North Dakota v. United States Environmental Protection Agency , 730 F.3d 750 ( 2013 )


Menu:
  •                  United States Court of Appeals
    For the Eighth Circuit
    ___________________________
    No. 12-1844
    ___________________________
    State of North Dakota
    lllllllllllllllllllllPetitioner
    v.
    United States Environmental Protection Agency, and Lisa P. Jackson, Administrator
    lllllllllllllllllllllRespondent
    Basin Electric Power Cooperative
    lllllllllllllllllllllIntervenor
    ___________________________
    No. 12-1961
    ___________________________
    Great River Energy
    lllllllllllllllllllllPetitioner
    v.
    United States Environmental Protection Agency, and Lisa P. Jackson, Administrator
    lllllllllllllllllllllRespondent
    Basin Electric Power Cooperative
    lllllllllllllllllllllIntervenor
    ___________________________
    No. 12-2331
    ___________________________
    National Parks Conservation Association; Sierra Club
    lllllllllllllllllllllPetitioners
    v.
    United States Environmental Protection Agency; Lisa P. Jackson, Administrator,
    United States Environmental Protection Agency
    lllllllllllllllllllllRespondents
    Basin Electric Power Cooperative; Great River Energy; Minnkota Power
    Cooperative; Square Butte Electric Cooperative; State of North Dakota
    lllllllllllllllllllllIntervenors
    ------------------------------
    Montana-Dakota Utilities Co., A Division of MDU Resources Group, Inc.;
    Northern Municipal Power Agency; Northwestern Corporation, doing business as
    NorthWestern Energy; Otter Tail Power Company
    lllllllllllllllllllllAmici on Behalf of Respondent
    ____________
    Petition for Review of an Order of the
    Environmental Protection Administration
    ____________
    Submitted: May 14, 2013
    Filed: September 23, 2013
    ____________
    -2-
    Before WOLLMAN, MURPHY, and SMITH, Circuit Judges.
    ____________
    WOLLMAN, Circuit Judge.
    In these consolidated petitions for review, the State of North Dakota (State),
    Great River Energy, and National Parks Conservation Association and Sierra Club
    (collectively Environmental Groups) challenge the final rule promulgated by
    Environmental Protection Agency (EPA) on April 6, 2012, see 
    77 Fed. Reg. 20,894
    -
    945 (the Final Rule). The Final Rule approved in part and disapproved in part two
    state implementation plans (SIPs) submitted by the State to address its obligations
    under §§ 110 and 169A of the Clean Air Act (CAA), 
    42 U.S.C. §§ 7401
    -7671q, and
    promulgated a federal implementation plan (FIP) to address those portions of the SIPs
    that were disapproved. We grant in part and deny in part the State’s and Great River
    Energy’s petitions for review, and deny the Environmental Groups’ petition for
    review and voluntary motion to dismiss under Federal Rule of Appellate Procedure
    42(b).
    I. Background
    A. Statutory Background
    “[I]n 1977, ‘[i]n response to a growing awareness that visibility was rapidly
    deteriorating in many places, such as wilderness areas and national parks,’ Congress
    added § 169A to the [Clean Air Act.]” Am. Corn Growers Ass’n v. EPA, 
    291 F.3d 1
    , 3 (D.C. Cir. 2002) (per curiam) (second alteration in original) (internal citation
    omitted) (quoting Chevron U.S.A., Inc. v. EPA, 
    658 F.2d 271
    , 272 (5th Cir. 1981)).
    “Section 169A established as a national goal the ‘prevention of any future, and the
    remedying of any existing, impairment in visibility in mandatory class I areas which
    -3-
    impairment results from manmade air pollution.’” 
    Id.
     (quoting Clean Air Act
    Amendments of 1977, Pub. L. No. 95-95, § 128, 
    91 Stat. 685
    , 742 (current version
    at 
    42 U.S.C. § 7491
    (a)(1))). In connection with § 169A, “Congress directed EPA to
    issue regulations requiring states to submit [SIPs] containing emission limits,
    schedules of compliance, and other measures necessary to make reasonable progress
    toward meeting the national visibility goal.” Id.
    Under the regional haze regulations promulgated by EPA, a state “must
    establish goals (expressed in deciviews) that provide for reasonable progress towards
    achieving natural visibility conditions” in “each mandatory Class I Federal area
    located within the State[.]”1 
    40 C.F.R. § 51.308
    (d)(1). In reaching these reasonable
    progress goals, the state must consider “the cost of compliance, the time necessary for
    compliance, the energy and non-air quality environmental impacts of compliance, and
    the remaining useful life of any potentially affected sources, and include a
    demonstration showing how these factors were taken into consideration in selecting
    a goal.” 
    Id.
     § 51.308(d)(1)(i)(A). The state must also analyze and determine the rate
    of progress necessary to achieve natural visibility conditions in the mandatory Class
    I Federal areas by the year 2064 and “consider the uniform rate of improvement in
    visibility and the emission reduction measures needed to achieve it for the period
    1
    “The deciview is an atmospheric haze index that expresses uniform changes
    in haziness in terms of common increments across the entire range of conditions, from
    pristine to extremely impaired environments. A one deciview change in haziness is
    a small but noticeable change in haziness under most circumstances when viewing
    scenes in mandatory Class I Federal areas.” 
    62 Fed. Reg. 41,145
     (internal footnote
    omitted). Areas designated as Class I Federal areas include all international parks,
    national wilderness areas which exceed 5,000 acres in size, national memorial parks
    which exceed 5,000 acres in size, and national parks which exceed 6,000 acres in
    size. 
    42 U.S.C. § 7472
    (a). “[T]he term ‘mandatory class I Federal areas’ means
    Federal areas which may not be designated as other than class I[.]” 
    42 U.S.C. § 7491
    (g)(5). There are two such areas in the State: Theodore Roosevelt National
    Park and Lostwood Wilderness Area.
    -4-
    covered by the implementation plan.” 
    Id.
     § 51.308(d)(1)(i)(B). If the state’s
    reasonable progress goals provide for a slower rate of improvement than necessary
    to achieve natural visibility conditions by 2064, the state must demonstrate “that the
    rate of progress for the implementation plan to attain natural conditions by 2064 is
    not reasonable; and that the progress goal adopted by the State is reasonable.” Id. §
    51.308(d)(1)(ii).
    In addition to the reasonable progress goals, § 169A and the regional haze
    regulations require states to determine the best available retrofit technology (BART)
    for certain major stationary sources built between 1962 and 1977 that are reasonably
    anticipated to cause or contribute to visibility impairment in any Class I area. See 
    42 U.S.C. § 7491
    (b)(2)(A); 
    40 C.F.R. §§ 51.301
    , 51.308(e). To address the requirements
    for BART, a state must submit a SIP that contains a list of all BART-eligible sources
    and an analysis that takes into consideration the technology available, the costs of
    compliance, the energy and non-air quality environmental impacts of compliance, any
    pollution control equipment in use at the source, the remaining useful life of the
    source, and the degree of improvement in visibility which may reasonably be
    anticipated to result from the use of such technology. 
    Id.
     § 51.308(e)(1)(i)-(ii). For
    BART-eligible sources that have a total generating capacity greater than 750
    megawatts, the state must also use Appendix Y to the BART Guidelines in making
    its determination. Id. § 51.308(e)(1)(B). Appendix Y creates a five-step process for
    determining BART on a case-by-case basis: (1) identify all available retrofit control
    technologies; (2) eliminate technically infeasible options; (3) evaluate control
    effectiveness of remaining control technologies; (4) evaluate impacts and document
    the results; and (5) evaluate visibility impacts. See 
    70 Fed. Reg. 39,164
    .
    The CAA also “charges EPA with setting National Ambient Air Quality
    Standards, or NAAQS, which prescribe the maximum permissible levels of common
    pollutants in the ambient air.” EME Homer City Generation, L.P. v. EPA, 
    696 F.3d 7
    , 12 (D.C. Cir. 2012). “The States implement the NAAQS within their borders
    -5-
    through . . . SIPs.” 
    Id. at 13
    . The CAA requires states to submit revised SIPs to
    address new or revised NAAQS within three years after promulgation of the NAAQS.
    
    42 U.S.C. § 7410
    (a)(1). Section 110(a)(2) identifies the required elements of a state’s
    interstate transport SIP submission, which include what is known as the “good
    neighbor” provision. 
    Id.
     § 7410(a)(2)(D). The good neighbor provision requires that
    a SIP contain four distinct components, one of which is a visibility component. Id.
    § 7410(a)(2)(D)(i)(II). The visibility component mandates that the SIP contain an
    adequate provision prohibiting any source of emissions within the state from emitting
    air pollutant in amounts that will interfere with measures required to be included in
    the applicable SIP for any other state to protect visibility. Id.
    “Under the Clean Air Act, both the Federal Government and the States exercise
    responsibility for maintaining and improving air quality.” Am. Trucking Ass’ns v.
    EPA, 
    600 F.3d 624
    , 625 (D.C. Cir. 2010). “The Act sets forth a basic division of
    labor: The Federal Government establishes air quality standards, but States have
    primary responsibility for attaining those standards within their borders.” EME
    Homer, 696 F.3d at 29. “The Act thus leaves it to the individual States to determine,
    in the first instance, the particular restrictions that will be imposed on particular
    emitters within their borders.” Id. at 12. But, if a state fails to submit a SIP, submits
    an incomplete SIP, or submits a SIP that does not meet the statutory requirements,
    EPA is obligated to implement its own FIP to correct the deficiency in the SIP, unless
    the State can correct the deficiency itself and EPA can approve that correction within
    two years. 
    42 U.S.C. § 7410
    (c). This is commonly referred to as cooperative
    federalism, and both § 169A and § 110 operate under this framework.
    B. Procedural Background
    The State submitted its interstate transport SIP for EPA approval on April 6,
    2009, and submitted its regional haze SIP on March 3, 2010. The State submitted a
    SIP Supplement No. 1 on July 27, 2010, and also a SIP Amendment No. 1 on July 28,
    -6-
    2011. EPA issued a proposed rule on September 21, 2011, see 
    76 Fed. Reg. 58,570
    -
    648 (Proposed Rule), proposing to disapprove the State’s regional haze SIP regarding
    its determination of BART for the Coal Creek Station, Milton R. Young Station Units
    1 and 2, and Leland Olds Station Unit 2, as well as the reasonable progress
    determination for the Antelope Valley Station Units 1 and 2, and to disapprove the
    State’s interstate transport SIP for failure to satisfy the visibility component. Along
    with the proposed partial disapprovals, EPA proposed the promulgation of a FIP to
    address the deficiencies in the SIPs. See 
    id. at 58,573-74
    .
    After the public notice and comments period on the Proposed Rule was
    completed, EPA issued its Final Rule. See 
    77 Fed. Reg. 20,894
    -945. The Final Rule
    differed in one major respect from the Proposed Rule—although EPA had proposed
    to disapprove the State’s BART determinations for Young Station Units 1 and 2 and
    Olds Station Unit 2, EPA instead decided to approve the State’s BART
    determinations for those units. See 
    77 Fed. Reg. 20,897
    -98. This determination was
    based primarily on the decision in United States v. Minnkota Power Cooperative,
    Inc., 
    831 F. Supp. 2d 1109
    , 1127-30 (D.N.D. 2011), which concluded that the State’s
    analysis of the best available control technology (BACT) for Young Station Units 1
    and 2 was not unreasonable—a conclusion contrary to EPA’s position at the time of
    EPA’s Proposed Rule.
    Because Minnkota was issued after the public notice and comments period had
    closed on EPA’s Proposed Rule, interested parties were unable to comment on EPA’s
    decision to rely upon it as persuasive authority for approving the State’s BART
    determinations for Young Station Units 1 and 2 and Olds Station Unit 2. The
    Environmental Groups filed a petition for reconsideration with EPA on June 5, 2012,
    see 
    42 U.S.C. § 7607
    (d)(7)(B), voicing their concerns with EPA’s reliance upon
    Minnkota and its subsequent approval of the State’s BART determination for Young
    Station Units 1 and 2 and Olds Station Unit 2. The Environmental Groups moved to
    have their petition for review before this court held in abeyance until EPA determined
    -7-
    whether it would entertain the petition for reconsideration. The Environmental
    Groups’ motion for abeyance was denied without prejudice on July 31, 2012.
    Thereafter, EPA granted the petition for reconsideration on November 19, 2012, and
    that reconsideration process is still ongoing. Following EPA’s grant of the petition
    for reconsideration, the Environmental Groups moved under Federal Rule of
    Appellate Procedure 42(b) to voluntarily dismiss the instant petition for review
    concerning the BART determinations for Young Station Units 1 and 2 and Olds
    Station Unit 2. That motion is still pending before us.
    II. Discussion
    A. Standard of Review
    We will set aside EPA’s Final Rule if it is “arbitrary, capricious, an abuse of
    discretion, or otherwise not in accordance with law,” or “in excess of statutory
    jurisdiction, authority, or limitations, or short of statutory right.” 
    42 U.S.C. § 7607
    (d)(9). This standard is the same as that used under the Administrative
    Procedures Act, 
    5 U.S.C. § 706
    (2). See EME Homer, 696 F.3d at 23 n.17. But,
    “[o]nly an objection to a rule or procedure which was raised with reasonable
    specificity during the period for public comment . . . may be raised during judicial
    review.” 
    42 U.S.C. § 7607
    (d)(7)(B). This administrative exhaustion provision is
    strictly enforced, Natural Res. Def. Council v. EPA, 
    571 F.3d 1245
    , 1259 (D.C. Cir.
    2009) (per curiam), “to ensure that the agency is given the first opportunity to bring
    its expertise to bear on the resolution of a challenge to a rule.” Appalachian Power
    Co. v. EPA (Appalachian Power I), 
    135 F.3d 791
    , 818 (D.C. Cir. 1998) (per curiam).
    B. Simultaneous Denial of a SIP and Promulgation of a FIP
    The State first contends that the Final Rule should be vacated because EPA
    procedurally erred under the CAA by simultaneously disapproving the State’s SIP
    -8-
    and promulgating its FIP in the same Final Rule. Under the CAA, reversal of an
    action because of procedural error is appropriate only when (1) the failure to observe
    the procedure is arbitrary or capricious; (2) the alleged error was raised during the
    comment period; and (3) the error was so serious and related to matters of such
    central relevance to the rule that there is a substantial likelihood that the rule would
    have been significantly changed if the error had not been made. 
    42 U.S.C. § 7607
    (d)(9)(D).
    Among other things, § 7607(d)(3) requires that a proposed rule under the CAA
    contain a statement of basis and purpose, which must include a summary of the
    factual data on which the proposed rule is based, the methodology used in obtaining
    the data and in analyzing the data, and the major legal interpretations and policy
    considerations underlying the proposed rule. The State argues that a proper statement
    of basis and purpose for EPA’s FIP could not be issued until a final rulemaking on
    its SIP was issued. Even assuming that the State’s interpretation of § 7607(d)(3) is
    correct, the State has failed to demonstrate that EPA’s error in this regard was “so
    serious and related to matters of such central relevance to the rule that there is a
    substantial likelihood that the rule would have been significantly changed if the error
    had not been made.” Id. at § 7607(d)(9)(D). Although “[i]t may be poor policy to try
    to distinguish between the SIP and FIP in a single action[,]” Oklahoma v. EPA, Nos.
    12-9526, 12-9527, 
    2013 WL 3766986
    , at *19 (10th Cir. July 19, 2013), the State has
    failed to demonstrate that vacating the Final Rule based upon this alleged procedural
    error is appropriate.
    C. Coal Creek Station
    The State and Great River Energy, the owner of the Coal Creek Station,
    challenge EPA’s disapproval of the State’s SIP determination that modified and
    additional separated overfire air with low NOx burner (SOFA plus LNB) with an
    emission limit of 0.17lb/MMBtu on a thirty-day rolling average basis was BART for
    -9-
    the Coal Creek Station. These petitioners also challenge EPA’s FIP determination
    that selective non-catalytic reduction (SNCR) plus SOFA plus LNB with an emission
    limit of 0.13lb/MMBtu on a thirty-day rolling average is BART for the Coal Creek
    Station.
    Energy production at the Coal Creek Station creates a by-product known as fly
    ash. Great River Energy is able to sell the fly ash created at the Coal Creek Station
    to construction companies to be used as a replacement for cement in the creation of
    concrete. During its BART analysis for the Coal Creek Station, the State concluded
    that using SNCR to control additional emissions at the plant would result in ammonia
    slip, which in turn would contaminate the fly ash, making it unsuitable for use in
    concrete. The State thus concluded that SNCR would cause Great River Energy to
    lose revenue from the sale of fly ash and would result in additional costs to dispose
    of the fly ash in landfills.
    The State requested information regarding fly ash sales from Great River
    Energy, which informed the State that it received $36 per ton of fly ash sold. The
    State used this information to calculate the estimated cost effectiveness of
    implementing SNCR as $8,551 per-ton-of-NOx removed. This estimate included the
    cost of lost fly ash revenue and the additional cost of disposing the unusable fly ash.
    See Great River Energy Add. 57. The State calculated the cost effectiveness of SOFA
    plus LNB as $411 per-ton-of-NOx removed. 
    Id.
     The State concluded that the
    incremental cost of SNCR over SOFA plus LNB was excessive, but that if fly ash
    sales were not lost using SNCR, that the cost would not be considered excessive. 
    Id. at 61
    . The State also found that the incremental improvement in visibility of SNCR
    over SOFA plus LNB was only 0.105 deciviews. The State concluded that “[b]ecause
    of the potential for lost sales of fly ash, the negative environmental effects of having
    to dispose of the fly ash instead of recycling it into concrete, and the very small
    amount of visibility improvement from the use of SNCR, this option is rejected as
    -10-
    BART.” 
    Id.
     Instead, the State proposed that “BART is represented by modified and
    additional SOFA plus LNB[.]” 
    Id.
    During its review of the State’s BART analysis for the Coal Creek Station,
    EPA identified a possible discrepancy regarding the projected costs associated with
    SNCR and requested additional information from Great River Energy to support its
    predictions on lost fly ash revenue. Great River Energy discovered that it had made
    a mistake in its disclosure to the State by stating that it received $36 per ton of fly ash
    in revenue, when its actual revenue from fly ash was only $5 per ton. On July 16,
    2011, Great River Energy submitted corrected data regarding lost fly ash revenue,
    resulting in a projected cost effectiveness of SNCR as $2,318 per-ton-of-NO x
    removed. After reviewing the new data, EPA disapproved the State’s BART
    determination for the Coal Creek Station. EPA concluded that the State’s SIP failed
    to properly consider the cost of compliance in any meaningful sense as required by
    
    40 C.F.R. § 51.308
    (e)(1)(ii)(A) because the cost of compliance analysis was based
    upon fundamentally flawed and greatly inflated cost estimates regarding lost fly ash
    revenue.
    Having disapproved the State’s BART determination, EPA proposed to
    promulgate a FIP imposing its own BART determination for the Coal Creek Station.
    After conducting its own BART analysis based upon the State’s baseline emissions
    numbers for the Coal Creek Station established in 2003-2004, as well as the corrected
    lost fly ash revenue projections, EPA proposed to find that BART was SNCR plus
    SOFA plus LNB with an emission limit of 0.12lb/MMBtu on a thirty-day rolling
    average. 
    76 Fed. Reg. 58,622
    . Great River Energy submitted several comments on
    EPA’s proposed BART determination, including its objections to EPA’s calculations
    regarding cost effectiveness on the ground that EPA had failed to consider existing
    control technology in use at the Coal Creek Station. See, e.g., 
    77 Fed. Reg. 20,927
    .
    From 2006 to 2009, Great River Energy tested a prototype pollution control
    technology that is now known as DryFining™. Great River Energy voluntarily
    -11-
    installed a full version of the technology at the Coal Creek Station in 2009, two years
    prior to EPA’s proposed BART determination. EPA acknowledged Great River
    Energy’s comments but concluded that it was not required to consider voluntarily
    installed control technology that was installed after the baseline period. 
    77 Fed. Reg. 20,918
    . EPA’s Final Rule concluded that BART was SNCR plus SOFA plus LNB,
    but determined that the emission limit should be 0.13lb/MMBtu on a thirty-day
    rolling average. 
    77 Fed. Reg. 20,899
    .
    1. Disapproval of the State’s BART determination
    The State and Great River Energy contend that EPA’s disapproval of the
    State’s BART determination for the Coal Creek Station was arbitrary, capricious, and
    an abuse of discretion. They contend that because EPA is required to approve a SIP
    submission that meets all of the requirements of § 169A, see 
    42 U.S.C. § 7410
    (k)(3),
    and because the State’s SIP contained an analysis of each mandatory BART factor,
    EPA was without authority to disapprove the SIP, notwithstanding that the cost of
    compliance factor was based upon admittedly erroneous data. Under the State and
    Great River Energy’s interpretation of § 169A, EPA’s role in reviewing a state’s
    BART determination is limited to ensuring that at least minimal consideration is
    given to each factor and does not permit EPA to examine the rationality or
    reasonableness of the underlying decision.
    EPA contends that it possessed the authority to disapprove the State’s BART
    determination because the State had failed to consider, in any meaningful sense, the
    cost of compliance, which is a factor that a state must consider under the statute and
    the applicable guidelines.         See 
    42 U.S.C. § 7491
    (g)(2); 
    40 C.F.R. § 51.308
    (3)(1)(ii)(A). EPA argues that although the BART analysis contained a
    discussion of the cost of compliance for SNCR, the discussion was based upon
    grossly erroneous data that skewed the results and prevented the State from properly
    considering this factor. Moreover, EPA notes that the State acknowledged in its SIP
    -12-
    that but for the cost of lost revenue for fly ash, the State would not have found the
    cost of compliance for SNCR excessive.
    Although the CAA grants states the primary role of determining the appropriate
    pollution controls within their borders, EPA is left with more than the ministerial task
    of routinely approving SIP submissions. The Tenth Circuit recently concluded that
    EPA acted within its power under § 169A in rejecting a BART determination on the
    basis that the state “did not properly take into consideration the costs of compliance
    when it relied on cost estimates that greatly overestimated the costs of dry and wet
    scrubbing to conclude these controls were not cost effective.” Oklahoma v. EPA,
    
    2013 WL 3766986
    , at *3, *5-6 (internal quotation marks omitted). The court held
    that because the state’s cost of compliance estimate was based upon fundamental
    methodological flaws, EPA had a reasonable basis for rejecting the state’s BART
    determination for failure to comply with the requisite BART guidelines. 
    Id. at *8
    .
    Moreover, in Alaska Department of Environmental Conservation v. EPA, 
    540 U.S. 461
     (2004), the Supreme Court rejected an argument similar to that raised here
    regarding EPA’s oversight role in the BACT determination process under § 167 of
    the CAA. The Court held that EPA was not limited simply to verifying that a BACT
    determination was actually made, concluding instead that EPA could examine the
    substance of the BACT determination to ensure that it was one that was “reasonably
    moored to the Act’s provisions” and was based on “reasoned analysis.” See id. at
    485, 490. Although the Court’s analysis was one under § 167, we nonetheless find
    it persuasive in the context of § 169A.
    We see little difference between the rejection of a factor containing
    methodological flaws that led to an overestimated cost of compliance, as occurred in
    Oklahoma v. EPA, and the rejection of a factor containing data flaws that led to an
    overestimated cost of compliance, as occurred in this case. In both cases, the flaw in
    the analysis prevented the state from conducting a meaningful consideration of the
    factor, as required by the BART guidelines. As did the Supreme Court in its § 167
    -13-
    analysis in Alaska Department of Environmental Conservation, we reject the
    argument that EPA is required under § 169A to approve a BART determination that
    is based upon an analysis that is neither reasoned nor moored to the CAA’s
    provisions. At oral argument, the State all but conceded EPA’s ability to review the
    substantive content of the BART determination when it acknowledged that EPA
    would have the authority to disapprove a SIP if the state plainly proceeded without
    a sufficient factual basis. Accordingly, we conclude that EPA’s disapproval of the
    State’s BART determination for failing to consider the cost of compliance as required
    under the statute and the BART guidelines was neither arbitrary, capricious, nor an
    abuse of discretion.2
    The State argues in the alternative that EPA’s decision was arbitrary and
    capricious because it prematurely rejected the State’s SIP based upon the data error
    in the cost of compliance factor before the State could supplement its SIP and address
    the data error. The State contends that it notified EPA that it would submit a
    supplemental BART determination for the Coal Creek Station once it received the
    projected final revised cost estimates from Great River Energy. The State argues
    further that EPA prematurely disapproved the State’s original BART determination
    in its regional haze SIP, knowing that a supplemental BART determination was
    forthcoming.
    2
    Nor do we find convincing Great River Energy’s argument that under Friends
    of the Boundary Waters Wilderness v. Dombeck, 
    164 F.3d 1115
    , 1129 (8th Cir.
    1999), EPA was first required to prove that the data error was material to the State’s
    determination before rejecting its BART determination all together. Friends of the
    Boundary Waters Wilderness is inapplicable because the data error discussed and
    addressed in that case was one contained in a factor voluntarily considered by the
    agency under a completely different regulatory act. In this case, the data error was
    contained in a factor that the State was obligated to properly consider under the CAA;
    thus, EPA need only demonstrate that the State failed to consider this factor as
    required by the CAA and accompanying regulations.
    -14-
    Under 
    42 U.S.C. § 7410
    (k)(2), EPA is required to take action on a SIP
    submission within twelve months of the date that the submission is deemed complete.
    EPA may approve the submission as a whole or in part, but whatever action it takes
    must be done within twelve months of the completed SIP submission. See 
    42 U.S.C. § 7410
    (k)(2)-(3). The State’s regional haze SIP submission was deemed complete on
    April 30, 2011, leaving EPA until April 30, 2012, to take action thereon. Although
    Great River Energy submitted initial information regarding lost fly ash revenue on
    June 16, 2011, as of April 2012, it had yet to submit its final revised calculations
    regarding the projected costs associated with lost fly ash sales. EPA took final action
    on the State’s SIP addressing the BART determination for the Coal Creek Station on
    April 6, 2012. Great River Energy did not submit its final revised calculations
    regarding the projected cost associated with lost fly ash sales until June 2012. The
    State has identified no provision of the CAA that obligated EPA to wait for its
    supplemental BART determination before disapproving its original Coal Creek
    Station BART determination. Nor has the State identified any provision that tolled
    the twelve-month period within which EPA was required to take final action. The
    State has thus failed to demonstrate that EPA’s disapproval of the State’s BART
    determination for the Coal Creek Station was arbitrary, capricious, or an abuse of
    discretion.
    2. Promulgation of a FIP for the Coal Creek Station
    In light of its decision to disapprove the State’s SIP related to its BART
    determination for the Coal Creek Station, EPA was obligated under the CAA to
    promulgate a FIP within two years of the disapproval “unless the State correct[ed] the
    deficiency, and the Administrator approve[d] the plan or plan revision, before the
    Administrator promulgate[d] such Federal implementation plan.” 
    42 U.S.C. § 7410
    (c)(1)(B). Great River Energy challenges EPA’s determination that SNCR is
    BART for the Coal Creek Station on the ground that EPA violated the CAA by
    refusing to consider existing pollution control technology at the station during its
    -15-
    BART analysis. One of the statutory factors that a state and EPA must consider when
    determining BART is “any existing pollution control technology in use at the source.”
    
    42 U.S.C. § 7491
    (g)(2). During its BART analysis EPA refused to consider the
    DryFining™ pollution control technology in use at the Coal Creek Station, stating in
    its Final Rule that “DryFining™ was not installed until after the baseline period and
    was installed voluntarily, not to meet any regulatory requirement[,]” and that EPA
    was not required to reconsider cost estimates based on voluntarily installed controls
    installed after the baseline period. 
    77 Fed. Reg. 20,918
    . Great River Energy contends
    that EPA’s refusal to consider the voluntarily installed pollution control technology
    in use at the Coal Creek Station demonstrates that EPA failed to consider all of the
    statutory factors required under 
    42 U.S.C. § 7491
    (g)(2) and 
    40 C.F.R. § 51.308
    (e)(1)(i)(A) and that its BART determination must therefore be vacated.
    EPA contends that it was not required to consider the voluntarily installed
    pollution controls at the Coal Creek Station, including the DryFining™ technology,
    because it permissibly interpreted the ambiguous phrase “existing pollution control
    technology in use at the source” to mean existing technology “incorporated into
    emission limits in an approved SIP or specified in a Clean Air Act permit for the
    facility and . . . adopted to meet Clean Air Act requirements.” EPA Br. 82. Making
    no mention of or giving any significance to the word “any” in § 7491(g)(2), EPA
    argues that its interpretation of the ambiguous statutory language “existing pollution
    control technology” is entitled to deference, presumably under Chevron, U.S.A., Inc.
    v. Natural Resources Defense Council, Inc., 
    467 U.S. 837
     (1984). Great River
    Energy contends that EPA’s interpretation of “any existing pollution controls” is
    entitled to no deference because the statutory language at issue is clear and
    unequivocal, not ambiguous.
    Chevron deference is appropriate when an agency exercises its generally
    conferred authority to resolve a particular statutory ambiguity and the resulting
    interpretation is based on a permissible construction of the statute. See Chevron, 467
    -16-
    U.S. at 842-43. To determine if an agency interpretation is entitled to Chevron
    deference,
    [W]e ask first whether the intent of Congress is clear as to the precise
    question at issue. If, by employing traditional tools of statutory
    construction, we determine that Congress’ intent is clear, that is the end
    of the matter. But if the statute is silent or ambiguous with respect to the
    specific issue, the question for the court is whether the agency’s answer
    is based on a permissible construction of the statute. If the agency’s
    reading fills a gap or defines a term in a reasonable way in light of the
    Legislature’s design, we give that reading controlling weight, even if it
    is not the answer the court would have reached if the question initially
    had arisen in a judicial proceeding.
    Baptist Health v. Thompson, 
    458 F.3d 768
    , 773 (8th Cir. 2006) (alteration in original)
    (citations omitted in original) (internal quotation marks omitted).
    Under the first step of the Chevron analysis, we employ the traditional tools of
    statutory interpretation to determine whether the statute makes clear the intent of
    Congress as to the meaning of the phrase “any existing pollution control technology
    in use at the source.” 
    42 U.S.C. § 7491
    (g)(2). “As in all such cases, we begin by
    analyzing the statutory language, ‘assum[ing] that the ordinary meaning of that
    language accurately expresses the legislative purpose.’” Hardt v. Reliance Standard
    Life Ins. Co., 
    560 U.S. 242
    , 
    130 S. Ct. 2149
    , 2156 (2010) (alteration in original)
    (quoting Gross v. FBL Fin. Servs., Inc., 
    557 U.S. 167
    , 175 (2009)).
    The Supreme Court has acknowledged that “‘any’ can and does mean different
    things depending upon the setting.” Nixon v. Mo. Mun. League, 
    541 U.S. 125
    , 132
    (2004). Nevertheless, “[i]n a series of cases, the Supreme Court has drawn upon the
    word ‘any’ to give the word it modifies an ‘expansive meaning’ when there is ‘no
    reason to contravene the clause’s obvious meaning.’” New York v. EPA, 
    443 F.3d 880
    , 885 (D.C. Cir. 2006) (quoting Norfolk S. Ry. Co. v. Kirby, 
    543 U.S. 14
    , 31-32
    -17-
    (2004)). This line of cases adopting an expansive meaning includes the interpretation
    of the term “any” under § 307(b)(1) of the CAA, 
    42 U.S.C. § 7607
    (b)(1). See
    Harrison v. PPG Indus., Inc., 
    446 U.S. 578
     (1980).
    An examination of the relevant statutory language in § 7491(g)(2) reveals “no
    reason to contravene the clause’s obvious meaning[,]” Kirby, 
    543 U.S. at 31-32
    , nor
    has EPA proffered any reason to do so. We thus afford the term its obvious and
    expansive meaning and conclude that Congress’s use of the term “any” to modify
    “existing pollution control technologies” demonstrates that it intended the decision
    maker to consider “one or some indiscriminately of whatever kind,” Webster’s Third
    International Dictionary (Unabridged), 97 (1981), of control technologies in use at
    the source, not simply those that are “incorporated into emission limits in an approved
    SIP or specified in a Clean Air Act permit for the facility and . . . adopted to meet
    Clean Air Act requirements.” EPA Br. 82.
    Because we find no ambiguity in the kind of technologies that must be
    considered under § 7491(g)(2), EPA’s interpretation that it was not required to
    consider the existing pollution control technologies in use at the Coal Creek Station
    is entitled to no deference. Just as the State was required to properly consider each
    statutory factor in the BART analysis in the implementation of its SIP, so too was
    EPA in the promulgation of its FIP. Accordingly, EPA’s refusal to consider the
    existing pollution control technology in use at the Coal Creek Station because it had
    been voluntarily installed was arbitrary and capricious and its FIP promulgating
    SNCR as BART for the Coal Creek Station is therefore vacated.
    D. Antelope Valley Station
    The State challenges EPA’s disapproval of its reasonable progress
    determination for Antelope Valley Station Units 1 and 2 and EPA’s subsequent
    promulgation of a FIP.
    -18-
    As discussed above, the CAA requires that states make determinations of
    reasonable progress for achieving natural visibility in Class I Federal areas. The state
    is required to analyze and determine the rate of progress necessary to achieve natural
    visibility conditions in the mandatory Class I Federal areas by the year 2064 and
    “consider the uniform rate of improvement in visibility and the emission reduction
    measures needed to achieve it for the period covered by the implementation plan.”
    
    40 C.F.R. § 51.308
    (d)(1)(i)(B). During its analysis, the State concluded that the rate
    of progress necessary “for the implementation plan to attain natural conditions by
    2064 [was] not reasonable[.]” 
    Id.
     § 51.308(d)(1)(ii). This determination allowed the
    State to implement a slower rate of progress but it also obligated the State to
    demonstrate that its reasonable progress goals were reasonable. Id.
    When the State established its reasonable progress goals for the Theodore
    Roosevelt National Park and Lostwood Wilderness Areas it determined that
    additional pollution control technologies for Antelope Valley Station Units 1 and 2
    were unnecessary to achieve reasonable progress. The State reached this conclusion
    after examining the four statutory factors that must be taken into account in
    determining reasonable progress under § 7491(g)(1): costs of compliance; the time
    necessary for compliance; the energy and non-air quality environmental impacts of
    compliance; and the remaining useful life of the units—as well as one nonstatutory
    factor, incremental visibility improvement. In its analysis of the projected
    improvement in visibility, the State created and used its own cumulative source
    visibility model, which employs current degraded background visibility conditions
    as its baseline. Using the cumulative source visibility model, the State concluded that
    the maximum combined improvement for the average of the 20% worst days was 0.11
    deciviews at Lostwood Wilderness Area and 0.03 deciviews at Theodore Roosevelt
    National Park. The State then chose to evaluate the cost effectiveness of additional
    controls at Antelope Valley using the dollar-per-deciview of improvement metric
    rather than the more conventional dollar-per-ton-of-NOx removed metric. With the
    visibility numbers calculated using the cumulative source visibility model, the State
    -19-
    found that the cost effectiveness of additional controls would be 618 million dollars-
    per-deciview of improvement at Lostwood Wilderness Area and 2.3 billion dollars-
    per-deciview of improvement at Theodore Roosevelt National Park. The State found
    these costs excessive and determined that installing additional controls at the
    Antelope Valley Station was not reasonable.
    EPA proposed to disapprove the State’s determination, concluding that the
    decision not to install additional controls was unreasonable in light of the State’s
    admission that it could not meet the uniform rate of progress to restore natural
    visibility in Class I Federal areas by 2064. EPA took issue with two aspects of the
    State’s reasonable progress determination: the results of the State’s incremental
    visibility improvement analysis and the results of the State’s cost effectiveness
    analysis. Both sets of results were based upon the State’s use of its cumulative source
    visibility modeling. In the Proposed Rule, EPA found “that North Dakota’s visibility
    modeling significantly understates the visibility improvement that would be realized
    for the control options under consideration.” 
    76 Fed. Reg. 58,627
    . EPA concluded:
    While it is reasonable for a state to consider visibility improvement as
    an additional factor in its reasonable progress analysis when evaluating
    visibility benefits from potential control options at individual sources,
    it is not appropriate to assume degraded background conditions, as the
    State did. As we note above, using degraded rather than natural
    background in the modeling produces estimates that greatly
    underestimate the benefits of potential control options. The ultimate
    goal of the regional haze program is to achieve natural visibility
    conditions, not to preserve degraded conditions.
    
    76 Fed. Reg. 58,629
    . EPA also found that because of the greatly underestimated
    improvement in visibility attributable to the State’s visibility model, that “cost
    effectiveness values, when expressed in dollars per deciview, were overestimated.”
    
    Id.
     EPA thus proposed to disapprove the reasonable progress determination for
    Antelope Valley Station Units 1 and 2. In its place, EPA proposed to promulgate a
    -20-
    FIP determining that separated overfire air plus low NOx burners (SOFA + LNB) with
    an emission limit of 0.17 lb/MMBtu on a thirty-day rolling average represented
    reasonable progress for Units 1 and 2. 
    76 Fed. Reg. 58,632
    . EPA concluded that this
    technology would cost approximately $586 and $661 per-ton-of-NOx removed at
    Units 1 and 2 and would result in the total removal of approximately 3,500 tons of
    NOx per unit per year. 
    Id.
    The State challenges EPA’s disapproval of its reasonable progress
    determination, contending that EPA’s rejection of the incremental visibility
    improvement results and the dollars-per-deciview of improvement results based upon
    the State’s cumulative source visibility modeling was arbitrary, capricious, and an
    abuse of discretion. Because this was a reasonable progress determination, the State
    contends that it was not obligated to use the single source visibility model required
    under the BART Guidelines and that it could instead develop and utilize its own
    visibility model. EPA concedes that the State was not obligated to use EPA’s single
    source visibility model, but argues that if a state chooses to consider incremental
    visibility improvement in the reasonable progress context, it must do so in a manner
    that is consistent with the CAA.
    As discussed above, EPA’s review of a SIP extends not only to whether the
    state considered the necessary factors in its determination, but also to whether the
    determination is one that is reasonably moored to the CAA’s provisions. See ante 12-
    14. This is especially true when a state is obligated to demonstrate that its
    determination is one that is reasonable, as was the case here. See 
    40 C.F.R. § 51.308
    (d)(1)(ii). In its review of the State’s reasonable progress determination,
    EPA concluded that the cumulative source visibility model employing the current
    degraded conditions as its baseline was not consistent with the CAA. EPA noted that
    the use of such a visibility model will rarely if ever demonstrate that emissions
    reductions at a single source will have an appreciable effect on incremental visibility
    improvement in a given area. “This is true because of the nonlinear nature of
    -21-
    visibility impairment. In other words, as a Class I area becomes more polluted, any
    individual source’s contribution to changes in impairment becomes geometrically
    less.” 
    77 Fed. Reg. 20,912
     (quoting 
    70 Fed. Reg. 39,124
    ). EPA found that rather
    than restore Class I areas to natural conditions, such a visibility model will serve
    instead to maintain current degraded conditions. EPA’s determination on this matter
    is entitled to judicial deference, as it involves “technical matters within its area of
    expertise[.]” Lockhart v. Kenops, 
    927 F.2d 1028
    , 1034 (8th Cir. 1991) (quoting
    Louisiana ex rel. Guste v. Verity, 
    853 F.2d 322
    , 329 (5th Cir. 1988)); see also Marsh
    v. Or. Natural Res. Council, 
    490 U.S. 360
    , 378 (1989) (“When specialists express
    conflicting views, an agency must have discretion to rely on the reasonable opinions
    of its own qualified experts even if, as an original matter, a court might find contrary
    views more persuasive.”).
    The State’s determination that no additional NOx controls were necessary for
    Antelope Valley Station Units 1 and 2 was based primarily on the lack of incremental
    visibility improvement expected from the installation of the technology and its
    excessive cost effectiveness on a dollars-per-deciview of improvement metric. Each
    of these conclusions, however, was reached through the use of the State’s cumulative
    source visibility modeling. Although the State was free to employ its own visibility
    model and to consider visibility improvement in its reasonable progress
    determinations, it was not free to do so in a manner that was inconsistent with the
    CAA. Because the goal of § 169A is to attain natural visibility conditions in
    mandatory Class I Federal areas, see 
    42 U.S.C. § 7491
    (a)(1), and EPA has
    demonstrated that the visibility model used by the State would serve instead to
    maintain current degraded conditions, we cannot say that EPA acted in a manner that
    was arbitrary, capricious, or an abuse of discretion by disapproving the State’s
    reasonable progress determination based upon its cumulative source visibility
    modeling.
    -22-
    Although the State has challenged EPA’s promulgation of its FIP—concluding
    that reasonable progress for Antelope Valley Station Units 1 and 2 was SOFA+LNB
    with a 0.17 lb/MMBtu emission limit on a thirty-day rolling average—it has done so
    only on procedural grounds, arguing that because the disapproval of the SIP was
    improper, so too was the promulgation of the FIP. Because we conclude that EPA
    properly disapproved the State’s reasonable progress determination, the State’s
    challenge to the FIP necessarily fails. Accordingly, the State’s petition for review of
    EPA’s disapproval of the State’s SIP and promulgation of a FIP is denied.
    E. Coyote Station
    The Environmental Groups challenge EPA’s approval of the 0.50 lb/MMBtu
    emission limit as reasonable progress for the Coyote Station.
    As part of its regional haze SIP, the State conducted a reasonable progress
    determination for the Coyote Station. During this determination, the State evaluated
    several possible pollution control technologies, including advanced separated overfire
    air (ASOFA). The State estimated that installing ASOFA would result in a 40%
    reduction of NOx emissions. Although the State determined that ASOFA would result
    in a cost effectiveness of $246 per-ton-of-NOx removed, it concluded that the more
    appropriate measure of cost effectiveness for determining reasonable progress was
    expressed in dollars-per-deciview of improvement. Using its own visibility modeling
    discussed above, the State calculated a combined maximum improvement in
    deciviews over the 20% worst days at Lostwood Wilderness Area and Theodore
    Roosevelt National Park. As with the determination for Antelope Valley Station
    Units 1 and 2, the State used the projected visibility improvements to calculate the
    cumulative cost effectiveness of additional technologies of approximately 618 million
    dollars-per-deciview of improvement at Lostwood Wilderness Area and 2.3 billion
    dollars-per-deciview of improvement at Theodore Roosevelt National Park. Based
    -23-
    upon these cost effectiveness calculations, the State concluded that no additional NO x
    controls were reasonably necessary at the Coyote Station.
    Notwithstanding this conclusion, the State engaged in negotiations with the
    owner of the Coyote Station, reaching an agreement that established an NOx emission
    limit of 0.50 lb/MMBtu on a thirty-day rolling average. This emission limit would
    be satisfied through the installation of additional pollution controls, assumed to be
    overfire air (OFA), that would remove approximately 4,213 tons of NOx, which
    represents an approximate 32% decrease in emissions from the station’s 2000-2004
    baseline. This agreement was made enforceable through a permit for construction at
    the Coyote Station and was submitted with the State’s SIP.
    In its review of the State’s reasonable progress determination, EPA concluded
    that the State had unreasonably rejected ASOFA as a potential technology
    representing reasonable progress because its decision was based on the same
    cumulative source visibility modeling discussed above. See 
    76 Fed. Reg. 58,630
    .
    Unlike the determination involving the Antelope Valley Station, however, the State
    nevertheless had included in its SIP an emission limit for the Coyote Station. EPA
    found the following:
    [W]e continue to disagree with the manner in which North Dakota
    evaluated visibility improvement when it evaluated single source
    controls and have disregarded this evaluation in our consideration of the
    reasonableness of North Dakota’s reasonable progress control
    determinations. We also disagree with some of North Dakota’s legal
    conclusions about the necessity of reasonable progress controls for
    certain sources—specifically, for Coyote Station for NOx and for
    Heskett Station 2 for sulfur dioxide (SO2). However, in these instances,
    North Dakota nonetheless included emission limits in the SIP that reflect
    reasonable levels of control for reasonable progress for this initial
    planning period. Here again, we understand that there is room for
    disagreement about the State’s analyses and appropriate limits. And,
    -24-
    again, we may have reached different conclusions had we been
    performing the determinations. However, the comments have not
    convinced us that the State, conducting specific case-by-case analyses
    for the relevant units, made unreasonable determinations for this initial
    planning period or that we should be disapproving the State’s reasonable
    progress determinations that we proposed to approve.
    
    77 Fed. Reg. 20,899
    . Therefore, after “disregard[ing] the State’s visibility analysis
    . . . and instead focus[ing] on the four reasonable progress factors[,]” EPA concluded
    that the State’s proposed 0.50 lb/MMBtu emission limit was not unreasonable. 
    77 Fed. Reg. 20,937
    .
    The Environmental Groups first argue that EPA’s approval of the
    0.50 lb/MMBtu emission limit as reasonable progress was arbitrary, capricious, and
    an abuse of discretion because EPA could not find that the State unreasonably
    rejected ASOFA as a potential technology representing reasonable progress, while
    simultaneously approving the more lax 0.50 lb/MMBtu emission limit. But EPA’s
    finding that the State unreasonably rejected ASOFA on the ground that it was not cost
    effective has no bearing on whether the emission limit was itself reasonable progress.
    EPA’s implicit conclusion that ASOFA would have been technology representing
    reasonable progress does not mean that EPA concluded that ASOFA was the only
    technology representing reasonable progress. Even if ASOFA were perhaps the most
    reasonable technology available, the CAA requires only that a state establish
    reasonable progress, not the most reasonable progress. EPA acknowledged that had
    it been making the decision in the first instance, it perhaps would have chosen
    ASOFA, but concluded that was not its decision to make. Given the procedural
    posture, EPA was obligated to review the State’s decision to ensure that the State’s
    determination represented reasonable progress, which it concluded the State had
    done. We thus find nothing arbitrary about EPA’s conclusion that ASOFA would
    have represented reasonable progress and its ultimate determination that the
    -25-
    0.50 lb/MMBtu emission limit contained in the SIP also represented reasonable
    progress.
    The Environmental Groups argue in the alternative that EPA’s decision
    approving the emission limit lacked a reasoned basis and therefore must be vacated.
    “While we may not supply a reasoned basis for the agency’s action that the agency
    itself has not given, . . . we will uphold a decision of less than ideal clarity if the
    agency’s path may reasonably be discerned.” Bowman Transp., Inc. v. Arkansas-Best
    Freight Sys., Inc., 
    419 U.S. 281
    , 285-86 (1974) (internal citation omitted). In its
    consideration of the emission limit as reasonable progress, EPA disregarded the
    State’s visibility modeling and instead evaluated the emission limit against the four
    statutory factors for reasonable progress. See 
    77 Fed. Reg. 20,937
    . In the Proposed
    Rule, EPA acknowledged that ASOFA was estimated to reduce emissions by
    approximately 40%, see 
    76 Fed. Reg. 58,626
    , but also acknowledged that the
    emission limit established for the Coyote Station was estimated to reduce emissions
    by approximately 32%, see 
    76 Fed. Reg. 58,628
    . Furthermore, OFA technology
    might well be considered cost effective in light of EPA’s conclusion that the more
    advanced version of the technology ASOFA was cost effective. Thus, although
    EPA’s decision in this instance is not a model of clarity, we nonetheless can discern
    its path.
    Because the Environmental Groups have failed to demonstrate that EPA’s
    approval of the 0.50 lb/MMBtu emission limit as reasonable progress for the Coyote
    Station was arbitrary, capricious, or an abuse of discretion, their petition for review
    of this issue is denied.
    F. Milton R. Young and Leland Olds Stations
    The Environmental Groups contend that EPA’s approval of the State’s BART
    determinations for Milton R. Young Station Units 1 and 2 and Leland Olds Station
    -26-
    Unit 2 was arbitrary, capricious, and an abuse of discretion because it violated
    applicable notice and comments requirements and failed to provide a rational basis
    for EPA’s change of position from the Proposed Rule to the Final Rule.3
    The State determined during its evaluation of its regional haze obligations that
    these three units were subject to the BART requirements of § 169A. As discussed
    above, the second step in the BART Guidelines evaluation process involves the
    elimination of technically infeasible control technologies. See 
    70 Fed. Reg. 39,164
    .
    When the State conducted its BART analysis for each of these units, it eliminated
    selective catalytic reduction (SCR) as a potential control technology, concluding that
    SCR was not technically feasible for a unit that burned lignite coal in a cyclone
    boiler. The State thus concluded that BART for these units was SNCR.
    Contemporaneously, the State was also determining the best available control
    technology (BACT) for Young Station Units 1 and 2 pursuant to a consent decree
    entered into between the owner of the station, the State, and EPA under the CAA’s
    Prevention of Significant Deterioration program. The consent decree gave the State
    the initial responsibility of determining BACT and gave EPA the authority to
    challenge that determination in the district court if it believed that it was
    unreasonable. BART and BACT both involve the elimination of technically
    infeasible control options, using substantially the same criteria. See 
    77 Fed. Reg. 20,897
    . In its BACT analysis, the State similarly concluded that SCR was technically
    infeasible because of the type of coal and type of boiler at issue and instead selected
    SNCR as BACT. EPA promptly challenged the State’s BACT determination in
    district court, contending that SCR was a technically feasible emission control and
    should have been selected as BACT.
    3
    Young Station Units 1 and 2 and Olds Station Unit 2 each generate electricity
    by burning North Dakota lignite coal in Babcock & Wilcox cyclone boilers. Because
    each of these units operates the same type of boiler and burns the same type of coal,
    the technical feasibility determination required under the BART Guidelines will be
    the same for each unit. They are thus addressed together.
    -27-
    While EPA’s petition challenging the State’s BACT determination was
    pending, it proposed to disapprove the State’s regional haze SIP, determining that
    BART for Young Station Units 1 and 2 and Olds Station Unit 2 was SNCR. The
    basis for EPA’s proposed disapproval of the SIP mirrored its position in its petition
    challenging the State’s BACT determination, namely, its belief that SCR was
    technically feasible and that the State’s determination that it was not technically
    feasible was unreasonable. EPA acknowledged the district court proceeding in the
    Proposed Rule, stating that its “proposed action here pertains to BART, not BACT,
    is governed by CAA provisions and regulations specific to regional haze and BART,
    and is not governed by [the] consent decree.” 
    76 Fed. Reg. 58,604
     n.41. EPA
    simultaneously proposed to promulgate a FIP finding that SCR was BART for these
    units. On December 21, 2011, after the notice and comment period for the Proposed
    Rule had closed, the district court issued its decision on EPA’s petition challenging
    the State’s BACT determination. The district court found that the State’s conclusion
    that SCR was not technically feasible was not unreasonable. See Minnkota Power
    Co-op., 831 F. Supp. 2d at 1127-30.
    Rather than disapproving the State’s determination that SNCR was BART for
    Young Station Units 1 and 2 and Olds Station Unit 2 and promulgating its own FIP,
    EPA’s Final Rule approved the State’s SIP. In explaining its decision, EPA found
    two portions of the BART Guidelines relevant. First, EPA noted that the technical
    feasibility determination under the BART and BACT analyses was substantially the
    same. See 
    77 Fed. Reg. 20,897
    . Second, EPA noted that the BART Guidelines
    permit a state to rely upon a BACT determination for purposes of selecting BART,
    unless new technologies have become available or best control levels for recent
    retrofits have become more stringent. See 
    id.
     EPA then acknowledged that over its
    “vigorous challenge of the information and analysis relied upon by North Dakota, the
    U.S. District Court upheld North Dakota’s recent BACT determination based on the
    same technical feasibility criteria that apply in the BART context.” 
    Id. at 20,897-98
    .
    EPA concluded that “[i]n light of the court’s decision and the views we have
    -28-
    expressed in our BART guidelines, we have concluded that it would be inappropriate
    to proceed with our proposed disapproval of SNCR as BART[.]” 
    Id. at 20,898
    .
    Accordingly, EPA approved the State’s SIP addressing the BART determinations for
    Young Station Units 1 and 2 and Olds Station Unit 2.
    Thereafter, the Environmental Groups filed this petition for review, while
    simultaneously filing a petition for reconsideration with EPA. On November 19,
    2012, after all of the petitioners had filed their initial briefs, EPA granted the
    Environmental Groups’ petition for reconsideration, a process that is still ongoing.
    On February 8, 2013, after briefing in the present case was completed, the
    Environmental Groups moved under Federal Rule of Appellate Procedure 42(b) to
    voluntarily dismiss their petition to the extent it challenges EPA’s approval of the
    State’s BART determination for Young Station Units 1 and 2 and Olds Station Unit 2.
    “[T]he procedural requirements of the Clean Air Act do not permit [petitioners]
    to raise . . . objection[s] for the first time on appeal.” Appalachian Power Co. v. EPA
    (Appalachian Power II), 
    249 F.3d 1032
    , 1055 (D.C. Cir. 2001) (first two alterations
    in original) (quoting Am. Petroleum Inst. v. Costle, 
    665 F.2d 1176
    , 1190-91 (D.C.
    Cir. 1981)). “Only an objection to a rule or procedure which was raised with
    reasonable specificity during the period for public comment . . . may be raised during
    judicial review.” 
    42 U.S.C. § 7607
    (d)(7)(B). Section 7607(d)(7)(B) is “a
    jurisdictional administrative exhaustion requirement,” Noel Canning v. NLRB, 
    705 F.3d 490
    , 497 (D.C. Cir. 2013), which courts are to strictly enforce, Natural Res. Def.
    Council, 
    571 F.3d at 1259
    . “The purpose of the exhaustion requirement is to ensure
    that the agency is given the first opportunity to bring its expertise to bear on the
    resolution of a challenge to a rule.” Appalachian Power I, 
    135 F.3d at 818
    .
    “Consequently, the court enjoys the benefit of the agency’s expertise and possibly
    avoids addressing some of the challenges unnecessarily.” Motor & Equip. Mfrs.
    Ass’n v. Nichols, 
    142 F.3d 449
    , 462 (D.C. Cir. 1998).
    -29-
    EPA contends that the Environmental Groups’ challenges to the approval of
    these BART determinations are not properly before us because they are being raised
    for the first time on appeal. The Environmental Groups acknowledge that because
    they had no notice that EPA was considering approving the BART determinations
    prior to publication of the Final Rule they did not raise a challenge to EPA’s approval
    during the rulemaking process. In such circumstances, “the CAA requires a petitioner
    to first raise its objection to the agency th[r]ough a petition for reconsideration.”
    Oklahoma v. EPA, 
    2013 WL 3766986
    , at *11 (alteration in original) (quoting
    Appalachian Power II, 
    249 F.3d at 1065
    ). The Environmental Groups have done just
    that, filing a petition for reconsideration that is still under consideration.
    Notwithstanding the Environmental Groups’ failure to raise these objections
    during the rulemaking process, Intervenors Minnkota Power Cooperative, Inc. and
    Square Butte Electric Cooperative argue that § 7607(d)(7)(B) does not deprive us of
    jurisdiction. Intervenors contend that because § 7607(d)(7)(B) permits courts to stay
    the effectiveness of a final rule during reconsideration, it “expressly contemplates that
    a reviewing court retains subject matter jurisdiction over the claims during the
    pendency of EPA reconsideration.” Intervenors Minnkota & Square Butte Br. 52
    (citing § 7607(d)(7)(B) (“Such reconsideration shall not postpone the effectiveness
    of the rule. The effectiveness of the rule may be stayed during such reconsideration,
    however, by . . . the court for a period not to exceed three months.”)). Intervenors are
    incorrect that this section contemplates that we retain jurisdiction to hear unexhausted
    claims. Rather, it establishes that we retain jurisdiction over the entire final rule
    pending the reconsideration of unexhausted claims, and thus have the authority to
    postpone the effectiveness of the entire final rule.
    Because the Environmental Groups’ challenges to EPA’s approval of the
    State’s BART determination for Young Station Units 1 and 2 and Olds Station Unit
    2 were not raised before EPA during the rulemaking process, we conclude that we are
    without jurisdiction to hear them under § 7607(d)(7)(B). This conclusion renders
    -30-
    moot the Environmental Groups’ motion to dismiss their petition for review of these
    matters under Federal Rule of Appellate Procedure 42(b).
    H. Interstate Transport SIP
    The State contends that EPA’s disapproval of its interstate transport SIP was
    arbitrary, capricious, and an abuse of discretion. In July 1997, EPA promulgated new
    NAAQS, which triggered the State’s obligation to submit an interstate transport SIP
    addressing the new standards. As discussed above, one of the elements of this SIP
    is the “good neighbor” provision, which contains a visibility component. See 
    42 U.S.C. § 7410
    (a)(2)(D)(i)(II). In 2006, EPA issued guidance to the states on
    satisfying the good neighbor provision. See Environmental Protection Agency,
    Guidance for State Implementation Plan Submissions to Meet Current Outstanding
    Obligations Under Section 110(a)(2)(D)(i) for the 8-Hour Ozone and PM 2.5 National
    Ambient Air Quality Standards (2006) [hereinafter 2006 Guidance].
    The first paragraph of the 2006 Guidance “emphasizes that this guidance
    document merely provides suggestions and . . . EPA may elect to follow or deviate
    from this guidance, as appropriate.” See 
    id. at 1
    . Regarding the visibility component
    of the good neighbor provision, the 2006 Guidance recognized that because states’
    regional haze SIPs were not due until December 17, 2007, it was “currently
    premature” to determine whether a state’s SIP complies with the good neighbor
    provision. 
    Id. at 9-10
    . Therefore, the 2006 Guidance suggested “that States may
    make a simple SIP submission confirming that it is not possible at this time to assess
    whether there is any interference with measures in the applicable SIP for another
    State designed to ‘protect visibility’ for the 8-hour ozone or PM 2.5 NAAQS until
    regional haze SIPs are submitted and approved.” 
    Id.
     “Thus, EPA’s recommendation
    to states as of that particular point in time was that they refer to the imminent regional
    haze SIP submission as the means by which they could address the visibility prong
    of [§ 7410(a)(2)(D)(i)].” 
    76 Fed. Reg. 58,642
    .
    -31-
    On April 6, 2009, the State submitted a SIP revision designed to satisfy its
    interstate transport requirements under the CAA. The State did not substantively
    address the visibility component, but instead referred to the 2006 Guidance and
    included a placeholder submission, stating that until regional haze SIPs were
    submitted, it was not possible to assess whether there is any interference with
    measures in another state’s applicable regional haze SIP. The State thus suggested
    that it planned to satisfy the visibility component through the submission of its
    regional haze SIP, which it submitted on March 3, 2010.
    EPA reviewed the State’s interstate transport SIP in 2011 and approved three
    of the four components, but disapproved the visibility component. EPA rejected the
    State’s use of the placeholder submission suggested in the 2006 Guidance and found
    that the SIP had failed to address substantively the visibility prong. EPA also
    concluded that the regional haze SIP could not be used to satisfy the visibility
    component because it was not fully approvable. See 
    76 Fed. Reg. 58,642
    . To address
    the visibility component, EPA proposed to promulgate a FIP. The FIP concluded that
    the visibility component would be satisfied by relying on a combination of the
    portions of the State’s regional haze SIP that had been approved and the FIP
    promulgated to replace the disapproved portions of the regional haze SIP.
    The State first contends that EPA acted arbitrarily by not following its 2006
    Guidance and refusing to accept its placeholder submission for the visibility
    component. We disagree, for the 2006 Guidance clearly placed the State on notice
    that EPA was not issuing binding regulations but was instead only issuing
    suggestions that left EPA free “to follow or deviate from this guidance, as
    appropriate.” 2006 Guidance at 1. Moreover, the 2006 Guidance suggested that it
    was “currently premature” to require a submission addressing visibility prior to the
    2007 deadline for regional haze SIP submissions. This demonstrates that the 2006
    Guidance contained time-sensitive suggestions. It is undisputed that the State did not
    submit its interstate transport SIP until 2009, well after the period discussed in the
    -32-
    2006 Guidance. Given the disclaimer within the 2006 Guidance that EPA was free
    to deviate from it, as well as the time frame during which it was issued—prior to the
    deadline for submitting regional haze SIPs—the State has failed to demonstrate that
    EPA’s refusal to accept the State’s placeholder statement regarding the visibility
    component was arbitrary, capricious, or an abuse of discretion.
    The State argues in the alternative that its submission of the regional haze SIP
    satisfied the visibility component of the interstate transport SIP. EPA concluded,
    however, that because the regional haze SIP was not fully approvable, it could not
    satisfy the visibility component of the interstate transport SIP. The State does not
    challenge EPA’s authority to disapprove the interstate transport SIP on this basis.
    Rather, it contends that because the regional haze SIP should have been approved as
    to all portions, it should have satisfied the visibility component in its interstate
    transport SIP. See State’s Reply Br. 36 (“Because EPA’s disapproval of North
    Dakota’s [Coal Creek Station] BART determination and [Antelope Valley Station
    reasonable progress] determinations were arbitrary and capricious, so too is EPA’s
    disapproval of North Dakota’s SIP as it pertains to interstate visibility.”). Because
    we have concluded that EPA properly disapproved portions of the State’s regional
    haze SIP, the State’s argument on this issue fails, and thus the State’s petition for
    review of EPA’s disapproval of the State’s interstate transport SIP is denied.
    III. Conclusion
    We grant the State’s and Great River Energy’s petitions for review to the extent
    that they challenge EPA’s BART determination for the Coal Creek Station
    promulgated in EPA’s FIP, and we vacate and remand that portion of the Final Rule
    to EPA for further proceedings consistent with this opinion. We deny the remainder
    of the State’s, Great River Energy’s, and the Environmental Groups’ petitions for
    review, as well as the Environmental Groups’ motion for voluntary dismissal under
    Federal Rule of Appellate Procedure 42(b).
    ____________________________
    -33-
    

Document Info

Docket Number: 12-1844, 12-1961, 12-2331

Citation Numbers: 730 F.3d 750

Judges: Murphy, Smith, Wollman

Filed Date: 9/23/2013

Precedential Status: Precedential

Modified Date: 8/7/2023

Authorities (21)

chevron-u-s-a-inc-v-united-states-environmental-protection-agency , 658 F.2d 271 ( 1981 )

state-of-louisiana-ex-rel-william-j-guste-jr-and-concerned-shrimpers , 853 F.2d 322 ( 1988 )

motor-equipment-manufacturers-association-v-mary-d-nichols-assistant , 142 F.3d 449 ( 1998 )

baptist-health-doing-business-as-baptist-memorial-medical-center-north , 458 F.3d 768 ( 2006 )

james-lockhart-gemma-lockhart-sandra-reub-american-indians-against , 927 F.2d 1028 ( 1991 )

friends-of-the-boundary-waters-wilderness-wilderness-watch-sawbill , 164 F.3d 1115 ( 1999 )

american-petroleum-institute-v-douglas-m-costle-administrator-and , 665 F.2d 1176 ( 1981 )

Natural Resources Defense Council v. Environmental ... , 571 F.3d 1245 ( 2009 )

Nixon v. Missouri Municipal League , 124 S. Ct. 1555 ( 2004 )

American Corn Growers Association v. Environmental ... , 291 F.3d 1 ( 2002 )

State of New York v. Environmental Protection Agency, Clean ... , 443 F.3d 880 ( 2006 )

American Trucking Associations v. Environmental Protection ... , 600 F.3d 624 ( 2010 )

appalachian-power-company-v-environmental-protection-agency-commonwealth , 249 F.3d 1032 ( 2001 )

Appalachian Power Company v. Environmental Protection ... , 135 F.3d 791 ( 1998 )

Harrison v. PPG Industries, Inc. , 100 S. Ct. 1889 ( 1980 )

Marsh v. Oregon Natural Resources Council , 109 S. Ct. 1851 ( 1989 )

Alaska Department of Environmental Conservation v. ... , 124 S. Ct. 983 ( 2004 )

Norfolk Southern Railway Co. v. James N. Kirby, Pty Ltd. , 125 S. Ct. 385 ( 2004 )

Gross v. FBL Financial Services, Inc. , 129 S. Ct. 2343 ( 2009 )

Hardt v. Reliance Standard Life Insurance , 130 S. Ct. 2149 ( 2010 )

View All Authorities »