Illinois Commerce Commission v. FERC , 721 F.3d 764 ( 2013 )


Menu:
  •                             In the
    United States Court of Appeals
    For the Seventh Circuit
    Nos. 11-3421, 11-3430, 11-3584, 11-3585, 11-3586,
    11-3620, 11-3787, 11-3795, 11-3806, 12-1027
    ILLINOIS C OMMERCE C OMMISSION, et al.,
    Petitioners,
    v.
    F EDERAL E NERGY R EGULATORY C OMMISSION,
    Respondent.
    Petitions to Review Orders of the
    Federal Energy Regulatory Commission.
    Nos. ER10-1791-000, ER10-1791-001, ER10-1791-002
    A RGUED A PRIL 10, 2013—D ECIDED JUNE 7, 2013
    Before P OSNER, W OOD , and W ILLIAMS, Circuit Judges.
    P OSNER, Circuit Judge. Control of more than half the
    nation’s electrical grid is divided among seven Regional
    Transmission Organizations, as shown in Figure 1. These
    are voluntary associations of utilities that own electrical
    transmission lines interconnected to form a regional grid
    and that agree to delegate operational control of the
    grid to the association. See 
    18 C.F.R. §§ 35.34
    (j), (k)(1)(i);
    Midwest ISO Transmission Owners v. FERC, 
    373 F.3d 1361
    ,
    2                      Nos.11-3421, 11-3430, 11-3584, et al.
    1363-65 (D.C. Cir. 2004). Power plants that do not own
    any part of the grid but generate electricity transmitted
    by it are also members of these associations, as are other
    electrical companies involved in one way or another
    with the regional grid.
    F IGURE 1
    R EGIONAL T RANSMISSION O RGANIZATIONS
    The RTOs play a key role in the effort by the Federal
    Energy Regulatory Commission “to promote competition
    in those areas of the industry amenable to competition,
    such as the segment that generates electric power, while
    ensuring that the segment of the industry characterized
    Nos. 11-3421, 11-3430, 11-3584, et al.                        3
    by natural monopoly—namely, the transmission grid
    that conveys the generated electricity—cannot exert
    monopolistic influence over other areas . . . . To further
    pry open the wholesale-electricity market and to
    reduce technical inefficiencies caused when different
    utilities operate different portions of the grid independ-
    ently, the Commission has encouraged transmission
    providers to establish ‘Regional Transmission Organiza-
    tions’—entities to which transmission providers would
    transfer operational control of their facilities for the
    purpose of efficient coordination . . . [and] has en-
    couraged the management of those entities by ‘Independ-
    ent System Operators,’ not-for-profit entities that operate
    transmission facilities in a nondiscriminatory manner.”
    Morgan Stanley Capital Group, Inc. v. Public Utility
    District No. 1, 
    554 U.S. 527
    , 536-37 (2008).
    Two Regional Transmission Organizations are involved
    in this case—Midwest Independent Transmission System
    Operator, Inc. (MISO) and PJM Interconnection, LLC
    (PJM). As shown in Figure 1, MISO operates in the mid-
    west and in the Great Plains states while PJM
    operates in the mid-Atlantic region but has midwestern
    enclaves in and surrounding Chicago and in southwestern
    Michigan.
    Each RTO is responsible for planning and directing
    expansions and upgrades of its grid. It finances these
    activities by adding a fee to the price of wholesale elec-
    tricity transmitted on the grid. 
    18 C.F.R. §§ 35.34
     (k)(1), (7).
    The Federal Power Act requires that the fee be “just and
    reasonable,” 16 U.S.C. § 824d(a), and therefore at least
    4                       Nos.11-3421, 11-3430, 11-3584, et al.
    roughly proportionate to the anticipated benefits to a
    utility of being able to use the grid. Illinois Commerce
    Commission v. FERC, 
    576 F.3d 470
    , 476 (7th Cir. 2009);
    Pacific Gas & Electric Co. v. FERC, 
    373 F.3d 1315
    , 1320-21
    (D.C. Cir. 2004). Thus “all approved rates [must] reflect
    to some degree the costs actually caused by the customer
    who must pay them.” K N Energy, Inc. v. FERC, 
    968 F.2d 1295
    , 1300 (D.C. Cir. 1992). Courts “evaluate compliance
    [with this principle, which is called ‘cost causation’] by
    comparing the costs assessed against a party to the bur-
    dens imposed or benefits drawn by that party.” Midwest
    ISO Transmission Owners v. FERC, 
    supra,
     373 F.3d at 1368.
    MISO began operating in 2002 and soon grew to have
    130 members. (Unfortunately, the voluminous briefs
    say little about the association’s governance structure.) In
    2010 it sought FERC’s approval to impose a tariff on its
    members to fund the construction of new high-voltage
    power lines that it calls “multi-value projects” (MVPs),
    beginning with 16 pilot projects. The tariff is mainly
    intended to finance the construction of transmission
    lines for electricity generated by remote wind farms.
    Every state in MISO’s region except Kentucky (which is
    barely in the region, see Figure 1) encourages or even
    requires utilities to obtain a specified percentage of their
    electricity supply from renewable sources, mainly wind
    farms. Indiana, North Dakota, and South Dakota
    have aspirational goals; the rest have mandates. The
    details vary but most of the states expect or require
    utilities to obtain between 10 and 25 percent of their
    electricity needs from renewable sources by 2025—and
    by then there may be federal renewable energy require-
    ments as well.
    Nos. 11-3421, 11-3430, 11-3584, et al.                  5
    “The dirty secret of clean energy is that while
    generating it is getting easier, moving it to market is
    not . . . . Achieving [a 20% renewable energy quota]
    would require moving large amounts of power over long
    distances, from the windy, lightly populated plains in
    the middle of the country to the coasts where many
    people live. . . The grid’s limitations are putting a
    damper on such projects already.” Matthew L. Wald,
    “Wind Energy Bumps into Power Grid’s Limits,” New
    York Times, Aug. 27, 2008, p. A1. MISO aims to overcome
    these limitations.
    To begin with, it has identified what it believes to be
    the best sites in its region for wind farms that will meet
    the region’s demand for wind power. They are the
    shaded ovals in Figure 2. Most are in the Great Plains,
    because electricity produced by wind farms there is
    cheaper despite the longer transmission distance; the
    wind flow is stronger and steadier and land is cheaper
    because population density is low (wind farms require
    significant amounts of land).
    6                      Nos.11-3421, 11-3430, 11-3584, et al.
    F IGURE 2
    W IND D EVELOPMENT Z ONES AND MVP P ROJECTS
    (dashed lines are initial proposals,
    solid lines approved projects)
    MISO has estimated that the cost of the transmission
    lines necessary both to bring electricity to its urban
    centers from the Great Plains and to integrate the
    existing wind farms elsewhere in its region with trans-
    mission lines from the Great Plains—transmission lines
    that the multi-value projects will create—will be
    more than offset by the lower cost of electricity produced
    by western wind farms. The new transmission lines
    will also increase the reliability of the electricity
    supply in the MISO region and thus reduce brownouts
    Nos. 11-3421, 11-3430, 11-3584, et al.                   7
    and outages, and also increase the efficiency with which
    electricity is distributed throughout the region.
    The cost of the multi-value projects is to be allocated
    among utilities drawing power from MISO’s grid in
    proportion to each utility’s share of the region’s total
    wholesale consumption of electricity. Before 2010, MISO
    allocated the cost of expanding or upgrading the transmis-
    sion grid to the utilities nearest a proposed transmission
    line, on the theory that they would benefit the most
    from the new line. But wind farms in the Great Plains
    can generate far more power than that sparsely popu-
    lated region needs. So MISO decided to allocate MVP costs
    among all utilities drawing power from the grid
    according to the amount of electrical energy used, thus
    placing most of those costs on urban centers, where
    demand for energy is greatest.
    FERC approved (with a few exceptions, one discussed
    later in this opinion) MISO’s rate design and pilot
    projects in two orders (for simplicity we’ll pretend
    they’re just one), precipitating the petitions for review
    that we have consolidated.
    Six issues are presented: the proportionality of benefits
    to costs; the procedural adequacy of the Commission’s
    treatment of proportionality; the propriety of appor-
    tioning the cost of the multi-value projects among
    utilities on the basis of their total power consumption
    while allocating no MVP costs to the plants that generate
    the power; whether MISO should be permitted to add
    the MVP fee to electricity transmitted to utilities that
    belong to the PJM Regional Transmission Organization
    8                       Nos.11-3421, 11-3430, 11-3584, et al.
    rather than to MISO; whether MISO should be permitted
    to assess some of the multi-value projects’ costs on depart-
    ing members of MISO; and whether the Commission’s
    approval of the MVP tariff—which if implemented will
    influence decisions by state utility commissions re-
    garding the siting of transmission lines—violates the
    Tenth Amendment to the Constitution by invading state
    prerogatives.
    The Tenth Amendment. The last issue is frivolous, so
    we dispatch it first. FERC approved the MVP tariff pursu-
    ant to its statutory authority to regulate interstate
    electrical rates, 
    16 U.S.C. § 824
    (a), but (unlike the reg-
    ulation of natural gas, a field in which FERC has juris-
    diction both over pricing and over the siting of interstate
    lines, see 15 U.S.C. § 717f(c)) the states retain authority
    over the location and construction of electrical trans-
    mission lines. 
    16 U.S.C. § 824
    (b)(1); New York v. FERC,
    
    535 U.S. 1
    , 24 (2002). Some of the petitioners complain
    that FERC’s approval of the MVP tariff coerces each
    state to approve all MVPs proposed within its territory.
    They argue that since the costs of each project are dis-
    tributed among all MISO utilities while any local
    benefits will be retained in the state in which the project
    is located, a state will deprive itself of the local benefits
    of a project subsidized by other utilities if it refuses to
    approve an MVP project.
    But this is just to say that the tariff provides a carrot
    that states won’t be able to resist eating; to obtain the
    benefits of the MVP program each state’s MISO mem-
    bers may have to shoulder costs of some specific projects
    Nos. 11-3421, 11-3430, 11-3584, et al.                       9
    that they’d prefer not to support. But that’s a far cry
    from the federal government’s conscripting a state gov-
    ernment into federal service. That it may not do. National
    Federation of Independent Businesses v. Sebelius, 
    132 S. Ct. 2566
    , 2601-09 (2012); New York v. United States, 
    505 U.S. 144
    , 149 (1992); Printz v. United States, 
    521 U.S. 898
    , 935
    (1997). This it may do. Cf. National Ass’n of Regulatory
    Utility Commissioners v. FERC, 
    475 F.3d 1277
    , 1282-83
    (D.C. Cir. 2007). It’s not as if FERC were ordering states
    to build transmission lines that the federal government
    wants to use for its own purposes. And to glance ahead
    a bit, there is nothing to prevent a member of MISO
    from withdrawing from the association and joining
    another Regional Transmission Organization.
    Five issues remain; we discuss them in the order in
    which we listed them, beginning with—
    Proportionality and Procedure (best discussed together).
    MISO used to allocate the cost of an upgrade to its grid
    to the local area (“pricing zone”) in which the upgrade
    was located. (There are 24 pricing zones in MISO.) But
    those were upgrades to low-voltage lines, which
    transmit power short distances and thus benefit only
    the local area served by the lines. MISO contends (and
    FERC agrees) that the multi-value projects, which
    involve high-voltage lines that transmit electricity over
    long distances, will benefit all members of MISO and so
    the projects’ costs should be shared among all members.
    The petitioners’ objections fall into two groups.
    One consists of objections lodged by the Michigan
    utilities and their regulator (we’ll call this set of objectors
    10                      Nos.11-3421, 11-3430, 11-3584, et al.
    “Michigan”), the other of objections by other petitioners
    led by the Illinois Commerce Commission. We’ll call
    these objectors “Illinois,” though they include other
    state utilities and regulators; and we’ll begin with
    their objections.
    Illinois contends that the criteria for determining
    what projects are eligible to be treated as MVPs are
    too loose, and that as a result all MISO members will
    be forced to contribute to the cost of projects that
    benefit only a few. To qualify as an MVP a project must
    have an expected cost of at least $20 million, must
    consist of high-voltage transmission lines (at least 100kV),
    and must help MISO members meet state renewable
    energy requirements, fix reliability problems, or provide
    economic benefits in multiple pricing zones. None of
    these eligibility criteria ensures that every utility in
    MISO’s vast region will benefit from every MVP project,
    let alone in exact proportion to its share of the MVP
    tariff. For example, Illinois power cooperatives are
    exempt from the state’s renewable energy requirements,
    83 Ill. Adm. Code 455.100; 20 ILCS 3855/1-75(c), and
    so would not benefit from MVPs that help utilities
    meet state renewable energy requirements. But FERC
    expects them to benefit by virtue of the criteria for MVP
    projects relating to reliability and to the provision of
    benefits across pricing zones.
    Bear in mind that every multi-value project is to be
    large, is to consist of high-voltage transmission (enabling
    power to be transmitted efficiently across pricing zones),
    and is to help utilities satisfy renewable energy require-
    Nos. 11-3421, 11-3430, 11-3584, et al.                     11
    ments, improve reliability (which benefits the entire
    regional grid by reducing the likelihood of brownouts or
    outages, which could occur anywhere on it, Illinois Com-
    merce Commission v. FERC, supra, 
    576 F.3d at 477
    ), facilitate
    power flow to currently underserved areas in the MISO
    region, or attain several of these goals at once. The 16
    projects that have been authorized are just the beginning.
    And FERC has required MISO to provide annual updates
    on the status of those projects. Should the reports show
    that the benefits anticipated by MISO and FERC are
    not being realized, the Commission can modify or
    rescind its approval of the MVP tariff.
    Illinois also complains that MISO has failed to show
    that the multi-value projects as a whole will confer
    benefits greater than their costs, and it complains too
    about FERC’s failure to determine the costs and benefits
    of the projects subregion by subregion and utility by
    utility. But Illinois’s briefs offer no estimates of costs
    and benefits either, whether for the MISO region as a
    whole or for particular subregions or particular utilities.
    And in complaining that MISO and the Commission
    failed to calculate the full financial incidence of the MVP
    tariff, Illinois ignores the limitations on calculability that
    the uncertainty of the future imposes. MISO did estimate
    that there would be cost savings of some $297 million to
    $423 million annually because western wind power
    is cheaper than power from existing sources, and that
    these savings would be “spread almost evenly across all
    Midwest ISO Planning Regions.” Midwest Independent
    Transmission System Operator, Inc., 133 F.E.R.C. 61221, ¶ 34
    (2010). It also estimated that the projected high-
    12                      Nos.11-3421, 11-3430, 11-3584, et al.
    voltage lines would reduce losses of electricity in trans-
    mission by $68 to $104 million, and save another $217
    to $271 million by reducing “reserve margin losses.” 
    Id.
    That term refers to electricity generated in excess of
    demand and therefore (because it can’t be stored)
    wasted. Fewer plants will have to be kept running in
    reserve to meet unexpected spikes in demand if by
    virtue of longer transmission lines electricity can be sent
    from elsewhere to meet those unexpected spikes. It’s
    impossible to allocate these cost savings with any
    precision across MISO members.
    The promotion of wind power by the MVP program
    deserves emphasis. Already wind power accounts for 3.5
    percent of the nation’s electricity, U.S. Energy Information
    Administration, “What is US Electricity Generation by
    Source?” May 9, 2013, www.eia.gov/tools/faqs/faq.cfm?id=
    427&t=3 (visited May 29, 2013), and it is expected to
    continue growing despite the downsides of wind power
    that we summarized in Muscarello v. Winnebago County
    Board, 
    702 F.3d 909
    , 910-11 (7th Cir. 2012). The use of
    wind power in lieu of power generated by burning
    fossil fuels reduces both the nation’s dependence on
    foreign oil and emissions of carbon dioxide. And its cost
    is falling as technology improves. No one can know
    how fast wind power will grow. But the best guess is
    that it will grow fast and confer substantial benefits on
    the region served by MISO by replacing more expensive
    local wind power, and power plants that burn oil or coal,
    with western wind power. There is no reason to think
    these benefits will be denied to particular subregions of
    MISO. Other benefits of MVPs, such as increasing the
    Nos. 11-3421, 11-3430, 11-3584, et al.                         13
    reliability of the grid, also can’t be calculated in advance,
    especially on a subregional basis, yet are real and will
    benefit utilities and consumers in all of MISO’s subregions.
    It’s not enough for Illinois to point out that MISO’s
    and FERC’s attempt to match the costs and the benefits
    of the MVP program is crude; if crude is all that is
    possible, it will have to suffice. As we explained in
    Illinois Commerce Commission v. FERC, supra, 
    576 F.3d at 477
    , if FERC “cannot quantify the benefits [to particular
    utilities or a particular utility] . . . but it has an articulable
    and plausible reason to believe that the benefits are at
    least roughly commensurate with those utilities’ share
    of total electricity sales in [the] region, then fine; the
    Commission can approve [the pricing scheme proposed
    by the Regional Transmission Organization for that
    region] . . . on that basis. For that matter it can presume
    [as it did in this case] that new transmission lines
    benefit the entire network by reducing the likelihood
    or severity of outages.”
    Illinois can’t counter FERC without presenting evi-
    dence of imbalance of costs and benefits, which it hasn’t
    done. When we pointed this out at oral argument,
    Illinois’s lawyer responded that he could not obtain
    the necessary evidence without pretrial discovery and
    that FERC had refused to grant his request for an eviden-
    tiary hearing even though the Commission’s rules
    make the grant of such a hearing a precondition to dis-
    covery. 
    18 C.F.R. § 385.504
    (b)(5). FERC refused because
    it already had voluminous evidentiary materials,
    including MISO’s elaborate quantifications of costs
    14                      Nos.11-3421, 11-3430, 11-3584, et al.
    and benefits—and these were materials to which the
    petitioners had access as well; they are, after all, members
    of MISO. The only information MISO held back was
    the production costs of particular power plants, which
    it deemed trade secrets and anyway are only tenuously
    related to the issue of proportionality. The need for dis-
    covery has not been shown; and for us to order it
    without a compelling reason two and a half years
    after the Commission rendered its exhaustive decision
    (almost 400 pages long) would create unconscionable
    regulatory delay.
    Michigan (which is to say Michigan utilities plus the
    state’s electric power regulatory agency) argues that
    unique features of the state’s power system will cause
    Michigan utilities to pay a share of the MVP tariff greatly
    disproportionate to the benefits they will derive from
    the multi-value projects. A Michigan statute, Mich.
    Comp. L. 460.1029(1), forbids Michigan utilities to count
    renewable energy generated outside the state toward
    satisfying the requirement in the state’s “Clean, Renew-
    able, and Efficient Energy Act” of 2008 that they obtain
    at least 10 percent of their electrical power needs from
    renewable sources by 2015. Michigan further argues
    that it won’t benefit from any multi-value projects con-
    structed in other states because its utilities draw very
    little power from the rest of the MISO grid, as a conse-
    quence of the limited capacity to transmit electricity
    from Indiana to Michigan. It argues that for these
    reasons it should be required to contribute only to the
    costs of multi-value projects built in Michigan.
    Nos. 11-3421, 11-3430, 11-3584, et al.                     15
    The second argument founders on the fact that the
    construction of high-voltage lines from Indiana to Michi-
    gan is one of the multi-value projects and will enable
    more electricity to be transmitted to Michigan at lower
    cost. Michigan’s first argument—that its law forbids it to
    credit wind power from out of state against the state’s
    required use of renewable energy by its utilities—trips
    over an insurmountable constitutional objection. Michigan
    cannot, without violating the commerce clause of Article I
    of the Constitution, discriminate against out-of-state
    renewable energy. See Oregon Waste Systems, Inc. v. Depart-
    ment of Environmental Quality, 
    511 U.S. 93
    , 100-01 (1994);
    Wyoming v. Oklahoma, 
    502 U.S. 437
    , 454-55 (1992); Alliance
    for Clean Coal v. Miller, 
    44 F.3d 591
    , 595-96 (7th Cir. 1995);
    Steven Ferrey, “Threading the Constitutional Needle
    with Care: The Commerce Clause Threat to the New
    Infrastructure of Renewable Power,” 7 Texas J. Oil, Gas
    & Energy Law 59, 69, 106-07 (2012).
    Like Illinois, Michigan objects to the Commission’s
    refusal to conduct an evidentiary hearing. It wants
    an opportunity to present evidence in a trial-type pro-
    ceeding involving cross-examination of expert wit-
    nesses. (All direct testimony at FERC’s evidentiary hear-
    ings is presented in writing; only cross-examination
    is oral.) It also wants pretrial discovery, like Illinois.
    But unlike Illinois it didn’t raise the issue until its reply
    brief, which is too late.
    FERC need not conduct an oral hearing if it can ade-
    quately resolve factual disputes on the basis of written
    submissions. Blumenthal v. FERC, 
    613 F.3d 1142
    , 1144-45
    16                       Nos.11-3421, 11-3430, 11-3584, et al.
    (D.C. Cir. 2010); California ex rel. Lockyer v. FERC, 
    329 F.3d 700
    , 713 (9th Cir. 2003); Pacific Gas & Electric Co. v.
    FERC, 
    306 F.3d 1112
    , 1119 (D.C. Cir. 2002); Cajun Electric
    Power Co-op., Inc. v. FERC, 
    28 F.3d 173
    , 176-77 (D.C. Cir
    1994) (per curiam); Moreau v. FERC, 
    982 F.2d 556
    , 568
    (D.C. Cir. 1993). Considering the highly technical
    character of the data and analysis required to match
    costs and benefits of transmission projects, the technical
    knowledge and experience of FERC’s members and staff,
    and the petitioners’ access to MISO’s studies, we would
    be creating gratuitous delay to insist at this late date
    on the Commission’s resorting to litigation procedures
    designed long ago for run-of-the-mine legal disputes.
    Michigan has failed to indicate what evidence that it
    might present in an evidentiary hearing would contribute
    to the data and analysis in the record already before
    the Commission.
    A further answer to both the substantive and procedural
    questions about proportionality is that MISO members
    who think they’re being mistreated by the MVP tariff
    can vote with their feet. Membership in an RTO is volun-
    tary and though there’s a “departure fee” (discussed
    later in this opinion), it is an unexceptionable feature of
    membership in a voluntary association, designed to
    prevent a departing member from reaping a windfall
    by leaving costs for which it is properly liable to be
    borne by the remaining members. A departure fee,
    which if properly calculated just deters windfalls, will
    not prevent a discontented MISO member from
    decamping to an adjacent RTO. As shown in the right-
    hand panel of Figure 3, Michigan abuts the border
    Nos. 11-3421, 11-3430, 11-3584, et al.                 17
    between MISO (light gray) and PJM (dark gray) and has
    claimed that 96.5 percent of its external grid connections
    are with PJM. It should therefore be able without great
    difficulty to quit MISO and join PJM. It doesn’t want to
    do that; so far as appears, it is objecting to the MVP
    program only in the hope of getting better terms.
    F IGURE 3:
    MISO-PJM B ORDER R EGION
    (MISO to left, PJM to right)
    2004                       2013
    18                       Nos.11-3421, 11-3430, 11-3584, et al.
    Allocation of cost on the basis of peak load versus total
    electricity consumption. Because a power grid must be
    built to handle peak loads (the amount of electricity
    transmitted when demand is greatest, as on hot summer
    days), some of the petitioners argue that the MVP sur-
    charge should be allocated according to each utility’s
    contribution to peak demand. The peak demanders
    would be paying for facilities built to accommodate that
    demand and thus minimize brownouts and outages.
    Instead MISO allocates the surcharge by the total amount
    of electricity that each utility receives over the MISO
    grid. A higher share of MVP costs is thus allocated
    to utilities receiving electricity to meet continuous de-
    mands, such as the demand by a factory for electricity
    much of which it uses in off-peak periods.
    The objection to MISO’s allocating costs by total rather
    than peak demand is refuted by the fact that a primary
    goal of the MVPs is to increase the supply of wind-pow-
    ered energy. The electricity generated by wind farms
    varies with the amount of wind rather than with demand
    and therefore is not a reliable source of energy to meet
    peak demand. That is why the states’ renewable energy
    standards are couched in terms of total energy rather
    than peak load. See, e.g., 20 ILCS 3855/1-75(c)(2); 
    Wis. Stat. § 196.378
    (1)(fm); Minn. Stat. § 216B.1691 subd. 2a(a).
    Furthermore, long-distance power transmission will
    enable fewer power plants to serve the grid’s off-peak
    demand. True, the projects are also intended to increase
    the grid’s reliability, which is challenged mainly by
    peak load (which is why outages are more frequent on
    hot summer days, when everyone is running his air
    Nos. 11-3421, 11-3430, 11-3584, et al.                   19
    conditioner at the same time). But MISO and FERC were
    entitled to conclude that the benefits of more and cheaper
    wind power predominate over the benefits of greater
    reliability brought about by improvement in meeting
    peak demand.
    Allocation of cost between power plants and the wholesale
    buyers of the power. Petitioners complain about MISO’s
    decision to allocate all MVP costs to the utilities that buy
    electricity from its grid and none to the power plants that
    generate that electricity. Because the power plants are
    required to pay for connecting to the grid and the multi-
    value projects will shorten the interconnection distance
    and thus reduce the cost to the power plants of
    connecting, the petitioners argue that the power plants
    should pay part of the MVP tariff. But the utilities benefit
    from cheaper power generated by efficiently sited wind
    farms whose development the multi-value projects will
    stimulate. The MVP tariff allocates to the wholesale
    buyers some of the costs of conferring these benefits on
    those buyers, though competition might do the same
    thing without the tariff because the power plants would
    pass some of their higher costs on to their customers,
    the wholesale buyers.
    An important consideration is that when wind farms
    are built in remote areas (which are the best places to
    site them), the costs of connecting them to the grid are
    very high, and by reducing those costs the multi-value
    projects, financed by the MVP tariff, facilitate siting
    wind farms at the best locations in MISO’s region rather
    than at inefficient ones that are however closer to the
    20                      Nos.11-3421, 11-3430, 11-3584, et al.
    existing grid and so would be preferred by the wind-farm
    developers if they had to pay for the connection. See
    California Independent System Operator Corp., 119 F.E.R.C.
    61061, ¶¶ 64-67 (2007); Southwest Power Pool, Inc., 127
    F.E.R.C. 61283, ¶¶ 5, 11, 28 (2009).
    Export charges to PJM. An issue that unlike the
    previous ones finds MISO and FERC at loggerheads
    is whether the Commission is unreasonable in pro-
    hibiting MISO from adding the MVP surcharge to electric-
    ity transmitted from its grid to the grid of PJM, an adjoin-
    ing Regional Transmission Organization. The Commis-
    sion permits MISO to charge for transmission to
    other RTOs.
    The prohibition arises from a concern with what in
    FERC-speak is called “rate pancaking” but is more trans-
    parently described as exploiting a locational monopoly
    by charging a toll. It is illustrated by Henrich von
    Kleist’s classic German novella Michael Kohlhaas. When the
    book was published in 1810, what is now Germany was
    divided into hundreds of independent states. A road from
    Munich to Berlin, say, would cross many boundaries, and
    each state that the road entered could charge a toll as a
    condition for allowing entry. The toll would be limited
    not by the cost imposed on the state by the traveler, in
    wear and tear on the road or traffic congestion, but by
    the cost to the traveler of using a less direct alternative
    route. See also Diginet, Inc. v. Western Union ATS, Inc., 
    958 F.2d 1388
    , 1400 (7th Cir. 1995); cf. Goulding v. Cook, 
    661 N.E.2d 1322
    , 1325 (Mass. 1996). Like early nineteenth-
    century Germany, the American electric grid used to be
    Nos. 11-3421, 11-3430, 11-3584, et al.                        21
    divided among hundreds of independent utilities, each
    charging a separate toll for the right to send electricity
    over its portion of the grid. The multiple charges
    imposed on long-distance transmission discouraged
    such transmission. FERC promoted the creation of the
    Regional Transmission Organizations as a way of eli-
    minating these locational monopolies. Wabash Valley
    Power Ass’n v. FERC, 
    268 F.3d 1105
    , 1116 (D.C. Cir.
    2001). For it required that the RTOs embrace coherent
    geographic regions and that each RTO charge a single fee
    for use of its entire grid. 
    18 C.F.R. §§ 35.34
    (j)(2), (k)(1)(ii).
    In the early 2000s Commonwealth Edison and American
    Electric Power had requested FERC’s permission to join
    PJM despite being inside MISO’s region (around Chicago
    and in southwestern Michigan, respectively). The Com-
    mission approved their requests yet was concerned that
    the irregular border (seen in the left-hand panel of
    Figure 3) between the two regions, by creating PJM en-
    claves in MISO’s region, violated the requirement that
    RTOs embrace coherent regions. The Commission was
    concerned for example with Michigan utilities’ having
    to pay PJM charges on power sent from elsewhere in
    MISO (such as Wisconsin), because those transmissions,
    though beginning and ending in MISO territory,
    traversed a PJM enclave—the area served by Common-
    wealth Edison.
    The Commission had another concern with the
    irregular border, what we’ll call the “power routing”
    concern. Notice in the left-hand panel of Figure 3 the
    MISO utilities that lie (or rather lay, as of 2004) on a south
    22                      Nos.11-3421, 11-3430, 11-3584, et al.
    to north diagonal in Kentucky and Ohio. Imagine a whole-
    sale buyer of electricity located on the diagonal. It would
    be more efficient for it to draw electricity from the
    PJM transmission lines to its immediate west or east
    than from the MISO lines that snake to the northeast and
    thus bring electricity from a great distance. But the
    buyer might be deflected from the most efficient
    routing option because buying from PJM would cross
    both MISO and PJM territory and thus require paying
    a double toll.
    So in 2003 FERC forbade export charges between MISO
    and PJM and ordered the two RTOs to negotiate a joint
    rate that would divide the costs of the cross-border trans-
    missions between them, much as with “divisions” of
    railroad rates for shipments in which more than one
    railroad participates. The Commission didn’t require a
    similar negotiation between MISO and the other RTOs
    that MISO abuts because no enclave or power-routing
    problem was created by transmission to those RTOs;
    there were no enclaves or highly irregular borders.
    The two RTOs negotiated a joint rate designed to
    share the costs of some transmission upgrades with cross-
    border benefits—but have not negotiated a joint rate for
    multi-value projects. MISO argues that the Commission
    should have reconsidered its 2003 prohibition of export
    charges to PJM and permitted such charges for multi-value
    projects that benefit electricity customers in PJM, in light
    of the changes (seen in the right-hand panel of Figure 3)
    in the MISO-PJM border between 2003-2004 and 2013.
    Those changes have straightened out the border and by
    Nos. 11-3421, 11-3430, 11-3584, et al.                  23
    doing so should have lessened the Commission’s concern
    that “the elongated and highly irregular seam between
    MISO and PJM. . ..would subject a large number of trans-
    actions in the region to continued rate pancaking.”
    Midwest Independent Transmission System Operating, Inc.,
    137 F.E.R.C 61074, ¶ 264 (2011). No longer are any parts
    of Ohio in MISO, though there still are PJM enclaves. For
    example, a transmission from a PJM enclave in northern
    Illinois or southwestern Michigan to Ohio or Pennsylvania
    runs through MISO lines in Indiana. But with the disap-
    pearance of the MISO diagonal that we mentioned, the
    power-routing problem, at least, appears to have been
    solved, though FERC wants more data from MISO to
    demonstrate this.
    A further concern about the continued validity of the
    2003 order prohibiting tolls on transmissions between
    MISO and PJM is that the order was issued at a time
    when all of MISO’s transmission projects were local and
    therefore provided only local benefits, so that an export
    charge would have shifted costs to PJM utilities that
    derived few or even no benefits from the projects. A
    related consideration behind the 2003 order was that
    export charges would not finance projects, but would
    merely operate as a toll exploiting a locational advantage.
    Cf. Illinois Commerce Commission v. FERC, supra, 
    576 F.3d at 473-74
    . The multi-value projects are new projects, not
    yet paid for, and since they will benefit electricity users
    in PJM, those users should contribute to the costs.
    The MVPs also are not local. They will “support all uses
    of the system, including transmission on the system that
    is ultimately used to deliver to an external load,” and
    24                      Nos.11-3421, 11-3430, 11-3584, et al.
    “benefit all users of the integrated transmission system,
    regardless of whether the ultimate point of delivery is to
    an internal or external load.” Midwest Independent Trans-
    mission System Operating, Inc., 133 F.E.R.C. 61221, ¶ 439
    (2010). (By “external” read PJM or any other recipient
    of electricity that is outside MISO.) That is an argu-
    ment for shifting some of the costs of the system to PJM
    utilities. The requirement of proportionality between
    costs and benefits requires that all beneficiaries—which
    the Commission has determined include all users of the
    MISO grid, including users in PJM—shoulder a rea-
    sonable portion of MVP costs.
    MISO and PJM may eventually negotiate an allocation
    agreement, as they did in the pre-MVP era, but the rest of
    the grid is left to pay for PJM’s share unless and until they
    do so. So far as we can tell, the Commission is being
    arbitrary in continuing to prohibit MISO from charging
    anything for exports of energy to PJM enabled by the
    multi-value projects while permitting it to charge for
    exports of energy to all the other RTOs. The Commission
    must determine in light of current conditions what if
    any limitation on export pricing to PJM by MISO is justi-
    fied. This part of the Commission’s decision must
    therefore be vacated.
    The departers. Two former members of MISO, FirstEnergy
    and Duke Energy, which lie on the diagonal that had
    created the power-routing problem, announced their
    intention to quit MISO before the MVP tariff was an-
    nounced. MISO wants nevertheless to allocate some
    MVP costs to them. FERC has ruled that allocation to
    Nos. 11-3421, 11-3430, 11-3584, et al.                     25
    departing utilities is proper in principle, but has not yet
    determined which if any costs may be allocated to the
    two utilities in particular. That determination FERC has
    ruled to be outside the scope of the present proceeding,
    the proceeding before us. Midwest Independent Transmis-
    sion System Operating, Inc., 133 F.E.R.C. 61221, ¶ 472 (2010).
    FirstEnergy and Duke respond that they can’t be made
    liable for any such costs because their membership
    contract with MISO does not provide for the imposition
    of such costs.
    When a firm withdraws from an association owing
    money to it, its withdrawal does not terminate its
    liability; an example is an employer who withdraws from
    a multiemployer ERISA plan. See, e.g., Concrete Pipe &
    Products v. Construction Laborers Pension Trust for
    Southern California, 
    508 U.S. 602
    , 608-09 (1993); Chicago
    Truck Drivers, Helpers & Warehouse Workers Union (Inde-
    pendent) Pension Fund v. CPC Logistics, Inc., 
    698 F.3d 346
    ,
    347-48 (7th Cir. 2012). The same may be true of
    withdrawal from a Regional Transmission Organization.
    If MISO began to incur costs relating to the MVPs (in-
    cluding the pilot projects) before the departing members
    announced their departure, those utilities may be liable
    for some of those costs. MISO contends that they are
    liable, but the Commission has reserved the question for
    a separate proceeding, see First Energy Service Co. v.
    Midwest Independent Transmission System Operating, Inc.,
    138 F.E.R.C. 61140, ¶ 74 (2012), as it is authorized to do.
    Mobil Oil Exploration & Producing Southeast Inc. v. United
    Distribution Cos., 
    498 U.S. 211
    , 230 (1991). That proceeding
    is pending.
    26                       Nos.11-3421, 11-3430, 11-3584, et al.
    The departing members’ attack on an order that
    amounts to a truism—that amounts to saying that if
    they’re liable they’re liable—is premature, and must
    therefore be dismissed for want of a final administrative
    decision on the matter. California Department of Water
    Resources v. FERC, 
    341 F.3d 906
    , 909 (9th Cir. 2003); Fourth
    Branch Associates v. FERC, 
    253 F.3d 741
    , 746 (D.C. Cir. 2001).
    In summary, the challenged orders are affirmed, except
    that the challenge by the departing MISO members
    is dismissed as premature and the determination re-
    garding export pricing to PJM is remanded for further
    analysis by the Commission in light of the discussion of
    the issue in this opinion.
    6-7-13
    

Document Info

Docket Number: 11-3421

Citation Numbers: 721 F.3d 764

Judges: Posner

Filed Date: 6/7/2013

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (21)

Alliance for Clean Coal, a Virginia Not-For-Profit ... , 44 F.3d 591 ( 1995 )

state-of-california-ex-rel-bill-lockyer-attorney-general-the-city-of , 329 F.3d 700 ( 2003 )

National Association of Regulatory Utility Commissioners v. ... , 475 F.3d 1277 ( 2007 )

Wabash Valley Power Ass'n v. Federal Energy Regulatory ... , 268 F.3d 1105 ( 2001 )

Pacific Gas & Electric Co. v. Federal Energy Regulatory ... , 306 F.3d 1112 ( 2002 )

california-department-of-water-resources-southern-california-edison , 341 F.3d 906 ( 2003 )

judith-b-moreau-n-robert-moreau-clara-lawrence-and-walter-lawrence-v , 982 F.2d 556 ( 1993 )

Midwest Iso Transmission Owners v. Federal Energy ... , 373 F.3d 1361 ( 2004 )

K N Energy, Inc. v. Federal Energy Regulatory Commission, ... , 968 F.2d 1295 ( 1992 )

Pacific Gas and Electric Company v. Federal Energy ... , 373 F.3d 1315 ( 2004 )

Blumenthal v. Federal Energy Regulatory Commission , 613 F.3d 1142 ( 2010 )

cajun-electric-power-cooperative-inc-v-federal-energy-regulatory , 28 F.3d 173 ( 1994 )

Mobil Oil Exploration & Producing Southeast, Inc. v. United ... , 111 S. Ct. 615 ( 1991 )

Wyoming v. Oklahoma , 112 S. Ct. 789 ( 1992 )

New York v. United States , 112 S. Ct. 2408 ( 1992 )

Concrete Pipe & Products of Cal., Inc. v. Construction ... , 113 S. Ct. 2264 ( 1993 )

Oregon Waste Systems, Inc. v. Department of Environmental ... , 114 S. Ct. 1345 ( 1994 )

Printz v. United States , 117 S. Ct. 2365 ( 1997 )

New York v. Federal Energy Regulatory Commission , 122 S. Ct. 1012 ( 2002 )

Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. ... , 128 S. Ct. 2733 ( 2008 )

View All Authorities »