Public Utilities Commission of v. FERC ( 2009 )


Menu:
  •                           In the
    United States Court of Appeals
    For the Seventh Circuit
    Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    ILLINOIS C OMMERCE C OMMISSION, et al.,
    Petitioners,
    v.
    F EDERAL E NERGY R EGULATORY C OMMISSION, et al.,
    Respondents.
    Petitions to Review Orders of the
    Federal Energy Regulatory Commission.
    A RGUED A PRIL 13, 2009—D ECIDED A UGUST 6, 2009
    Before C UDAHY, P OSNER, and T INDER, Circuit Judges.
    P OSNER, Circuit Judge. We have before us challenges to a
    decision by the Federal Energy Regulatory Commission
    concerning the reasonableness of rates for the transmission
    of electricity over facilities owned by utilities that belong
    to a Regional Transmission Organization (that is, a power
    pool) called PJM Interconnection. PJM Interconnection,
    L.L.C., 119 F.E.R.C. ¶ 61,063 (2007), rehearing denied, 122
    F.E.R.C. ¶ 61,082 (2008); see 16 U.S.C. § 824e; Atlantic City
    Electric Co. v. FERC, 
    295 F.3d 1
    , 10 (D.C. Cir. 2002). (“PJM”
    2           Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    stands for “Pennsylvania-New Jersey-Maryland,” but the
    full name is not used any more.) “RTOs are voluntary
    associations in which each of the owners of transmission
    lines that comprise an integrated regional grid cedes
    to the RTO complete operational control over its transmis-
    sion lines.” Richard J. Pierce, Jr., “Regional Transmission
    Organizations: Federal Limitations Needed for Tort
    Liability,” 
    23 Energy L.J. 63
    , 64 (2002); see also Regional
    Transmission Organizations, 
    65 Fed. Reg. 810
    -01, 
    2000 WL 4557
     (FERC Jan. 6, 2000); Morgan Stanley Capital Group
    Inc. v. Public Utility District No. 1, 
    128 S. Ct. 2733
    , 2741
    (2008). PJM’s region stretches east and south from the
    Chicago area, primarily to western Michigan and eastern
    Indiana, Ohio, Pennsylvania, New Jersey, Delaware,
    Maryland, the District of Columbia, and Virginia. PJM
    Interconnection, L.L.C., supra, p. 3, see FPL Energy Marcus
    Hook, L.P. v. FERC, 
    430 F.3d 441
    , 442-43 (D.C. Cir. 2005).
    The region is home to more than 50 million consumers
    of electricity.
    Two issues are presented. The first, raised by American
    Electric Power Service Corporation and the Public
    Utilities Commission of Ohio (participation by state
    commissions in rate proceedings before FERC is au-
    thorized by 16 U.S.C. § 825g(a); see also § 825l(a)), involves
    the pricing of electricity transmitted from the Midwest
    to the East through Ohio. PJM wants that transmission to
    be priced on the basis of the cost to American Electric
    of transmitting one more unit of electricity, that is, the
    marginal cost; and FERC agrees. Such a price excludes
    the cost that the company incurred when it built the
    transmission facilities. That cost—which American
    Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239          3
    Electric wants to be permitted to reflect in its rates—is
    what economists call a “sunk” cost, that is, a cost that has
    already been incurred. So while its financial burden can
    be shifted (from American Electric to the eastern utili-
    ties), the cost itself cannot be shifted, and therefore
    shifting the financial burden created by the cost from one
    set of shoulders to another will have no direct effect on
    service or investment.
    Had FERC decided that American Electric would not
    be permitted to charge a price that covered the cost of
    building a new transmission facility or upgrading an
    existing one, its decision would have affected the alloca-
    tion of resources and not just of money. It would have
    deterred the building of new facilities that benefited
    customers outside American Electric’s service area, be-
    cause building them would become an unprofitable
    venture. FERC emphasizes, however, that the company’s
    existing facilities, which are all that are involved in this
    case, were built before 2001 when PJM became a Regional
    Transmission Organization, and were intended to serve
    American Electric’s customers only. So even if the
    facilities had not been fully paid for, there would be no
    economic basis for shifting any part of their costs to
    other members, because American Electric did not
    expect when it built the facilities that any part of their
    cost would be defrayed by anyone besides its customers.
    PJM and FERC have made clear that American Electric will
    be allowed to charge a price that covers its costs for
    transmission to other utilities over new or upgraded
    facilities.
    4           Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    American Electric points out that some of its existing
    facilities are not fully depreciated. But it can continue to
    depreciate them over their remaining useful life in order
    to create an accounting reserve or obtain a tax benefit.
    And when it builds a new facility it will be allowed, as
    we said, to recover the full costs of that facility in its prices.
    The company may be trying to extract a monopoly price
    for the use of its facilities. It stands between western
    sellers of electricity and their eastern customers and
    would like to extract a toll for giving the former passage
    to the latter, a toll that has no relation to its costs of render-
    ing that service. It charged its customers for the costs
    of building its existing facilities and recovered those
    costs fully and now wants to recover them all over again
    from another group of consumers. And it’s not as if
    American Electric were being required to provide trans-
    mission to the east at zero price. It is permitted to
    charge for the service—just not to include in the charge
    its sunk costs.
    The second issue relates to the financing of new trans-
    mission facilities. Here the Ohio commission joins its
    Illinois counterpart, representing the interests of the
    midwestern utilities in PJM’s region, in objecting to
    PJM’s proposed method, approved by FERC, for pricing
    new transmission facilities that have a capacity of 500
    kilovolts or more. Heretofore all new facilities in PJM’s
    region have been financed by contributions from the
    region’s electrical utilities calculated on the basis of the
    benefits that each utility receives from the facilities. This
    will continue to be the rule for facilities with capacities of
    Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239         5
    less than 500 kV. But for the higher-voltage facilities
    FERC has decided that all the utilities in PJM’s region
    should contribute pro rata; that is, their rates should be
    raised by a uniform amount sufficient to defray the facili-
    ties’ costs.
    FERC’s stated reasons are that some of PJM’s members
    entered into similar pro rata sharing agreements with
    each other more than forty years ago and would like to
    follow that precedent, that figuring out who benefits
    from a new transmission facility and by how much is
    very difficult and so generates litigation, and that every-
    one benefits from high-capacity transmission facilities
    because they increase the reliability of the entire net-
    work. Despite the stakes in the dispute—the new policy
    might, for example, force Commonwealth Edison to
    contribute hundreds of millions of dollars to an above-500
    kV eastern project called “Project Mountaineer,” when it
    would not have had to pay a dime under the benefits-
    based system applicable to lower-voltage transmission
    facilities—no data are referred to in FERC’s two opinions
    (the original opinion and the opinion on rehearing). No
    lawsuits are mentioned. No specifics concerning difficul-
    ties in assessing benefits are offered. No particulars are
    presented concerning the contribution that very high-
    voltage facilities are likely to make to the reliability of
    PJM’s network. Not even the roughest estimate of likely
    benefits to the objecting utilities is presented. The first
    sentence in this paragraph is an adequate summary of the
    Commission’s reasoning, minus recourse to metaphor, as
    in the Commission’s repeated references to very high-
    voltage facilities as the “backbone” of PJM’s network. The
    Commission’s insouciance about the basis for its ruling
    6          Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    is mirrored by its lawyers: their brief devotes only five
    pages to the 500 kV pricing issue.
    The objections to the Commission’s ruling pivot on an
    asymmetry between the eastern and western portions
    of PJM’s region. In the west the electrical generating
    plants usually are close to the customers—Chicago for
    example is ringed by power plants. As a result, relatively
    low-voltage transmission facilities—mainly 345 kV—are
    preferred. In the east, where the power plants generally
    are farther away from the customers, 500 kV and even
    higher-voltage transmission facilities are preferred,
    because high voltage is more efficient than low for trans-
    mitting electricity over long distances. So far as appears,
    few if any such facilities will be built in the objectors’
    service areas, that is, in the Midwest, within the fore-
    seeable future. FERC seems not to care whether any will
    ever be built, because the reasons it gave for approving
    PJM’s new pricing method are independent of where
    the facilities are located.
    The first two reasons the Commission gave can be
    dispatched briefly. The fact that some of the same
    members of PJM who agreed to share the costs of such
    facilities with each other many years ago would like
    contributions from midwestern utilities carries no
    weight. The eastern utilities that created PJM refer to
    themselves revealingly as the “classic” PJM utilities, and
    the fact that these utilities thought it appropriate to
    share costs in 1967 says nothing about the advantages
    and disadvantages of such an arrangement in the larger,
    modern PJM network.
    Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239              7
    The Commission said that it would be inclined to defer
    to “regional consensus,” but acknowledged there was
    none; the midwestern utilities are part of PJM’s region
    but did not agree to the eastern utilities’ cost-sharing
    proposal. As we shall see, the fact that one group of
    utilities desires to be subsidized by another is no reason
    in itself for giving them their way.
    The second reason the Commission gave for approving
    PJM’s pricing scheme—the difficulty of measuring
    benefits and the resulting likelihood of litigation over
    them—fails because of the absence of any indication that
    the difficulty exceeds that of measuring the benefits to
    particular utilities of a smaller-capacity transmission
    line. Like the D.C. Circuit in Sithe/Independence Power
    Partners, L.P. v. FERC, 
    285 F.3d 1
    , 5 (D.C. Cir. 2002) (citation
    omitted), we acknowledge “that feasibility concerns play
    a role in approving rates, indicating that FERC is not
    bound to reject any rate mechanism that tracks the cost-
    causation principle less than perfectly.” But we also agree
    that “the Commission’s cursory response simply will not
    do. At no point did the Commission explain how these
    considerations [that the tariffs and refund mechanism
    produced ‘efficient price signals,’ and that petitioner’s
    requested refunds would somehow disrupt that price
    signaling, would be ‘infeasible,’ and a matter of ‘unending
    controversy’] applied. Why, we wonder, would a dif-
    ferent method of refunds, based more closely on cost-
    causation principles, jeopardize desirable price signaling
    or be infeasible?” 
    Id.
    No doubt the more a transmission facility costs, and
    therefore the greater the stakes in a dispute between
    8           Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    potential contributors to that cost, the more litigation
    there is likely to be. But how much more (at least approxi-
    mately) is the critical consideration and the Commission
    ignored it.
    That leaves for consideration the benefits that the
    midwestern utilities might derive from the greater re-
    liability that the larger-capacity transmission facilities
    might confer on the network as a whole. The reason for
    building such facilities is to satisfy the demand of eastern
    consumers for electricity, but the more transmission
    capacity there is, the less likely are blackouts or brownouts
    caused by surges of demand for electricity on hot
    summer days or by accidents that shut down a part of the
    electrical grid. Because the transmission lines in PJM’s
    service region are interconnected, a failure in one part of
    the region can affect the supply of electricity in other
    parts of the network. So utilities and their customers in the
    western part of the region could benefit from higher-
    voltage transmission lines in the east, but nothing in
    FERC’s opinions in this case enables even the roughest
    of ballpark estimates of those benefits.
    At argument FERC’s counsel reluctantly conceded that
    if Commonwealth Edison would derive only $1 million
    in expected benefits from Project Mountaineer, for which
    it is being asked to chip in (by its estimate) $480 million,
    the disparity between benefit and cost would be unrea-
    sonable. The concession was prudent. Algonquin Gas
    Transportation Co. v. FERC, 
    948 F.2d 1305
    , 1313 (D.C. Cir.
    1991); Pacific Gas & Electric Co. v. FERC, 
    373 F.3d 1315
    , 1320-
    21 (D.C. Cir. 2004). As FERC itself explained in Trans-
    Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239             9
    continental Gas Pipe Line Corp., 112 F.E.R.C. ¶ 61,170, 61,924-
    61,925 (2005), “a claim of generalized system benefits
    is not enough to justify requiring the existing shippers to
    subsidize the uncontested increase in electric costs caused
    by the Cherokee project. . . . The rehearing applicants
    suggest that the use of the Cherokee shippers’ transporta-
    tion quantities in deriving the fuel retention percentages
    and their payment of such charges reduce the fuel costs
    borne by the existing shippers. However, they point to
    no evidence in the record that seeks to quantify this
    benefit, or even shows that such a benefit has occurred . . . .
    The Commission concludes that all these alleged
    benefits are simply too speculative and unsupported to
    be taken into account.”
    FERC is not authorized to approve a pricing scheme
    that requires a group of utilities to pay for facilities from
    which its members derive no benefits, or benefits that are
    trivial in relation to the costs sought to be shifted to its
    members. “ ‘[A]ll approved rates [must] reflect to some
    degree the costs actually caused by the customer who must
    pay them.’ KN Energy, Inc. v. FERC, 
    968 F.2d 1295
    , 1300
    (D.C. Cir. 1992); Transmission Access Policy Study Group v.
    FERC, 
    225 F.3d 667
    , 708 (D.C. Cir. 2000); Pacific Gas & Elec.
    Co. v. FERC, No. 03-1025, 
    373 F.3d 1315
    , 1320-21 (D.C. Cir.
    2004). Not surprisingly, we evaluate compliance with
    this unremarkable principle by comparing the costs
    assessed against a party to the burdens imposed or
    benefits drawn by that party.” Midwest ISO Transmission
    Owners v. FERC, 
    373 F.3d 1361
    , 1368 (D.C. Cir. 2004); see
    also Alcoa Inc. v. FERC, 
    564 F.3d 1342
    , 1346-47 (D.C. Cir.
    2009); Sithe/Independence Power Partners, L.P. v. FERC, supra,
    10         Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    
    285 F.3d at 4-5
    ; Federal Power Act, 16 U.S.C. § 824d. To
    the extent that a utility benefits from the costs of new
    facilities, it may be said to have “caused” a part of those
    costs to be incurred, as without the expectation of its
    contributions the facilities might not have been built, or
    might have been delayed. But as far as one can tell from
    the Commission’s opinions in this case, the likely benefit
    to Commonwealth Edison from new 500 kV projects is
    zero. The opinion on rehearing attributes the need for
    new transmission capacity in PJM to the threat of “de-
    graded reliability in Eastern PJM,” 122 F.E.R.C. ¶ 61,082,
    p. 13 (emphasis added), and nowhere do the Commission’s
    opinions suggest that degraded reliability is a danger
    in Midwestern PJM.
    No doubt there will be some benefit to the midwestern
    utilities just because the network is a network, and there
    have been outages in the Midwest. But enough of a benefit
    to justify the costs that FERC wants shifted to those
    utilities? Nothing in the Commission’s opinions enables
    an answer to that question. Although the Commission
    did say that a 500 kV transmission line has twice the
    capacity of a 345 kV line, it added that “the reliability of
    500 kV and above circuits in terms of momentary and
    sustained interruptions is 70 percent more reliable than
    138 kV circuits and 60 percent more than 230 kV circuits
    on a per mile basis,” PJM Interconnection, L.L.C., supra,
    119 F.E.R.C. ¶ 61,063, p. 23; 122 F.E.R.C. ¶ 61,082, p. 16
    (emphasis added)—but did not compare the reliability
    of a 500 kV line to that of a 345 kV line, even though
    network reliability is the benefit that the Commission
    Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239          11
    thinks the midwestern utilities will obtain from new
    500 kV lines in the East.
    Rather desperately FERC’s lawyer, and the lawyer for
    the eastern utilities that intervened in support of its
    ruling, reminded us at argument that Commission has a
    great deal of experience with issues of reliability and
    network needs, and they asked us therefore (in effect) to
    take the soundness of its decision on faith. But we
    cannot do that because we are not authorized to uphold
    a regulatory decision that is not supported by substantial
    evidence on the record as a whole, or to supply reasons
    for the decision that did not occur to the regulators. E.g.,
    
    5 U.S.C. § 706
    ; Bethany v. FERC, 
    276 F.3d 934
    , 940 (7th
    Cir. 2002); Central Illinois Public Service Co. v. FERC, 
    941 F.2d 622
    , 627 (7th Cir. 1991); Pacific Gas & Electric Co. v.
    FERC, supra, 373 F.3d at 1319. The reasons that did occur
    to FERC are inadequate.
    We do not suggest that the Commission has to calculate
    benefits to the last penny, or for that matter to the last
    million or ten million or perhaps hundred million dollars.
    Midwest ISO Transmission Owners v. FERC, supra, 373
    F.3d at 1369 (“we have never required a ratemaking
    agency to allocate costs with exacting precision”);
    Sithe/Independence Power Partners, L.P. v. FERC, supra,
    
    285 F.3d at 5
    . If it cannot quantify the benefits to the
    midwestern utilities from new 500 kV lines in the East,
    even though it does so for 345 kV lines, but it has an
    articulable and plausible reason to believe that the benefits
    are at least roughly commensurate with those utilities’
    share of total electricity sales in PJM’s region, then fine;
    12         Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    the Commission can approve PJM’s proposed pricing
    scheme on that basis. For that matter it can presume that
    new transmission lines benefit the entire network by
    reducing the likelihood or severity of outages. E.g., Western
    Massachusetts Elec. Co. v. FERC, 
    165 F.3d 922
    , 927 (D.C.
    Cir. 1999). But it cannot use the presumption to avoid the
    duty of “comparing the costs assessed against a party to
    the burdens imposed or benefits drawn by that party.”
    Midwest ISO Transmission Owners v. FERC, supra, 373 F.3d
    at 1368. Nor did it in the Western Massachusetts case.
    In Midwest ISO, where the objecting utilities con-
    tended that they were being asked to pay far more
    than their share of the benefits—which they said was a
    measly 5 percent—the court found that they were mis-
    representing the record. 373 F.3d at 1370. There is no
    comparable basis on which to affirm the Commission’s
    decision in this case. Our review of decisions by FERC is
    deferential, e.g., Town of Norwood v. FERC, 
    962 F.2d 20
    , 22
    (D.C. Cir. 1992); “we require only that the agency have
    made a reasoned decision based upon substantial
    evidence in the record.” 
    Id.
     But the Commission failed to
    do that, and so the case must be remanded for further
    proceedings; we intimate no view on their outcome.
    To summarize, the petitions for review that concern
    the pricing of existing transmission facilities are denied,
    but the petitions concerning the pricing of new facilities
    that have a capacity of 500 kilovolts or more are granted.
    Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239                 13
    C UDAHY, Circuit Judge, concurring in part and dissenting
    in part. I concur fully in the majority’s approval of FERC’s
    rate design for existing facilities’ transmission costs.
    I write separately to express my concerns over the major-
    ity’s disapproval of the proposed rate design for new
    transmission lines operating at voltages at or in excess
    of 500,000 volts.
    The United States is now engaged in an urgent project
    to upgrade its electric transmission grid, which for years
    has been generally regarded as inadequate,1 and may
    become more deficient with the addition of major new
    anticipated loads.2 The existing transmission system
    originally served vertically integrated utilities that built
    their own generation relatively close to their customers.
    The system was not designed for long-distance power
    1
    E.g., House Report on the Energy Policy Act of 2005, H.R. Rep.
    No. 109-215(I), at 171 (“Investment in electric transmission
    expansion has not kept pace with electricity demand. Moreover,
    transmission system reliability is suspect as demonstrated by
    the blackout that hit the Northeast and Midwest in August of
    2003. Legislation is needed to address the issues of transmis-
    sion capacity, operation, and reliability. In addition, state reg-
    ulatory approval delays siting of new transmission lines by
    many years. Even if a project is completed, there is uncer-
    tainty as to whether utilities will be able to recover all of their
    investment, which hinders new transmission construction.”).
    2
    See, e.g., Argonne, Impact of Plug-in Hybrid Electric Vehicles on
    the Electricity M arket in Illinois, available at
    http://www.dis.anl.gov/news/Illinois_PluginHybrids.htm l
    (visited 7/27/09).
    14          Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    transfers between different parts of the country. The
    inadequacy of the present network and the urgency of
    the need for its improvement has only been exacerbated
    by the additional burdens imposed by deregulation (or
    restructuring), which “unbundled” generation and trans-
    mission and created a need to bring power from distant
    generators.3 Additional challenges have been posed by
    the demand for power from renewable generation
    sources (such as wind farms) that are often located in
    places remote from centers of electric consumption.4
    Long-distance transmission, which inherently presents
    challenges to reliability, is accomplished most efficiently
    by the highest levels of voltage—500 kV and above.
    According to FERC, “500 kV and above circuits . . . [are]
    70 percent more reliable than 138 kV circuits and 60
    percent more than 230 kV circuits on a per mile basis.” PJM
    Interconnection LLC, 
    122 FERC ¶ 61,082
    , 
    2008 WL 276596
    ,
    at *16 (Jan. 31, 2008) (order on rehearing). Further,
    because power transfer capability increases with the
    square of voltage,5 extra-high voltage transmission also
    3
    See Mark Cooper, Electricity Deregulation Puts Pressure on the
    Transmission Network and Increases its Cost, available at
    http://www.consumersunion.org/Transmission%20brief%208.
    27.pdf (visited 7/27/09).
    4
    See Matthew L. Wald, Debate on Clean Energy Leads to
    Regional Divide, N.Y. Times, July 14, 2009, at A13.
    5
    See generally Peter W. Sauer, Reactive Power and Voltage Control
    Issues in Electric Power Systems, Applied Mathematics for
    (continued...)
    Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239                  15
    facilitates enormous transfers of power: “the maximum
    transfer capability at 500 kV and above is approximately
    6 times greater than a similar transmission line operated
    at 230 kV and more than twice that at 345 kV . . . .” 
    Id.
    In light of its unique contributions to reliability and
    transfer capability, extra-high voltage transmission is
    especially fitted to be financed equally by all utilities
    that benefit from its role as the “backbone” of the system.6
    Pro rata rates for extra-high voltage transmission, through
    their simplicity of application, also provide a strong
    incentive to build transmission undeterred by fruitless
    controversy over the allocation of costs.
    It is significant that FERC’s conclusion that the costs of
    extra-high voltage transmission facilities should be
    shared is consistent with the proposals of fifteen of PJM’s
    seventeen members. In the course of this proceeding,
    5
    (...continued)
    Restructured Electric Power Systems: Optimization, Control,
    and Computational Intelligence (Joe H. Chow, Felix F. Wu &
    James A. Momoh, eds.) (2005).
    6
    These are “backbone” facilities because they “integrate major
    system resources,” Pacific Gas & Elec. Co., 
    53 FERC ¶ 61146
    ,
    61520-21 & n.65, 
    1990 WL 319356
    , at *10 (Oct. 31, 1990), by
    facilitating major transfers of power between and among
    regions. To my knowledge, no court prior to ours has
    objected to the metaphor. See Public Serv. Co. of Ind., Inc. v. FERC,
    
    575 F.2d 1204
    , 1217 (7th Cir. 1978); see also Cal. Dep’t of Water
    Res. v. FERC, 
    489 F.3d 1029
    , 1035 (9th Cir. 2007); Boston Edison
    Co. v. FERC, 
    441 F.3d 10
    , 11 (1st Cir. 2006); Cajun Elec. Power
    Coop., Inc. v. FERC, 
    924 F.2d 1132
    , 1134 (D.C. Cir. 1991).
    16         Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    various parties proposed voltages lower than 500 kV as
    the threshold above which proportional cost-sharing
    should apply. Although PJM’s members were unable to
    agree on a specific voltage cutoff, they were broadly in
    agreement that the rate structure should be designed to
    share the costs of facilities providing general systemic
    benefits. There was thus an effort by many parties to
    broaden the area of rate-simplification by enlarging the
    set of new transmission facilities to be governed by cost-
    sharing, not to narrow or eliminate it. I think these
    efforts illustrate the value of simplification and the dif-
    ficulties in the design of a transmission rate structure
    that attempts rigidly and in all circumstances to trace
    benefits to specific utilities.
    However theoretically attractive may be the principle of
    “beneficiary pays,” an unbending devotion to this rule
    in every instance can only ignite controversy, sustain
    arguments and discourage construction while the nation
    suffers from inadequate and unreliable transmission.
    Unsurprisingly, it is not possible to realistically deter-
    mine for each utility and with reference to each major
    project the likelihood that rate-simplification will reduce
    litigation, or to calculate the precise value of not having
    to cover the costs of power failures and of not paying
    costs associated with congestion, and all this over the
    next forty to fifty years. Concerns about the real value
    to individual utilities of the stability and efficiency pro-
    vided by improvements to the backbone grid are
    answered by their voluntary participation in the power
    pool and its collaborative “RTEP” (or regional transmission
    expansion planning) process. Rate-making based on cost
    Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239              17
    causation is assured by this process, since universal
    cost-sharing is recommended only when developments
    are found to benefit the integrated system as a whole.7
    Contrary to the majority’s suggestion, FERC did not
    violate principles of “cost causation” by failing to propose
    a number that would represent the specific monetary
    benefits to each utility of a more reliable network. Cost
    causation requires that “approved rates reflect to some
    degree the costs actually caused by the customer who must
    pay them.” Midwest ISO Transmission Owners v. FERC, 
    373 F.3d 1361
    , 1368 (D.C. Cir. 2004) (Roberts, J.) (quoting KN
    Energy, Inc. v. FERC, 
    968 F.2d 1294
    , 1300 (D.C. Cir. 1992))
    (internal quotation marks omitted). However, until today,
    no court has found that cost causation requires FERC to
    monetize the benefits of reliability improvements in
    7
    “Project Mountaineer,” with which the majority seems
    particularly concerned, is no exception. Project Mountaineer is
    a plan to construct hundreds of miles of 500 and 765 kV linkages
    between eastern and western PJM. The PJM literature, to
    which Commonwealth Edison could have objected but did not,
    indicates that Project Mountaineer was a response to the
    nearly 200% increase in congestion costs from 2004 to 2005.
    Ventyx, Major Transmission Constraints in PJM, at *3 n.4 (2007),
    available at http://www.ventyx.com/pdf/wp07-transmission-
    constraints.pdf (visited 7/14/09). These increased congestion
    costs were partly due to the expansion of PJM’s footprint. 
    Id.
     As
    part of its cost allocation process, PJM determined that Project
    Mountaineer “would bring about substantial congestion relief
    and reliability improvements increasing Midwest-to-east
    transfers by 5,000 MW.” Id. at *3.
    18         Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    order to share the costs. Indeed, the cases the majority
    cites support the opposite conclusion. Most notably, in
    Midwest ISO, the panel was quite clear that utilities that
    draw benefits from being a part of a power pool should
    share the cost of having a power pool. Id. at 1371. As then-
    Judge Roberts explained, “upgrades designed to preserve
    the grid’s reliability constitute system enhancements
    that are presumed to benefit the entire system.” Id. at 1369
    (internal quotation marks, citations and alterations omit-
    ted, and emphasis added); see also Entergy Servs., Inc. v.
    FERC, 
    319 F.3d 536
    , 543 (D.C. Cir. 2003); Western Massachu-
    setts Elec. Co. v. FERC, 
    165 F.3d 922
    , 927 (D.C. Cir. 1999).
    Since there is a presumption that enhanced reliability
    benefits all of the systems members, Commonwealth
    Edison (ComEd) can be required to bear a proportional
    share of an improvement’s costs even where it is not
    possible to determine precisely how much it benefits.
    Put otherwise, the burden is on ComEd to show that it
    would not benefit from the newly planned transmission
    facilities; the burden is not on FERC to estimate how
    much ComEd would benefit from a more reliable grid.
    Indeed, in Midwest ISO, the panel rejected the objecting
    utility’s argument that it could not be made to pay sixty
    to seventy percent of an investment’s costs because it
    would obtain only five percent of the benefits. 373 F.3d
    at 1370. As the majority notes, the panel found no
    record support for the utility’s claim that its benefits
    would be so low. (Maj. Op. at 12.) However, the panel
    also held that cost causation principles do not require
    the costs of a new facility to be apportioned based on the
    objecting utility’s actual use of that facility. To the
    Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239                19
    contrary, the “benefits” of system enhancements must be
    understood more broadly than this. Again, then-Judge
    Roberts:
    even if they are not in some sense using the ISO
    [roughly a term for a power pool], the MISO Owners
    still benefit from having an ISO. In this sense, MISO is
    somewhat like the federal court system. It costs a
    considerable amount to set up and maintain a court
    system, and these costs—the costs of having a court
    system—are borne by the taxpayers, even though the
    vast majority of them will have no contact with that
    system (will not use that system) in any given year . . .
    The MISO Owners’ position is tantamount to saying
    that if they are not a litigant, they should not be
    made to pay for any of the costs of having a court
    system. Since the MISO Owners do, in fact, draw
    benefits from being a part of the MISO regional trans-
    mission system, FERC correctly determined that they
    should share the cost of having an ISO.
    Id. at 1371. I fear that the majority has lost sight of this
    basic principle.8
    8
    The other cases on which the majority relies also do not hold
    that FERC is required to explain the benefits of reliability. For
    instance, in Algonquin Gas Transmission Co. v. FERC, 
    948 F.2d 1305
     (D.C. Cir. 1991), the court rejected FERC’s proposal to
    share the costs of a new gas pipeline because FERC had not
    provided any evidence that the pipeline would provide system-
    wide benefits. 
    Id. at 1313
    . In the present case, by contrast, there
    (continued...)
    20          Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    Because the majority’s decision is based on an
    unusually narrow conception of cost-causation, its char-
    acterizations of FERC’s and the intervenor’s arguments
    as “insouciant” (Maj. Op. at 5) and “desperate” (Maj. Op.
    at 11) strike me as conspicuously misplaced. FERC re-
    sponded to ComEd’s objections by indicating that the
    proposed projects would improve reliability and reduce
    congestion. See PJM Interconnection, 
    2008 WL 276596
    , at *16.
    It did not explain how PJM’s members benefit from a
    reliable network because no court had hitherto re-
    quired it to do so. Until now, it went without saying
    that network reliability benefits the network’s members.
    This is not insouciance; “[e]xplanations come to an end
    somewhere.” Ludwig Wittgenstein, Philosophical Investiga-
    tions §1 (G.E.M. Anscombe trans., 1968).
    The big picture here is that FERC’s proposal to spread
    the cost of very high voltage transmission on a uniform
    8
    (...continued)
    is no dispute that the transmission facilities at issue would
    increase network transfer capacity and improve network
    reliability.
    Along the same lines, Alcoa Inc. v. FERC, 
    564 F.3d 1342
     (D.C.
    Cir. 2009), provides no support at all for the majority’s robust
    understanding of the requirements of cost causation. In that
    case, the D.C. Circuit rejected Alcoa’s claim that it was
    being asked to pay more than its fair share of the costs of
    maintaining network reliability, holding instead that because
    rate design rests on technical issues and policy judgments
    that lie at the core of the regulatory mission, FERC’s explanation
    for its rate scheme “although admittedly spare, is nonetheless
    adequate.” 
    Id. at 1347-48
    .
    Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239                  21
    basis seems to me in the interest of efficient, high-capacity
    transfer capability and of the closely linked improve-
    ment of reliability, which affects the system generally.9
    Deregulation created a demand for competitive sources of
    power, often at a distance. Because 500 kV and above lines
    satisfy these new systemic needs, their separate treat-
    ment for rate-making purposes is both sensible and
    innovative. While an effort to identify specific benefits to
    9
    Indeed, the majority concedes that reliability problems affect
    all of the system’s users when it acknowledges that failures
    in one part of an integrated network can affect the supply of
    electricity in other parts of the network. (Maj. Op. at 8). So-called
    “cascading outages” have occurred on a number of occasions
    in the recent past. Most notably, in 2003 a power failure that
    started in Ohio spread through eight states, including parts of
    PJM’s footprint, leaving 50 million people without power and
    causing an estimated $12 billion in economic losses. E.g., Peter
    Fox-Penner, A Year Later, Lessons From the Blackout, N.Y. Times,
    Aug. 15, 2004, at 14WC. As the majority notes, FERC has not
    estimated the probability that degraded reliability in Eastern
    PJM could affect Midwestern PJM. However, even if this
    probability is vanishingly small, a very low number multiplied
    by billions of dollars may still yield a very high number.
    Further, there is no reason to suppose that ComEd’s customers
    are unaffected by problems with the reliability of the PJM grid.
    By one estimate, power outages and disturbances cause $4
    to $7 billion in damages per year in Illinois alone. See Primen,
    The Cost of Power Disturbances to Industrial & Digital
    Economy Companies (June 29, 2001), at D-1, available at
    http://www. onpower.com/pdf/EPRICostOfPowerProblems.pdf
    (visited 7/8/09).
    22         Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239
    specific utilities is a traditional rate design approach and
    may be appropriate for most electric plant facilities, it
    may miss the forest and focus on the trees when applied
    to very high voltage “backbone” facilities having a gen-
    eralized role in supporting reliability and high capacity
    power transfer. Perhaps as important in this picture is the
    urgency of the need to build transmission and the need
    for incentives to that end. Pro rata assignment of costs
    eliminates not only lawsuits but nitpicking controversies
    of every sort and delays standing in the path of action.
    From that point of view, I think FERC may be in a better
    position to implement a policy leading to prompt im-
    provement in a deficient transmission grid than this court,
    focused as it is on the inevitable complaints of utilities
    demanding more for their money. I therefore respectfully
    dissent from the majority’s unfortunate rejection of
    FERC’s rate scheme for new transmission lines carrying
    500 kV or higher.
    8-6-09
    

Document Info

Docket Number: 08-2239

Judges: Posner

Filed Date: 8/6/2009

Precedential Status: Precedential

Modified Date: 9/24/2015

Authorities (16)

Boston Edison Co. v. Ederal Energy Regulatory Commission , 441 F.3d 10 ( 2006 )

village-of-bethany-illinois-and-amoco-production-co , 276 F.3d 934 ( 2002 )

FPL Energy Marcus Hook, L.P. v. Federal Energy Regulatory ... , 430 F.3d 441 ( 2005 )

central-illinois-public-service-company-v-federal-energy-regulatory , 941 F.2d 622 ( 1991 )

public-service-company-of-indiana-inc-v-federal-energy-regulatory , 575 F.2d 1204 ( 1978 )

California Department of Water Resources v. Federal Energy ... , 489 F.3d 1029 ( 2007 )

Entergy Services, Inc. v. Federal Energy Regulatory ... , 319 F.3d 536 ( 2003 )

Western Massachusetts Electric Company v. Federal Energy ... , 165 F.3d 922 ( 1999 )

Midwest Iso Transmission Owners v. Federal Energy ... , 373 F.3d 1361 ( 2004 )

K N Energy, Inc. v. Federal Energy Regulatory Commission, ... , 968 F.2d 1295 ( 1992 )

Sithe/Independence Power Partners, L.P. v. Federal Energy ... , 285 F.3d 1 ( 2002 )

Pacific Gas and Electric Company v. Federal Energy ... , 373 F.3d 1315 ( 2004 )

Alcoa Inc. v. Federal Energy Regulatory Commission , 564 F.3d 1342 ( 2009 )

algonquin-gas-transmission-company-v-federal-energy-regulatory-commission , 948 F.2d 1305 ( 1991 )

cajun-electric-power-cooperative-inc-v-federal-energy-regulatory , 924 F.2d 1132 ( 1991 )

Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. ... , 128 S. Ct. 2733 ( 2008 )

View All Authorities »