Walton General Cont. v. Chicago Forming Inc. , 111 F.3d 1376 ( 1997 )


Menu:
  •                         United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ___________
    No. 96-1028
    ___________
    Walton General Contractors,           *
    Inc./Malco Steel, Inc.,               *
    *
    Appellant,                 *
    *
    v.                               *
    *
    Chicago Forming, Inc.;                *
    Peerless Insurance Company,           *
    *
    Appellees.                 *
    _______________________________
    Chicago Forming, Inc.,                *
    *
    Third Party Plaintiff,           *   Appeals and Cross-Appeals
    *   from the United States
    v.                               *   District Court for the
    *   Western District of Missouri.
    United States Fidelity and            *
    Guaranty Company,                     *
    *
    Third Party Defendant.           *
    ___________
    No. 96-1324
    ___________
    Walton General Contractors,           *
    Inc./Malco Steel, Inc.,               *
    *
    Appellee,                  *
    *
    v.                               *
    *
    Chicago Forming, Inc.;                *
    *
    Appellant,                 *
    *
    Peerless Insurance Company,           *
    *
    Appellee.                  *
    _____________________________
    Chicago Forming, Inc.,                *
    *
    Third Party Plaintiff-Appellant,*
    *
    v.                               *
    *
    United States Fidelity and            *
    Guaranty Company,                     *
    *
    Third Party Defendant-Appellee. *
    ___________
    No. 96-1326
    ___________
    Walton General Contractors,       *
    Inc./Malco Steel, Inc.,               *
    *
    Appellee,                  *
    *
    v.                               *
    *
    Chicago Forming, Inc.,                *
    *
    Appellee,                  *
    *
    Peerless Insurance Company,           *
    *
    Appellant.                 *
    _______________________________
    Chicago Forming, Inc.,                *
    *
    Third Party Plaintiff,*
    *
    v.                               *
    *
    United States Fidelity and            *
    Guaranty Company,                     *
    *
    Third Party Defendant.*
    -2-
    ___________
    Submitted:   December 9, 1996
    Filed: April 22, 1997
    ___________
    Before WOLLMAN, BRIGHT and MURPHY, Circuit Judges.
    ___________
    BRIGHT, Circuit Judge.
    These appeals bring to this court a dispute between a contractor
    (Walton General Contractors, Inc./Malco Steel, Inc.), its subcontractor
    (Chicago Forming, Inc.), and the subcontractor’s surety (Peerless Insurance
    Company).      Initially, the contractor claimed that the subcontractor’s
    delayed and defective performance caused the general contractor damages in
    excess of the agreed amount remaining due and owing under the subcontract,
    $352,408.    The contractor sought a declaratory judgment determining its
    proper withholding under the subcontract and joined the subcontractor’s
    surety because the contractor’s claim exceeded the unpaid balance of the
    subcontract.    Subsequently, the subcontractor filed a counterclaim for the
    full subcontract balance of $352,408.
    A magistrate judge presided over the jury trial, resolved the post-
    trial motions and entered judgments regarding the controversy.                 The
    magistrate made the following awards:
    1.     According to the jury’s findings, the subcontract entitled the
    contractor     to   withhold   $233,629     for   damages   resulting   from   the
    subcontractor’s delayed and defective performance.           This award was less
    than the contractor initially claimed as damages.
    -3-
    2.    According to the jury’s findings, the subcontractor substantially
    performed the subcontract and, therefore, was entitled to the full $352,408
    subcontract   balance   subject    to   the    contractor’s   damages   withholding
    discussed in item 1 above.       The magistrate judge, therefore, ordered the
    contractor to pay the $118,779 difference between the two awards.
    3.     The magistrate judge granted the subcontractor prejudgment
    interest on $352,408 calculated from May 7, 1993, when the subcontractor
    demanded payment.
    4.    Although the subcontract included a provision entitling the
    prevailing party to attorneys’ fees, the magistrate judge denied both the
    contractor’s and the subcontractor’s motions for attorneys’ fees.
    5.    The magistrate judge dismissed the subcontractor’s surety from
    the damages portion of the trial because the contractor reduced its damages
    claim below the subcontract balance of $352,408 shortly before trial, but
    retained   jurisdiction   over    the   surety    for   purposes   of   determining
    attorneys’ fees.    After the trial, the magistrate judge awarded the surety
    $148,726.24 in attorneys’ fees against the subcontractor pursuant to their
    performance bond.
    The parties appealed from the judgments and awards, and raise the
    following issues for our review:
    1.    The contractor claims that the subcontractor was not entitled to
    credit for excusable delays during the subcontract performance and,
    consequently, the magistrate judge erred by admitting the subcontractor’s
    evidence of excusable delays.     We reject the contractor’s argument because
    the contractor introduced
    -4-
    evidence that the subcontractor caused the delays and, thereby, opened the
    door for the subcontractor to submit rebuttal evidence.
    2.     The   contractor   claims   that    the   magistrate   judge    erred    by
    instructing the jury on the issue of substantial performance on the
    subcontractor’s     counterclaim.       The    contractor     contends     that     the
    subcontractor offered insufficient evidence of substantial performance to
    warrant the instruction.       In addition, the contractor asserts that the
    instructions failed to inform the jury that the subcontractor could not
    substantially     perform   with   respect    to   the   subcontract’s     provisions
    requiring the subcontractor to provide a ten-day notice of excusable
    delays.    We reject both of these arguments and affirm the magistrate
    judge’s choice and form of jury instructions.
    3.    The contractor claims the subcontract entitled the contractor to
    judgment as a matter of law against the subcontractor on the counterclaim
    because the subcontract authorized the contractor to withhold funds, even
    excessive amounts, without breaching the terms of the subcontract.                   We
    reject this claim.     The parties’ pleadings and presentation of evidence
    required   the    jury’s    determination     on   the   appropriateness     of     the
    contractor’s withholding of payment and the amount to which the contractor
    could withhold.
    4.    The contractor disputes the award of prejudgment interest granted
    to the subcontractor.       We agree that the magistrate judge erroneously
    granted prejudgment interest to the subcontractor for the full amount of
    the subcontract balance without offsetting the contractor’s damages.
    -5-
    5.      The contractor and subcontractor appeal the magistrate judge’s
    denial of their motions for attorneys’ fees pursuant to the subcontract.
    We agree with the magistrate judge’s decision because both parties breached
    the subcontract and, therefore, the subcontract entitled neither party to
    recover attorneys’ fees.
    6.      The subcontractor claims that the magistrate judge erred by
    granting the surety attorneys’ fees without determining whether the fees
    were reasonable.     We reject this claim because the subcontractor fails to
    demonstrate that the magistrate judge abused his discretion.
    7.       The   surety   argues   that     the   contractor,   rather   than   the
    subcontractor, bears the liability for the surety’s attorneys’ fees
    according to the subcontract and because the contractor brought its claim
    against the surety in bad faith.      We conclude that the subcontract creates
    no obligation on the part of the contractor to reimburse the surety for its
    litigation costs and that the contractor brought its claim in good faith.
    Accordingly, we reject both of the surety’s arguments.
    8.      The surety claims that its performance bond agreement with the
    subcontractor entitles the surety to reimbursement of $20,000 it paid to
    settle a claim against the subcontractor by one of its suppliers.                  The
    contractor also claims that the subcontract entitles it to withhold $30,010
    until the subcontractor provides the requisite waiver from the supplier of
    its claim.    We remand both of these claims to the magistrate judge because
    the parties never raised them appropriately below.          The facts appear to be
    undisputed.
    Our discussion of each of these issues follows.
    -6-
    I.    BACKGROUND
    In 1992, Kansas City, Missouri entered into a construction contract
    with the contractor to build a convention center expansion.            The contractor
    then entered into a subcontract with the subcontractor for $1,560,000 to
    build four cement pylons used to support the roof of the convention center.
    The subcontract required the subcontractor to obtain a surety to issue a
    bond in the contractor’s favor guaranteeing the subcontractor’s performance
    and   payment   of    its    suppliers.     The   performance   bond    between   the
    subcontractor and surety incorporated the subcontract.
    During    the   construction     project,   the   contractor     believed   the
    subcontractor performed defective and untimely work.              The contractor,
    therefore, began withholding payments from the subcontractor and at the
    time of trial, $352,408 of the subcontract remained unpaid.            The contractor
    claimed it withheld $49,297 as retainage1 because the subcontractor had
    work to complete, defects in the subcontractor’s work placed the contractor
    at risk of further liability, and Kansas City had not accepted the work or
    paid the contractor.        The subcontract authorized the contractor to withhold
    as much as ten percent retainage from each progress payment.
    In addition to retainage, the contractor withheld $30,010 allegedly
    to protect itself from a potential claim for payment by one of the
    subcontractor’s suppliers (Continental Steel & Conveyor Company).                 The
    contractor believed the subcontractor did not pay the supplier.                   The
    subcontract authorized the contractor to
    1
    Retention is money withheld from payment until completion
    and acceptance of a construction project to insure that the
    subcontractor completes its work.
    -7-
    withhold payment until the subcontractor demonstrated that it paid all of
    its suppliers.     Sometime after the trial, the subcontractor’s surety paid
    the supplier $20,000 in settlement of its claim against the subcontractor.
    Finally, the contractor claimed it withheld $319,398 as compensation
    for damages resulting from the subcontractor’s breach of the subcontract.
    The contractor claimed the following amounts as damages:                   $151,102 due to
    the subcontractor’s deficient work, $45,624 caused by the subcontractor’s
    failure to perform work according to specifications, $51,087 of additional
    overtime costs, and $60,094 resulting from the subcontractor’s failure to
    perform in a timely manner.        Thus, the contractor claimed the subcontract
    entitled   it    to    withhold   the   entire      $352,408    subcontract    balance    as
    retainage, security for the supplier’s claim and compensation for damages.
    The     contractor      brought     this       diversity     action     against     the
    subcontractor and its surety, seeking a declaratory judgment that the
    subcontractor breached the subcontract, thereby entitling the contractor
    to $352,408 in damages.      This sum represents the full extent of the unpaid
    balance on the subcontract.         The contractor also sought attorneys’ fees
    from the subcontractor and the surety pursuant to the subcontract.                       The
    subcontractor filed a counterclaim against the contractor for payment of
    the $352,408 subcontract balance, additional damages and attorneys’ fees.
    Finally, the surety filed a cross-claim against the subcontractor for
    attorneys’      fees   pursuant    to   the     performance      bond   agreement   and   a
    counterclaim against the contractor for any of the subcontractor’s rights
    under the performance bond or the subcontract.                 All the parties agreed to
    have a magistrate judge preside over the litigation.
    -8-
    The subcontractor completed its portion of the construction by the
    time of trial, but the parties disputed the quality of the work.          The
    convention center construction as a whole, however, was not complete.
    Shortly before trial, the contractor reduced its claim for damages from
    $352,408 to $319,907.   Because the contractor claimed damages in an amount
    less than the remaining subcontract balance, the magistrate judge dismissed
    the surety from the liability portion of the lawsuit.          The magistrate
    judge, however, retained jurisdiction over the surety for purposes of
    assigning liability for costs, attorneys’ fees and expenses.     In addition,
    the magistrate judge limited the subcontractor’s damages to the $352,408
    remaining under the subcontract or less.       Finally, the parties agreed to
    submit the issue of attorneys’ fees to the magistrate judge’s discretion.
    The jury returned one verdict in favor of the contractor on its claim
    against the subcontractor for $233,629 in damages caused by delays and
    defects in the subcontractor’s work.     The jury returned another verdict for
    the subcontractor on its claim for payment against the contractor in the
    amount of $352,408.    This sum represented the undisputed amount remaining
    unpaid under the subcontract.      The magistrate judge also awarded the
    subcontractor prejudgment interest on the entire $352,408 subcontract
    balance.   The contractor filed motions for judgment as a matter of law and
    for a new trial, but the magistrate judge denied both motions.
    The subcontract entitled the “prevailing party” to recover attorneys’
    fees, costs and expenses.   The contractor sought $232,458.50 in attorneys’
    fees and $6,718.58 in expenses from the subcontractor and the surety.
    Likewise, the subcontractor sought approximately $155,000 in attorneys’
    fees and expenses from the contractor.       The magistrate judge denied both
    parties’ motions for
    -9-
    attorneys’ fees, but awarded the surety $148,726 in attorneys’ fees against
    the subcontractor.2
    II.   DISCUSSION
    This diversity case raises several issues that require us to apply
    Missouri’s substantive law “as we think the highest court of Missouri
    would.”    See Havens Steel Co. v. Randolph Eng’g Co., 
    813 F.2d 186
    , 188 (8th
    Cir. 1987).    We review the magistrate judge’s determination of state law
    and the application of that law to the facts de novo.   Salve Regina College
    v. Russell, 
    499 U.S. 225
    , 231 (1991).
    A.    Evidentiary Issues
    The subcontractor failed to timely complete its work, but introduced
    evidence that certain delays were excusable because of bad weather.      The
    contractor contends that the magistrate judge erroneously admitted the
    evidence.    According to the subcontract, “Any claims by Subcontractor for
    an extension of time to complete the Work must be submitted in writing for
    General Contractor’s consideration not more than ten (10) calendar days
    after commencement of the alleged cause of the delay or it will be forever
    waived.”    Appellant App. at 516 (containing subcontract).   The contractor
    contends that state courts strictly enforce contract provisions requiring
    notice even if such enforcement seems unconscionable.    Walton Br. at 22-23
    (citing Southwest Eng’g Co. v. Reorganized Sch. Dist. R-9, 
    434 S.W.2d 743
    ,
    750 (Mo. Ct. App. 1968)); see also Steinberg v. Fleischer, 
    706 S.W.2d 901
    ,
    904-05
    2
    The amount of time spent on this case reflected in the
    attorneys’ fees demonstrates that this controversy was one for
    compromise and settlement rather than litigation.
    -10-
    (Mo.   Ct.    App.   1986).      Thus,    the    contractor    contends   that     the
    subcontractor’s failure to provide written notice of excusable delay
    combined with its failure to timely complete its work rendered the
    subcontractor’s performance not excusable under the subcontract.                   The
    contractor,    therefore,     claims   that     the   subcontractor’s   evidence    of
    excusable delays was irrelevant and prejudicial.
    We review a magistrate judge’s decision to admit evidence for abuse
    of discretion.    Lamb Eng’g & Constr. v. Nebraska Pub. Power Dist., 
    103 F.3d 1422
    , 1432 (8th Cir. 1997).       “Furthermore, we will not disturb a jury’s
    verdict ‘absent a showing that the evidence was so prejudicial as to
    require a new trial which would be likely to produce a different result.’”
    
    Id. (quoting O’Dell
    v. Hercules, Inc., 
    904 F.2d 1194
    , 1200 (8th Cir.
    1990)); see also Fed. R. Evid. 403.
    According to the magistrate judge, the evidence of excusable delays
    remained relevant “not necessarily to liability[,] but rather to the jury’s
    determination of the amount of [the contractor’s] damages and the amount
    of those damages legally attributable to [the subcontractor].”            Appellant
    App. at 179 (Jan. 31, 1995 Dist. Ct. Order).           In addition, the magistrate
    judge admitted the evidence because the contractor offered testimony
    alleging that it claimed damages for delays caused by the subcontractor,
    see Tr. Vol. VI at 71-76, and thereby opened the door for the subcontractor
    to offer rebuttal evidence.      Appellant App. at 179 (Jan. 31, 1995 Dist. Ct.
    Order).      Finally, the magistrate judge determined that the contractor
    suffered no harm from the evidence because “the jury unquestionably awarded
    [the contractor] the damages for delays assigned to [the subcontractor] by
    [the contractor].”     
    Id. -11- We
    agree with the magistrate judge.             The contractor offered testimony
    that it calculated its claim for damages due to delay of performance based
    on delays caused by the subcontractor.                See Tr. Vol. VI at 71-76.            By
    offering evidence that the subcontractor caused certain delays, the
    contractor     opened   the    door   for   the    subcontractor      to   offer   rebuttal
    evidence.    Although the rebuttal evidence failed to excuse the delays, it
    challenged the credibility of the contractor’s calculations.                     Cf. United
    States for and on behalf of Cannon Air Corp. v. National Homes, 
    581 F.2d 157
    , 163 (8th Cir. 1978) (concluding that district court did not abuse its
    discretion by admitting rebuttal evidence that would otherwise appear
    prejudicial).        Accordingly,     the   magistrate      judge    did   not   abuse    its
    discretion by admitting the subcontractor’s evidence of weather delays.
    B.     Jury Instructions
    The     contractor       also    challenges      the   magistrate      judge’s      jury
    instructions to render a verdict in the subcontractor’s favor on its
    counterclaim    if   the   subcontractor       substantially        performed    under    the
    contract.      See Appellant App. at 508 (Jury Instruction No. 9).                        The
    contractor argues that, as a matter of law, the subcontractor’s performance
    was insufficient to support its claim.             The contractor also argues that the
    magistrate judge failed to instruct the jury that certain provisions of the
    subcontract, such as the notice provisions discussed in Part A, required
    complete performance.
    The form of the jury instructions is a procedural matter governed by
    federal law.    H.H. Robertson Co. v. V.S. DiCarlo Gen. Contractors, 
    950 F.2d 572
    , 576 (8th Cir. 1991).             A federal court exercising its diversity
    jurisdiction is not required to give the precise instruction set out in the
    Missouri Approved Instructions
    -12-
    (MAI) but, rather, retains broad discretion to instruct the jury so long
    as the form and language of the instructions provide a fair and adequate
    presentation of the state law.        
    Id. Thus, “We
    will not reverse for
    instructional error unless the instruction, read as a whole, failed to
    fairly and adequately present the relevant state law.”        
    Id. at 577.
    We believe the subcontractor offered sufficient evidence that it
    substantially performed under the contract to warrant the magistrate
    judge’s instruction.     The subcontractor introduced evidence that the four
    cement pylons, the subject of the subcontract, were complete and adequate
    for their intended purpose despite alleged defects.        See Tr. Vol. VII at
    193-94 (including testimony that concrete pylons contain no structural
    problems although potential for maintenance problems exists).     In addition,
    although a federal court is not bound to instruct the jury with state
    instructions, the magistrate judge chose to use MAI 26.07.       The Committee
    Comment to MAI 26.07 advises courts to use that instruction “where recovery
    is sought on a building contract,” and state law regards the instruction
    as particularly appropriate in construction contract disputes because “it
    is highly unusual for a project to be completed in exact accordance with
    the original plans and specifications.”      See Lindsey Masonry Co. v. Jenkins
    & Assoc., 
    897 S.W.2d 6
    , 13 (Mo. Ct. App. 1995).     The magistrate judge’s use
    of the state’s instruction fairly and adequately presented the relevant
    state law to the jury.    Thus, we conclude that the magistrate judge did not
    err in its decision to submit the substantial performance instruction or
    in the form of the instruction.
    -13-
    C.    Judgment as a Matter of Law
    The contractor next argues that the magistrate judge erroneously
    denied the contractor’s motion for judgment as a matter of law on the
    subcontractor’s      counterclaim.3        According    to    the    contractor,     the
    subcontract’s unambiguous language entitled the contractor to withhold the
    subcontractor’s payment and, therefore, the contractor never breached the
    subcontract.       Specifically, the contractor contends that the award of
    almost $234,000 in damages, the supplier’s $30,000 claim for payment and
    the   subcontract’s     authorization     of     retainage   demonstrate      that   the
    contractor acted within its contractual rights and, therefore, did not
    breach the contract as a matter of law.
    We review de novo the magistrate judge’s decision to deny the
    contractor’s motion for judgment as a matter of law.                 See Lamb Eng’g &
    Constr. 
    Co., 103 F.3d at 1430
    .           “A court should not set aside a jury’s
    verdict lightly . . . .”         Nicks v. Missouri, 
    67 F.3d 699
    , 704 (8th Cir.
    1995).     A court should grant a motion for judgment as a matter of law if
    “the nonmoving party has presented insufficient evidence to support a jury
    verdict in [its] favor, and this is judged by viewing the evidence in the
    light most favorable to the nonmoving party and giving [it] the benefit of
    all   reasonable    inferences    from   the     evidence,   but    without   assessing
    credibility.”    Abbott v. City of Crocker, 
    30 F.3d 994
    , 997 (8th Cir. 1994)
    (citation omitted).     Furthermore, we review the magistrate judge’s decision
    to deny judgment as a matter of law
    3
    The contractor properly motioned for judgment as a matter
    of law at the close of the evidence pursuant to Fed. R. Civ. P.
    50(a), see Tr. Vol. X at 43, and renewed its motion after the
    jury returned its verdict pursuant to Fed. R. Civ. P. 50(b). See
    Appellant App. at 177 (Jan. 31, 1995 Dist. Ct. Order).
    -14-
    with deference to the jury’s verdict.          See Mears v. Nationwide Mut. Ins.
    Co., 
    91 F.3d 1118
    , 1121 (8th Cir. 1996).
    After reviewing the record, we agree with the magistrate judge’s
    conclusion that “the jury was presented with sufficient evidence to support
    a verdict for both plaintiff and defendant on their respective claims.”
    Appellant App. at 178 (Jan. 31, 1995 Dist. Ct. Order).           The subcontractor
    offered sufficient evidence, when viewed in the light most favorable to the
    subcontractor, that the contractor breached its obligation to pay amounts
    due under the subcontract.       The contractor admitted it withheld $352,408,
    despite claiming only $319,907 in damages.        Furthermore, the subcontractor
    introduced evidence that it completed the four cement pylons without
    significant structural problems.        See Tr. Vol. VII at 193-94.
    Thus, the evidence demonstrated that the subcontractor substantially
    performed its contractual obligations, and that the contractor breached its
    contractual   obligation    to    pay   amounts    owed   to   the   subcontractor.
    Accordingly, we affirm the magistrate judge’s denial of the contractor’s
    motion for judgment as a matter of law.
    D.   Prejudgment Interest
    The contractor contends that the magistrate judge erroneously awarded
    the   subcontractor prejudgment interest based on the entire $352,408
    subcontract balance.   State law provides that “[c]reditors shall be allowed
    to receive interest at the rate of nine percent per annum . . . for all
    moneys after they become due and payable, on written contracts.”           Mo. Rev.
    Stat. § 408.020 (1979).    The magistrate judge ordered the contractor to pay
    prejudgment interest
    -15-
    on the subcontractor’s $352,408 award commencing on May 7, 1993, which is
    thirty days after the subcontractor demanded payment.         See Appellant App.
    at 189 (Dec. 5, 1995 Dist. Ct. Judgment), and decided not to offset the
    contractor’s damages when calculating the subcontractor’s prejudgment
    interest because “[a]n offset . . . would have the practical effect of
    awarding prejudgment [interest] on the [contractor’s] award.”             Appellant
    App. at 191 (Nov. 27, 1995 Dist. Ct. Order).
    The contractor argues that the subcontractor was not entitled to any
    prejudgment interest because the amount due to the subcontractor was not
    fixed    or ascertainable until the jury determined the extent of the
    contractor’s damages.    In the alternative, the contractor argues that the
    magistrate judge erred by calculating prejudgment interest based on the
    subcontractor’s entire award without first offsetting the contractor’s
    $233,629 in damages.     According to the contractor, the subcontract never
    entitled    the   subcontractor   to   receive   $233,629   and,    therefore,   the
    magistrate judge should not award prejudgment interest for amounts that
    never became due under the subcontract.
    State law governs issues of prejudgment interest.          Total Petroleum,
    Inc. v. Davis, 
    822 F.2d 734
    , 738 (8th Cir. 1987) (citing California &
    Hawaiian Sugar Co. v. Kansas City Terminal Warehouse Co. Inc., 
    788 F.2d 1331
    , 1333 (8th Cir. 1986)).      Missouri provides for prejudgment interest
    only if “the trial court finds the amount indisputably due under the
    contract.    In order to be liquidated as to bear interest a claim must be
    fixed and determined or readily determinable . . . .”        Mel-Lo Enters., Inc.
    v. Belle Starr Saloon, Inc., 
    716 S.W.2d 828
    , 829-30 (Mo. Ct. App. 1986)
    (citations omitted).    Missouri courts consider a claim liquidated when the
    parties fix the amount due by agreement.         Huffstutter v. Michigan
    -16-
    Mut. Ins. Co., 
    778 S.W.2d 391
    , 394-95 (Mo. Ct. App. 1989).       “It is also
    well settled under Missouri law that the fact that a defendant interposes
    counterclaims, setoffs, recoupment, or defenses does not alter the fact
    that the amount claimed by the plaintiff is ‘ascertainable,’ even though
    the amount of the defendant’s counterclaim, setoff, or recoupment may not
    itself be reasonably ascertainable.”        St. Joseph Light & Power Co. v.
    Zurich Ins. Co., 
    698 F.2d 1351
    , 1356 (8th Cir. 1983); see also 
    Huffstutter, 778 S.W.2d at 395
    (“The existence of a bona fide dispute as to the amount
    owed does not preclude recovery of interest.”     (citation omitted)).
    The jury’s award reflected a fixed and determined amount because both
    parties agreed that $352,408 remained unpaid under the subcontract.
    Although the contractor raised a bona fide dispute as to the amount due in
    light of the subcontractor’s defective performance, that dispute fails to
    preclude the subcontractor’s recovery of prejudgment interest subject to
    any offset.
    The contractor, however, properly contests the amount of prejudgment
    interest awarded by the magistrate judge.    According to this court’s recent
    decision in Gateway Western Ry. Co. v. Morrison Metalweld Process Corp.,
    
    46 F.3d 860
    (8th Cir. 1995), “[I]n computing prejudgment interest, a
    judgment for amounts due under a contract must be reduced by the other
    party’s offsetting recovery under a counterclaim for breach of the same
    contract, including any recovery of consequential or special damages.”   
    Id. at 864
    (emphasis added) (discussing Herbert & Brooner Constr. Co. v.
    Golden, 
    499 S.W.2d 541
    (Mo. Ct. App. 1973)); see also Solter v. P.M. Place
    Stores, Co., 
    748 S.W.2d 919
    , 922 (Mo. Ct. App. 1988) (“[T]he existence of
    a setoff or counterclaim will not prevent the    recovery of interest on the
    balance of the demand . . . .”
    -17-
    (emphasis in original)).       Although the Missouri Supreme Court has not
    addressed the issue, we believe it would follow this rule.           See   Gateway
    Western Ry. 
    Co., 46 F.3d at 864
    .    Accordingly, we reverse and remand to the
    magistrate judge with instructions to enter an award of prejudgment
    interest in favor of the subcontractor based on the $118,779 difference
    between the subcontractor’s award and the contractor’s damages, less
    properly withheld retainage of $35,240.80.4
    E.   Prevailing Party
    The contractor and the subcontractor both argue that the magistrate
    judge erred by failing to award attorneys’ fees.                According to the
    subcontract, “If any party to this Agreement is required to seek the
    services of an attorney to enforce any provisions of this Agreement, the
    prevailing party shall be entitled to recover its costs, expenses and
    reasonable attorneys’ fees incurred . . . .”        Appellant App. at 516.      The
    magistrate judge, however, declined “to find either party a ‘prevailing
    party’ and enforce an attorneys’ fee clause in the contract both parties
    saw fit to breach.”    Appellant App. at 183 (Jan. 31, 1995 Dist. Ct. Order).
    On   appeal,     the   contractor    argues   that   it   prevailed   on   the
    “significant” issues of the litigation because the jury determined that the
    subcontractor breached the subcontract and awarded the
    4
    See supra at 7 (discussing subcontract provision regarding
    retainage). No prejudgment interest is due on ten percent of the
    final payment which can be withheld until Kansas City accepts the
    contractor’s performance. Accordingly, the magistrate judge
    shall determine any prejudgment interest on retention as of the
    date Kansas City accepted the project, rather than the date the
    subcontractor demanded payment.
    -18-
    contractor the greater share of the subcontract balance in damages.        On
    cross-appeal, the subcontractor contends that Missouri law favors a “net
    judgment rule.”    CFI Br. at 11 (citing 
    Solter, 748 S.W.2d at 923
    ).   Because
    the jury awarded the contractor $233,629 and the subcontractor $352,408,
    the magistrate judge entered a net judgment in the subcontractor’s favor
    for $118,779.     The subcontractor argues that this favorable net judgment
    demonstrates that it prevailed at trial and, therefore, is entitled to
    attorneys’ fees.
    We agree with the magistrate judge’s conclusion that the parties
    intended the attorneys’ fees provision of the subcontract to provide an
    additional remedy for a nonbreaching party.          Both parties, however,
    breached the subcontract.    Thus, we affirm the magistrate judge’s decision
    to deny the requests for attorneys’ fees.
    F.    Reasonableness of Attorneys’ Fees Awarded
    On cross-appeal, the subcontractor challenges the magistrate judge’s
    award of attorneys’ fees to the surety pursuant to the performance bond.
    The   subcontractor made no objections to the amount of the surety’s
    attorneys’ fees before the magistrate judge, see generally Dist. Ct. Doc.,
    but   now   contends that the magistrate judge failed to determine the
    reasonableness of the surety’s attorneys’ fees.     We review the magistrate
    judge’s decision to award attorneys’ fees for abuse of discretion and its
    factual findings control unless they are clearly erroneous.      See Pinkham
    v. Camex, Inc., 
    84 F.3d 292
    , 294 (8th Cir. 1996).    “The amount of an award
    of attorney’s fees rests within the sound discretion of the court and we
    will not disturb it absent clear abuse of that discretion.”            Litton
    Microwave Cooking Products v. Leviton Mfg.
    -19-
    Co., 
    15 F.3d 790
    , 796 (8th Cir. 1994).                 Assuming, arguendo, that the
    subcontractor preserved its objection to the amount of the surety’s
    attorneys’ fees, it failed to demonstrate that the magistrate judge abused
    his discretion.       Thus, we affirm the magistrate judge’s award of attorneys’
    fees in favor of the surety.
    G.   Liability for Payment of Attorneys’ Fees Under Performance Bond
    On cross-appeal the surety argues that it constituted a prevailing
    party under the subcontract as incorporated by the surety bond and,
    therefore, liability for its attorneys’ fees falls on the contractor
    instead of the subcontractor.           In the alternative, the surety argues that
    the magistrate judge mistakenly refused to award the surety attorneys’ fees
    against the contractor because the contractor brought its claim against the
    surety in bad faith.            We reject both of these arguments.
    The contractor was not a party to the performance bond entered
    between      the    subcontractor     and   the    surety   and,   therefore,   owed    no
    contractual obligation under the bond to the surety.               Although the surety’s
    obligations under the bond run toward the contractor, the reverse is not
    true.     Essentially, the subcontractor paid the surety to guarantee the
    contractor         that   the    subcontractor     would    perform.      Although     the
    subcontractor and surety decided to incorporate the subcontract, that
    decision did not affect the rights of the contractor or any other non-party
    to the bond.
    In addition, we disagree with the surety’s assertion that the
    contractor brought its claim in bad faith.             Although the magistrate judge
    appropriately granted the surety judgment as a matter of law on the
    contractor’s claim for damages because the contractor’s
    -20-
    claim    failed to exceed the amount the contractor withheld from the
    subcontractor, see Appellant App. at 177 (Jan. 31, 1995 Dist. Ct. Order),
    the magistrate judge retained jurisdiction over the surety for purposes of
    determining liability for attorneys’ fees.    See Peerless Br. at 10.   As a
    result, although the contractor failed to raise a claim for damages against
    the surety, the contractor’s claim for attorneys’ fees was reasonable and
    not in bad faith.    Accordingly, we affirm the magistrate judge’s decision
    to order the subcontractor, rather than the contractor, to pay the surety’s
    attorneys’ fees.
    H.   Indemnity Rights of Surety
    Finally, the surety requests that this court increase its judgment
    against the subcontractor to compensate the surety for paying the supplier
    $20,000 to settle the supplier’s claim against the subcontractor.        The
    surety claims that its performance bond with the subcontractor entitles the
    surety to reimbursement.      The subcontractor admits that the surety, on
    behalf of the subcontractor, settled the supplier’s claim for $20,000, CFI
    Br. at 6; CFI Reply Br. at 10, but the parties never provided the
    magistrate judge with an opportunity to rule on this issue.    Accordingly,
    we remand this issue for further proceedings in accordance with the
    seemingly undisputed facts presented by the parties.
    In addition, the contractor argues that the subcontract entitles the
    contractor to withhold $30,010 from the subcontractor’s judgment as
    security until the subcontractor provides an unconditional waiver or
    release of lien by the supplier.    See Appellant’s App. at 516.   The court
    record, however, appears to contain such a release of the supplier’s claim
    against
    -21-
    the contractor.     See Appellee Chicago Forming App. at 26.    Because the
    contractor’s claim appears to question whether the surety settled the
    supplier’s claim, we refer the matter to the magistrate judge to resolve
    in conjunction with the surety’s claim for indemnification.
    III.   CONCLUSION
    For the above-mentioned reasons, we affirm in part, reverse in part
    and remand the case to the magistrate judge for further proceedings in
    accordance with this opinion.
    A true copy.
    Attest:
    CLERK, U. S. COURT OF APPEALS, EIGHTH CIRCUIT.
    -22-
    

Document Info

Docket Number: 96-1028

Citation Numbers: 111 F.3d 1376

Filed Date: 4/22/1997

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (17)

David Mears v. Nationwide Mutual Insurance Company , 91 F.3d 1118 ( 1996 )

H.H. Robertson Company, Cupples Products Division v. V.S. ... , 950 F.2d 572 ( 1991 )

Richard Eugene Abbott v. City of Crocker, Missouri James ... , 30 F.3d 994 ( 1994 )

sandra-nicks-v-state-of-missouri-bellefontaine-habilitation-center-keith , 67 F.3d 699 ( 1995 )

Lamb Engineering & Construction Company v. Nebraska Public ... , 103 F.3d 1422 ( 1997 )

California & Hawaiian Sugar Company v. Kansas City Terminal ... , 788 F.2d 1331 ( 1986 )

Huffstutter v. Michigan Mutual Insurance Co. , 778 S.W.2d 391 ( 1989 )

Total Petroleum, Inc. v. Gary J. Davis, D/B/A Gary J. Davis ... , 822 F.2d 734 ( 1987 )

Havens Steel Company v. Randolph Engineering Company , 813 F.2d 186 ( 1987 )

litton-microwave-cooking-products-a-division-of-litton-systems-inc , 15 F.3d 790 ( 1994 )

Gateway Western Railway Co. v. Morrison Metalweld Process ... , 46 F.3d 860 ( 1995 )

Lindsey Masonry Co. v. Jenkins & Associates Inc. , 897 S.W.2d 6 ( 1995 )

Southwest Engineering Co. v. Reorganized School District R-9 , 434 S.W.2d 743 ( 1968 )

steven-odell-jana-odell-tim-odell-paul-odell-ruby-bridges-v , 904 F.2d 1194 ( 1990 )

Steinberg v. Fleischer , 706 S.W.2d 901 ( 1986 )

Herbert & Brooner Construction Co. v. Golden , 499 S.W.2d 541 ( 1973 )

Salve Regina College v. Russell , 111 S. Ct. 1217 ( 1991 )

View All Authorities »