Sunbelt Chlor Alkali Partnership v. Surface Transportation Board ( 2018 )


Menu:
  •          Case: 16-15701   Date Filed: 01/26/2018   Page: 1 of 8
    [DO NOT PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________
    No. 16-15701
    ________________________
    Agency No. 42130
    SUNBELT CHLOR ALKALI PARTNERSHIP,
    Petitioner,
    versus
    SURFACE TRANSPORTATION BOARD,
    UNITED STATES OF AMERICA,
    Respondents,
    NORFOLK SOUTHERN RAILWAY COMPANY,
    Intervenor.
    ________________________
    Petition for Review of a Decision of the
    Surface Transportation Board
    ________________________
    (January 26, 2018)
    Case: 16-15701      Date Filed: 01/26/2018   Page: 2 of 8
    Before WILLIAM PRYOR, JILL PRYOR and ANDERSON, Circuit Judges.
    PER CURIAM:
    Sunbelt Chlor Alkali Partnership petitions for review of the Surface
    Transportation Board’s decision that the rate Norfolk Southern Railway Company
    charges Sunbelt is reasonable. After careful review and with the benefit of oral
    argument, we deny the petition for review.
    I.      BACKGROUND
    Sunbelt manufactures chlorine in its plant in McIntosh, Alabama and ships
    its product by rail from the plant to LaPorte, Texas. For the first leg of the route,
    from McIntosh to New Orleans, Louisiana, Norfolk Southern is the only available
    rail service provider. In July 2011, Sunbelt filed a complaint before the Board
    challenging as unreasonable the rate for this leg of the route. To support its claim,
    Sunbelt used the Board’s stand-alone cost (“SAC”) test, which requires the
    complaining shipper to create a hypothetical, stand-alone railroad (“SARR”).
    Under the SAC test, if the existing railroad’s challenged rate exceeds the amount
    the SARR would need to charge to serve the shipper, cover the SARR’s costs, and
    earn a reasonable return on investment, the rate is unreasonable.
    As required by the SAC test, in its opening evidence Sunbelt proposed a
    SARR along with a detailed operating plan, which it contended showed that
    Norfolk Southern’s rate was unreasonable. Relevant here, Sunbelt’s plan proposed
    2
    Case: 16-15701    Date Filed: 01/26/2018   Page: 3 of 8
    a hub at Birmingham, which lies between McIntosh and New Orleans. At the
    Birmingham hub, Sunbelt chose not to include a hump yard, which would be more
    expensive to construct but more efficient at managing high rail car traffic. Sunbelt
    also proposed that the SARR would amortize its debt by making quarterly interest-
    only payments (“coupon method”).
    In response, Norfolk Southern submitted its own operating plan for the
    SARR, which it contended showed that the rate it charged Sunbelt was reasonable.
    Notably, that plan included a hump yard at Birmingham to manage traffic. Norfolk
    Southern also proposed the standard debt amortization method under Board
    precedent, which would require the SARR to pay down its debt gradually over
    time, similar to payments on a mortgage. By including the Birmingham hump yard
    and having the SARR pay both interest and principal on its debt, Norfolk
    Southern’s proposal was considerably more expensive than Sunbelt’s. On rebuttal,
    Sunbelt continued to maintain that a hump yard at Birmingham was unnecessary
    and that it had properly accounted for the SARR’s expenses regarding its debt.
    Evaluating the parties’ competing proposals, the Board determined, and
    Sunbelt does not challenge here, that the SARR needed a hump yard at
    Birmingham to serve the traffic. The Board explained that this “major design
    flaw” rendered Sunbelt’s plan infeasible: therefore, the Board accepted Norfolk
    3
    Case: 16-15701        Date Filed: 01/26/2018        Page: 4 of 8
    Southern’s operating plan. Decision at 13 (JA 1036).1 Additionally, the Board
    rejected Sunbelt’s method of debt amortization as inconsistent with the SAC test,
    adopting Norfolk Southern’s proposal instead. After conducting the SAC analysis
    using Norfolk Southern’s operating plan and debt amortization method, the Board
    concluded that Sunbelt had failed to demonstrate that the rate Norfolk Southern
    charged was unreasonable.
    Sunbelt petitioned the Board for reconsideration. Sunbelt argued that once
    the Board determined a hump yard was necessary, the Board should have
    incorporated a hump yard into Sunbelt’s operating plan, rather than accepting
    Norfolk Southern’s plan. Sunbelt also argued that the Board erred in rejecting
    Sunbelt’s use of the coupon method to amortize its debt. The Board rejected
    Sunbelt’s arguments.
    Sunbelt now petitions this Court for review of the Board’s order.
    II.    STANDARD OF REVIEW
    The Administrative Procedure Act requires federal courts to “hold unlawful
    and set aside agency action, findings, and conclusions” that are “arbitrary,
    capricious, an abuse of discretion, or otherwise not in accordance with law.”
    5 U.S.C. § 706(2)(A). To make this determination, courts must “consider whether
    the decision was based on a consideration of the relevant factors and whether there
    1
    Citations to material in the administrative record are to the joint appendix filed in this
    Court.
    4
    Case: 16-15701       Date Filed: 01/26/2018   Page: 5 of 8
    has been a clear error of judgment.” N. Buckhead Civic Ass’n v. Skinner, 
    903 F.2d 1533
    , 1538 (11th Cir. 1990) (internal quotation marks omitted).
    III.    DISCUSSION
    The Board regulates the rates charged by interstate railroads. See BNSF Ry.
    Co. v. Surface Transp. Bd., 
    526 F.3d 770
    , 773 (D.C. Cir. 2008). When a single
    railroad exercises “market dominance,” meaning there is an “absence of effective
    competition from other rail carriers or modes of transportation” in the relevant
    market, a party may bring a complaint before the Board challenging the railroad’s
    rate. 49 U.S.C. §§ 10701(d)(1), 10707(a)-(b). The Board then determines whether
    the rate charged by the railroad is reasonable.
    Here, the parties agree that Norfolk Southern exercised market dominance
    for the route from McIntosh to New Orleans, meaning the Board had the authority
    to review Sunbelt’s challenge to the rate for this route. The parties disagree over
    the Board’s determination that Norfolk Southern’s rate was reasonable.
    Sunbelt argues that the Board’s decision was arbitrary and capricious for two
    reasons. First, it argues that the Board should have inserted Norfolk Southern’s
    hump yard into Sunbelt’s proposed plan, creating a hybrid plan, rather than
    accepting Norfolk Southern’s plan. Second, it argues that the Board erred in
    accepting Norfolk Southern’s method for debt amortization over Sunbelt’s. We
    address these arguments in turn.
    5
    Case: 16-15701       Date Filed: 01/26/2018      Page: 6 of 8
    A.     The Hump Yard
    Sunbelt argues that once the Board determined that a hump yard was
    necessary at Birmingham, it should have substituted a hump yard for the flat yard
    in Sunbelt’s operating plan, instead of accepting Norfolk Southern’s plan. We
    disagree.
    After Norfolk Southern proposed the hump yard in its operating plan,
    Sunbelt could have modified its own plan to include a hump yard. Instead, in its
    rebuttal brief, Sunbelt continued to oppose the addition of a hump yard. It was
    only in its petition for reconsideration, after the Board’s decision in Norfolk
    Southern’s favor, that Sunbelt for the first time argued that the Board should create
    a hybrid plan. But as the Board explained in its decision denying reconsideration,
    the Birmingham hump yard was the “keystone to the entire system’s
    functionality,” so the Board could not “simply try to stitch [Norfolk Southern’s]
    hump yard onto Sunbelt’s operating plan . . . without requiring additional changes
    to evidence that the Board was not in a position to make.” Recons. Decision at 4-5
    (JA 1340-41). Indeed, doing so would have required the Board to assess
    independently the hump yard’s impact on the complex Rail Traffic Controller
    (“RTC”) model,2 as well as the added costs to the operating plan.
    2
    The RTC is a computer program that tests the feasibility of the infrastructure in the
    operating plan. As the Board has explained, the RTC “provides essential evidence to support a
    6
    Case: 16-15701       Date Filed: 01/26/2018      Page: 7 of 8
    We agree with the Board that, after making the tactical choice to oppose the
    addition of a hump yard until its petition for reconsideration, “Sunbelt may not
    now claim error” based on the Board’s failure to incorporate a hump yard into
    Sunbelt’s SARR. 
    Id. at 6
    (JA 1342). Although we agree with Sunbelt that the
    Board is more than a passive arbiter, it is not required “to identify alternatives that
    parties did not identify, particularly when . . . the effect of those changes is
    unclear.” 
    Id. at 6
    -7 (JA 1342-43). Therefore, we cannot say that the Board’s
    decision to reject Sunbelt’s proposal on reconsideration to incorporate a hump yard
    into Sunbelt’s operating plan was arbitrary or capricious.
    B.     Debt Amortization
    Sunbelt also argues that the Board erred in adopting Norfolk Southern’s
    proposal for debt amortization. Again, we disagree. The parties proposed different
    plans for paying off the SARR’s debt. Sunbelt proposed the coupon method, under
    which the SARR would make interest-only payments and then take on new debt as
    the principal became due. Norfolk Southern, by contrast, proposed that the SARR
    would pay off the principal gradually over time, along with decreasing interest
    payments. The Board selected Norfolk Southern’s proposal, determining that
    Sunbelt’s coupon method would allow the SARR to avoid paying for its assets in
    SARR’s configuration and certain broader operating statistics.” Recons. Decision at 5 (JA
    1341).
    7
    Case: 16-15701     Date Filed: 01/26/2018   Page: 8 of 8
    violation of the SAC test, which assesses “whether the SARR can pay the cost of
    constructing, maintaining and operating its system.” Decision at 191 (JA 1214).
    According to the Board, Norfolk Southern’s proposal was consistent “with long-
    standing policy.” Recons. Decision at 10 (JA 1346).
    Sunbelt argues that it was arbitrary and capricious for the Board to reject its
    plan for interest-only debt amortization in favor of Norfolk Southern’s mortgage-
    style proposal because requiring the SARR to pay its principal constitutes a barrier
    to entry—which “must be omitted from the SAC analysis”—because existing
    railroads use the coupon method. Decision at 5 (JA 1028). As the Board noted,
    however, allowing the SARR to pay only interest would “abandon the fundamental
    structure of the SAC test.” 
    Id. at 191
    (JA 1214). Furthermore, under “Board
    precedent . . . the SARR’s debt payments contain an interest component and a
    principal component, and the interest portion decreases as the debt is amortized
    over time.” 
    Id. Sunbelt points
    to no case where the Board applied a different debt
    amortization method than the one Norfolk Southern proposed. We therefore
    cannot conclude that the Board’s decision to apply that method here was arbitrary
    and capricious.
    IV.   CONCLUSION
    For the reasons set forth above, we deny Sunbelt’s petition for review.
    DENIED.