NLRB v. Seedorff Masonry, Inc. , 812 F.3d 1158 ( 2016 )


Menu:
  •                     United States Court of Appeals
    For the Eighth Circuit
    ___________________________
    No. 15-1302
    No. 15-2039
    ___________________________
    National Labor Relations Board
    lllllllllllllllllllll                         Petitioner/Cross-Respondent
    International Union of Operating Engineers, Local 150, AFL-CIO
    lllllllllllllllllllllIntervenor
    v.
    Seedorff Masonry, Inc.
    lllllllllllllllllllll                   Respondent/Cross-Petitioner
    ____________
    Submitted: September 21, 2015
    Filed: February 10, 2016
    ____________
    Before LOKEN, BENTON, and SHEPHERD, Circuit Judges.
    ____________
    LOKEN, Circuit Judge.
    On September 7, 2012, with an arbitrator selected to hear a pending grievance,
    Local 150 of the International Union of Operating Engineers (“Local 150”) filed an
    unfair labor practice charge, alleging that Seedorff Masonry, Inc. (“Seedorff”), a
    masonry contractor based in Strawberry Point, Iowa, violated the National Labor
    Relations Act (“NLRA”) “by repudiating the parties’ collective bargaining
    agreement” (“CBA”). The National Labor Relations Board’s General Counsel filed
    a Complaint alleging that Seedorff had violated NLRA §§ 8(a)(1) and (5), 
    29 U.S.C. §§ 158
    (a)(1), (5), by repudiating a CBA between the Quad Cities Builders
    Association (“QCBA”) and Local 150 to which Seedorff had agreed to be bound.
    After an evidentiary hearing, the Board’s Administrative Law Judge (“ALJ”)
    ruled that Seedorff violated §§ 8(a)(1) and (5) by repudiating a valid pre-hire CBA
    with Local 150 and by failing “to abide by the hiring hall and benefit provisions of
    the contract.” The ALJ rejected as largely irrelevant Seedorff’s claim that its actions
    were a lawful response to a jurisdictional dispute between Local 150 and the
    Laborers’ International Union of North America (“the Laborers”) over whether
    Seedorff was properly assigning masonry work that fell within the overlapping
    coverages of the two unions’ pre-hire CBAs to members of the Laborers. The Board
    affirmed the ALJ’s analysis and issued a Decision and Order requiring Seedorff to
    pay Local 150’s members “for any loss of earnings and other benefits suffered as a
    result of [Seedorff’s] failure to honor” its CBA with Local 150. Seedorff Masonry,
    Inc., 360 N.L.R.B. No. 107, at *2 (2014). At oral argument, counsel for the Board
    confirmed that this back pay remedy could include work that had been performed by
    Laborers consistent with that union’s CBA. The Board petitions to enforce its
    Decision and Order. Seedorff cross-petitions to review and vacate the Order. Local
    150 has intervened in support of the Board. Concluding that the Board’s analysis was
    contrary to the NLRA and pre-hire CBAs as construed in prior judicial decisions and
    the Board’s own precedent, we deny enforcement and vacate the Decision and Order.
    I. Background.
    A. Section 8(f) Pre-Hire Agreements. Based on established practice in the
    construction industry, Congress enacted § 8(f) of the NLRA to modify the rule that
    an employer may not enter into a CBA with a union that does not represent a majority
    of the employees in the bargaining unit. See 
    29 U.S.C. § 159
    (a); McKenzie Eng’g
    -2-
    Co. v. NLRB, 
    303 F.3d 902
    , 906 (8th Cir. 2002). Section 8(f) “allows construction
    industry employers and unions to enter into agreements setting the terms and
    conditions of employment for the workers hired by the signatory employer without
    the union’s majority status first having been established in the manner provided for
    under § 9 of the Act.” Jim McNeff, Inc. v. Todd, 
    461 U.S. 260
    , 266 (1983).
    For many years, the Board held that a construction industry employer could
    unilaterally repudiate a § 8(f) pre-hire agreement any time before the union attained
    majority status. However, the Board overturned this rule in John Deklewa & Sons,
    Inc.1 Under Deklewa, § 8(f) agreements are “binding, enforceable, and not subject
    to unilateral repudiation” throughout their term. 275 N.L.R.B. at 1389. We expressly
    upheld the Deklewa rule in NLRB v. W.L. Miller Co., 
    871 F.2d 745
    , 747-48 (8th Cir.
    1989). Although the rule provides that neither party may be compelled to negotiate
    a successor agreement after expiration of a § 8(f) agreement, the Board has ruled that
    an automatic renewal provision in a § 8(f) agreement extends the no-unilateral-
    repudiation rule, a holding we upheld in Cedar Valley Corp. v. NLRB, 
    977 F.2d 1211
    , 1219 (8th Cir. 1992), cert. denied, 
    508 U.S. 907
     (1993).
    Under Deklewa, an employer’s unilateral repudiation of a § 8(f) agreement
    before its expiration violates the employer’s § 8(a)(5) duty to bargain, just as
    repudiation of a CBA with a majority-status union has long been held to violate
    § 8(a)(5).2 McKenzie Eng’g, 
    303 F.3d at 908
    . However, the Board has carved a
    1
    
    282 N.L.R.B. 1375
    , 1389 (1987), enforced sub nom. Int’l Ass’n of Bridge
    Workers, Local 3 v. NLRB, 
    843 F.2d 770
     (3d Cir.), cert. denied, 
    488 U.S. 889
     (1988).
    2
    § 8(a)(5) cryptically provides: “It shall be an unfair labor practice for an
    employer . . . to refuse to bargain collectively with the representatives of his
    employees, subject to the provisions of [§ 9(a)].” 
    29 U.S.C. § 158
    (a)(5).
    -3-
    “single-employee unit” exception to its no-unilateral-repudiation rule for § 8(f) CBAs
    which is critical in this case:
    [W]hen a unit consists of no more than a single permanent employee at
    all material times, an employer has no statutory duty to bargain and thus,
    will not be found in violation of the Act for disavowing a bargaining
    agreement and refusing to bargain.
    Haas Garage Door Co., 
    308 N.L.R.B. 1186
    , 1187 (1992). The Board has explained
    that this exception is based on a fundamental tenet of the NLRA: “[T]he principle of
    collective bargaining presupposes that there is more than one eligible person who
    desires to bargain. The Act therefore does not empower the Board to certify a one-
    man unit.” Foreign Car Ctr., Inc., 
    129 N.L.R.B. 319
    , 320 (1960); see Stack Elec.,
    Inc., 
    290 N.L.R.B. 575
    , 577 (1988).
    B. The Union/Employer Relationships at Issue. Seedorff is a union
    contractor with an office in the Quad-Cities area that seasonally employs “between
    ten and thirty Bricklayers all of the time, and ten to thirty Laborers all of the time.”
    Seedorff’s President, Robert Marsh, testified that Seedorff as a masonry subcontractor
    only enters into § 8(f) pre-hire CBAs; it has § 8(f) CBAs with the Laborers Union and
    the Bricklayers Union. The administrative hearing record includes a multi-employer
    § 8(f) agreement with the Laborers, to which Seedorff was a party; a § 8(f) agreement
    between Seedorff and Operators Local 234; a multi-union § 8(f) Project Labor
    Agreement (“PLA”) governing construction of a state prison in Iowa, to which Local
    150 and Seedorff were parties; and the QCBA agreement here at issue.
    In June 1988, the multi-employer QCBA and its contractor members entered
    into a Building Agreement with Local 150’s predecessor in which each contractor
    recognized Local 150 as the sole collective bargaining agent for employees engaged
    in construction work covered by the agreement. Though not a member of QCBA,
    -4-
    Seedorff signed an individual Building Agreement in July 1988 agreeing that it
    “hereby becomes a signatory employer” and further reciting:
    [Seedorff] who is not a member of the [QCBA] agrees to be bound by
    any amendments, extensions, or changes in this Agreement agreed to by
    the Union and the [QCBA], and further agrees to be bound by the terms
    and conditions of all subsequent contracts negotiated between the Union
    and the [QCBA] unless ninety (90) days prior to the expiration of this
    or any subsequent agreement [Seedorff] notifies the Union in writing
    that it revokes such authorization.
    After 1988, the QCBA and Local 150 entered into ten successor agreements,
    including the one at issue, which was effective from June 1, 2010, to May 31, 2014
    (the “2010 QC Agreement”). Although not apparent from its terms (at least not to
    us), it is undisputed that the 2010 QC Agreement was, as to Seedorff, a § 8(f) pre-hire
    agreement. It is also undisputed that Seedorff never gave Local 150 timely ninety-
    day notice revoking QCBA’s authority to bind Seedorff to the 2010 QC Agreement.
    The record contains little evidence of relations between Seedorff and Local 150
    from 1988 until Seedorff and Local 150 entered into the Iowa prison PLA in the
    spring of 2010. Marsh testified, based on his personal knowledge and review of
    Seedorff’s payroll records, that Seedorff continuously worked in Local 150’s
    jurisdictional territory but only one Operator was ever employed by Seedorff after
    Marsh was hired in 2006, a member of Operators Local 234 who worked on a project
    in Local 150’s territory for three months in 2009, causing Seedorff to make payments
    to Local 150’s benefit funds. On cross examination, Marsh recalled that 1993 payroll
    records showed that Seedorff then employed a Local 150 member who had retired in
    2003. Neither the General Counsel nor Local 150, whose records would doubtless
    show such information, introduced evidence that Seedorff employed any other Local
    150 Operator. In 2011, Local 150 requested that Seedorff sign an agreement that
    -5-
    appears to be a majority-status CBA between Local 150 and a different multi-
    employer bargaining association. Seedorff declined.
    C. The Work Dispute at Issue. Marsh testified that Seedorff has historically
    and contractually assigned the work of “mason tending” to members of the Laborers
    Union for the last 55 years. Mason tending encompasses a variety of tasks, and it
    includes “conveying of all materials used by Masons by any mode or method.” In
    2011, Local 150 challenged Seedorff’s work assignments under its § 8(f) CBA with
    the Laborers. This was hardly a surprising development. As the Seventh Circuit
    noted some years earlier, “[t]he Laborers and Operators were fierce rivals for mason-
    tending forklift work on construction projects,” resulting in “substantial litigation
    before the NLRB.” Hutter Constr. Co. v. IUOE, Local 139, 
    862 F.2d 641
    , 642 n.7
    (7th Cir. 1988).
    In July 2011, Local 150 filed a grievance claiming that Seedorff violated its
    § 8(f) PLA with Local 150 by assigning Laborers to operate forklifts at the Iowa
    prison project. An arbitrator dismissed the grievance, concluding that Seedorff had
    properly assigned the forklift work to the Laborers. Changing tactics, Local 150 filed
    two new grievances in October, claiming that Seedorff had violated the 2010 QC
    Agreement, first, by assigning a Laborer to operate a “boom truck” at a project in
    Burlington, Iowa, and second, by assigning equipment maintenance work to Laborers
    at the Iowa prison project. In both grievances, commonly referred to as “pay-in-lieu”
    grievances, Local 150 demanded “back wages and fringe benefits lost by all affected
    members of the bargaining unit [established by the 2010 QC Agreement] who would
    be working had you honored our Agreement.”
    Seedorff declined to pay the demanded amounts. On November 3, Marsh sent
    Local 150 an email inquiry:
    -6-
    To my knowledge, Seedorff Masonry, Inc. is not a signatory to the
    [2010] Quad City Agreement . . . . If you disagree, please identify the
    document(s) upon which you are relying. We will need this information
    to be able to address your grievances further.
    Within hours, Local 150 sent Seedorff a memorandum and correspondence
    “pertaining to the QC Building Agreement,” which are not part of the administrative
    record. The parties then proceeded through the Agreement’s grievance procedures,
    ultimately selecting an arbitrator and setting possible dates for an arbitration hearing
    to resolve both grievances in the spring of 2012.
    D. Seedorff Seeks Relief from the Board. The NLRA provides that it is an
    unfair labor practice for a union to coerce an employer “to assign particular work to
    employees in a particular labor organization . . . rather than to employees in another
    labor organization.” 
    29 U.S.C. § 158
    (b)(4)(D). When an employer charges a union
    with violating § 8(b)(4)(D), § 10(k) authorizes the Board “to hear and determine the
    dispute out of which such unfair labor practice shall have arisen.” Usually, the
    dispute involves competing claims to work by two unions; often, both have
    “legitimate contractual claims.” Local 30, United Slate Workers v. NLRB, 
    1 F.3d 1419
    , 1428 (3d Cir. 1993). In resolving the § 10(k) dispute by awarding the work to
    one of the competing unions, the Board looks “beyond the four corners of the [CBA]
    to consider the parties’ practice, usage, and custom regarding the agreement.”
    McKenzie Eng’g Co. v. NLRB, 
    182 F.3d 622
    , 625-26 (8th Cir. 1999).
    On January 3, 2012, Seedorff wrote the Great Plains Laborers’ District Council,
    advising that Local 150 was pressuring Seedorff to reassign the operation and
    maintenance of equipment used to transport masonry materials to the operating
    engineers and giving notice that Seedorff “is considering the reassignment of this
    work.” On January 31, Seedorff filed an unfair labor practice charge against the
    Laborers, alleging that Seedorff’s past practice was to assign the work of transporting
    masonry material to the Laborers, Local 150 was pressuring Seedorff to reassign the
    -7-
    work, and the Laborers “have threatened to strike and picket” work sites if Seedorff
    reassigned the work. In late February, the Board’s Regional Director dismissed the
    charge without a hearing, explaining in one paragraph of a letter to Seedorff’s counsel
    that the PLA provided a method to resolve the Iowa prison site dispute and “there are
    no competing claims for the same work” at the Burlington project.3
    E. Seedorff Provokes This Proceeding. Denied a remedy by the Board,
    Seedorff was left with its contractual remedies and obligations.4 With an arbitrator
    selected to hear Local 150’s grievances, counsel for Seedorff wrote Local 150’s
    counsel “to discuss settlement” of the PLA and Burlington grievances. Regarding the
    PLA grievance, Seedorff noted the prior favorable arbitration ruling, predicted “the
    arbitrator would rule similarly in the case at hand,” and offered to settle the grievance
    3
    The latter, unexplained ruling is, in a word, inexplicable. Under the 2010 QC
    Agreement, Local 150 claimed the “operation and maintenance of . . . any [] power
    machine that may be used by [Seedorff] for the construction, alteration, repair or
    wrecking of a building.” Under its § 8(f) CBA with Seedorff, the Laborers claimed
    “conveying of all materials used by Masons by any mode or method.”
    In the months before and after the Board’s decision in this case, the Board held
    § 10(k) hearings to resolve similar disputes between other Operators and Laborers
    local unions, concluding there were competing claims -- the Operators’ pay-in-lieu
    grievances, and the Laborers’ threats to strike if the work was reassigned -- and
    awarding the disputed work to the Laborers. Laborers Local 310 (KMU Trucking),
    361 N.L.R.B. No. 37 (Sept. 3, 2014); Laborers Local 894 (Donley’s, Inc.), 360
    N.L.R.B. No. 20 (Jan. 10, 2014). The merits of the Regional Director’s ruling are not
    at issue. What is troubling is the ALJ’s treatment of the no-competing-claims issue
    as resolved by the Regional Director’s ruling despite overwhelming evidence of
    competing claims in the hearing record.
    4
    Grievance/arbitration contractual remedies subject to judicial review under
    § 301(a) of the Labor Management Relations Act, 
    29 U.S.C. § 185
    (a), and § 10(k)
    decisions by the Board, are alternative methods for resolving jurisdictional work
    assignment disputes. Carey v. Westinghouse Elec. Corp., 
    375 U.S. 261
    , 266 (1964).
    -8-
    by paying $846.40 to the Local 150 Assistance Fund. Regarding the Burlington
    grievance, to which the PLA did not apply, Seedorff asserted there was no basis for
    the grievance because “no collective bargaining agreement currently exists between
    Seedorff and Local 150,” and “therefore request[ed] that Local 150 withdraw the
    Burlington grievance.” On September 7, Local 150 filed this unfair labor practice
    charge alleging that the April 12 letter “violated the Act by repudiating the parties’
    collective bargaining agreement.”
    II. Discussion.
    The ALJ and the Board first ruled that Seedorff was bound by the 2010 QC
    Agreement prior to sending Local 150 the April 12 letter. Substantial evidence
    supports this ruling. See NLRB v. Whitesell Corp., 
    638 F.3d 883
    , 890 (8th Cir. 2011)
    (standard of review). In July 1988, Seedorff agreed to be bound to the then-existing
    Quad Cities Agreement and to “all subsequent contracts negotiated between” Local
    150 and the QCBA. Seedorff concedes it did not timely revoke QBCA’s
    authorization to bargain the 2010 QC Agreement in the manner prescribed. In Cedar
    Valley, we enforced the Board’s order that an employer was bound by a subsequent
    § 8(f) pre-hire agreement in virtually identical circumstances. 
    977 F.2d at 1220
    ;
    accord Local 257, IBEW v. Grimm, 
    786 F.2d 342
    , 346 (8th Cir. 1986).
    In the April 12 letter, Seedorff asserted that, after July 1988, it “consistently
    has informed Local 150 that it has not assigned its bargaining rights to the [QCBA]
    and has not agreed to a [CBA] with Local 150.” Assuming without deciding that
    such conduct would distinguish our decision in Cedar Valley, Seedorff presented no
    evidence supporting this assertion at the administrative hearing. Rather, Seedorff
    argued that Local 150 itself terminated a prior Quad Cities agreement with a March
    2006 letter to the QCBA asking to “start negotiations leading to a new agreement.”
    The ALJ’s finding that this letter served only as notice to start negotiation of a
    successor agreement, not as notice to terminate the existing agreement, was well
    -9-
    supported by the hearing record, including QCBA’s response to Local 150.
    Moreover, even if the 2006 letter had terminated the then-existing Quad Cities
    agreement, we fail to see how that would have affected QCBA’s authority to bind
    Seedorff to the successor 2010 QC Agreement. See Cedar Valley, 
    977 F.2d at 1220
    (“[T]he decisive issue is whether [the employer] affirmatively, and in compliance
    with the terms of the 1978 agreements, revoked [the association’s] authority to bind
    it to successive agreements.”).
    The ALJ and the Board went on to conclude: (A) that the April 12, 2012, letter
    was a “clear and unequivocal” repudiation of the 2010 QC Agreement; (B) that the
    repudiation charge filed by Local 150 was not time-barred by the six-month statute
    of limitations in § 10(b) of the NLRA; and (C) that Seedorff failed to prove its single-
    employee unit “affirmative defense.” We conclude that each of these rulings was
    legally flawed.
    A. The Repudiation Issue. After concluding that Seedorff was bound by the
    2010 QC Agreement, the ALJ stated, “I further find that [Seedorff] violated Section
    8(a)(5) and (1) of the Act5 by failing to abide by the terms of the agreement and by
    repudiating its collective-bargaining relationship with [Local 150].” The “failing to
    abide” finding was a reference to Seedorff assigning to the Laborers work that fell
    within the broad classes of construction work covered by the 2010 QC Agreement,
    an issue not raised in Local 150’s charge for obvious reasons, as we will later explain.
    Neither the ALJ nor the Board discussed why Seedorff’s statement in the April 12
    letter, “Thus, no collective bargaining agreement currently exists between Seedorff
    and Local 150, and there is no basis for Local 150’s Burlington grievance,”
    5
    “A violation of Section 8(a)(5) of the Act produces a derivative violation of
    Section 8(a)(1) by interfering with the collective bargaining rights of employees.”
    St. John’s Mercy Health Sys. v. NLRB, 
    436 F.3d 843
    , 846 n.5 (8th Cir. 2006)
    (quotation omitted). Here, the parties focus exclusively on § 8(a)(5) issues.
    -10-
    constituted a refusal-to-bargain repudiation. The Supreme Court explicitly cautioned
    in Jim McNeff, 
    461 U.S. at
    270 n.11, that context matters in deciding “what specific
    acts would affect the repudiation of a prehire agreement.” Because “[a]rbitrators and
    courts are still the principal sources of contract interpretation,” and repudiation is a
    question of contract interpretation, we review this issue de novo. Litton Fin. Printing
    Div. v. NLRB, 
    501 U.S. 190
    , 202-03 (1991).
    When Seedorff wrote the April 12 letter, it had been denied a § 10(k) remedy
    by the Board and was facing an arbitration hearing on Local 150’s grievances. As
    relevant here, Seedorff had three arbitration defenses -- that it was not bound by the
    2010 QC Agreement; that it could unilaterally repudiate a § 8(f) CBA that purported
    to cover a single-employee unit; and that it had properly assigned work covered under
    the two overlapping § 8(f) CBAs to the Laborers. The first two defenses challenged
    whether there was a CBA for the arbitrator to enforce. Those questions of
    arbitrability are for a court to decide, not the arbitrator, unless the parties agree
    otherwise. See AT & T Techs., Inc. v. Commc’ns Workers of Am., 
    475 U.S. 643
    ,
    648-49 (1986). If those defenses failed, the third issue, whether Seedorff had
    properly assigned the work, was unquestionably for the arbitrator. See 
    id. at 650
    (“[T]hat the employer has violated the [CBA] is to be decided, not by the court asked
    to order arbitration, but as the parties have agreed, by the arbitrator.”).
    After receiving the April 12 letter, Local 150 had various procedural options
    to resolve the jurisdictional contract dispute. It could inquire whether Seedorff
    agreed that the arbitrator would decide arbitrability, in which case the parties would
    schedule the arbitration hearing. It could ask the arbitrator to schedule the hearing,
    leaving Seedorff the option to file a § 301 suit to enjoin arbitration. It could file a
    § 301 suit to compel arbitration. Or Local 150 and Seedorff could petition the Board
    to reconsider the competing claims issue and conduct a § 10(k) hearing. Local 150
    invoked none of these available remedies. Instead, it filed this § 8(a)(5) repudiation
    charge, a procedure that effectively excluded the competing Laborers Union.
    -11-
    In these circumstances, the Board could not decide the contract repudiation
    issue without considering the context of the April 12 letter. The letter did not refuse
    to bargain any issue, the explicit focus of § 8(a)(5). Rather, Seedorff asserted there
    was “no basis” for the breach of contract Local 150 alleged in the Burlington pay-in-
    lieu grievance. Seedorff also offered to settle the Iowa prison work assignment
    grievance; Local 150 had framed that grievance as a breach of the 2010 QC
    Agreement, but Seedorff argued it would be controlled by prior arbitration under the
    PLA. The ALJ and the Board failed to explain why the April 12 letter, standing
    alone and in context, was a repudiation of the § 8(f) 2010 QC Agreement. “[M]ere
    noncompliance with the contract does not in itself suffice to establish repudiation.”
    Grimm, 
    786 F.2d at 346
    .
    B. The § 10(b) Statute of Limitations Issue. Section 10(b) of the NLRA
    provides: “[N]o complaint shall issue based upon any unfair labor practice occurring
    more than six months prior to the filing of the charge with the Board.” 
    29 U.S.C. § 160
    (b). The six-month limitation period begins to run when the charging party
    receives “clear and unequivocal notice that the unfair labor practice had occurred.”
    NLRB v. La-Z-Boy Midwest, 
    390 F.3d 1054
    , 1061 n.1 (8th Cir. 2004). “[A]
    repudiation need not be an express, written repudiation but instead can be manifested
    in a variety of ways.” NLRB v. Jerry Durham Drywall, 
    974 F.2d 1000
    , 1004 (8th Cir.
    1992). Seedorff has the burden to establish this defense by proving that Local 150
    was put on notice more than six months before its September 2012 charge that
    Seedorff had repudiated the 2010 QC Agreement. See 
    id.
     (collecting Board cases);
    AMCAR Div., ACF Indus., Inc. v. NLRB, 
    596 F.2d 1344
    , 1351-52 (8th Cir. 1979).
    The ALJ found that Local 150’s charge was timely because Seedorff’s
    communications relating to the work assignment disputes in 2011 and 2012 were
    equivocal and therefore the April 2012 letter was the first clear and unequivocal
    notice of repudiation Local 150 received. The ALJ also found, elsewhere in the
    opinion, that Seedorff breached the 2010 QC Agreement by “using Laborers to
    -12-
    perform union work.” Numerous Board and court decisions establish that a valid
    § 8(f) CBA may be repudiated by “open and notorious acts by one party, known to
    the other, which are inconsistent with the continuance of the contract.” Contractors
    Health & Welfare Plan v. Harkins Constr. & Equip. Co., 
    733 F.2d 1321
    , 1326 (8th
    Cir. 1984) (remanding a § 301 case for a finding on this issue); see Laborers Health
    & Welfare Tr. Fund v. Westlake Dev., 
    53 F.3d 979
    , 982-83 (9th Cir. 1995); In re
    CAB Assocs., 
    340 N.L.R.B. 1391
    , 1392 (2003).
    From the inception of the 2010 QC Agreement, Seedorff did not hire any Local
    150 member for work that Local 150 contends was covered by that agreement, nor
    did Seedorff make contributions to the Operators benefit funds that hiring Local 150
    members would have required. This conduct, known to Local 150 no later than its
    filing of the October 2011 grievances, appears to have been “open and notorious acts
    . . . inconsistent with the continuance of the contract.” Yet the ALJ did not consider
    whether Seedorff had repudiated the 2010 QC Agreement by conduct well before its
    April 2012 letter, and the Board did not address the issue. If there was repudiation
    by conduct before March 2012, the Board would have been compelled to dismiss the
    General Counsel’s complaint. See St. Barnabas Med. Ctr., 
    343 N.L.R.B. 1125
    , 1127
    (2004) (“[I]f the repudiation occurred outside the 10(b) period, all subsequent failures
    . . . to honor the terms of the [CBA] are deemed consequences of the initial
    repudiation for which the union may not recover.”).
    C. The Single-Employee Unit Issue. Seedorff argues that it lawfully
    repudiated the 2010 QC Agreement because the Board recognizes that an employer
    may unilaterally repudiate a § 8(f) CBA during its term if the union has not achieved
    majority status. We join the Seventh Circuit in recognizing the single-employee unit
    exception in the § 8(f) context. See J.W. Peters, Inc. v. Bridge Workers, Local 1, 
    398 F.3d 967
    , 973-75 (7th Cir. 2005); accord Westlake Dev., 53 F.3d at 982-83. Because
    employment fluctuates greatly in the construction industry, a § 8(f) bargaining unit
    may fall to fewer than two employees with some frequency. See Jim McNeff, 461
    -13-
    U.S. at 266. Therefore, for the exception to apply, the Board “require[s] proof that
    the purportedly single-employee unit is a stable one, not merely a temporary
    occurrence.” McDaniel Elec., 
    313 N.L.R.B. 126
    , 127 (1993).
    Here, Marsh, Seedorff’s President, testified that Seedorff had not employed a
    Local 150 member since 2003 and had employed only one member of Operators
    Local 234 when he worked briefly in Local 150’s territory in 2009. In rejecting the
    single-employee unit defense, the ALJ first held that Seedorff had failed to meet its
    burden of proof on this affirmative defense because Seedorff failed to introduce
    payroll records supporting Marsh’s “conclusory testimony.” This ruling was an error
    of law. The single-employee unit exception is a defense that an employer must
    invoke. But the exception is based on the principle that the NLRA does not empower
    the Board to certify a one-man unit. Therefore, when the defense is properly invoked,
    the Board has recognized that a § 8(a)(5) unfair labor practice charge must be
    dismissed if “the General Counsel has failed to establish” that the appropriate
    bargaining unit consisted of more than one employee during the time in question. D
    & B Masonry, 
    275 N.L.R.B. 1403
    , 1409 (1985) (emphasis added), followed in Stack
    Elec., 290 N.L.R.B. at 577-78. We have carefully reviewed the Board cases cited by
    the ALJ; none support her ruling reversing these contrary burden-of-proof rulings.
    Marsh’s testimony was clearly sufficient to require that the General Counsel submit
    evidence proving the absence of a single-employee unit. In summarily affirming the
    ALJ on this issue, the Board lost sight of the important distinction between an
    employer’s burden of going forward with evidence establishing a prima facie case for
    the exception, and the General Counsel’s ultimate burden of persuasion. See
    generally NLRB v. Mastro Plastics Corp., 
    354 F.2d 170
    , 176-78 (2d Cir. 1965).
    The ALJ went on to conclude that Seedorff’s single-employee unit defense
    failed because Seedorff “used Laborers to perform union work as defined in the
    QCBA agreement.” This alternative holding is based on two more serious errors of
    law. First, the General Counsel’s complaint alleged that the bargaining unit consisted
    -14-
    of “the employees described in Article 11” of the 2010 QC Agreement, which set
    forth wages and classifications for all Operators covered by the agreement. The
    General Counsel submitted no evidence supporting that allegation. The ALJ’s ruling
    implicitly decided an issue which to our knowledge the Board has never addressed --
    when an employer has entered into § 8(f) pre-hire CBAs that define overlapping work
    coverages, and the employer has validly assigned all the work to members of another
    union and claims the single-employee unit exception to its § 8(a)(5) duty to bargain
    with the charging party union, does the bargaining unit to which the exception applies
    include the second union’s employees? In our view, the logical answer is no. But in
    any event, we will not enforce an order that simply refused to address the issue.
    Second, the ALJ concluded (assumed would be more accurate) that Seedorff
    violated the 2010 QC Agreement by assigning work covered by that pre-hire CBA to
    members of the Laborers Union.6 This ruling was contrary to the well-recognized
    principle that, when an employer has entered into § 8(f) CBAs with competing craft
    unions, the NLRB and § 301 courts look beyond the four corners of the CBAs to
    consider the parties’ practice, usage, and custom in determining whether the employer
    violated the NLRA in assigning the work at issue. See McKenzie Eng’g, 
    303 F.3d at 908-10
    ; Sheet Metal Workers Int’l Ass’n Local Union No. 27 v. E.P. Donnelly,
    Inc., 
    737 F.3d 879
    , 888 (3d Cir. 2013). Here, since the General Counsel declined to
    introduce evidence addressing the question, the record can only support the
    conclusion that Seedorff did not violate the 2010 QC Agreement by continuing its
    long-standing practice of assigning mason-tending work at the Burlington and Iowa
    prison projects to members of the Laborers Union. By refusing to resolve this issue,
    the Board entered an Order that may enrich Local 150’s members for work they were
    not entitled to perform and may force Seedorff to pay for work that it already properly
    6
    The ALJ also found that Seedorff “created this ‘jurisdictional dispute’ . . .
    when it attempted to assign union work to the Laborers,” an assertion made by the
    Operators and rejected by the Board in KMU Trucking, 361 N.L.R.B. No. 37, at *3,
    and in Donley’s, Inc., 360 N.L.R.B. No. 20, at *4.
    -15-
    paid Laborers to do. This we will not enforce. McKenzie Eng’g, 373 F.3d at 894
    (NLRA remedy may not confer a “windfall” nor be “unduly punitive”).
    III. Conclusion.
    By refusing to acknowledge these issues and present evidence addressing them,
    the General Counsel and Local 150 as Charging Party failed to prove essential
    elements of the Complaint, as was true in McKenzie Eng’g, 
    303 F.3d at 911
    . By
    ruling that these issues were irrelevant and failing to resolve them, the ALJ and the
    Board issued an unlawful Order that may not be enforced. Accordingly, we deny the
    Board’s Application for Enforcement, grant Seedorff’s Cross Petition for Review, and
    vacate the Board’s Decision and Order dated May 7, 2014.
    ______________________________
    -16-
    

Document Info

Docket Number: 15-1302

Citation Numbers: 812 F.3d 1158

Filed Date: 2/10/2016

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (19)

national-labor-relations-board-v-mastro-plastics-corporation-and-french , 354 F.2d 170 ( 1965 )

local-30-united-slate-tile-and-composition-roofers-damp-and-waterproof , 1 F.3d 1419 ( 1993 )

amcar-division-acf-industries-incorporated-v-national-labor-relations , 596 F.2d 1344 ( 1979 )

National Labor Relations Board v. Whitesell Corp. , 638 F.3d 883 ( 2011 )

hutter-construction-co-and-wisconsin-laborers-district-council-and , 862 F.2d 641 ( 1988 )

jw-peters-inc-v-bridge-structural-and-reinforcing-iron-workers-local , 398 F.3d 967 ( 2005 )

Cedar Valley Corporation v. National Labor Relations Board , 977 F.2d 1211 ( 1992 )

McKenzie Engineering Company, Petitioner/cross-Respondent v.... , 182 F.3d 622 ( 1999 )

National Labor Relations Board v. La-Z-Boy Midwest, a ... , 390 F.3d 1054 ( 2004 )

St. John's Mercy Health Systems, Doing Business as St. John'... , 436 F.3d 843 ( 2006 )

McKenzie Engineering Company, Petitioner-Cross-Respondent v.... , 303 F.3d 902 ( 2002 )

Local 257, International Brotherhood of Electrical Workers, ... , 786 F.2d 342 ( 1986 )

national-labor-relations-board-v-wl-miller-company-eastern-missouri , 871 F.2d 745 ( 1989 )

National Labor Relations Board v. Jerry Durham Drywall, ... , 974 F.2d 1000 ( 1992 )

contractors-laborers-teamsters-engineers-health-welfare-plan , 733 F.2d 1321 ( 1984 )

Carey v. Westinghouse Electric Corp. , 84 S. Ct. 401 ( 1964 )

At&T Technologies, Inc. v. Communications Workers , 106 S. Ct. 1415 ( 1986 )

Litton Financial Printing Div., Litton Business Systems, ... , 111 S. Ct. 2215 ( 1991 )

Jim McNeff, Inc. v. Todd , 103 S. Ct. 1753 ( 1983 )

View All Authorities »