Ronald A. Krentz v. Robertson Fire , 228 F.3d 897 ( 2000 )


Menu:
  •                       United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ___________
    No. 99-4235
    ___________
    Ronald A. Krentz,                            *
    *
    Appellant,                     *
    *
    v.                                    *
    *
    Robertson Fire Protection District;          *
    Stephen E. Kirwan, individually and in *         Appeal from the United States
    his official capacity as Director and        *   District Court for the
    President of the Robertson Fire              *   Eastern District of Missouri
    Protection District; Robert S. Zoellner, *
    Individually and in his official capacity as *   [PUBLISHED]
    Director and Secretary of the Robertson *
    Fire Protection District; Vince Grillo,      *
    Individually and in his official capacity as *
    Member and Treasurer of the Robertson *
    Fire Protection District,                    *
    *
    Appellees.                     *
    ___________
    Submitted: June 15, 2000
    Filed: October 6, 2000
    ___________
    Before WOLLMAN, Chief Judge, BEAM and BYE, Circuit Judges.
    ___________
    BYE, Circuit Judge.
    Ronald Krentz was fired as chief of the Robertson Fire Protection District (the
    District) roughly ten months into a seven-year contract. Krentz filed suit against the
    District, its three governing board members, and their attorney alleging violations of his
    federal constitutional rights, breach of contract, and several Missouri law claims. In
    an omnibus order disposing of all of Krentz’s claims, the district court1 dismissed some
    claims, and granted summary judgment in favor of the defendants on others. We
    affirm.
    FACTUAL BACKGROUND
    The District is managed by a board consisting of three elected members. These
    members decide personnel matters, make policy for the District, and resolve the range
    of issues that require managerial oversight.
    Krentz became chief of the District in 1987. Almost a decade later, on January
    4, 1997, the District signed Krentz to a new seven-year contract. Although the board
    apparently found Krentz’s performance satisfactory during his first decade as chief, the
    Board became increasingly disenchanted with Krentz’s performance during the first
    half of 1997.
    In June 1997, the board informed Krentz at an executive session that the District
    suffered from a severe morale problem. The board asked Krentz to present a plan to
    remedy the firefighters’ lack of morale. Krentz never responded. At roughly the same
    time, the board began to question whether Krentz and other officials used District
    cellular phones to place personal calls.
    1
    The Honorable Catherine D. Perry, United States District Judge for the Eastern
    District of Missouri.
    -2-
    On September 23, 1997, virtually all of the District’s firefighters presented the
    board with a signed petition expressing a lack of confidence in Krentz. The petition
    asked for Krentz’s removal. At least one employee specifically complained that Krentz
    had passed him over for promotion improperly. Finally, on September 29, 1997, the
    board placed Krentz on paid leave based upon the allegation that Krentz had offered
    jobs to two firefighters without board approval.
    Krentz attributed the board’s changing attitude toward him to its new
    membership. In the spring of 1997, Robert Zoellner was elected to the board. During
    the election, Zoellner’s campaign had received the support of a firefighter’s union.
    Perhaps because of his union affiliation, Zoellner disliked the fact that several fire
    officials in the district — including Krentz — received long-term employment
    contracts. Krentz felt that Zoellner unfairly targeted him because of his long-term
    contract with the District.
    On November 6, 1997, following an investigation, the board sent Krentz a letter
    detailing his substandard performance in the preceding months. In that letter, the board
    announced its decision to terminate Krentz’s employment. The board offered Krentz
    an opportunity to present arguments and evidence in his defense at a special board
    meeting scheduled for November 16. The letter demanded that Krentz return District
    property in his possession by November 20 — unless the board changed its mind about
    his termination.
    Krentz attended the November 16 special board meeting with his attorney.
    Krentz’s attorney advised the board, in a hand-delivered letter, that he objected to the
    procedures employed by the board. The letter did not dispute the substantive
    allegations levied against Krentz and his management regime. Krentz stated that he
    wanted to hear the board members’ view of the situation, but the board’s attorney,
    Stuart Berkowitz, insisted on speaking for the board at the meeting. Krentz’s attorney
    attempted to explain Krentz’s side of the story, but the board demanded to hear from
    -3-
    Krentz personally. Because Krentz refused to address the board or answer questions,
    he and his attorney left the meeting.2 The District removed Krentz from its payroll on
    November 20, 1997.
    PROCEDURAL HISTORY
    Krentz filed suit in district court on July 24, 1998. He named five defendants:
    (1)    Robertson Fire Protection District;
    (2)    Stephen Kirwan, both individually and in his official capacity as a
    District board member;
    (3)    Zoellner, both individually and in his official capacity as a District
    board member;
    (4)    Vince Grillo, both individually and in his official capacity as a
    District board member; and
    (5)    Berkowitz, both individually and in his official capacity as the
    District’s attorney.
    Krentz stated five separate sets of claims:
    (1)    Violations of his due process and equal protection rights under the
    Fourteenth Amendment committed by Kirwan, Zoellner, Grillo and
    Berkowitz;
    (2)    Violations of his free speech, due process and equal protection
    rights under the First and Fourteenth Amendments committed by
    the District;
    (3)    Breach of contract committed by the District;
    (4)    Tortious interference with a contractual relationship committed by
    Zoellner and Berkowitz (a state-law claim); and
    (5)    Intentional infliction of emotional distress against Kirwan, Zoellner
    and Berkowitz (a state-law claim).
    2
    No transcript or record was made of the November 16 board meeting, but the
    parties’ accounts of the board meeting are generally consistent.
    -4-
    Shortly after Krentz filed suit, the defendants filed a motion to dismiss the
    claims. The district court did not immediately resolve the motion. After engaging in
    discovery, the parties filed cross-motions for summary judgment. On August 25, 1999,
    the court disposed of all of Krentz’s claims (some by dismissal, others by summary
    judgment) and entered judgment against him.
    Almost two weeks later, on September 7, 1999, Krentz filed a motion to alter or
    amend the judgment (in effect, a motion for reconsideration) under Fed. R. Civ. P.
    59(e). The district court denied Krentz’s Rule 59(e) motion in an order filed October
    18, 1999.
    Krentz timely appealed discrete portions of the claims raised in his first three
    counts — certain procedural due process issues and the state-law breach of contract
    claim. Krentz does not challenge the district court’s rulings on two of his state-law
    claims (claims (4) and (5)). Krentz also leaves unchallenged many of the federal
    claims, including the equal protection claims and the free speech claim.
    DISCUSSION
    A.    Procedural Due Process Claims
    1.     Post-Deprivation Procedural Safeguards
    Krentz argues that the district court erred in granting the defendants summary
    judgment on his procedural due process claims. We review de novo a district court’s
    grant of summary judgment by applying the same standard as the district court. See
    Treanor v. MCI Telecomm. Corp., 
    200 F.3d 570
    , 573 (8th Cir. 2000). Summary
    judgment is appropriate when the evidence — viewed in the light most favorable to the
    nonmoving party — demonstrates that there are no disputed issues of material fact and
    -5-
    the moving party is entitled to judgment as a matter of law. See Celotex Corp. v.
    Catrett, 
    477 U.S. 317
    , 322-23 (1986).
    The Due Process Clause of the 14th Amendment provides that, "[n]o State shall
    . . . deprive any person of life, liberty, or property, without due process of law." U.S.
    Const. amend. XIV, § 1. Procedural due process claims require a two-step analysis.
    Initially, a plaintiff must demonstrate that the state deprived him of some “life, liberty,
    or property” interest. If successful, the plaintiff must then establish that the state
    deprived him of that interest without sufficient “process.”
    Krentz can establish a property interest in his job as fire chief because his
    contract with the District anticipated a term of seven years.3 When a state deprives a
    public employee of a contractually-created property right to continued employment,
    that deprivation “must be preceded by notice and opportunity for hearing appropriate
    to the nature of the case.” Cleveland Bd. of Educ. v. Loudermill, 
    470 U.S. 532
    , 542
    (1985) (quoting Mullane v. Central Hanover Bank & Trust Co., 
    339 U.S. 306
    , 313
    (1950)). Loudermill divides procedural due process claims into three stages. Initially,
    an employee receives notice that he will be terminated, and he is given an opportunity
    to respond: that is “pretermination process.” Then, the employer actually fires the
    employee. Finally, in the third stage, an employee has an opportunity to receive some
    measure of post-termination process, usually a hearing with heightened procedural
    safeguards. Loudermill instructs us that extensive post-termination proceedings may
    cure inadequate pretermination proceedings. See 
    Loudermill, 470 U.S. at 546-48
    .
    We have interpreted Loudermill to require only limited pretermination process,
    especially if post-termination proceedings are available and extensive.
    3
    The District protests to the contrary. The District contends that the contract’s
    seven-year term violated Missouri law, and was therefore void. We disagree.
    -6-
    The indispensable requirements of a pretermination hearing are notice of
    the charges, an explanation of the employer’s evidence, and an
    opportunity for the employee to present his side of the story. The hearing
    does not have to precede the termination decision, but only must precede
    the termination of benefits. It does not have to be a formal hearing;
    informal meetings with supervisors are sufficient. The Loudermill Court
    emphasized that as long as there are adequate post-termination hearings
    available, the pre-termination hearing need not be extensive.
    Schleck v. Ramsey County, 
    939 F.2d 638
    , 641-42 (8th Cir. 1991) (internal punctuation
    and quotations altered and omitted) (internal citations omitted).
    In sum, although a public employee should receive a hearing, that hearing “need
    not be elaborate.” 
    Loudermill, 470 U.S. at 544
    . “[T]he tenured public employee is
    entitled to oral or written notice of the charges against him, an explanation of the
    employer’s evidence, and an opportunity to present his side of the story.” 
    Id. at 546.
    Krentz’s pretermination process was twofold. First, the board notified Krentz
    of its decision to terminate him by letter of November 6. That letter informed Krentz
    of the nature of the charges against him. The letter also announced a special meeting
    at which Krentz would be offered an opportunity to respond to the board’s decision.
    Second, the meeting itself offered Krentz an opportunity to present his side of the
    story.4 See 
    id. at 546.
    4
    Krentz argues that the November 16 meeting was actually post-termination
    process, because he had been fired by the terms of the November 6 letter. We
    disagree. For purposes of a procedural due process claim, an employee’s termination
    becomes effective once the employer ceases to provide benefits. See 
    Schleck, 939 F.2d at 641
    . Because the District continued to provide benefits to Krentz until
    November 20, Krentz was not terminated on November 6.
    -7-
    The board provided Krentz constitutionally adequate pretermination process —
    though barely so. The board apparently refused to answer Krentz’s questions (or those
    of his attorney) on the advice of its counsel. The board neglected to record or
    transcribe the hearing. Further, the board peevishly insisted that Krentz’s attorney
    could not participate in the hearing.5 Nevertheless, Krentz received notice of the
    charges against him. And he could have remained at the November 16 hearing to
    address the concerns enunciated in the November 6 letter. Ultimately, our conclusion
    that Krentz received adequate pretermination process depends heavily upon the fact
    that robust post-termination proceedings may cure superficial pretermination
    proceedings. See 
    id. at 547
    n.12 (“the existence of post-termination procedures is
    relevant to the necessary scope of pretermination procedures”).
    We turn now to the question of post-termination process. Missouri law
    demonstrates the availability and adequacy of post-termination proceedings. See 
    id. at 545
    (“Under state law, respondents were later entitled to a full administrative hearing
    and judicial review.”).
    The district court determined that fire districts, creatures of state law, are
    “agencies” for purposes of the Missouri Administrative Procedure Act (MAPA), Mo.
    Rev. Stat. §§ 536.010 - .150.6 We agree. An “‘agency’ means any administrative
    officer or body existing under the constitution or by law and authorized by law or the
    constitution to make rules or to adjudicate contested cases.” 
    Id. § 536.010(1).
    A
    5
    Although our cases do not establish that the board had an obligation to listen to
    Krentz’s attorney in place of Krentz himself, cf. Riggins v. Board of Regents, 
    790 F.2d 707
    , 712 (8th Cir. 1986), the board’s failure to conduct a hearing in which all sides
    could meaningfully participate detracts from its contention that its conduct satisfied the
    Due Process Clause.
    6
    The parties have not directed us to any Missouri cases that analyze whether fire
    districts are MAPA agencies. Our research efforts have likewise ended empty-handed.
    -8-
    “contested case” is a “proceeding before an agency in which legal rights, duties or
    privileges of specific parties are required by law to be determined after hearing.”
    Wheeler v. Board of Police Comm’rs of Kansas City, 
    918 S.W.2d 800
    , 804 n.2 (Mo.
    Ct. App. 1996) (punctuation omitted).
    The Missouri Supreme Court has suggested that state entities with the power to
    hire and fire employees effectively engage in the resolution of contested cases. See
    Byrd v. Board of Curators, 
    863 S.W.2d 873
    , 875 (Mo. 1993). Accordingly, such
    entities are “agencies.” We agree with the district court that because the Robertson
    Fire Protection District had the power to hire and fire employees — indeed, Krentz’s
    termination is but one example of its power — the District was an “agency” for MAPA
    purposes. Cf. Green v. St. Louis Hous. Auth., 
    911 F.2d 65
    , 72 (8th Cir. 1990)
    (“Because we do not find that the district court’s ruling on this [MAPA] question is
    fundamentally deficient in analysis, without a reasonable basis, or contrary to reported
    state-court opinion, we affirm”).
    Because the District is a MAPA agency, Krentz could have instituted a
    “contested case” proceeding under the MAPA after his termination became effective
    on November 20.7 See Mo. Rev. Stat. § 536.063; 20 MISSOURI PRACTICE § 9.02 (West
    1995) (“[M]any contested cases are initiated other than by an agency . . . . For
    example, a public employee may challenge his dismissal.”) (citing Bland v. City of
    Trenton, 
    618 S.W.2d 438
    , 439-40 (Mo. Ct. App. 1981)). But Krentz declined to
    pursue the available MAPA post-termination remedy.
    7
    The MAPA’s “contested case” provisions contemplate extensive proceedings.
    See Mo. Rev. Stat. § 536.070. A party to a contested case may call and examine
    witnesses under oath, introduce documents and exhibits, file supporting affidavits, and
    object to the introduction of evidence. See 
    id. § 536.070(1)-(3),
    (5)-(12). The agency
    must record all proceedings and make transcripts available upon request. See 
    id. § 536.070(4).
    -9-
    Further, the MAPA’s contested case provisions, explained in footnote 7, comport
    with post-termination requirements imposed by the Due Process Clause. See
    
    Loudermill, 470 U.S. at 546
    (“Our holding rests in part on the provisions in Ohio law
    for a full post-termination hearing.”) (emphasis added). The extensive procedural
    protections provided in Mo. Rev. Stat. § 536.070 suffice to protect the constitutional
    interests of aggrieved employees in post-termination proceedings. A MAPA contested
    case is tantamount to a “full post-termination hearing.” 
    Id. Our cases
    explain that an employee waives a procedural due process claim by
    refusing to participate in post-termination administrative or grievance procedures made
    available by the state. See Riggins v. Board of Regents of the Univ. of Neb., 
    790 F.2d 707
    , 711 (8th Cir. 1986); Bohn v. County of Dakota, 
    772 F.2d 1433
    , 1441 (8th Cir.
    1985). In both Riggins and Bohn, the respective plaintiffs were found to have waived
    their due process claims because they were aware of the available administrative
    procedures, yet they did not pursue relief thereunder. See 
    Riggins, 790 F.2d at 709-10
    ;
    
    Bohn, 772 F.2d at 1441
    . Krentz’s case is analogous. Krentz could have sought a
    contested case hearing under the MAPA, but he did not.
    Krentz’s contention that he was unaware that the MAPA’s provisions applied
    to personnel actions taken by fire districts is unavailing. His contention rests upon a
    legal (rather than factual) misunderstanding. And in Missouri, “[p]ersons are
    conclusively presumed to know the law.” Missouri Highway & Transp. Comm’n v.
    Myers, 
    785 S.W.2d 70
    , 75 (Mo. 1990); In re Estate of Pittman, 
    16 S.W.3d 639
    , 642
    (Mo. Ct. App. 2000). Krentz “could have . . . ascertained” the applicability of the
    MAPA’s contested case provisions “from a reading of the statutes and pertinent cases.”
    
    Myers, 785 S.W.2d at 75
    .
    -10-
    2.     Decisionmaker’s Bias
    Krentz also raises the specter of bias in the District board’s decision. The right
    to a fair and impartial decisionmaker forms an essential part of the protection afforded
    by the Due Process Clause. But Krentz must overcome a “presumption of honesty and
    integrity in policymakers with decision making power,” and show that the District
    board’s decision to terminate him was “infected with bias.” Hortonville Joint Sch.
    Dist. No. 1 v. Hortonville Educ. Ass’n, 
    426 U.S. 482
    , 497 (1976).
    Instead of demonstrating pervasive bias, Krentz raises mere accusations about
    a single board member’s views about labor unions. Krentz succeeds in showing that
    one of the board members may have harbored pro-union sentiment, an approach
    apparently in conflict with Krentz’s own views. But this showing falls far short of
    raising a factual dispute necessary to defeat summary judgment.
    3.     Conclusion
    We hold that the MAPA’s contested case provisions offered Krentz a
    constitutionally adequate post-termination opportunity to be heard. In addition, Krentz
    failed to establish that the board was biased against him. Accordingly, the district court
    properly granted the defendants’ motion for summary judgment as to Krentz’s
    procedural due process claims.
    B.    Breach of Contract
    The district court dismissed Krentz’s breach of contract claim for failure to state
    a claim upon which relief could be granted. See Fed. R. Civ. P. 12(b)(6). The court
    concluded, as a matter of law, that Krentz’s claim was barred because he neglected to
    exhaust his MAPA remedies. We review de novo a district court’s grant of a motion
    to dismiss for failure to state a claim under Rule 12(b)(6). See Gordon v. Hansen, 168
    -11-
    F.3d 1109, 1113 (8th Cir. 1999). “A complaint should not be dismissed for failure to
    state a claim unless it appears beyond doubt that the plaintiff can prove no set of facts
    in support of his claim which would entitle him to relief.” Parnes v. Gateway 2000,
    Inc., 
    122 F.3d 539
    , 545-46 (8th Cir. 1997) (quoting Fusco v. Xerox Corp., 
    676 F.2d 332
    , 334 (8th Cir. 1982)). “A complaint must be viewed in the light most favorable to
    the plaintiff and should not be dismissed merely because the court doubts that a plaintiff
    will be able to prove all of the necessary factual allegations. Thus, as a practical
    matter, a dismissal under Rule 12(b)(6) is likely to be granted only in the unusual case
    in which a plaintiff includes allegations that show on the face of the complaint that there
    is some insuperable bar to relief.” 
    Parnes, 122 F.3d at 546
    .
    As we explained above, fire districts are MAPA agencies. If a MAPA agency
    employee is terminated, that employee must exhaust his administrative remedies under
    the MAPA before commencing suit in court. See Council House Redev. Corp. v. Hill,
    
    920 S.W.2d 890
    , 892 (Mo. 1996). In this case, however, Krentz did not exhaust his
    administrative remedies. Indeed, Krentz never brought an administrative claim, and the
    time has passed in which he could have filed such a claim.
    Even if, as Krentz argues, the District neglected to give him the process he was
    due under the MAPA, Krentz’s sole remedy lay within the procedural confines of the
    MAPA itself. See 
    Byrd, 863 S.W.2d at 876
    (citing Franklin v. Harris, 
    762 S.W.2d 847
    ,
    849 (Mo. Ct. App. 1989)). Having failed to pursue a MAPA claim in timely fashion,
    Krentz is foreclosed from litigating the matter in federal court. The district court
    properly dismissed Krentz’s breach of contract claim.
    We affirm.
    -12-
    BEAM, Circuit Judge, dissenting.
    I respectfully suggest that under controlling law, Krentz did not waive his
    constitutional right to procedural due process. I also suggest that had Krentz been
    afforded the Missouri Administrative Procedures Act (MAPA) (Mo. Stat. Ann. §
    536.063) "contested case" hearing now required by the court, his constitutional rights
    would still have been violated. Accordingly, I dissent.
    A short analysis of this dispute and the court's resolution is in order. From
    Krentz's allegations, it appears that until a more recent run-in with the firefighter's
    union, he had had no problems for many years in the performance of the duties of his
    tenured position. With union help, Zoellner was elected to the three-person board of
    the Robertson Fire Protection District (District), and from there things went down hill
    for Krentz. After repeated complaints from union officials and Zoellner, Krentz was
    given notice of his termination. At the District board's request, he attended the
    November 16, 1997, meeting at which the District chose to speak only through its
    lawyer but specifically prohibited Krentz from speaking through his retained counsel.
    Krentz excused himself from this one-sided encounter and filed suit in district court,
    alleging, for purposes of this dissent, a violation of his constitutional right to procedural
    due process. The district court determined for the first time that in Missouri, a local fire
    protection district is an "agency" as defined by MAPA and the court in this appeal now
    rules that Krentz's failure to exhaust administrative procedures under MAPA
    constituted a waiver of constitutional rights. With this determination, I disagree.
    I do, however, agree with several interim conclusions reached by the court. I
    agree that Krentz had a property interest in his seven-year contract of employment with
    the District and that absent a valid waiver, such interest could not be erased through job
    termination without his being accorded procedural due process under the Fourteenth
    Amendment. I further agree that his termination occurred on November 20, 1997,
    when his benefits were discontinued and that the inelaborate hearing the District
    -13-
    afforded Krentz on November 16, 1997, met the pre-termination hearing requirements
    established by Cleveland Board of Education v. Loudermill, 
    470 U.S. 532
    (1985). At
    that point, however, I respectfully part company with the court.
    The Supreme Court's holding that a pre-termination hearing need not be
    elaborate rested, in substantial part, on the fact that Loudermill received a full post-
    termination hearing. See 
    Loudermill, 470 U.S. at 546
    -47. In this 42 U.S.C. § 1983
    claim concerning a vested property interest, it is clear that Krentz did not receive a
    constitutionally adequate post-termination hearing, and I do not understand the court
    to seriously contest this conclusion. However, the court states that Krentz was
    responsible for this problem because he walked out of his November 16 meeting with
    the District's board and did not thereafter institute a "contested case," as permitted by
    MAPA. See Mo. Stat. Ann. §§ 536.010(2) & 536.063(1). I disagree. It was the
    District that violated Krentz's procedural due process rights by not providing the "full
    post-termination hearing" required by Loudermill and other Supreme Court and Eighth
    Circuit precedent. For starters, a tenured employee is simply not required to exhaust
    state administrative remedies before bringing a federal action to vindicate constitutional
    rights. See Patsy v. Florida Bd. of Regents, 
    457 U.S. 496
    , 516 (1982).
    At its core, procedural due process requires "the opportunity to be heard 'at a
    meaningful time and in a meaningful manner.'" Mathews v. Eldridge, 
    424 U.S. 319
    ,
    333 (1976) (quoting Armstrong v. Manzo, 
    380 U.S. 545
    , 552 (1965)). In a termination
    setting, we have stated that a meaningful opportunity to be heard requires:
    1)      clear and actual notice of the reasons for termination in sufficient
    detail to enable him or her to present evidence relating to them;
    2)     notice of both the names of those who have made allegations
    against the [employee] and the specific nature and factual basis for
    the charges;
    3)     a reasonable time and opportunity to present testimony in his or her
    own defense; and
    -14-
    4)     a hearing before an impartial board or tribunal.
    Riggins v. Board of Regents, 
    790 F.2d 707
    , 712 (8th Cir. 1986).
    The court does not dispute these requirements. Instead, it says that procedures
    under the "contested case" provisions of MAPA provide Fourteenth Amendment due
    process and that Krentz had the duty to seek out and use these particular state remedies
    to avoid a waiver of his constitutional rights. This is wrong for several reasons.
    Prior to the district court's holding, Krentz had no hint that MAPA was
    applicable to his particular dispute nor did he have a reasonable opportunity to present
    a defense because a local fire protection district had never before been found to be an
    "agency" within the purview of MAPA. Also, under MAPA, and the facts of this
    action, there is no provision for a hearing before an impartial board or tribunal as
    required by Riggins. Indeed, this newly minted MAPA agency, acting through its
    board, the post-hearing decision-maker under MAPA, had already decided to terminate
    Krentz well before the pre-termination Loudermill hearing. How the court can
    conclude that under these circumstances, MAPA procedure passes constitutional
    muster as the provider of a fair and impartial decision-maker is difficult to understand.
    Of much greater concern to me is the court's conclusion that Krentz waived his
    constitutional rights by not unilaterally insisting upon an unconstitutional MAPA
    procedure. The court says,
    Because the District is a MAPA agency, Krentz could have instituted a
    "contested case" proceeding under the MAPA after his termination
    became effective on November 20. See Mo. Rev. Stat. § 536.063; 20
    MISSOURI PRACTICE § 9.02 (West 1995) ("[M]any contested cases are
    initiated other than by an agency . . . . For example, a public employee
    may challenge his dismissal.") (citing Bland v. City of Trenton, 618
    -15-
    S.W.2d 438, 439-40 (Mo. Ct. App. 1981)). But Krentz declined to
    pursue the available MAPA post-termination remedy.
    Ante at 9 (footnote omitted).
    The court relies upon two of our cases to support this unusual requirement,
    
    Riggins, 790 F.2d at 711
    and Bohn v. County of Dakota, 
    772 F.2d 1433
    , 1441 (8th Cir.
    1985). Both are clearly inapposite. The court states, "In both Riggins and Bohn, the
    respective plaintiffs were found to have waived their due process claims because they
    were aware of the available administrative procedures, yet they did not pursue relief
    thereunder. See 
    Riggins, 790 F.2d at 709-10
    ; 
    Bohn, 772 F.2d at 1441
    ." (Emphasis
    added.) The emphasized language highlights the court's error. In Riggins, for instance,
    the University had a formal grievance procedure, which Riggins had used before, and
    she testified that she was aware of it. See 
    Riggins, 790 F.2d at 709
    . Krentz contends
    that he was unaware that MAPA's provisions applied to personnel actions taken by fire
    districts. The court's response is,
    in Missouri, "[p]ersons are conclusively presumed to know the law."
    Missouri Highway & Transp. Comm'n v. Myers, 
    785 S.W.2d 70
    , 75 (Mo.
    1990); In re Estate of Pittman, 
    16 S.W.3d 639
    , 643 (Mo. Ct. App. 2000).
    Krentz "could have . . . ascertained" the applicability of the MAPA's
    contested case provisions "from a reading of the statutes and pertinent
    cases." 
    Myers, 785 S.W.2d at 75
    .
    Ante at 10.
    There is a twofold problem with this answer. Waiver of a constitutional right is
    exclusively a question of federal law, Brookhart v. Janis, 
    384 U.S. 1
    , 4 (1966). This
    court has acknowledged this principle. "[W]aiver becomes a federal question about
    which the federal courts are obligated to make their own independent determination."
    Williams v. Brewer, 
    509 F.2d 227
    , 232 (8th Cir. 1974). And, under federal law, a
    -16-
    waiver of a constitutionally guaranteed right must be "an intentional relinquishment or
    abandonment of a known right or privilege." Johnson v. Zerbst, 
    304 U.S. 458
    , 464
    (1938).
    The court concedes that prior to this case no court, state or federal, had ever held
    that fire districts were "agencies" for purposes of MAPA. See ante at 8. However, the
    court now establishes precedent that a tenured employee must have the necessary legal
    skills or hire and pay counsel with the necessary legal skills to research state law to find
    any potentially applicable administrative procedures or risk waiver of a constitutional
    right. This flies in the face of established precedent.
    I concede that the Supreme Court has, to date, been reluctant to spell out the
    difference, if any, in waiver concepts as they may apply in the civil or criminal context.
    However, it has strongly implied, without specifically deciding, that waiver
    requirements are the same in either instance. In D.H. Overmyer Co. v. Frick Co., 
    405 U.S. 174
    , 185 (1972), the Court assumed without deciding that the same standards
    apply in both contexts. In Fuentes v. Shevin, 
    407 U.S. 67
    , 95 (1972), the Court again
    avoided holding that the standards are the same in civil and criminal cases, but said, "a
    waiver of constitutional rights in any context must, at the very least, be clear." 
    Id. (emphasis in
    original). In Ohio Bell Telephone Co. v. Public Utilities Commission, the
    Court in a civil case said, "we do not presume acquiescence in the loss of fundamental
    rights." 
    301 U.S. 292
    , 307 (1937). Seven circuits (Second, Third, Fourth, Fifth, Sixth,
    Ninth and Eleventh) have either held or strongly stated that the standard for judging
    waiver should be the same in both civil and criminal cases.8
    8
    See Lake James Community Volunteer Fire Dep't Inc. v. Burke County, 
    149 F.3d 277
    , 280 (4th Cir. 1998) (stating that a contractual waiver of a constitutional right
    must be knowing and voluntary); Gete v. INS, 
    121 F.3d 1285
    , 1293 (9th Cir. 1997)
    (stating that principles governing waiver of constitutional rights apply equally in
    criminal and civil context); W.B. v. Matula, 
    67 F.3d 484
    , 497 (3d Cir. 1995) (same);
    United States v. Local 1804-1, 
    44 F.3d 1091
    , 1098 (2d Cir. 1995) (same); K.M.C. Co.
    -17-
    In any event, I see no reasoned basis for a different standard. And, returning to
    Johnson v. Zerbst, the Court notes that the "courts indulge every reasonable
    presumption against waiver of a fundamental constitutional right" and they will not
    "presume acquiescence in the loss of fundamental 
    rights." 304 U.S. at 464
    . The Court
    further states that a person cannot waive a constitutional right through ignorance or
    negligence. See 
    id. at 465-68.
    In the face of this precedent, to require Krentz to be knowledgeable about
    whatever administrative remedy may be lurking among state statutes or suffer a waiver
    of constitutional proportions is serious enough. But to charge him with predicting
    where the law might go with regard to whether or not a local fire district is an agency
    within the purview of MAPA borders on the excessive both as a matter of policy and
    as a matter of law. Indeed, in Curtis Publishing Co. v. Butts, 
    388 U.S. 130
    (1967), the
    Supreme Court ruled to the contrary. Curtis was a libel case filed by a public figure,
    but not a public official, that had been tried prior to the Supreme Court's decision in
    New York Times v. Sullivan, but had not been appealed until after the Sullivan
    decision.9 Curtis Publishing first asserted a First Amendment based defense–relying
    on the Sullivan decision–in a motion for a new trial. The motion was denied, and the
    Fifth Circuit Court subsequently held that Curtis Publishing had waived any First
    Amendment based defenses by failing to assert them at trial. The Fifth Circuit found
    that Curtis Publishing should have seen "'the handwriting on the wall'" and known that
    v. Irving Trust Co., 
    757 F.2d 752
    , 756 (6th Cir. 1985) (same); Mosley v. St. Louis
    S.W. Ry., 
    634 F.2d 942
    , 946 n.5 (5th Cir. 1981) (Mosley also serves as precedent for
    the Eleventh Circuit. See Bonner v. City of Prichard, 
    661 F.2d 1206
    , 1207 (11th Cir.
    1981)). A search of the circuits yielded no case that held there was a different standard
    in the civil context.
    9
    In New York Times Co. v. Sullivan, the Supreme Court for the first time
    explicitly stated that because of First Amendment considerations a court cannot award
    libel/slander damages to a public official, for a falsehood related to his official conduct,
    without proof of actual malice. 
    376 U.S. 254
    (1964).
    -18-
    the Supreme Court would possibly craft a rule providing Curtis Publishing with this
    additional defense. Curtis 
    Publishing, 388 U.S. at 143
    (quoting Curtis Publ'g Co. v.
    Butts, 
    351 F.2d 702
    , 734 (5th Cir. 1965)).
    The Supreme Court, by an eight to one margin, held that Curtis Publishing had
    not waived its constitutional defense on these facts.10 Although there had previously
    been indications in dissenting opinions, and in extra-judicial statements made by a
    justice, that a First Amendment rule limiting libel actions brought by public officials
    might be crafted, it was not unreasonable for a defendant to assert only state-based
    defenses in a trial prior to the Sullivan decision. See 
    id. at 144.
    Under these
    circumstances, Curtis Publishing could not have waived a "known right" before it was
    aware of the decision in Sullivan. 
    Id. at 145.
    The Supreme Court indicated a person does not knowingly waive a constitutional
    right by failing to predict how the law might develop. Applied to Krentz, waiver should
    not be found upon his failure to predict the District subsequently would be held to be
    an "agency" subject to MAPA provisions.
    I believe the court's opinion fundamentally changes the legal landscape in this
    circuit with regard to waiver of constitutional rights. In doing so, it establishes
    exceedingly unfair precedent, especially for tenured employees who do not
    independently understand the need for or cannot afford a lawyer to search state statutes
    for potentially applicable administrative procedures no matter now obscure.
    10
    The opinion of the court was a plurality opinion joined by four justices. Two
    other justices, who had dissented from the final result of the case (which found that no
    waiver had been made but that the libel judgment should stand against Curtis
    Publishing), explicitly joined in the opinion relating to waiver. And two justices who
    dissented from the result indicated that they also believed the constitutional defense had
    not been waived because they would have ruled in favor of Curtis Publishing. Curtis
    
    Publ'g, 388 U.S. at 133
    , 170, 172 n.1.
    -19-
    The summary judgment should be reversed and Krentz's constitutional claim should be
    remanded for trial.
    Accordingly, I dissent.
    A true copy.
    Attest:
    CLERK, U.S. COURT OF APPEALS, EIGHTH CIRCUIT.
    -20-
    

Document Info

Docket Number: 99-4235

Citation Numbers: 228 F.3d 897

Filed Date: 10/6/2000

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (32)

Larry Bonner v. City of Prichard, Alabama , 661 F.2d 1206 ( 1981 )

wb-parent-of-the-minor-ej-on-her-own-behalf-and-on-behalf-of-her , 67 F.3d 484 ( 1995 )

Curtis Publishing Company v. Wallace Butts, Wallace Butts v.... , 351 F.2d 702 ( 1965 )

Aaron MOSLEY Et Al., Plaintiffs-Appellants, v. ST. LOUIS ... , 634 F.2d 942 ( 1981 )

Lake James Community Volunteer Fire Department, ... , 149 F.3d 277 ( 1998 )

K.M.C. Co., Inc. v. Irving Trust Company , 757 F.2d 752 ( 1985 )

Charlotte Fusco and Daniel Boe v. Xerox Corporation , 676 F.2d 332 ( 1982 )

ari-parnes-deborah-slyne-corey-emert-faye-martin-anderson-edward-r-pepper , 122 F.3d 539 ( 1997 )

Byrd v. Board of Curators of Lincoln University of Missouri , 863 S.W.2d 873 ( 1993 )

Yolanda Fuentes Riggins v. Board of Regents of the ... , 790 F.2d 707 ( 1986 )

John Schleck and Robert Kraft v. Ramsey County, Suzanne ... , 939 F.2d 638 ( 1991 )

Christine Treanor v. MCI Telecommunications Corporation , 200 F.3d 570 ( 2000 )

wayne-louis-bohn-and-sharon-anne-bohn-individually-and-as-natural , 772 F.2d 1433 ( 1985 )

percy-green-ii-v-st-louis-housing-authority-michael-jones-ind-and-in , 911 F.2d 65 ( 1990 )

Ohio Bell Telephone Co. v. Public Utilities Commission , 57 S. Ct. 724 ( 1937 )

In Re Estate of Pittman , 16 S.W.3d 639 ( 2000 )

Franklin v. Harris , 762 S.W.2d 847 ( 1989 )

Wheeler v. Board of Police Commissioners of Kansas City , 918 S.W.2d 800 ( 1996 )

Council House Redevelopment Corp. v. Hill , 920 S.W.2d 890 ( 1996 )

Johnson v. Zerbst , 58 S. Ct. 1019 ( 1938 )

View All Authorities »