Lamb Engineering Co. v. NE Public Power Dist ( 1997 )


Menu:
  •                                    ____________
    No. 95-3398
    ____________
    Lamb Engineering & Construction         *
    Company,                                *
    *
    Appellee,           *
    * Appeal from the United States
    v.                                * District Court for the
    * District of Nebraska
    Nebraska Public Power District,         *
    *
    Appellant.          *
    ____________
    Submitted:    May 13, 1996
    Filed:     January 9, 1997
    ____________
    Before McMILLIAN, FAGG and LOKEN, Circuit Judges.
    ____________
    McMILLIAN, Circuit Judge.
    Nebraska Public Power District ("NPPD") appeals from a final judgment
    entered in the United States District Court for the District of Nebraska
    awarding Lamb Engineering & Construction Co. ("Lamb") $1,129,620 in
    contract damages.   Lamb Eng'g & Constr. Co. v. Nebraska Pub. Power Dist.,
    No. 4:CV94-29 (D. Neb. June 22, 1995) (Judgment) (Lamb Eng'g).            For
    reversal, NPPD argues the district court erred in denying its amended
    motion for judgment as a matter of law or, in the alternative, for a new
    trial, interpreting the contract, instructing the jury, and admitting
    certain evidence.
    NPPD also argues the district court erred in awarding attorney fees
    in the amount of $277,649.50.      
    Id. (Aug. 25,
    1995).   NPPD argues that the
    award of attorney fees was contrary to Nebraska law and unsupported by the
    evidence.
    For the reasons discussed below, we affirm in part and reverse in
    part the order of the district court and remand the case to the district
    court for a new trial.
    I.     Background
    NPPD, a public power district, is a public corporation and political
    subdivision of the State of Nebraska.        On October 2, 1992, consistent with
    certain statutory competitive bidding requirements, NPPD opened bids for
    Contract No. 92-71 (the "contract") for refurbishing and upgrading 65 miles
    of NPPD's 115 kilovolt transmission line which runs along the Platte River
    from Columbus to Grand Island, Nebraska.           The transmission line consists
    of three distinct sections which are separated by substations:           section 1,
    from Grand Island to Central City; section 2, from Central City to Silver
    Creek; and section 3, from Silver Creek to Columbus.           The line consists of
    523 total structures.
    NPPD wrote the contract as a unit-price contract in which estimated
    quantities of work were provided to bidders in order to compare bids
    offered under the contract on a uniform basis.          On October 29, 1992, NPPD
    awarded the contract to Lamb as the responsible bidder who submitted the
    lowest and best bid of $769,300.          The exact compensation payable to Lamb
    under the contract was to be determined on the basis of the unit-prices for
    work actually performed.      On January 18, 1993, Lamb began work on the line,
    which was to be completed by June 5, 1993.
    Lamb encountered difficulties in performing the contract.                  The
    circumstances giving rise to the difficulties are disputed.           Lamb contends
    that NPPD administered the contract in bad faith, causing Lamb to be unable
    to   fully   perform   the   contract.      Lamb   maintains   that   "[d]uring   the
    evaluation of the several bids, a faction developed within NPPD's System
    Planning and Engineering Division which opposed awarding the Contract to
    Lamb."   Brief for Appellee
    -2-
    at 1.      Lamb also maintains that "these same individuals who opposed
    awarding Lamb the Contract, were given responsibility for administering the
    Contract and they never relented in their opposition to having Lamb perform
    the work."       
    Id. at 2.
      Lamb claims that the faction tried to hinder and
    financially oppress Lamb through the faction's administration of the
    contract.    
    Id. On January
    29, 1993, NPPD sent a letter to Lamb seeking assurances
    that Lamb would timely complete the contract.        Lamb interpreted the letter
    as a threat that work be accelerated immediately or Lamb would face
    possible termination, based on the fact that NPPD sent a copy of the letter
    to   Lamb's surety, who was only to be contacted in the event of a
    termination for default.        Brief for Appellee at 2.        Lamb suggests that
    NPPD's bad faith administration of the contract is evidenced by the fact
    that    almost    immediately   after   NPPD   awarded   Lamb   the   contract,   NPPD
    increased its original estimate of work to be performed by 80%, but refused
    to extend Lamb's time for performance.          
    Id. at 2-3.
        Lamb maintains that
    it was entitled to a time extension under the contract's force majeure
    clause1 because of the additional work imposed by NPPD and
    1
    The force majeure clause provided, in pertinent part:
    The CONTRACTOR agrees that ... he has taken
    into consideration ... all of the ordinary delays
    due to normally inclement weather, in securing
    materials or workmen, or otherwise. In the event
    that the CONTRACTOR is delayed in the performance
    of the work as a result of causes beyond his
    control and which he could not have reasonably
    anticipated and without his fault or negligence,
    such as acts of God, fire, flood, war, or
    governmental or judicial action ..., the time
    specified in the Contract Documents for completion
    of the work may be extended for an appropriate
    period reflecting the actual effect of the delay on
    the performance of the work... If the CONTRACTOR
    encounters extra costs as a result of delays which
    are beyond his control and which he could not have
    reasonably anticipated and without his fault or
    negligence, including those delays which are due to
    the actions of the DISTRICT ..., the CONTRACTOR
    shall promptly give the DISTRICT notice ... of such
    -3-
    due to "unexpected and abnormally wet and muddy soil conditions during
    January through April, 1993."          
    Id. at 3.
           Lamb claims that NPPD's
    unwillingness to extend the June 5, 1993, completion date resulted in
    greatly increased costs to Lamb for labor, equipment, and materials.           
    Id. at 4.
    NPPD's   description   of    the     circumstances    surrounding   Lamb's
    performance is markedly different from Lamb's.         NPPD notes that "[a]lthough
    Lamb characterizes itself as an experienced contractor, it primarily has
    worked on substations and has had very limited experience with electric
    transmission lines."    Reply Brief for Appellant at 8.          NPPD claims that,
    not only did Lamb's field superintendent have no prior experience with an
    electric    transmission   line     project,    but    also   Lamb's   right-of-way
    coordinator and material coordinator lacked any experience with such work.2
    
    Id. at 8-9.
         As further proof of Lamb's inexperience, NPPD notes that
    neither Lamb's president nor Lamb's estimator, who prepared the bid,
    understood the contract's unit-pricing.          
    Id. NPPD maintains
    that, for
    these reasons, NPPD's transmission engineering department discouraged
    awarding the contract to Lamb.       
    Id. After the
    contract was awarded to Lamb, however, NPPD claims to have
    taken "extraordinary steps to assist Lamb on the project," none of which
    were required under the contract.          For example, NPPD allegedly performed
    an advance ground-level inspection of the line, prepared summary sheets for
    Lamb showing the expected work at each structure location, contacted
    landowners to arrange access routes for Lamb, and hired an outside expert
    to perform aerial inspection work.      
    Id. The ground-level
    inspection of the
    line revealed that
    extra costs.
    Contract No. 92-71, at D-13 to 14.
    2
    Those two positions were assigned to the 18- and 21-year-old
    sons of Lamb's president. Reply Brief for Appellant at 9.
    -4-
    more poles required replacement than anticipated, resulting in an increase
    of approximately 11% over the original work estimate contained in the
    contract, with a total price increase of approximately $85,403.                     NPPD
    suggests that "Lamb's president mistakenly interpreted this increase to
    apply only to the first section of the line," rather than to the total
    contract.     
    Id. at 10.
         NPPD claims that due to "Lamb's lack of progress
    during the first month of the project and the continued failure of Lamb's
    project manager to deliver required construction schedules to NPPD," it
    sent Lamb the January 29, 1993, letter seeking assurance that Lamb intended
    to complete the project on time.            
    Id. NPPD maintains
    that the letter
    "expressly advised Lamb that the transmission line needed to be returned
    to service by the scheduled June 5th completion date in order to handle
    NPPD's increased summer load," and thus no extensions would be granted.
    
    Id. NPPD maintains
    that the force majeure clause did not apply to the
    difficulties encountered by Lamb.            At trial, NPPD presented extensive
    expert testimony by a meteorologist and a geotechnical engineer that "the
    precipitation, temperature, groundwater, and soil conditions experienced
    on the project were typical of conditions along the Platte River in
    Nebraska    during   winter    and    spring,   and   should   reasonably   have    been
    anticipated by Lamb."      
    Id. at 11.
        NPPD claims that it informed Lamb that,
    even though the force majeure clause did not apply, Lamb had the right
    under the contract to stop work if the weather or soil conditions were
    unsuitable.    
    Id. In March
    1993, NPPD notified Lamb that it should simply
    perform as much work as possible before June 5th.              
    Id. In March
    1993, Lamb and NPPD negotiated a tentative "standby"
    agreement by which Lamb would temporarily shut down the project due to the
    weather and soil conditions.         Lamb claims that the agreement was finalized,
    thus justifying Lamb's decision to send its crews home on March 17.                Brief
    for Appellee at 5.    NPPD asserts, however, that the terms of the agreement
    were subject to further review of
    -5-
    applicable labor and equipment rates.              Reply Brief for Appellant at 11.
    NPPD argues that it was justified in rejecting the "standby" agreement
    because    it   had   not    been   reduced   to   writing   and   faxed   to   Lamb   for
    modification or execution as agreed.            
    Id. In April
    1993, Lamb's performance increased as the weather and soil
    conditions improved.        On April 21, 1993, NPPD suggested in a letter to Lamb
    that all work in section 3 of the transmission line be deleted from the
    contract, as Lamb had not yet begun any of that work.                Lamb rejected the
    proposal and on May 6, 1993, demanded that it be allowed to perform the
    work on section 3 as provided in the contract.
    On May 7, 1993, NPPD gave Lamb written notice that it was terminating
    the contract under the contract's termination clause, which provided:
    The DISTRICT may at any time, and without cause,
    terminate this Contract by mailing a written notice
    thereof to the CONTRACTOR at the address given in the
    Proposal Section of these Contract Documents. Upon any
    such Termination, the DISTRICT shall pay the CONTRACTOR
    reasonable and proper charges for termination.
    Contract No. 92-71, at D-12.         As of that date, Lamb had partially performed
    its work under the contract on the first two sections of the transmission
    line.     Lamb had performed work on 262 of the 523 structures on the
    transmission line and had completed work on 123 of those structures.
    During the project, Lamb submitted four progress payment invoices for
    work performed through February 24, 1993, March 17, 1993, April 7, 1993,
    and April 23, 1993.         NPPD made adjustments to the invoices and deducted a
    5% retainage fee, ultimately paying Lamb $260,991.22.              Lamb also submitted
    an invoice to NPPD for state use taxes in the amount of $969.44, which NPPD
    paid in full on
    -6-
    June 30, 1993.    Lamb submitted additional invoices for:         claimed extra work
    in preparing the transmission line for re-energization and in demobilizing
    before the temporary shutdown of the project in mid-March 1993, totalling
    $36,473.00;      "standby"     costs    during     the   temporary    shutdown     and
    remobilization costs totalling $83,755.50; "down time" or "force majeure"
    costs    totalling       $186,817.33;   and      "acceleration"    costs   totalling
    $122,764.74.     Lamb refused to accept partial payment tendered by NPPD for
    the   claimed    costs    associated    with   the   temporary    shutdown,   namely,
    demobilization costs of $5,416.00 and standby costs of $25,907.40.                NPPD
    denied the remaining invoices.
    Following the termination of the contract, Lamb submitted three
    "termination" invoices, apparently for costs in addition to those included
    in the progress payment invoices submitted during the project.                   These
    termination invoices included labor, equipment, and material charges for
    the entire project, totalling $1,239,817.20.             NPPD refused to pay the
    termination invoices and requested that Lamb submit invoices for any unpaid
    unit-price work and for any reasonable and proper termination charges, as
    provided by the contract.
    Lamb originally filed its complaint in the United States District
    Court for the District of Utah on September 2, 1993, and subsequently
    amended it twice.        NPPD's motion to dismiss for lack of jurisdiction was
    denied, but the district court granted NPPD's motion to change venue to the
    United States District Court for the District of Nebraska.
    In its second amended complaint, Lamb alleged:               (1) breach of
    contract for wrongful termination; (2) account stated for reasonable and
    proper charges for termination, including profit and post-termination
    demobilization charges; and (3) unjust enrichment in an amount equal to the
    reasonable value of materials and services furnished.             NPPD answered and
    asserted a counterclaim,
    -7-
    seeking:    (1) a declaratory judgment establishing the amount due to Lamb
    for work performed under the contract based on unit-prices and any other
    "reasonable and proper charges for termination" under the contract; and (2)
    judgment    awarding   damages   in   favor   of   NPPD   for   all    cleanup   costs,
    restoration costs, property damages, and rework costs for which Lamb was
    responsible under the contract.
    Upon review of NPPD's Motion for Partial Summary Judgment, the
    district court granted the motion in part, holding that NPPD did not breach
    the contract by "enlarging the scope of work" or wrongfully terminate the
    contract.     Lamb Eng'g, slip op. at 7 (Feb. 15, 1995).                 However, the
    district court denied NPPD's motion for partial summary judgment with
    respect to Lamb's second and third causes of action.             
    Id. During the
    course of the trial, Lamb's first and third causes of
    action and NPPD's counterclaim were voluntarily dismissed.                Only Lamb's
    account stated claim was submitted to the jury.                  The district court
    submitted, over NPPD's objections, a special interrogatory to the jury to
    determine whether NPPD acted in bad faith in administering the contract.
    Tr. at 3865:22-3866:13.    The jury returned a verdict in favor of Lamb for
    $1,129,620.00 in damages and responded affirmatively to the special
    interrogatory, finding that NPPD administered the contract in bad faith.
    The district court denied NPPD's motion for judgment as a matter of law or,
    in the alternative, for new trial.      The district court subsequently granted
    Lamb's motion for an award of attorney fees based on the jury's finding of
    bad faith or alternatively, on the district court's own finding of bad
    faith.   Lamb Eng'g, slip op. at 1 (Aug. 25, 1995).             NPPD appeals.
    -8-
    II.   Discussion
    A.    Trial Errors
    NPPD contends that various errors committed by the district court
    entitle it to judgment as a matter of law or, in the alternative, a new
    trial.     For clarity, we consolidate NPPD's issues on appeal and address
    the purported errors by the district court.        "We review the district
    court's denial of a motion for judgment as a matter of law de novo using
    the same standards as the district court."   McKnight v. Johnson Controls,
    Inc., 
    36 F.3d 1396
    , 1400 (8th Cir. 1994) (citations omitted).    A motion for
    judgment as a matter of law presents us with a legal question on review:
    "whether there is sufficient evidence to support a jury verdict."        
    Id. NPPD argues
    that the district court erred in denying its motion for
    judgment as a matter of law because Lamb failed to prove any reasonable and
    proper charges for termination.     We do not find it appropriate to grant
    judgment as a matter of law in favor of NPPD because the reasonable and
    proper charges for termination must be decided by the factfinder on remand.
    We review a district court's denial of a new trial motion for an
    abuse of discretion.   Farmland Indus., Inc. v. Morrison-Quirk Grain Corp.,
    
    54 F.3d 478
    , 483 (8th Cir. 1995).     We will reverse the District Court's
    decision if it "represents a clear abuse of discretion or a new trial is
    necessary to avoid a miscarriage of justice."    
    Id. For the
    reasons stated
    below, we hold that the erroneous instruction of the jury regarding damages
    and   contract interpretation and the erroneous admission of evidence
    regarding expected loss of gross margin, total costs, and breach of
    contract costs were sufficiently prejudicial to warrant setting aside the
    jury's award of damages and require a new trial.       Accordingly, we affirm
    in part and reverse in part and remand this case to the district court for
    a new trial on damages, to be submitted to the jury in a manner consistent
    with this opinion.
    -9-
    Damages Under the Contract's Unit-Price Provision
    The interpretation of a contract presents a question of law to be
    reviewed de novo.   See Simeone v. First Bank Nat'l Ass'n, 
    971 F.2d 103
    , 106
    (8th Cir. 1992); International Union of Operating Eng'rs Local 571 v.
    Hawkins Constr. Co., 
    929 F.2d 1346
    , 1348 (8th Cir. 1991).
    NPPD argues the district court erred in ruling that "[w]hether the
    contract was a unit-priced contract does not govern matters of damage under
    the termination clause."   Lamb Eng'g, slip op. at 2 (Aug. 23, 1995).   NPPD
    contends the district court should have construed the termination clause
    in conjunction with the other payment provisions in the contract.3        A
    contract must be construed as a whole, and "the meaning which arises from
    a particular portion of an agreement cannot control the meaning of the
    entire agreement where such inference runs counter to the agreement's
    overall scheme or plan."    Rafos v. Outboard Marine Corp., 
    1 F.3d 707
    , 709
    (8th Cir. 1993).    We agree with NPPD that the unit-price provision governs
    payment owing under this contract for work already performed by Lamb.
    Thus, evidence concerning work performed, for which Lamb was paid by NPPD,
    is irrelevant and inadmissable on remand.   Damages for work performed, for
    which Lamb has not been paid, must be calculated pursuant to the contract's
    unit-price provision.      That amount is equal to Lamb's unit bid price
    multiplied by the quantity of work performed by Lamb.   See Contract No. 92-
    71, at C-3.
    3
    Contrary to Lamb's assertion, Brief for Appellee at 12, NPPD
    properly preserved its objection to the district court's
    interpretation of the termination clause.        See Answer and
    Countercl., App. for Appellant at 19-35; Mtn. in Limine,
    Supplemental App. for Appellant at 110-115; Pretrial Conference
    Order, App. for Appellee at 121-25; and Mtns. for Judgment
    Notwithstanding   the  Verdict   and  Alternatively   New  Trial,
    Appellant's Addendum at 15.
    -10-
    Damages for Future Profits
    NPPD also argues the district court erred in admitting expected loss
    of gross margin evidence.     We agree.
    The contract's termination clause provided:
    The DISTRICT may at any time, and without cause,
    terminate this Contract by mailing a written notice
    thereof to the CONTRACTOR at the address given in the
    Proposal Section of these Contract Documents. Upon any
    such Termination, the DISTRICT shall pay the CONTRACTOR
    reasonable and proper charges for termination.
    Contract No. 92-71, at D-12.       Under Nebraska law, loss of profit damages
    may be awarded only where a wrongful termination occurred.          Von Dorn v.
    Mengedoht, 
    59 N.W. 800
    , 802 (Neb. 1894) (cited with approval in Kroeger v.
    Franchise Equities, Inc., 
    212 N.W.2d 348
    , 349 (Neb. 1973)); accord Makskym
    v. Loesch, 
    937 F.2d 1237
    , 1245 (7th Cir. 1991) (When a contract is
    "terminated by either party without breach or liability, the only money
    owing to either is money that has accrued from the past performance of the
    contract.").   Here, the termination clause explicitly gave NPPD the right
    to terminate the contract "at any time and without cause."
    The district court also erroneously instructed the jury on damages
    by permitting the jury to "consider all the circumstances, including the
    amount of work expected to be performed ... and any other factors that are
    shown by the evidence and that bear on the issue on what charges for
    termination    are   reasonable   and   proper."   Appellant's   Addendum   at 8
    (emphasis added).    Because a damage award for loss of expected gross margin
    is contrary to Nebraska law, the district court abused its discretion in
    admitting this evidence and allowing the jury to consider it in determining
    damages.
    -11-
    Reasonable and Proper Charges for Termination
    NPPD also argues the district court erred in instructing the jury to
    determine the meaning of the termination clause.4            NPPD specifically
    objects to the district court's instructions that "any doubt concerning the
    meaning [of the contract] must be resolved against the party that drafted
    the contract language [NPPD]," and the jury should interpret the contract
    in a way which will prevent "oppressive or inequitable results."               Tr.
    3866:14-3867:25.   Under Nebraska law, the proper construction of a written
    contract is a question of law to be determined by the court.         Swanson v.
    Baker Indus., Inc., 
    615 F.2d 479
    , 483 (8th Cir. 1980).       Where a provision
    in a written contract is not ambiguous, the trial court must determine its
    meaning as a matter of law, and not submit the issue to the jury.         Smith
    v. Wrehe, 
    261 N.W.2d 620
    , 625 (Neb. 1978).
    Here, the district court found that the termination clause was
    unambiguous.     Lamb Eng'g, slip op. at 3 (May 26, 1995).          Because the
    contract was unambiguous, the district court committed reversible error in
    submitting the issue to the jury.         See United States Fire Ins. Co. v.
    Pressed Steel Tank Co., Inc., 
    852 F.2d 313
    , 316-17 (7th Cir. 1988).
    We read the unambiguous provision in the termination clause providing
    for the "reasonable and proper charges for termination" to include only
    those reasonable and proper expenses incurred, or disbursements made, in
    connection with the termination.     See BLACK'S LAW DICTIONARY 233 (6th ed.
    1990) (defining charges as "[t]he expenses which have been incurred, or
    disbursements made, in connection with a contract, suit, or business
    transaction").      The   determination    of   which   expenses   incurred,    or
    disbursements made, in
    4
    After examining the trial transcript, we reject Lamb's
    contention that NPPD did not properly object to the jury
    instruction regarding contract interpretation. See Tr. at 3779:20-
    3780:5; 3782:20-3783:13.
    -12-
    connection with the termination were reasonable and proper is a question
    of fact for the factfinder.
    We agree with NPPD that the district court abused its discretion in
    admitting total costs evidence.    This court gives "great deference to a
    district court's rulings on admissibility of evidence and will reverse only
    if the court has committed a clear abuse of discretion."   United States v.
    Jackson, 
    914 F.2d 1050
    , 1053 (8th Cir. 1990).     Furthermore, we will not
    disturb a jury's verdict "absent a showing that the evidence was so
    prejudicial as to require a new trial which would be likely to produce a
    different result."   O'Dell v. Hercules, Inc., 
    904 F.2d 1194
    , 1200 (8th Cir.
    1990).   Lamb's total costs evidence, showing the magnitude of Lamb's
    expenses during the entire project, is irrelevant to the determination of
    the reasonable and proper expenses incurred, or
    disbursements made, in connection with the termination.5
    NPPD argues the district court erred in admitting Trial Exhibits 112
    and 113 and William Schwartzkopf's testimony
    5
    We address additional reasons that the testimony and exhibits
    used to present the total cost evidence was inadmissible, since the
    issue may recur on remand. Trial Exhibit 293, dated May 15, 1995,
    was a report prepared by Bruce Wisan, a certified public
    accountant, for Lamb's attorney just weeks before trial.        The
    report explicitly indicated that it was prepared solely for use in
    the Lamb and NPPD litigation, thus, it is does not qualify as a
    business record under Fed. R. Evid. 803(6) as an exception to the
    hearsay rule.    See Potamkin Cadillac Corp. v. B.R.I. Coverage
    Corp., 
    38 F.3d 627
    , 632 (2d Cir. 1994); Paddack v. Dave
    Christensen, Inc., 
    745 F.2d 1254
    , 1258-59 (9th Cir. 1984).
    Similarly, Wisan's testimony, which was based upon his personal
    review and audit of Lamb's costs records, was inadmissible without
    Wisan's designation as an expert witness because his testimony was
    based upon the report he prepared for use in the litigation and not
    in the ordinary course of business.      See Burlington N. R.R. v.
    Nebraska, 
    802 F.2d 994
    , 1004-05 (8th Cir. 1986).
    -13-
    concerning them.6   Trial Exhibit 113 lists two methods for calculating the
    reasonable and proper termination charges.7       App. for Appellee at 256.      The
    Termination Invoices method is based upon Lamb's termination invoice
    requests, minus payments Lamb received for completed work.           The Cost Method
    is based upon Lamb's adjusted costs, overhead, profit, owned equipment
    value, and loss of gross margin on uncompleted work, minus payment already
    received for completed work.     Evidence admitted for purposes of the jury's
    determination of reasonable and proper termination charges must be relevant
    to the reasonable and proper expenses incurred, or disbursements made, in
    connection with the termination, and shall not include lost profits, costs
    incurred which had already been reimbursed at the time of the termination,
    or costs that are not connected with the termination.
    NPPD also argues the district court erred in admitting Trial Exhibits
    185, 193, and 196 ("termination" invoices), Trial Exhibits 139, 141, and
    165   ("force   majeure"   or   "down   time"   invoices),   Trial     Exhibit   171
    ("acceleration" invoice), and testimony regarding those trial exhibits.
    Lamb admits in its brief that this evidence was admitted as relevant to its
    breach of contract claim, which was subsequently withdrawn.               Brief for
    Appellee at 21.     Lamb argues that this evidence remained relevant to the
    termination clause claim to "show the magnitude of the increase in Lamb's
    costs resulting from performing its work in the changed and abnormally
    severe conditions."    
    Id. While NPPD
    failed to request a limiting instruction regarding this
    evidence and its questionable applicability to the termination
    6
    After reviewing the trial transcript, we reject Lamb's
    assertion that NPPD did not object to the admission of this
    evidence. See Tr. at 1765:23-1766:5; 1761:2-6; 1769:15-17.
    7
    The contents of Trial Exhibit 112 are duplicated in Trial
    Exhibit 113. For simplicity, we address only Trial Exhibit 113,
    but our findings apply to both Trial Exhibits.
    -14-
    clause damages, we find NPPD's initial objection to the relevancy of the
    evidence sufficient to preserve this issue for appellate review.              This
    evidence was relevant only to the breach of contract claim and should not
    have been admitted to determine damages owed under the termination clause.
    "That    these   errors   caused,   or   contributed   to,   a   prejudicial
    conclusion is obvious when one considers the jury verdict."        GFH Fin. Serv.
    Corp. v. Kirk, 
    437 N.W.2d 453
    , 460 (Neb. 1989) (finding obvious error where
    "[t]he language of this instruction allowed the jury to consider a total
    damages figure before any credits were given for the 'reasonable sales
    value' of the equipment, it allowed the jury to consider storage fees which
    were not recoverable under the lease, and it allowed the jury to consider
    the attorney fees expended by the plaintiff when such fees are not
    recoverable under the laws of the State of Nebraska").        Any money owed by
    NPPD to Lamb for work already performed must be calculated using the
    contract's unit-price provision.      Damages available under the reasonable
    and proper termination charges provision are limited to the reasonable and
    proper expenses incurred, or disbursements made, in connection with the
    termination.
    Because the jury returned only a general verdict, it is impossible
    to determine whether the inadmissible evidence did not affect the verdict,
    See Square Liner 360E, Inc. v. Chisum, 
    691 F.2d 362
    (8th Cir. 1982),
    therefore warranting a new trial.    A new trial is also required because the
    district court improperly allowed the jury to interpret an unambiguous
    contract.   See Green Tree Acceptance, Inc. v. Wheeler, 
    832 F.2d 116
    , 117-18
    (8th Cir. 1987) ("Because we cannot be confident that the jury verdict was
    not tainted by the erroneous and prejudicial submission of an unambiguous
    contract for jury interpretation, we reverse and remand
    -15-
    for a new trial.").8      Finally, a new trial on the issue of damages is
    warranted based on the district court's erroneous submission of the bad
    faith special interrogatory to the jury.9          See Libbey-Owens-Ford Co. v.
    Insurance Co. of N. Am., 
    9 F.3d 422
    , 427 (6th Cir. 1993) ("One ground for
    a new trial is the submission to the jury of an issue not appropriate for
    its consideration.")10; see also Feldman v. Connecticut Mut. Life Ins. Co.,
    
    142 F.2d 628
    , 634 (8th Cir. 1944) ("[T]he submission of an improper special
    interrogatory, or the submission of a special interrogatory without such
    explanation or instruction as will enable the jury competently to answer
    it,   manifestly   may   constitute   reversible   error   where   the   record   is
    convincing that the answer made to the special interrogatory has determined
    the result of the jury's general verdict.").       For these reasons, we reverse
    the damages award and remand the case to the district court for a new trial
    on the issue of damages.11
    B.    Attorney Fees Award
    It is not clear whether the district court awarded attorney fees to
    Lamb under state law or federal law.       Thus, we address the
    8
    We reject Lamb's assertion, Brief for Appellee at 25-26, that
    because NPPD failed to request a special interrogatory to determine
    upon which method of costs the jury relied, NPPD cannot show
    prejudice sufficient to warrant a new trial.
    9
    After reviewing the record, we find, contrary to Lamb's
    assertion, Brief for Appellee at 45, that NPPD did properly object
    to the submission of the bad faith issue to the jury.       Tr. at
    3779:1-10; 1867:22-1868:20; 1869:11-16; 1870:23-1871:8.
    10
    The bad faith issue was erroneously submitted to the jury for
    the reasons discussed under the attorney fee award issue.
    11
    We reject Lamb's claim that NPPD did not properly assert the
    grounds which warrant a new trial, as NPPD's brief incorporates the
    grounds   asserted    in   its   Amended   Motions   for   Judgment
    Notwithstanding the Verdict and Alternatively New Trial. App. for
    Appellant at 93-100.
    -16-
    propriety of the award under both state and federal law.12          For the
    following reasons, we vacate the district court's award of attorney fees.
    Nebraska Law
    NPPD maintains that Nebraska law does not authorize attorney fees for
    bad faith pre-litigation conduct.    We agree.
    We review the district court's application of state law to the facts
    de novo.   Price v. Seydel, 
    961 F.2d 1470
    , 1475 (9th Cir. 1992) (Price); see
    also Actors' Equity Ass'n v. American Dinner Theatre Inst., 
    802 F.2d 1038
    ,
    1042 (8th Cir. 1986) (Actors' Equity Ass'n) ("The legal principles that the
    court relies on to inform its discretion [in awarding attorney fees],
    however, are subject to de novo review.").    In a diversity case "where the
    state law does not run counter to a valid federal statute or rule of court,
    and usually it will not, state law denying the right to attorney's fees or
    giving a right thereto, which reflects a substantial policy of the state,
    should be followed."    Alyeska Pipeline Co. v. Wilderness Soc'y, 
    421 U.S. 240
    , 259 n.31 (1975) (Alyeska); see also 
    Price, 961 F.2d at 1475
    (a federal
    court applies state law in awarding attorney fees when those fees are
    connected to the substance of the case);     Public Serv. Co. v. Continental
    Cas. Co., 
    26 F.3d 1508
    , 1520 (10th Cir. 1994) (the right to recover
    attorney fees is substantive and thus determined by state law in diversity
    cases); Ross v. Inter-Ocean Ins. Co., 
    693 F.2d 659
    , 661 (7th Cir. 1982)
    (the right to attorney fees in a diversity action is governed by
    12
    In its motion for an award of attorney fees, Lamb asserted
    its entitlement to the award "under applicable federal and/or state
    law relating to bad faith pre-litigation or litigation conduct."
    App. for Appellant at 80, 83. The district court specified in its
    Order that it granted attorney fees "on the basis of bad faith pre-
    litigation conduct and not on the basis of litigation conduct."
    Lamb Eng'g & Constr. Co. v. Nebraska Pub. Power Dist., No. 4:CV94-
    29 (D. Neb. Aug. 25, 1995) (Lamb Eng'g).
    -17-
    state law); Shelak v. White Motor Co., 
    636 F.2d 1069
    , 1072 (5th Cir. 1981)
    ("[I]n an ordinary diversity case, state rather than federal law governs
    the issue of the awarding of attorney's fees."); Western Sur. Co. v. Lums
    of   Cranston,    Inc.,   
    618 F.2d 854
    ,   855    (1st   Cir.   1980)   ("[B]ecause
    jurisdiction in this case rested upon diversity of citizenship, state law
    would govern an award of attorney's fees.").
    Nebraska law allows the recovery of attorney fees only where such
    recovery is provided by statute or where the uniform course of procedure
    has been to allow such recovery.          Holt County Coop. Ass'n v. Corkle's,
    Inc., 
    336 N.W.2d 312
    , 315 (Neb. 1983) (Holt County Coop. Ass'n).               We find
    no Nebraska statute which provides for recovery of attorney fees in a
    contract action.13    Nor do we find that Nebraska has adopted a course of
    procedure by which attorney fees may be awarded in this case.              Although the
    Nebraska Supreme Court has recognized a court's inherent power to award
    attorney fees against a party based on its bad faith, such an award is
    limited to cases in which the bad faith pertains to conduct during the
    course of litigation.     
    Id. (emphasis added).
           The district court explicitly
    awarded attorney fees "on the basis of bad faith pre-litigation conduct and
    not on the basis of litigation conduct."            Lamb Eng'g, slip op. at 1 (Aug.
    25, 1995).      We hold that such an award of attorney fees is contrary to
    Nebraska law.    We further opine that the Nebraska Supreme Court would not
    extend Holt County Coop. Ass'n to include such pre-litigation conduct.              In
    City of Gering v. Smith Co., 
    337 N.W.2d 747
    (Neb. 1983), the Nebraska
    Supreme Court refused to extend its prohibition concerning the
    13
    Neb. Reissue Rev. Stat. § 25-824 (2), (4) (1995), provides
    for attorney fee awards based on bad faith litigation conduct.
    This statutory attorney fee provision was enacted by the Nebraska
    Legislature subsequent to the Nebraska Supreme Court's 1983
    decision in Holt County Coop. Ass'n v. Corkle's, Inc., 
    336 N.W.2d 312
    (Neb. 1983).
    -18-
    allowance of attorney fees beyond that provided in Holt County Coop. Ass'n.
    Federal Law
    NPPD also argues the district court's inherent power to award
    attorney fees for bad faith is inapplicable because in this case the bad
    faith conduct was pre-litigation conduct.       We agree.
    We review the District Court's award of attorney fees de novo.
    Once the trial court has made a finding of bad faith, an
    award of attorneys' fees is within its discretionary
    power and will not be disturbed absent an abuse of
    discretion. The legal principles that the court relies
    on "to inform its discretion, however, are subject to de
    novo review."
    Actors' Equity 
    Ass'n, 802 F.2d at 1042
    (citations omitted).
    Federal courts have the inherent power to assess attorney fees in
    narrowly defined circumstances, despite the so-called "American rule,"
    which prohibits fee shifting in most cases.14    Chambers v. NASCO, Inc., 
    501 U.S. 32
    , 45 (1991) (Chambers).   Courts have established limited exceptions
    to the American rule, however, such as "when the losing party has acted in
    bad faith, vexatiously, wantonly, or for oppressive reasons."15   
    Id. at 45-
    46 (quoting other cases).    Federal courts sitting in diversity can use
    their inherent power to assess attorney fees as a sanction for bad faith
    conduct even if the applicable state law does not recognize the bad
    14
    The American rule on the award of attorney fees in federal
    litigation is well-settled in its requirement that, absent a
    statute or an enforceable contract, each party is responsible for
    its own fees.    Actors' Equity Ass'n v. American Dinner Theatre
    Inst., 
    802 F.2d 1038
    , 1041 (8th Cir. 1986) (citing Alyeska Pipeline
    Serv. Co. v. Wilderness Soc'y, 
    421 U.S. 240
    , 247, 257 (1975)).
    15
    For simplicity, we recognize this standard as the "bad faith
    exception" to the American rule.
    -19-
    faith exception to the general rule against fee shifting.      
    Id. at 51-52.
    In the present case, we examine the district court's inherent power to
    award attorney fees for bad faith pre-litigation conduct.
    A court's inherent power to award attorney fees pursuant to the bad
    faith exception "depends not on which party wins the lawsuit, but on how
    the parties conduct themselves during the litigation."    
    Id. at 53
    (emphasis
    added).    This court has recently adopted the view promulgated by various
    circuits that, in determining whether to award attorney fees based on the
    litigant's bad faith, "'[t]he court may consider conduct both during and
    prior to the litigation, although the award may not be based solely on the
    conduct that led to the substantive claim.'"     McLarty v. United States, 6
    
    16 F.3d 545
    , 549 (8th Cir. 1993) (McLarty)     (quoting Perales v. Casillas, 
    950 F.2d 1066
    , 1071 (5th Cir. 1992)); accord Association of Flight Attendants
    v.   Horizon Air Indus., Inc., 
    976 F.2d 541
    , 548-50 (9th Cir. 1992)
    (Association of Flight Attendants); Shimman v. International Union of
    Operating Eng'rs, Local 18, 
    744 F.2d 1226
    , 1233 (6th Cir. 1984) (Shimman),
    cert. denied, 
    469 U.S. 1215
    (1985).
    Lamb relies upon Yonker Constr. Co. v. Western Constr. Corp., 
    935 F.2d 936
    , 942 (8th Cir. 1991) (Yonker Constr. Co.), as well as Richardson
    v. Communication Workers, 
    530 F.2d 126
    , 132 (8th Cir.) (Richardson), cert.
    denied, 
    429 U.S. 824
    (1976), in arguing that
    16
    McLarty v. United States, 
    6 F.3d 545
    (8th Cir. 1993),
    involved the recovery of attorney fees against the government under
    the Equal Access to Justice Act (EAJA), 28 U.S.C. § 2412(b), which
    authorizes an award of attorney fees to a prevailing party where
    the government's position is not substantially justified.
    Consistent with a court's inherent power to award attorney fees
    against a litigant guilty of bad faith, attorney fees are awarded
    under the EAJA where the government has acted "in bad faith,
    vexatiously, wantonly, or for oppressive reasons." 
    Id. at 549.
    Under the EAJA, the government is liable for fees and expenses to
    the same extent as any other party under the common law. 
    Id. -20- the
    court has the inherent power to award attorney fees for bad faith
    prefiling conduct.    In Yonker Constr. Co., we held that "[b]ad faith may
    occur during either contract performance or 
    litigation." 935 F.2d at 942
    .
    In Richardson, we allowed recovery of attorney fees under the bad faith
    exception based on a labor union's intentional failure to discharge its
    fiduciary duty to represent plaintiff in his grievance and its actual
    inducement of his wrongful 
    discharge. 530 F.2d at 133
    .
    We take this opportunity to clarify and distinguish these cases in
    light of McLarty.    In McLarty, this court acknowledged that in determining
    a litigant's bad faith, the court may consider conduct both during and
    prior to the litigation, but it may not base an award solely on the conduct
    that led to the substantive 
    claim. 6 F.3d at 549
    .     The Sixth Circuit
    explained this rule by stating that fees awarded under the bad faith
    exception "are designed to punish the abuse of the judicial process rather
    than the original wrong."      
    Shimman, 744 F.2d at 1232
    n.9.      Thus, "[a]
    person who harms another in bad faith is nonetheless entitled to defend a
    lawsuit in good faith."     
    Id. at 1232.
       In Yonker Constr. Co., the jury
    found that the defendant acted in bad faith in performing the subcontract
    and in initiating its 
    counterclaim. 935 F.2d at 942
    .      We recognize the
    filing of a counterclaim as litigation conduct.
    We similarly distinguish Richardson, in which attorney fees were
    awarded for defendant Unions' failure to represent the plaintiff in
    grievance proceedings and its inducement of the plaintiff's 
    discharge. 530 F.2d at 133
    .   We presume, without commenting on whether we agree, that the
    Richardson panel found the grievance proceedings to be akin to litigation
    conduct.   Similarly, the Ninth Circuit has distinguished Richardson from
    the line of cases from which McLarty evolved on the basis that Richardson
    involved both bad faith in refusing to recognize a clear legal right, thus
    necessitating that an action be filed and justifying an
    -21-
    award of attorney fees, and bad faith in the conduct underlying the cause
    of action, which alone, under McLarty, would not justify an award of
    attorney fees.      See Association of Flight 
    Attendants, 976 F.2d at 549
    .17
    In other words, Richardson is an "exceptional case," 
    id., because, in
    that
    case, defendant Unions refused to provide legal representation despite its
    clear obligation to do so, thus making litigation inevitable.                    Thus, the
    attorney fees award in Richardson was not based solely on the conduct that
    led to the substantive wrongful discharge claim.                 See 
    McLarty, 6 F.3d at 549
    .
    We find support for our holding today implicitly in the language of
    the Chambers majority opinion and explicitly in the dissenting opinions.
    Justice Kennedy's dissent in Chambers is not based so much upon a differing
    view of the rule regarding attorney fees for bad faith litigation conduct,
    but instead on a different interpretation of the district court's opinion.
    
    Id. at 72-73
    (Kennedy, J., dissenting).             More specifically, the majority
    opinion     held   that   "the   District   Court    did   not    attempt   to   sanction
    petitioner for breach of contract, but rather imposed sanctions for the
    fraud he perpetrated on the court and the bad faith he displayed toward
    both his adversary and the court throughout the course of the litigation."
    
    Id. at 54.
        The majority opinion expressed "no opinion as to whether the
    District Court would have had the inherent power to sanction Chambers for
    conduct relating to the underlying breach of contract."                
    Id. at 55
    n.16.
    The four dissenting Justices, however, read the district court opinion as
    imposing sanctions for "petitioner's flagrant, bad-faith breach of
    17
    The Sixth Circuit interpreted Richardson v. Communication
    Workers, 
    530 F.2d 126
    (8th Cir.) (Richardson), cert. denied 
    429 U.S. 824
    (1976), as an effort by this court to expand the bad faith
    exception to include bad faith in the conduct giving rise to the
    underlying claim and rejected any such extension.       Shimman v.
    International Union of Operating Eng'rs, Local 18, 
    744 F.2d 1226
    ,
    1233 (6th Cir. 1984) (Shimman), cert. denied, 
    469 U.S. 1215
    (1985).
    We believe the Sixth Circuit interpreted Richardson too broadly and
    agree with the analysis that court used in Shimman.
    -22-
    contract."     
    Id. at 60
    (Scalia, J., dissenting).            In his dissent, Justice
    Kennedy, joined by Chief Justice Rehnquist and Justice Souter, concluded
    that the majority opinion's assertion that the district court did not
    impose sanctions for breach of contract "appears to disclaim that its
    holding    reaches    prelitigation     conduct."       
    Id. at 72
      (Kennedy,    J.,
    dissenting).     Justice Kennedy suggested that,
    [d]espite the Court's equivocation on the subject, it is
    impermissible to allow a District Court acting pursuant
    to its inherent authority to sanction such prelitigation
    primary conduct. A court's inherent authority extends
    only to remedy abuses of the judicial process.
    
    Id. at 74
    (Kennedy, J., dissenting) (citation omitted).                  Justice Scalia
    "emphatically agree[d] with Justice Kennedy" that the district court had
    no power to impose sanctions based upon bad faith breach of contract.                 
    Id. at 60
    (Scalia, J., dissenting).        Justice Scalia further recognized that the
    American rule,
    deeply rooted in our history and in congressional
    policy,    prevents   a   court    (without   statutory
    authorization) from engaging in what might be termed
    substantive fee shifting, that is, fee shifting as part
    of the merits award. It does not in principle bar fee
    shifting as a sanction for procedural abuse.
    
    Id. at 59
    (Scalia, J., dissenting) (citations omitted).
    We infer support for our holding today from the Chambers majority
    opinion,     which   stated   that   "the   sanctions    imposed     applied   only    to
    sanctionable acts which occurred in connection with the proceedings in the
    trial court."18      
    Id. at 55
    .      This statement, combined with the explicit
    denial of the Supreme Court's
    18
    One incidence of petitioner Chambers' bad faith conduct was
    his fraudulent transfer of assets, which, although it "took place
    before the suit was filed, it occurred after Chambers was given
    notice, pursuant to court rule, of the pending suit," and thus was
    considered part of the proceeding. Chambers v. NASCO, Inc., 
    501 U.S. 32
    , 55 n.17 (1991).
    -23-
    adjudication of the applicability of attorney fees for pre-litigation
    breach of contract, leads us to hold that the district court's inherent
    power to award attorney fees as a sanction for bad faith conduct does not
    extend to pre-litigation conduct.
    In the present case, the bad faith conduct, or more specifically, the
    bad faith administration of the contract, was part of the underlying
    substantive claim.     In fact, Lamb originally pleaded a breach of contract
    claim based upon NPPD's contract administration, but subsequently dismissed
    it voluntarily.     Second Am. Compl., App. for Appellant at 12.         As developed
    during oral argument, Lamb's claim for reasonable and proper damages under
    the contract's termination clause is essentially a breach of contract
    claim, as NPPD did not pay what Lamb says it owed Lamb under the
    termination damages clause.         Lamb cannot circumvent the McLarty rule by
    voluntarily dismissing the original substantive claim, but using the
    conduct upon which that claim was based as a means to obtain attorney fees.
    Thus, we hold that NPPD's bad faith administration of the contract
    was   pre-litigation      conduct    upon   which   the    underlying    substantive
    termination clause claim is based.          Under McLarty, such conduct does not
    provide a basis upon which the court may use its inherent power to award
    attorney    fees.     
    6 F.3d 545
    .   Because     the   bad   faith   exception   is
    inapplicable to this case as a matter of law, we see no reason to review
    the district court's factual finding of bad faith administration of the
    contract.    Similarly, because the bad faith exception does not apply in
    this case, the bad faith issue should not have been submitted to the jury.
    For these reasons, we vacate the district court's award of attorney fees.
    -24-
    III.   Conclusion
    Accordingly, the District Court's judgment is affirmed in part and
    reversed in part and the case is remanded to the district court for a new
    trial on damages.
    A true copy.
    Attest:
    CLERK, U.S. COURT OF APPEALS, EIGHTH CIRCUIT.
    -25-
    

Document Info

Docket Number: 95-3398

Filed Date: 1/9/1997

Precedential Status: Precedential

Modified Date: 10/13/2015

Authorities (34)

Western Surety Company v. Lums of Cranston, Inc., Western ... , 618 F.2d 854 ( 1980 )

public-service-company-of-colorado-a-colorado-corporation , 26 F.3d 1508 ( 1994 )

John C. Shimman v. International Union of Operating ... , 744 F.2d 1226 ( 1984 )

john-shelak-norman-jean-shelak-personal-representative-of-the-estate-of , 636 F.2d 1069 ( 1981 )

Zulema De La Garza Perales, Cross-Appellants v. Richard ... , 950 F.2d 1066 ( 1992 )

potamkin-cadillac-corp-potamkin-total-leasing-inc-potamkin-toyota , 38 F.3d 627 ( 1994 )

Square Liner 360o, Inc., Appellant/cross v. Finis Lavell ... , 691 F.2d 362 ( 1982 )

Frances Louise Ross v. Inter-Ocean Insurance Company , 693 F.2d 659 ( 1982 )

Green Tree Acceptance, Inc. v. John W. Wheeler , 832 F.2d 116 ( 1987 )

United States v. Kevin Jackson , 914 F.2d 1050 ( 1990 )

international-union-of-operating-engineers-local-571-v-hawkins , 929 F.2d 1346 ( 1991 )

United States Fire Insurance Company v. Pressed Steel Tank ... , 852 F.2d 313 ( 1988 )

Libbey-Owens-Ford Company v. Insurance Company of North ... , 9 F.3d 422 ( 1993 )

Walter P. Maksym, Jr. v. Dolores Loesch , 937 F.2d 1237 ( 1991 )

Scott McLarty v. United States , 6 F.3d 545 ( 1993 )

Stuart A. Rafos v. Outboard Marine Corporation , 1 F.3d 707 ( 1993 )

Burlington Northern Railroad Company v. State of Nebraska ... , 802 F.2d 994 ( 1986 )

actors-equity-association-v-american-dinner-theatre-institute-firehouse , 802 F.2d 1038 ( 1986 )

dale-c-richardson-appellant-cross-appellee-v-communications-workers-of , 530 F.2d 126 ( 1976 )

40-fed-r-evid-serv-965-prodliabrep-cch-p-14079-randy-c-mcknight , 36 F.3d 1396 ( 1994 )

View All Authorities »