PSC Custom, LP v. United Steel, Paper and Forestry, Rubber, Manufacturing, Energy, Allied Industrial and Service Workers International Union, Local No. 11-770 , 756 F.3d 627 ( 2014 )


Menu:
  •                  United States Court of Appeals
    For the Eighth Circuit
    ___________________________
    No. 13-1943
    ___________________________
    PSC Custom, LP, doing business as Polar Tank Trailers
    lllllllllllllllllllll Plaintiff - Appellant
    v.
    United Steel, Paper and Forestry, Rubber, Manufacturing, Energy, Allied
    Industrial and Service Workers International Union, Local No. 11-770
    lllllllllllllllllllll Defendant - Appellee
    ____________
    Appeal from United States District Court
    for the Western District of Missouri - Springfield
    ____________
    Submitted: February 13, 2014
    Filed: June 26, 2014
    ____________
    Before RILEY, Chief Judge, LOKEN and BYE, Circuit Judges.
    ____________
    LOKEN, Circuit Judge.
    PSC Custom, LP, doing business as Polar Tank Trailers (“Polar Tank”),
    manufactures tank trailers at its Springfield, Missouri facility. At the time in
    question, employees were governed by a Collective Bargaining Agreement (“CBA”)
    between Polar Tank and United Steelworkers Local No. 11-770 (the “Union”). In
    June 2011, Polar Tank discharged maintenance technician Bonita Symons for failing
    to safely complete repair of an overhead crane. The Union grieved the discharge, and
    the unresolved grievance was submitted to arbitration. The arbitrator partially upheld
    the grievance, reducing Symons’s discipline to a thirty-day unpaid suspension. Polar
    Tank sued to vacate the arbitration award. The Union counterclaimed to enforce it.
    The district court1 granted summary judgment enforcing the award. Polar Tank
    appeals, arguing the arbitrator’s ruling was contrary to unambiguous provisions of the
    CBA that mandated discharge and is therefore unenforceable. The arbitrator’s
    findings of fact are not at issue. Reviewing the district court’s decision de novo and
    the arbitrator’s award under the deferential standard of review mandated by the
    Supreme Court, we affirm.
    I.
    Polar Tank’s facility uses a ceiling-based crane system that runs the length of
    the production area. The cranes are mounted on twin rails, more than twenty feet
    above the floor. A set of gears are used in moving cranes along each rail. Both sets
    of gears must be in good working order or the crane will not move smoothly along
    the rails. On June 10, 2011, the manufacturing engineering manager learned that one
    crane was not running smoothly and instructed Symons to investigate and repair the
    problem, using a “scissors lift” to access the gears. Near the end of her shift, Symons
    reported that she had repaired the north-rail side of the crane by installing a new gear,
    because the old gear had dislodged entirely, and that she had checked the south-rail
    side of the crane and found it tight and in good working condition. Symons also told
    Keith Fowler, a maintenance technician on the next shift, that she had not found the
    lost north-rail gear, a serious safety issue because a lost gear could fall from the rail
    and injure someone or, worse yet, cause the crane to derail. Fowler shut down the
    1
    The Honorable Matt J. Whitworth, United States Magistrate Judge for the
    Western District of Missouri, presiding with consent of the parties pursuant to 28
    U.S.C. § 636(c)(1).
    -2-
    crane to look for the gear. Technician John Brannon went up in the scissors lift and
    quickly found the lost gear in plain sight on the rail frame less than twenty feet from
    where Symons had performed the north-side repair. Brannon also checked the south-
    rail side and found the gear “finger loose.” The Allen key sockets were packed with
    grease, suggesting that Symons had not accessed the gear to check if it was loose.
    After interviewing Symons and those involved in the incident (along with the
    Union’s president), Polar Tank’s Human Relations Manager, Larry LaForge,
    discharged Symons on June 21 based on the crane repair incident. LaForge’s
    Discipline Report listed as the reasons for discharge:
    1. Clear failure [to] properly do an inspection that could have resulted
    in serious, possibly fatal, accident.
    2. Clear disregard for doing the job. By not locating the loose gear
    lying on the track a serious accident could have happened if it would
    have been thrown off, or the crane derailed.
    3. Passive attitude about avoiding assignments by any means available.
    Wasting time, not asking for direction.
    Article 21 of the CBA provided: “No employee shall be discharged, demoted,
    or otherwise disciplined without good and sufficient cause.” “Should there be any
    dispute between the Company and the Union concerning the existence of good and
    sufficient cause for discharge . . . such dispute shall be adjusted in accordance with
    the Grievance and Arbitration provisions.” The Union grieved Symons’s discharge
    under the grievance and arbitration provisions in Article 6 of the CBA. When the
    grievance could not be resolved, the parties submitted the dispute to arbitration. As
    is typical, Article 6 provided that arbitration awards are “final and binding on the
    Company, the Union and the employee(s),” and it limited the arbitrator’s authority by
    prohibiting him from adding to, disregarding, or altering the terms of the CBA. The
    -3-
    parties submitted the following issues to the arbitrator: “1. Did the Company have
    good and sufficient cause or just cause to discharge [Symons] on June 21, 2011? 2.
    If not, what shall the remedy be?”
    At the lengthy arbitration hearing, LaForge explained his discharge decision,
    testifying that Symons’s misconduct in failing to properly repair the crane violated
    five standards of employee behavior enumerated in Part B of the Standards of
    Conduct Polar Tank had adopted and publicized prior to the effective date of the CBA
    -- insubordination, careless or poor workmanship, continued unsatisfactory
    performance of work duties, violation of safety rules, and providing false information
    to the company. Part B provides that violation of its standards “is considered
    grievous and will result in immediate termination.” On cross examination, LaForge
    admitted that he did not refer to these violations in the termination “paperwork.”
    The arbitrator issued a written decision upholding the grievance in part. Citing
    due process concerns, the arbitrator limited his consideration of just cause to the
    grounds for discipline stated at the time Symons was disciplined, which did not
    include a reference to the Standards of Conduct. The arbitrator accepted Polar Tank’s
    version of the facts underlying the crane repair incident and ruled that Symons had
    “engage[d] in negligence involving safety issues [that put] her Company job and
    potentially her fellow employees in serious jeopardy.” However, the arbitrator
    concluded, Symons’s conduct did not rise to the level of insubordination because it
    amounted to simple negligence rather than “willful or deliberate defiance of
    supervisory authority.” In the arbitrator’s view, “a disciplinary suspension for thirty
    work days . . . constitutes a legitimate balance between the importance of proper
    performance of those duties and the . . . non-showing of insubordination involved
    here.” Accordingly, Polar Tank did not have just cause to discharge Symons. The
    award ordered her reinstated with back pay “minus pay for the thirty work day
    disciplinary suspension ordered here.” This lawsuit followed.
    -4-
    II.
    Labor arbitration awards are entitled to substantial but not unlimited judicial
    deference. Although an arbitrator “may not ignore the plain language of the contract”
    or impose his own “notions of industrial justice,” we are bound to enforce an award
    if the arbitrator “is even arguably construing or applying the contract and acting
    within the scope of his authority.” United Paperworkers Int’l Union v. Misco, Inc.,
    
    484 U.S. 29
    , 38 (1987); see Major League Baseball Players Ass’n v. Garvey, 
    532 U.S. 504
    , 509 (2001). As has often been said, a labor arbitration award is legitimate “‘so
    long as it draws its essence from the collective bargaining agreement.’” Boehringer
    Ingelheim Vetmedica, Inc. v. United Food & Commercial Workers, Dist. Union Local
    Two, 
    739 F.3d 1136
    , 1140 (8th Cir. 2014), quoting United Steelworkers of Am. v.
    Enter. Wheel & Car Corp., 
    363 U.S. 593
    , 597 (1960). Applying this standard, the
    district court concluded that the award at issue drew its essence from the CBA and
    must be enforced. We agree.
    Polar Tank argues that the district court erred, and the arbitration award may
    not be enforced, because the arbitrator disregarded unambiguous provisions of the
    CBA and therefore the award reflects “the arbitrator’s own notions of industrial
    justice.” The principle is sound, but it is rarely breached by experienced labor
    arbitrators. (Here, Article 6 of the CBA required the parties to obtain a list of seven
    qualified arbitrators from the Federal Mediation and Conciliation Service. The
    arbitrator selected by the parties, Ronald Hoh, has been an arbitrator since 1980 and
    has multiple professional affiliations.)
    Polar Tank argues the arbitrator disregarded two provisions of the CBA that
    unambiguously mandated that Symons be discharged for the misconduct the arbitrator
    found she had committed. First, Article 29 of the CBA declared that “[a]ll rules of
    the Company now in force shall be observed by all employees.” The arbitrator failed
    to obey Article 29, Polar Tank asserts, because it prescribed the disciplinary penalties
    -5-
    for five enumerated violations, including, as relevant here, “Insubordination such as
    refusal to work on the job assigned . . . (penalty-discharge).” This contention is
    contrary to controlling Supreme Court decisions. The arbitrator did not ignore the
    “insubordination” mandate in Article 29. He carefully considered Symons’s poor
    performance and concluded that it constituted negligence but not the type of
    “insubordination” for which Article 29 mandated discharge. We are bound to enforce
    that decision “arguably construing or applying” Article 29 under Misco, Garvey, and
    other Supreme Court cases. An arbitrator “may not ignore the plain language of the
    contract; but . . . a court should not reject an award on the ground that the arbitrator
    misread the contract.” 
    Misco, 484 U.S. at 38
    . We add, though it is not necessary to
    our decision, that the need for this type of analysis in a just cause proceeding is hardly
    surprising given the ambiguity inherent in the term “insubordination.”2
    Second, Polar Tank argues that the arbitrator improperly ignored LaForge’s
    testimony that Symons violated five behavior standards for which discharge was
    mandated by Part B of Polar Tank’s Standards of Conduct. Polar Tank contends the
    arbitrator was wrong to disregard these Standards on the ground that they “were
    2
    Polar Tank relies on two prior Eighth Circuit decisions we conclude are
    distinguishable. In St. Louis Theatrical Co. v. St. Louis Theatrical Bhd. Local 6, the
    grievant violated a “No Strikes - No Lock Outs” CBA provision that declared: “Any
    employee violating this provision may be disciplined or discharged and shall have no
    recourse to any other provisions of this Agreement except as to the fact of
    participation.” Because of this limitation, we concluded that “the arbitrator has no
    authority to evaluate the propriety of the Company’s discipline.” 
    715 F.2d 405
    , 408
    (8th Cir. 1983). Article 29 of this CBA had no comparable limitation. In Northern
    States Power Co. v. I.B.E.W., Local 160, we vacated an award because the
    arbitrator’s finding that the company had “‘demonstrated justification’ for its decision
    to terminate” was a finding of “just cause” that precluded the arbitrator from ordering
    a different remedy. 
    711 F.3d 900
    , 903 (8th Cir. 2013). Here, the arbitrator found that
    Symons’s conduct was not insubordination that was governed by Article 29,
    proceeded to determine whether there was nonetheless just cause to discharge
    Symons, and explicitly found no just cause.
    -6-
    implemented unilaterally by the Company without agreement of the Union.” The
    Management Rights clause of the CBA, to which the Union agreed after the
    Standards were adopted, expressly gave Polar Tank the right to “make reasonable
    rules and regulations” and to suspend or discharge employees “for violation of such
    rules or other proper and just cause.” This contention has two fatal flaws. First, the
    reason the arbitrator gave for disregarding the Standards of Conduct was that “none
    of them was included or cited in grievant’s termination letter or in any other
    notification to the grievant.” Polar Tank asserts this statement was “contrary to the
    Record,” but it was based on the uncontroverted testimony of decision-maker
    LaForge. Polar Tank does not argue the arbitrator’s “due process” ruling was error
    that precludes enforcing the award, and rightly so. Even if we disagreed with the
    arbitrator’s notion of due process, “arbitrators have long been applying notions of
    ‘industrial due process’ to ‘just cause’ discharge cases.” Chauffeurs Local Union No.
    878 v. Coca-Cola Bottling Co., 
    613 F.2d 716
    , 719 (8th Cir.), cert. denied, 
    446 U.S. 988
    (1980); see 
    Misco, 484 U.S. at 39-40
    & n.8.
    Second, and more importantly, Polar Tank’s reliance on the Management
    Rights clause is contrary to controlling Eighth Circuit precedent that “differentiates
    between explicit contractual language and rules or policies promulgated under a
    general management rights clause.” 
    Boehringer, 739 F.3d at 1141
    , citing Trailmobile
    Trailer LLC v. Int’l Union of Elec. Workers, 
    223 F.3d 744
    , 748 (8th Cir. 2000).
    “Only when the union has unambiguously agreed to an exception to the just cause
    limitation, either in the CBA or in an agreement resolving a particular disciplinary
    situation, will the arbitrator be precluded from conducting the collectively bargained
    just cause analysis.” 
    Id. Thus, even
    though the CBA acknowledged Polar Tank’s
    right to adopt work rules, and the employees’ duty to observe those rules, “that does
    not include the right to renege on the collectively bargained agreement that the
    employer will only discharge an employee ‘for [good and sufficient] cause.’” 
    Id. Here, when
    Polar Tank submitted the issue of just cause to the arbitrator, “[i]t was for
    the arbitrator to harmonize any discordant provisions within the contract relating to
    -7-
    the discretionary authority granted management and the just-cause requirements
    limiting that authority.” 
    Trailmobile, 223 F.3d at 747
    . The arbitrator’s resolution of
    that often-difficult issue is what the parties agreed to in the CBA and therefore drew
    its essence from the CBA.
    For the foregoing reasons, the judgment of the district court enforcing the
    arbitration award is affirmed.
    ______________________________
    -8-