A&C Construction & Installatio v. Zurich American Insurance Com ( 2020 )


Menu:
  •                                In the
    United States Court of Appeals
    For the Seventh Circuit
    ____________________
    No. 19-3325
    A&C CONSTRUCTION & INSTALLATION, CO. WLL,
    Plaintiff-Appellant,
    v.
    ZURICH AMERICAN INSURANCE COMPANY and THE INSURANCE
    COMPANY OF THE STATE OF PENNSYLVANIA,
    Defendants-Appellees.
    ____________________
    Appeal from the United States District Court for the
    Northern District of Illinois, Eastern Division.
    No. 17-cv-04307 — Harry D. Leinenweber, Judge.
    ____________________
    ARGUED MAY 26, 2020 — DECIDED JUNE 30, 2020
    ____________________
    Before FLAUM, SCUDDER, and ST. EVE, Circuit Judges.
    ST. EVE, Circuit Judge. The Miller Act, 40 U.S.C. § 3131 et
    seq., seeks to protect subcontractors against nonpayment for
    work performed on federal government construction projects
    by requiring the prime contractor to provide a payment bond
    on which the subcontractor can then make a claim for pay-
    ment. A&C Construction & Installation, Co. WLL was a sub-
    contractor on an air base project in Qatar and claims that it
    2                                                    No. 19-3325
    was not paid approximately $8.5 million for work it per-
    formed on the project, so it filed this action against the prime
    contractor’s two sureties, Zurich American Insurance Com-
    pany and The Insurance Company of the State of Pennsylva-
    nia. As strict preconditions to payment, however, the Miller
    Act requires that subcontractors provide a notice of nonpay-
    ment within ninety days after the last day of work performed
    and then file suit within one year of the last date of work. The
    district court found that A&C missed both deadlines and
    granted summary judgment in favor of the sureties. Because
    A&C did not meet the Miller Act’s notice requirement, we af-
    firm the judgment.
    I. Background
    This dispute arises from a federal construction project
    with the United States Army Corps of Engineers for the con-
    struction of two billets on the Al Udeid Air Base in Qatar. The
    Miller Act provides that on any contract of more than
    $100,000 for “the construction, alteration, or repair of any
    public building or public work of the Federal Government”
    the contractor must supply “[a] payment bond with a surety
    satisfactory to the officer for the protection of all persons sup-
    plying labor and material in carrying out the work provided
    for in the contract for the use of each person.” 40 U.S.C.
    § 3131(b)(2). Amec Foster Wheeler Environment & Infrastruc-
    ture, Inc., was the prime contractor on the Qatar air base pro-
    ject. As such, Amec Foster Wheeler, as principal, and defend-
    ants Zurich American Insurance Company and The Insurance
    Company of the State of Pennsylvania, as sureties, executed
    and delivered to the Army Corps the required payment bond.
    Amec Foster Wheeler awarded certain work on the project
    to a subcontractor, Black Cat Engineering & Construction
    No. 19-3325                                                   3
    WLL—first mechanical work and later additional fire sup-
    pression work. Black Cat, in turn, subcontracted with A&C
    for some of that work. A&C, therefore, was the sub-subcon-
    tractor or second-tier subcontractor on the project. On January
    31, 2013, Black Cat and A&C entered into a contract for A&C
    to perform portions of the mechanical, electrical, and plumb-
    ing services that Amec Foster Wheeler awarded to Black Cat
    (the “MEP Agreement”). On July 1, 2013, Black Cat and A&C
    entered into a second contract for A&C to perform portions of
    the fire suppression work awarded to Black Cat (the “Fire
    Suppression Agreement”). Together, the work for these two
    contracts forms the basis of this lawsuit.
    A&C later subcontracted some of the ductwork under the
    MEP Agreement to Raymond Nahra for Electrical & Mechan-
    ical Works Co., W.L.L. (“RNC”). Thus, on the project, RNC
    was a third-tier subcontractor. From all accounts, RNC per-
    formed work on the project through the project’s completion
    date in February 2017.
    The relationship between Black Cat and A&C eventually
    deteriorated. On December 16, 2015, Black Cat terminated
    A&C from the Fire Suppression Agreement. The sureties con-
    tend that A&C had already stopped most of its work related
    to the MEP Agreement in November 2015 and that A&C last
    performed any work on the project on May 16, 2016. A&C dis-
    putes this characterization, primarily as it relates to the date
    it last performed any work on the project. Specifically, A&C
    insists that, despite the termination, it continued to provide
    labor and equipment after that date because its equipment re-
    mained on the site for Black Cat’s use, and it continued to pro-
    vide supervision of one of its subcontractors (RNC) through
    the project’s completion on February 28, 2017. Accordingly,
    4                                                    No. 19-3325
    A&C asserts that the date it last performed labor or supplied
    material for the project was February 28, 2017.
    It is undisputed, however, that A&C provided its notice
    under the Miller Act on August 16, 2016. That notice claimed
    that Black Cat owed A&C $8,449,710 for “Mechanical, Electri-
    cal and Plumbing and Fire Suppression works.” As to the
    “[d]ate on which the last of the labor, services, equipment or
    materials were furnished,” A&C stated that “[c]ertain A&C
    equipment remains onsite.”
    A&C filed its complaint on June 7, 2017, alleging a single
    Miller Act claim against the sureties for payment on the bond
    in the amount of $8,637,423. After discovery, the sureties
    moved for summary judgment, arguing that A&C’s last day
    of work was—at the latest—May 16, 2016. The notice date,
    August 16, 2016, is ninety-one days after May 16, 2016, and
    outside of the mandatory ninety-day notice period. A&C also
    did not file suit until June 7, 2017, more than one year after
    the sureties allege A&C last provided labor or material on the
    project. A&C disputed the May 16, 2016, date and instead ar-
    gued that it leased equipment to Black Cat that was utilized
    on the project up until its conclusion on February 28, 2017,
    and its subcontractor RNC also continued to provide labor
    until the completion date. Thus, A&C countered, it filed the
    lawsuit within one year of that date. Further, as to the fact that
    its Miller Act notice was served far more than ninety days be-
    fore its alleged last day of work, A&C simply argued that it
    “provided too much notice” and there was nothing that barred
    it from providing the notice earlier than required.
    The district court granted the sureties’ motion for sum-
    mary judgment. The court found that even if A&C was able
    to use leased equipment to Black Cat as its claimed last day of
    No. 19-3325                                                      5
    work performed as a legal matter, the argument still failed be-
    cause A&C did not provide notice “within 90 days” of that
    date (February 28, 2017). As to the “too much notice” argu-
    ment, the district court similarly rejected it because it did “not
    meet with the requirement that the limitations periods consti-
    tute conditions precedent and are to be strictly construed.”
    Based on some admitted misstatements in the district
    court’s opinion, A&C filed a post-judgment motion pursuant
    to Federal Rule of Civil Procedure 59(e) to alter or amend the
    judgment, alleging that the decision rested on “a manifest er-
    ror of fact.” In three places, the opinion erroneously stated
    that A&C did not file its complaint within one year of its Mil-
    ler Act notice. (E.g., “If Plaintiff is to rely upon its 90-day no-
    tice, then it needed to bring suit with one year or by August
    19, 2017 [sic] …. It did not do so. In fact, its Complaint, which
    was filed on June 7, 2017, ….”). But A&C in fact had—the no-
    tice date was August 16, 2016, and the lawsuit was filed ten
    months later on June 7, 2017. The problem for A&C, though,
    is that the one-year limitation does not run from the notice
    date. Both the notice period and lawsuit period run from the
    last day of claimed work. So the district court’s miscalculated
    time period was irrelevant.
    Nevertheless, A&C seized on these mistakes and argued
    for the first time that, according to the district court’s own rea-
    soning, “if A&C is not entitled to recover for work performed
    after the date of its notice (as the Court has held), then the last
    date of recoverable work was on August 16, 2016, the date of
    the notice.” A&C now contended that it served its Miller Act
    notice “contemporaneous[ly] with work performed by A&C
    (in the form of, at the least, leasing equipment),” and, because
    its complaint “was filed within one year of that date,” it was
    6                                                  No. 19-3325
    “not barred from seeking payment for its pre-notice work.”
    The district court denied A&C’s Rule 59(e) motion,
    “apologi[zing] for the sloppy proof reading” but “not[ing]
    that it cited and applied the correct standard” throughout the
    opinion. Despite the few misstatements, the court found that
    it committed no manifest error of fact or law.
    A&C now appeals from the district court’s summary judg-
    ment ruling.
    II. Discussion
    This appeal presents a seemingly straightforward ques-
    tion—whether A&C’s notice and civil action were timely un-
    der the Miller Act. The parties, however, dispute the correct
    date of the last work performed, which is the relevant trigger-
    ing event from which the time periods run. We review the
    district court’s summary judgment ruling de novo and con-
    sider facts and draw inferences in the light most favorable to
    the nonmoving party. Hall v. City of Chicago, 
    953 F.3d 945
    , 950
    (7th Cir. 2020). Summary judgment is appropriate when
    “there is no genuine dispute as to any material fact and the
    movant is entitled to judgment as a matter of law.” Fed. R.
    Civ. P. 56(a).
    Section 3133 of the Miller Act governs the right to bring a
    civil action on a payment bond, and provides two express
    timing requirements. First, a sub-subcontractor must give
    “written notice to the contractor within 90 days from the date
    on which the person did or performed the last of the labor or
    furnished or supplied the last of the material for which the
    claim is made.” 40 U.S.C. § 3133(b)(2). That is, the sub-sub-
    contractor must first notify the general contractor of the situ-
    ation before it can sue on the bond. Second, assuming the
    No. 19-3325                                                     7
    general contractor does not pay the outstanding bill, any “ac-
    tion brought under this subsection must be brought no later
    than one year after the day on which the last of the labor was
    performed or material was supplied by the person bringing
    the action.”
    Id. § 3133(b)(4).
    Though the Miller Act is “reme-
    dial and to be liberally construed,” giving written notice and
    bringing suit within the prescribed time limits are strict con-
    ditions precedent to the right to maintain the action. United
    States ex rel. Material Serv. Div. of Gen. Dynamics Corp. v. Home
    Indem. Co., 
    489 F.2d 1004
    , 1005 (7th Cir. 1973).
    Before we can decide the timeliness of A&C’s notice and
    lawsuit, we must confront a threshold question regarding
    waiver. At summary judgment, A&C opposed the sureties’
    motion on the basis that (1) its August 16, 2016 notice was
    timely because it provided “too much notice,” being served
    earlier than the claimed last date of work, February 28, 2017;
    (2) its lawsuit was timely filed on June 7, 2017, because it was
    filed within one year of the claimed last date of work, Febru-
    ary 28, 2017; and, therefore, (3) it was entitled to recover for
    all work performed through its claimed last day of work, Feb-
    ruary 28, 2017. In its post-judgment motion, A&C’s position
    shifted to argue that: (1) its August 16, 2016 notice was timely
    for work performed on or before that date; (2) its lawsuit was
    timely filed within one year of the notice; and, therefore, (3) it
    was entitled to recover for its pre-notice work, or through Au-
    gust 16, 2016. Now on appeal, A&C continues to press its the-
    ory of partial recovery for pre-notice work only. That argu-
    ment was not properly presented to the district court and, as
    a consequence, A&C has waived it.
    The purpose of Federal Rule of Civil Procedure 59(e) is to
    allow a party to bring to the district court’s attention a
    8                                                    No. 19-3325
    manifest error of fact or law so that it may correct, or at least
    address, the error in the first instance. Moro v. Shell Oil Co.,
    
    91 F.3d 872
    , 876 (7th Cir. 1996). A Rule 59(e) motion, however,
    “does not allow a party to introduce new evidence or advance
    arguments that could and should have been presented to the
    district court prior to the judgment.” Bordelon v. Chicago Sch.
    Reform Bd. of Trs., 
    233 F.3d 524
    , 529 (7th Cir. 2000) (quoting
    
    Moro, 91 F.3d at 876
    ); LB Credit Corp. v. Resolution Tr. Corp.,
    
    49 F.3d 1263
    , 1267 (7th Cir. 1995) (“[A] motion to alter or
    amend a judgment is not appropriately used to advance ar-
    guments or theories that could and should have been made
    before the district court rendered a judgment.”). The district
    court’s “opinions are not intended as mere first drafts, subject
    to revision and reconsideration at a litigant’s pleasure.”
    Quaker Alloy Casting Co. v. Gulfco Indus., Inc., 
    123 F.R.D. 282
    ,
    288 (N.D. Ill. 1988). A&C had the opportunity to make the ar-
    gument that it now advances during the summary judgment
    proceedings but failed to do so. A&C must live with that de-
    cision.
    A&C’s attempt to characterize this argument as merely
    “narrow[ing] the issues on appeal” does not save the day.
    Though A&C nominally maintains the same claimed last day
    of work of February 28, 2017, A&C did not—before the dis-
    trict court entered judgment—discuss the pre-notice period as
    a separate recoverable period or its entitlement thereto. There
    was no mention of this pre-notice, partial recovery theory in
    A&C’s summary judgment briefing, and all of its allegations
    both before and during summary judgment related to full re-
    covery for work performed through the project’s completion
    in February 2017. It was not until after the district court issued
    its summary judgment opinion that A&C grabbed hold of cer-
    tain (erroneous) language and unveiled its new partial
    No. 19-3325                                                    9
    recovery theory, arguing that by the court’s own reasoning it
    was now entitled to recover for its pre-notice work. Far from
    simply narrowing issues to present for appellate review, this
    represents a complete shift in A&C’s alleged right to recover
    that materially alters the resulting legal analysis. The record
    before the district court at summary judgment was silent as to
    A&C’s claim for partial recovery and we will not take up the
    merits of that argument for the first time.
    With the scope of our review settled, we turn to the ques-
    tion properly before us. Though a factual dispute still exists
    regarding A&C’s last day of work—the sureties assert May
    16, 2016, and A&C claims February 28, 2017—we need not re-
    solve that issue to decide the appeal. As the district court did,
    we will assume that the date A&C last performed work for
    purposes of its Miller Act claim is February 28, 2017. There is
    no dispute, however, that A&C served its Miller Act notice on
    August 16, 2016. As one of the strict preconditions to the right
    to bring a civil action on the payment bond, a sub-subcontrac-
    tor must give “written notice to the contractor within 90 days
    from the date on which the person did or performed the last
    of the labor or furnished or supplied the last of the material
    for which the claim is made.” 40 U.S.C. § 3133(b)(2). August
    16, 2016, is not “within 90 days” of February 28, 2017. The stat-
    ute is unambiguous on the timing of the notice requirement
    and we must enforce it as written. See U.S. ex rel. S & G Exca-
    vating, Inc. v. Seaboard Sur. Co., 
    236 F.3d 883
    , 885 (7th Cir.
    2001). A&C failed to timely serve its Miller Act notice and
    therefore cannot maintain an action against the sureties on the
    payment bond.
    10                                                 No. 19-3325
    III. Conclusion
    The Miller Act aims to protect subcontractors on federal
    construction projects against nonpayment, but nonetheless
    demands strict compliance with certain conditions precedent
    to the right to recover. Having waived its partial recovery ar-
    gument for pre-notice work only, we are left with a straight-
    forward question of whether A&C provided its required Mil-
    ler Act notice within ninety days of the date it claimed for its
    last day of recoverable work. A&C did not and therefore can-
    not sue on the payment bond. The judgment of the district
    court is
    AFFIRMED.