zivitz and Nancy Zivitz v. Joel Greenberg , 279 F.3d 536 ( 2002 )

United Steelworkers of America, afl-cio.clc v. Smoke-Craft, ... , 652 F.2d 1356 ( 1981 )

Agco Corporation v. Max Anglin , 216 F.3d 589 ( 2000 )

In the Matter of Chicago, Milwaukee, St. Paul & Pacific ... , 78 F.3d 285 ( 1996 )

Flender Corporation v. Techna-Quip Company and Robert J. ... , 953 F.2d 273 ( 1992 )

Gingiss International, Inc. v. Norman E. Bormet and Phyllis ... , 58 F.3d 328 ( 1995 )

lafarge-conseils-et-etudes-sa-v-kaiser-cement-gypsum-corp , 791 F.2d 1334 ( 1986 )

International Association of MacHinists and Aerospace ... , 900 F.2d 1005 ( 1990 )

John Wiley & Sons, Inc. v. Livingston , 84 S. Ct. 909 ( 1964 )

At&T Technologies, Inc. v. Communications Workers , 106 S. Ct. 1415 ( 1986 )

Steel Co. v. Citizens for a Better Environment , 118 S. Ct. 1003 ( 1998 )

Associated General Contractors of California, Inc. v. ... , 103 S. Ct. 897 ( 1983 )

Moses H. Cone Memorial Hospital v. Mercury Construction ... , 103 S. Ct. 927 ( 1983 )

View All Authorities »