Va Venutre Pueblo, LLC v. Principi , 119 F. App'x 274 ( 2004 )


Menu:
  •              NOTE: Pursuant to Fed. Cir. R. 47.6, this disposition is not
    citable as precedent. It is a public record.
    United States Court of Appeals for the Federal Circuit
    04-1243
    VA VENTURE PUEBLO, LLC,
    Appellant,
    v.
    Anthony J. Principi, SECRETARY OF VETERANS AFFAIRS
    Appellee.
    _______________________
    DECIDED: December 16, 2004
    _______________________
    Before RADER, Circuit Judge, ARCHER, Senior Circuit Judge, and BRYSON, Circuit
    Judge.
    PER CURIAM.
    In this government contracts case, VA Venture Pueblo, LLC (“VA Venture”)
    appeals from the decision of the Department of Veterans Affairs Board of Contract
    Appeals (“Board”), VABCA Nos. 6959 & 7006. We affirm.
    I
    On April 29, 2001, the VA awarded Lease No. V101-183R-567-004-01 to VA
    Venture for a building to be used as a VA Nursing Home Care Unit. A thirty-one day
    extension was agreed to in response to certain additional construction requests made
    by the Department of Veterans Affairs (“VA”).        These additional requests were
    formalized on June 4, 2002, in a series of supplemental agreements (“SA”) between the
    parties made pursuant to the changes clause of the lease.      The price of each SA
    included the maximum ten percent markup for overhead and for profit as provided by
    the changes clause of the lease. Section 3.12(2)(d) of the lease, “Contract Changes,”
    provides that “[a]llowances not to exceed 10 percent each for overhead and profit for
    the party performing the work will be based on the value of labor, material, and the use
    of construction equipment required to accomplish the change.” Subsection (j) of the
    clause provides:
    Overhead and contractor’s fee percentages shall be considered to include
    insurance other than mentioned herein[,] field and office supervisors and
    assistants, security police, use of small tools, incidental job burdens, and
    general home office expenses and no separate allowance will be made
    therefor. Assistants to office supervisors include all clerical, stenographic
    and general office help. Incidental job burdens include, but are not
    necessarily limited to office equipment and supplies, temporary toilets,
    telephone and conformance to OSHA requirements.
    VA Venture presented a list that it referred to as “General Conditions Costs for
    VA Extras” as evidence of various costs incurred during the delay period for which it
    sought compensation from the VA. It included items such as clean-up labor, project
    manager, administrative, field office, dumpsters, temporary toilets, job truck/fuel,
    supervision, temporary water, temporary heat, travel, temporary electric, temporary gas,
    and temporary storage. VA Venture attached to this list a collection of invoices in
    support of the costs claimed. The VA stipulated to VA Venture’s entitlement to thirty-
    one days of delay and to the reasonable, allocable, and allowable direct costs.
    The Board determined that VA Venture “received full compensation for the
    monies owed it pursuant to the Changes Clause” and that the thirty-one day extension
    did not entitle it to further compensation for overhead costs incurred during that period.
    The Board also found that VA Venture’s claim for $10,844.25 in labor costs for “clean-
    up” was unreasonable in light of the lack of any probative evidence as to why so many
    04-1243                                     2
    laborers were necessary. Additionally, the Board found that all other costs sought by
    VA Venture were for overhead expenses and, therefore, were already fully
    compensated by the ten percent markup for overhead paid by the VA pursuant to the
    SAs.   Finally, the Board concluded that VA Venture was not entitled to recover
    construction loan interest it incurred during the thirty-one day period because interest
    upon borrowings is not allowable.
    VA Venture now appeals. We have jurisdiction pursuant to 
    41 U.S.C. § 607
    (g).
    II
    We must affirm the decision of an agency board of contract appeals unless “the
    decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to
    necessarily imply bad faith, or if such decision is not supported by substantial evidence.”
    
    41 U.S.C. § 609
    (b).
    The thrust of VA Venture’s arguments is directed to the fact that the Board made
    findings that were inconsistent with those made by the Contracting Officer (“CO”) and
    rejected awards the VA did not oppose.           What VA Venture fails to acknowledge,
    however, is that “once an action is brought following a contracting officer’s decision, the
    parties start in court or before the board with a clean slate.” Wilner v. United States, 
    24 F.3d 1397
    , 1402 (Fed. Cir. 1994). “Where an appeal is taken to a board or a court, the
    contracting officer’s award is not to be treated as if it were the unappealed
    determination of a lower tribunal which is owed special deference or acceptance on
    appeal.” Assurance Co. v. United States, 
    813 F.3d 1202
    , 1206 (Fed. Cir. 1987). In
    other words, the “contractor has the burden of proving the fundamental facts of liability
    and damages de novo.” Wilmer, 
    24 F.3d at 1401
    .
    04-1243                                     3
    The Board found that VA Venture received the maximum markup of ten percent
    overhead and ten percent profit in each of the supplemental agreements. The Board
    also determined that several of the costs sought by VA Venture were for field office
    overhead charges. As such, the Board properly reasoned that VA Venture had already
    been compensated for these charges under the provisions of the SAs.
    With respect to those charges not considered allocable to overhead expense, the
    Board provided a reasoned explanation for its allowance or disallowance of the claims.
    For example, in regard to the “clean up labor” charge, the Board determined that the
    amount sought by VA Venture was unreasonable because it exceeded the amount that
    would be incurred by a prudent person in the conduct of competitive business. The
    Board then determined an appropriate allowance for clean up labor. Other charges
    disallowed by the Board were so treated because VA Venture had not provided
    sufficient explanation for the charges and the Board could derive no tie for the charges
    to the delay. We discern no error in the Board’s treatment of the charges claimed by VA
    Venture, and we are not persuaded by arguments of VA Venture to the contrary.
    Additionally,   we   conclude   that   substantial   evidence   supports   the   Board’s
    determinations.
    Finally, VA Venture challenges the Board’s refusal to award interest on
    borrowings it was required to pay as a result of the government’s delay. The Board
    found that there was no statute that was applicable to this question. Additionally, the
    Board noted “’Interest on borrowings (however represented)[,] . . . cost of financing and
    refinancing capital . . . are unallowable.’”    Slip op at 21 (quoting FAR 31.205-20);
    Servidone Construction Corp., 
    391 F.2d 860
    , 863 (Fed. Cir. 1991) (“The CDA [Contracts
    04-1243                                     4
    Dispute Act] contains an explicit statutory grant for the collection of interest on a
    recovery under a claim, . . . but has no separate provision for recovery of interest on
    borrowings.”). We discern no error in the Board’s treatment of VA Venture’s request for
    recovery of loan interest due to the government’s delay.
    04-1243                                    5
    

Document Info

Docket Number: 2004-1243

Citation Numbers: 119 F. App'x 274

Judges: Archer, Bryson, Per Curiam, Rader

Filed Date: 12/16/2004

Precedential Status: Non-Precedential

Modified Date: 8/3/2023