Alexis M. Herman v. Assoc. Electric ( 1999 )


Menu:
  •                     United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ___________
    No. 98-1876
    ___________
    Alexis M. Herman, Secretary of Labor; *
    Department of Labor,                   *
    *
    Appellees,                 *   Appeal from the United States
    *   District Court for the
    v.                               *   Eastern District of Missouri.
    *
    Associated Electric Cooperative, Inc., *
    *
    Appellant.                 *
    ___________
    Submitted: December 14, 1998
    Filed: April 20, 1999
    ___________
    Before FAGG, HEANEY, and WOLLMAN, Circuit Judges.
    ___________
    WOLLMAN, Circuit Judge.
    Associated Electric Cooperative, Inc. (Associated) appeals from the district
    court’s order granting summary judgment in favor of the Secretary of Labor and
    permanently enjoining Associated from excluding inspectors of the Mine Safety and
    Health Administration (MSHA) from its power-generating facility. Because we
    conclude that Associated is not a “mine” within the meaning of the Federal Mine
    Safety and Health Act, 30 U.S.C. §§ 801-962 (Mine Act), we reverse.
    I.
    Associated operates the Thomas Hill Energy Center, a three-unit, coal-fired
    electric power generating facility in Randolph County, Missouri. The facility obtains
    its coal from two mines in the Powder River Basin in Wyoming. Before shipment,
    the mines crush the coal into pieces approximately 2.5 inches in size. The coal is then
    shipped to the facility by rail. Associated engages in various preparation activities
    before burning the coal for electricity. All coal passes through grates to sift out large
    debris and under magnets to remove scrap metal. For one generator unit, coal is
    crushed into powder with pulverizers. For the other two units, coal is broken into
    quarter-inch pieces with hammer mills. Associated also performs sampling to ensure
    that the coal complies with emission standards.
    In September 1995, the federal Occupational Safety and Health Administration
    (OSHA) received a complaint about coal dust from an employee at the facility. An
    OSHA inspector visited the facility and took air samples. Subsequently, OSHA
    informed Associated that it was referring the matter to MSHA to determine which
    agency had jurisdiction to inspect the facility’s coal processing operations. An
    MSHA inspector visited the facility in August 1996. MSHA informed Associated in
    March 1997 that it had jurisdiction over the coal processing activities, from the point
    where coal is unloaded from railroad cars until it is ready for combustion.
    On June 23, 1997, an MSHA inspector attempted to complete a formal
    inspection of the facility’s coal processing operations. Associated denied the
    inspector entrance to the facility. MSHA issued Associated a citation under section
    813(a) of the Mine Act for refusing to allow the inspector entrance. Associated
    continued to deny MSHA entrance to the facility, whereupon the Secretary brought
    this suit to enjoin Associated from denying MSHA entrance.
    After finding that it had subject matter jurisdiction to determine whether
    Associated is a “mine” within the meaning of the Mine Act, the district court found
    -2-
    that Associated qualified as a mine because of its coal processing activities. The
    court then issued a permanent injunction requiring Associated to grant MSHA
    inspectors access to the facility.
    II.
    Initially, Associated claims that the district court did not have subject matter
    jurisdiction to determine its status as a “mine” under the Mine Act. Because the
    parties do not dispute the underlying facts, we review the court’s determination of
    subject matter jurisdiction de novo. See United States v. Lawrence, 
    51 F.3d 150
    , 151-
    52 (8th Cir. 1995) (reviewing a determination of subject matter jurisdiction de novo);
    Drevlow v. Lutheran Church, Missouri Synod, 
    991 F.2d 468
    , 470 (8th Cir. 1993)
    (same).
    According to Associated, the Mine Act only confers federal jurisdiction in
    cases involving “‘habitual’ offenders of the regulatory scheme” of the Act. See
    Appellant’s Br. at 8 (quoting Thunder Basin Coal Co. v. Reich, 
    510 U.S. 200
    , 209
    (1994)). Undoubtedly, the Mine Act confers federal jurisdiction when the Secretary
    believes that a mine operator “is engaged in a pattern of violation of the mandatory
    health or safety standards” of the Act. 30 U.S.C. § 818(a)(2). Associated overlooks
    the significance of section 818(a)(1), however, which provides for federal jurisdiction
    in many other cases, including when a mine operator “refuses to admit [MSHA]
    representatives to the . . . mine.” 
    Id. § 818(a)(1)(C).
    The Supreme Court has recognized that the Mine Act confers federal
    jurisdiction when any triggering event under section 818(a)(1) occurs. See Donovan
    v. Dewey, 
    452 U.S. 594
    , 604-05 (1981) (stating that section 818(a) would confer
    federal jurisdiction when a mine operator denies an MSHA inspector access to a
    facility). The Third Circuit has asserted subject matter jurisdiction in a case strikingly
    similar to the present one. In Marshall v. Stoudt’s Ferry Preparation Co., an operator
    -3-
    claimed that its facility was not a “mine” within the meaning of the Mine Act and
    denied entrance to an MSHA inspector. 
    602 F.2d 589
    , 590 (3d Cir. 1979). The Third
    Circuit held that the facility qualified as a mine under the Act and enjoined the
    operator from denying MSHA inspectors access to the facility. 
    Id. at 592.
    Interpreting the Mine Act to confer federal jurisdiction only when operators
    habitually violate the Act would render section 818(a)(1) nugatory. This would
    contradict fundamental principles of statutory construction. See United States v.
    Talley, 
    16 F.3d 972
    , 975-76 (8th Cir. 1994) (citing Moskal v. United States, 
    498 U.S. 103
    , 109-10 (1990)) (holding that whenever possible, statutes should be construed to
    give effect to all of their clauses and words). Accordingly, we conclude that the
    district court had subject matter jurisdiction over this case under section 818(a)(1)(C).
    III.
    Associated also asserts that it is not a mine within the meaning of the Mine Act.
    We review the district court’s construction of the term “mine” in the Act de novo.
    See United Energy Servs., Inc. v. Federal Mine Safety & Health Admin., 
    35 F.3d 971
    ,
    974 (4th Cir. 1994); Bush & Burchett, Inc. v. Reich, 
    117 F.3d 932
    , 935-36 (6th Cir.),
    cert. denied, 
    118 S. Ct. 46
    (1997).
    The Act provides:
    “coal or other mine” means (A) an area of land from which minerals are
    extracted in nonliquid form . . . , (B) private ways and roads appurtenant
    to such area, and (C) lands, excavations, underground passageways,
    shafts, slopes, tunnels and workings, structures, facilities, equipment,
    machines, tools, or other property . . . used in, or to be used in, or
    resulting from, the work of extracting such minerals from their natural
    deposits . . . [or in] the milling of such minerals, or the work of
    -4-
    preparing coal or other minerals, and includes custom coal preparation
    facilities.
    30 U.S.C. § 802(h)(1). The Act goes on to define “the work of preparing coal” as
    “breaking, crushing, sizing, cleaning, washing, drying, mixing, storing, and loading
    of bituminous coal, lignite, or anthracite, and such other work of preparing such coal
    as is usually done by the operator of the coal mine.” 
    Id. § 802(i).
    The issue before
    us is whether a utility company that performs some of these tasks on previously
    processed coal is a mine under the Act.
    In adopting the Mine Act, “Congress was plainly aware that the mining
    industry is among the most hazardous in the country.” 
    Dewey, 452 U.S. at 602
    .
    Therefore, it designed the Act to “improv[e] the health and safety conditions in the
    Nation’s underground and surface mines.” 
    Id. The statute
    expressly declares, “[I]t is
    the purpose of this chapter . . . to protect the health and safety of the Nation’s coal or
    other miners.” 30 U.S.C. § 801(g). See also Thunder 
    Basin, 510 U.S. at 209-10
    (discussing Congress’s purpose for adopting the Act).
    To achieve these goals, Congress intended that “what is considered to be a
    mine and to be regulated under this Act be given the broadest possibl[e]
    interpretation.” S. Rep. No. 95-181, at 14 (1977), reprinted in 1977 U.S.C.C.A.N.
    3401, 3414; see also Bush & 
    Burchett, 117 F.3d at 936-37
    (stating that the word
    “mine” should be construed broadly due to the remedial nature of the Act); RNS
    Servs., Inc. v. Secretary of Labor, 
    115 F.3d 182
    , 187 (3d Cir. 1997) (same); United
    
    Energy, 35 F.3d at 975
    (same); Donovan v. Carolina Stalite Co., 
    734 F.2d 1547
    ,
    1553-54 (D.C. Cir. 1984) (same). The remedial nature of the Mine Act does not
    allow courts to extend its coverage without limit, however. “It is clear that every
    company whose business brings it into contact with minerals is not to be classified
    as a mine within the meaning of section [802](h).” Carolina 
    Stalite, 734 F.2d at 1551
    ;
    -5-
    see also Pennsylvania Elec. Co. v. Federal Mine Safety & Health Review Comm’n,
    
    969 F.2d 1501
    , 1510 (3d Cir. 1992) (Mansmann, Circuit Judge, dissenting).
    In Old Dominion Power Co. v. Donovan, the Secretary attempted to assert
    MSHA jurisdiction over a utility that sold electricity to a mine and periodically
    entered mine property to read the meter. See 
    772 F.2d 92
    , 93-94 (4th Cir. 1985). The
    Fourth Circuit found no MSHA jurisdiction because Congress did not intend all
    independent contractors that work at a mine to be considered “mine operators” under
    the Act. 
    Id. at 96-97.
    Similarly, in Bush & Burchett the Secretary asserted MSHA
    jurisdiction over a bridge that a mine built to accommodate its traffic on a state
    highway between the mine and a loading facility on a nearby river. 
    See 117 F.3d at 933
    . The Sixth Circuit held that MSHA did not have jurisdiction over the bridge
    because it was dedicated to the state highway system for public use. According to the
    court, “without some limitation on the meaning of ‘roads appurtenant to,’ MSHA
    jurisdiction could conceivably extend to unfathomable lengths.” 
    Id. at 937.
    Likewise, not all businesses that perform tasks listed under “the work of
    preparing coal” in section 802(i) can be considered mines. The Act was designed
    primarily to protect miners, not employees of coal purchasers such as electric utilities
    and steel mills. See Pennsylvania Electric, 969 at 1510 (Mansmann, Circuit Judge,
    dissenting) (quoting Secretary of Labor v. Pennsylvania Elec. Co., 11 FMSHRC
    1875, 1889-90 (1989) (Doyle, Comm’r, dissenting)); see also S. Rep. No. 95-461, at
    37 (1977) (stating that the Act was meant to regulate “mining activity”). Although
    Associated performs some coal processing operations listed in section 802(i), its
    employees are not “miners,” even in the broadest sense of the word. “[I]nherent in
    the determination of whether an operation properly is classified as ‘mining’ is an
    inquiry not only into whether the operation performs one or more of the listed work
    activities, but also into the nature of the operation performing such activities.”
    Secretary of Labor v. Elam, 4 FMSHRC 5, 7 (1982).
    -6-
    The Secretary relies on decisions of the Mine Safety and Health Review
    Commission that subject utilities to MSHA jurisdiction. Such decisions, while
    instructive, are not binding. Further, they can be distinguished from the present case.
    In Secretary of Labor v. United Energy, the Commission held that a utility located
    adjacent to a mine was itself operating as a mine because it maintained a conveyor
    system to transport coal refuse from the mine and performed all processing activities
    needed to make the refuse a marketable product. See 15 FMSHRC 2022, 2058
    (1993). Similarly, in Pennsylvania Electric, the Commission subjected a utility to
    MSHA jurisdiction because it operated a conveyor that transported run-of-mine, or
    unprocessed, coal from a mine to a separately-owned custom coal preparation facility
    located on the utility’s property. See 11 FMSHRC at 1880. In that case, the
    Secretary did not attempt to assert MSHA jurisdiction beyond the custom coal
    preparation facility. 
    Id. at 1876.
    See also Secretary of Labor v. Alexander Bros., Inc.,
    4 FMSHRC 541, 545 (1982) (subjecting an operator to MSHA jurisdiction because
    it performed all processing tasks necessary to convert refuse into marketable coal);
    Secretary of Labor v. Westwood Energy Properties, 11 FMSHRC 2408, 2413-14
    (1989) (same); Air Prods. & Chems., Inc. v. Secretary of Labor, 15 FMSHRC 2428,
    2429-31 (1993) (same).
    The Commission decisions subjecting utilities to MSHA jurisdiction thus fall
    into two categories: (1) where the utility maintains a presence at a mine to assist in
    transporting coal to its generating facility, and (2) where the utility performs all
    processing tasks necessary to convert coal refuse into a marketable product. Circuit
    court decisions subjecting utilities to MSHA jurisdiction can be similarly categorized.
    See 
    RNS, 115 F.3d at 185
    (utility performed all processing tasks on coal refuse);
    United 
    Energy, 35 F.3d at 973
    (utility maintained conveyor system at mine and
    processed coal waste into marketable coal); Pennsylvania 
    Electric, 969 F.2d at 1503
    (utility maintained conveyor system to transport run-of-mine coal from adjacent
    mines). In essence, after a mine delivers processed, marketable coal to a utility any
    further operations to prepare the coal for combustion are not subject to MSHA
    -7-
    jurisdiction. See United 
    Energy, 35 F.3d at 975
    (holding that “delivery of coal to a
    consumer after it is processed usually does not fall under the coverage of the Mine
    Act”).
    In the present case, Associated purchased coal that was processed into a
    marketable form by the mine.1 Associated did not participate in transporting the coal
    from the mine, nor were its processing activities necessary to make the coal
    marketable. Therefore, its coal-handling operations are more properly characterized
    as “manufacturing” than “mining.” While MSHA may have expertise in regulating
    the hazards of coal dust, Congress designed the Mine Act primarily to protect miners.
    The Secretary cannot claim that Associated’s employees are miners. If Congress
    wishes to expand the Act to cover consumers of coal such as utilities and steel mills,
    it is better suited to that task than this court. We simply hold that under the current
    version of the Mine Act, a utility that receives processed coal from a mine does not
    itself become a “mine” by further processing the coal for combustion.
    Associated’s coal processing operations remain subject to OSHA jurisdiction.
    See 29 C.F.R. §§ 1910.269(a)(1)(i)(B)(1) (stating that OSHA regulations apply to
    coal-handling installations at utility companies), 1910.269(v)(11)(xii) (requiring
    utilities to eliminate or control coal dust). Indeed, in prior cases the Secretary has
    asserted that MSHA has a “policy of inspecting those areas of a power plant that
    involve the handling and processing of run-of-mine coal and of leaving to OSHA the
    inspection of those areas that involve the handling of previously processed coal.” See
    Pennsylvania Electric, 11 FMSHRC at 1884, cited in Westwood, 11 FMSHRC at
    2417. Extending MSHA jurisdiction to the coal-handling operations in the present
    case would result in needless confusion for utility workers about whether MSHA or
    OSHA regulations apply to their conduct. “Requiring electric utility employees
    1
    The mine sold its coal to approximately 50 industrial, commercial, and utility
    customers. See Stipulated Facts ¶ 12, J.A. at 87.
    -8-
    suddenly to adhere to conflicting standards depending on their job location can only
    lead to danger, especially where work around high voltage is involved.” Old
    
    Dominion, 772 F.2d at 99
    .
    The judgment of the district court is reversed, and the case is remanded with
    instructions to dismiss the Secretary’s request for preliminary and permanent
    injunctions.
    HEANEY, Circuit Judge, dissenting.
    I agree that the district court had subject matter jurisdiction under §
    818(a)(1)(C) but would join the Secretary of Labor and the district court in holding
    that Congress unambiguously conferred jurisdiction upon MSHA to ensure worker
    safety at coal-processing operations like those present at Thomas Hill. Accordingly,
    I respectfully dissent.
    Associated receives approximately 83,000 tons of coal each week from two
    mines located in the Powder River Basin of Wyoming. The coal from these mines is
    crushed before shipment to a size such that the largest pieces of coal will pass through
    a 2½ inch hole. No further crushing, sizing, or other preparation occurs.
    When a train carrying coal arrives at Thomas Hill, it is directed to the Car
    Dumper Building where the coal is unloaded into hoppers one carload at a time. At
    the top of each hopper is a "grizzly," or grate, which removes large clumps of coal or
    other material that could block the hopper chutes. The coal travels by conveyor belt
    to the Sample Building, where it passes under magnets to remove scrap metal. Next,
    it travels by conveyor to Transfer House No. 3, and then to Transfer House No. 1,
    both of which also contain magnets.
    -9-
    At Transfer House No. 1, the coal is divided into two parts. Coal to be burned
    in Power Generating Units Nos. 1 and 2 moves by a series of conveyor belts to the
    Units Nos. 1 and 2 Track Hoppers, to ready piles, and then to the Units Nos. 1 and 2
    Crusher House. The crusher house crushes the coal into the 1/4 inch pieces required
    for the Thomas Hill Units Nos. 1 and 2 Cyclone Boilers. After crushing, the coal is
    fed onto Conveyors Nos. 3A and 3B for transport to the Units Nos. 1 and 2 Plant
    Storage Silos located in the power generation building. Coal to be burned in
    Generating Unit No. 3 is transported by conveyor from Transfer House No. 1 to ready
    piles, and is then fed through coal crackers to break up large clumps of coal. Next,
    it travels by conveyor to Transfer House No. 2, where it passes under magnets and
    through a granulator (ring crusher) to reduce its diameter to 1½ to 2 inches. Finally,
    the coal is dumped onto Conveyors Nos. 39 and 40 for transport to the Unit No. 3
    Storage Silos in the power generation building. The coal for Unit No. 3 (a pulverized
    coal boiler) is ground to a powder in the power generation building.
    In September 1995, the Kansas City OSHA office received a complaint from
    an Associated employee alleging exposure to health (inhalation) and safety (fire and
    explosion) hazards from the presence of coal dust in several of the coal-processing
    areas described above. After an onsite visit by an OSHA inspector revealed the
    extensive nature of the coal processing operations at the Thomas Hill facility, OSHA
    referred the matter to MSHA to assist in determining which agency had jurisdiction
    over the coal-processing operation. To resolve that question, a MSHA inspector
    visited Thomas Hill. The inspector submitted a report to the national MSHA office
    which, after receiving a legal opinion by the Office of the Solicitor, determined that
    MSHA had jurisdiction over all areas of the Thomas Hill facility having to do with
    coal, including unloading, storage, and preparation areas. This determination
    delineating their respective jurisdictions over the Thomas Hill operations was
    memorialized in a June 1997 document signed by an OSHA Regional Administrator
    and an MSHA district manager. Associated declined to meet with MSHA, notified
    -10-
    MSHA that it disagreed with the jurisdictional determination, and refused to permit
    MSHA to inspect the Thomas Hill coal-processing operation.
    On June 23, 1997, a MSHA inspector went to Thomas Hill to conduct an
    inspection but was denied entry. The inspector issued a citation to Associated for
    refusing to allow the inspection and, subsequently, an order was issued based on
    Associated’s refusal to abate the original violation. On July 3, 1997, the Secretary
    filed this action in federal district court. On July 16, 1997, Associated contested
    MSHA’s citation and order before the Federal Mine Safety and Health Review
    Commission (Commission).2 In its February 18, 1998 decision, the district court
    noted that Associated’s coal-handling activities as stipulated by the parties included
    “moving the coal by means of an extensive conveyor system, magnetically cleaning
    the coal to remove scrap metal, storing coal, and cracking and crushing coal to reduce
    its size.” Herman v. Associated Elec. Corp., 
    994 F. Supp. 1147
    , 154 (E.D. Mo. 1998).
    On this basis, the court concluded that “the areas from the point at which the coal is
    unloaded from the train cars to the locations where coal is dumped onto conveyors
    3A, 3B, 39 and 40 for transport into the power generation building are within the
    statutory jurisdiction of the [MSHA].” 
    Id. Accordingly, the
    district court entered
    summary judgment in favor of the Secretary, granting preliminary and permanent
    injunctions prohibiting Associated from refusing to permit MSHA inspections of the
    specified portions of the Thomas Hill.
    Initially, I believe that the Secretary’s determination that MSHA has
    jurisdiction over the Thomas Hill coal-processing operation is entitled to judicial
    deference under Chevron U.S.A. Inc. v. Natural Resources Defense Council, Inc., 
    467 U.S. 837
    (1984). Even if our review is de novo, however, the Mine Act clearly
    2
    On April 10, 1998, a Commission ALJ issued a decision dismissing
    Associated’s case based on the collateral estoppel effect of the district court’s
    February 18, 1998 decision.
    -11-
    applies to the Thomas Hill coal-processing operation. The Mine Act applies to
    “[e]ach coal or other mine, the products of which enter . . . or . . . affect commerce.”
    30 U.S.C. § 803 (1998). The Mine Act defines “coal or other mine” to include not
    only lands and equipment associated with the extraction of coal and other minerals,
    but also “lands . . . structures, facilities, equipment, machines, tools, or other property
    . . . used in, or to be used in . . . the work of preparing coal or other minerals, and
    includes custom coal preparation facilities.” 30 U.S.C. § 802(h)(1)(C) (1998). Mine
    Act coverage is to be given the “broadest possible” scope, Pennsylvania Elec. Co.
    v. Federal Mine Safety & Health Review Comm'n, 
    969 F.2d 1501
    , 1503 (3d. Cir.
    1992), and the statute “was intended to provide a ‘sweeping definition’ of the word
    ‘mine,’ encompassing much more than the usual meaning attributed to it.” Bush &
    Burchett, Inc. v. Reich, 
    117 F.3d 932
    , 936 (6th Cir. 1997) (quoting Donovan v.
    Carolina Stalite Co., 
    734 F.2d 1547
    , 1551 (D.C. Cir. 1984)). The question before
    us, therefore, is whether Thomas Hill is a “facilit[y] . . . used in . . . the work of
    preparing coal,” and/or whether it is a custom coal preparation facility.3
    While the Mine Act does not define “custom coal preparation facility,” it
    defines the “work of preparing coal” as “the breaking, crushing, sizing, cleaning,
    washing, drying, mixing, storing, and loading of bituminous coal, lignite, or
    anthracite, and such other work of preparing such coal as is usually done by the
    operator of the coal mine.” 30 U.S.C. § 802(i) (1998). It is uncontested that
    Associated engages in most, if not all, of the activities enumerated in § 802(i).
    Accordingly, the Thomas Hill coal-processing operation falls under the plain meaning
    of § 802(i).
    3
    It is not clear whether this is a single inquiry. Because that determination does
    not affect my conclusion that the Mine Act applies to the Thomas Hill coal-
    processing operation, I do not differentiate between what may, in fact, be two
    separate inquiries.
    -12-
    This conclusion is further supported by the legislative history of the Mine Act.
    The House Conference Report states:
    Both the Senate bill and the House amendment broadly defined mine to
    include all underground or surface areas from which the mineral is
    extracted, and all surface facilities used in preparing or processing the
    minerals, as well as roads, structures, dams, impoundments, tailing
    ponds and like facilities related to the mining activity.
    H.R. Conf. Rep. No. 95-655, at 38 (1977), reprinted in 1977 U.S.C.C.A.N. 3485,
    3486 (emphasis added). The Senate Report acknowledges that “there may be a need
    to resolve jurisdictional conflicts,” and in resolving this conflict, “what is considered
    to be a mine and to be regulated under this Act [should] be given the broadest
    possibl[e] interpretation, and . . . doubts [should] be resolved in favor of inclusion of
    a facility within the coverage of the Act.” S. Rep. No. 95-181, at 14 (1977), reprinted
    in 1977 U.S.C.C.A.N. 3401, 3414 (emphasis added). Moreover, the Act’s definition
    provisions are to be construed broadly so as to effectuate the statutory purpose of
    preserving the safety of mining operations. To the extent that there is doubt as to
    whether the Mine Act applies to Thomas Hill’s coal-processing operation, Congress
    has directed that all doubts be resolved in favor of finding MSHA jurisdiction.
    The majority contends that the Mine Act does not apply for two reasons. First,
    the Mine Act was passed to protect “miners” and Associated’s coal-processing
    employees are not miners. Second, the Thomas Hill coal-processing operation was
    more akin to “manufacturing” than “mining.” Neither distinction is persuasive or
    even on point.
    Certainly, Congress designed the Mine Act to protect the health of miners. Just
    as clearly, Congress gave a broad definition of the facilities to be covered by the act.
    Thus, just as we must construe broadly the definition of “mine,” so must we broadly
    construe the meaning of “miner” to give effect to Congress’ clear intent to protect
    -13-
    workers from the unique dangers posed by working in substantial coal-processing
    operations.
    While the majority does not provide a definition of “miner,” I would define a
    miner as a worker engaged in substantial coal-processing activities enumerated in §
    802(i). Under such a definition, Associated employees who engage in coal
    processing at Thomas Hill would be covered by the Mine Act. Quite obviously,
    MSHA has the expertise, experience, and equipment to guarantee the safety of
    workers who are involved in coal-processing operations like those present in this
    case. This expertise is made clear by the fact that OSHA referred the Thomas Hill
    investigation to MSHA. Moreover, MSHA’s regulatory framework in areas such as
    coal dust standards; sampling procedures; respiratory equipment; and structural,
    equipment, mechanical, and electrical safety in coal-processing facilities is much
    more extensive than the OSHA regulatory framework set forth by the majority. See
    30 C.F.R. §§ 70.100-70.305; 77.203-77.217; 77.400-77.411; 77.500-77.516 (1998).
    In this light, the majority’s reliance on Old Dominion Power Co. v. Donovan,
    
    772 F.2d 92
    (4th Cir. 1985) is inapposite. In that case, the Fourth Circuit was asked
    to interpret the Mine Act’s definition of “operator,” defined by the statute to mean
    “any owner, lessee, or other person who operates, controls, or supervises a coal or
    other mine or any independent contractor performing services or construction at such
    mine.” 30 U.S.C. § 802(d) (1998). The issue in Old Dominion was whether a utility
    company that provided electricity to a mine, did not perform any maintenance at the
    mine’s substation, including on the lines thereto, and whose actions were limited to
    installing equipment to measure voltage and amperage for its meter, maintaining the
    meter, and sending workers to the meter once a month and ensuring that the meter
    was functioning properly fell within this definition. 
    See 772 F.2d at 93
    . The issue
    arose when a utility worker was injured. See 
    id. After analyzing
    § 802(d), the Fourth
    Circuit determined that “Congress intended to include within the Mine Act’s
    definition of ‘operator’ only those independent contractors who are involved in mine
    -14-
    construction or extraction and who have a ‘continuing presence’ at the mine.” 
    Id. at 96.
    While we are not called upon to interpret § 802(d) in this case, insofar as there
    is an analogy, I agree with the Fourth Circuit that the extent to which an employee is
    involved in coal processing determines whether a particular employee is an intended
    beneficiary of Mine Act protection.4 To that end, a meter reader is factually
    distinguishable from a coal-processor. Unlike Associated’s coal-processing
    employees, the utility workers in Old Dominion were on the mine’s premises for the
    limited purpose of checking a meter. Here, Associated’s employees are engaged in
    substantial coal-processing operations that bring it within the plain language and
    express purpose of the Act’s coverage.
    The majority additionally asserts that utility workers will suffer confusion if
    the Mine Act were to apply to the Thomas Hill coal-processing operation. In its
    submissions to the district court, the Secretary of Labor included a 1979 Interagency
    Agreement between MSHA and OSHA. As part of the agreement, “MSHA and
    OSHA will endeavor to develop compatible safety and health standards, regulations,
    and policies with respect to the mutual goals of the two organizations including joint
    rulemaking, where appropriate. This interagency coordination may also include
    cooperative training, shared use of facilities, and technical assistance.” (Ex. 9 at 5.)
    The Secretary of Labor also submitted to the district court 1995 OSHA guidelines for
    enforcing 29 C.F.R. § 1910.269:
    4
    Similarly inapposite is the majority’s reliance on Bush & 
    Buchett, 117 F.3d at 932
    . The majority confuses the facts and claims that “the Secretary [of Labor]
    asserted MSHA jurisdiction over a bridge that a mine built to accommodate its traffic
    on a state highway between the mine and a loading facility on a nearby river.” The
    issue in Bush & Burchett was whether the construction company that built the bridge
    was properly cited under OSHA regulations. 
    See 117 F.3d at 933
    . While Bush &
    Burchett involved a question of MSHA jurisdiction over the construction site, the
    construction company, not the Secretary, argued that MSHA had jurisdiction. See 
    id. In fact,
    both OSHA and MSHA determined that MSHA lacked jurisdiction. See 
    id. at 935.
    -15-
    The requirements in 1910.269 are intended to apply to conditions and
    installations for which MSHA does not in fact “exercise statutory
    authority . . . .” MSHA’s jurisdiction relative to power generation plants
    covers the processing of coal prior to final transport of the coal into the
    power generation building (where the coal is burned). Processing
    includes activities such as mixing, breaking, crushing, sizing, washing,
    and mechanically assisted drying. The location of these activities
    whether on or off the property owned or leased by the power generation
    company is not an issue.
    (Ex. 10 at 7.) This interagency agreement eliminates any confusion that might have
    existed without it.
    The majority also misses the point by attempting to characterize the Thomas
    Hill coal-processing operation as manufacturing. By its terms, the Mine Act applies
    to the Thomas Hill coal-processing operation if Associated engages in “the breaking,
    crushing, sizing, cleaning, washing, drying, mixing, storing, and loading of
    bituminous coal, lignite, or anthracite, and such other work of preparing such coal as
    is usually done by the operator of the coal mine.” 30 U.S.C. § 802(i) (1998). In
    employing a functional analysis of the Thomas Hill coal-processing operation, the
    dispositive issue cannot be a matter of geography or the fact that the coal processor
    is also the end user. Rather, it must be the extent and type of processing that
    determines whether the Mine Act applies.
    In 1982, the Federal Mine Safety and Health Review Commission recognized
    this principle and outlined the basic framework for determining whether a particular
    coal-processing operation is subject to MSHA jurisdiction, stating that “inherent in
    the determination of whether an operation properly is classified as ‘mining’ is an
    inquiry not only into whether the operation performs one or more of the listed work
    activities, but also into the nature of the operation performing such activities.”
    Secretary of Labor v. Elam, 4 FMSHRC 5, 7 (1982). The Commission also stated
    that the “‘work of preparing coal’ connotes a process, usually performed by the mine
    -16-
    operator engaged in the extraction of the coal or by custom preparation facilities,
    undertaken to make coal suitable for a particular use or to meet market
    specifications.” 
    Id. at 8.
    This reasoning supports the conclusion that location and
    ownership are secondary to the nature of the processing that occurs at the facility.
    The Fourth Circuit has also recognized the absurdity of limiting MSHA
    jurisdiction to a commercial inquiry:
    We think it irrelevant that United Energy is transporting and delivering
    the coal to the power plant it operates, rather than to another consumer
    of coal. The statute sets forth a functional analysis, not one turning on
    the identity of the consumer, and United Energy’s activities meet the
    functional test. Although delivery of coal to a consumer after it is
    processed usually does not fall under the coverage of the Mine Act,
    United Energy’s activities occur a step earlier in the overall process.
    They involve the transportation of coal to the preparation facility and
    thus are part of the “work of preparing coal.”
    United Energy Servs., Inc. v. Federal Mine Safety & Health Admin., 
    35 F.3d 971
    , 975
    (4th Cir. 1994) (emphasis added); see also RNS Servs., Inc. v. Secretary of Labor, 
    115 F.3d 182
    , 184 (3d Cir. 1997) (adopting functional analysis).
    That a power plant is the end user of coal it substantially processes is no
    answer to whether the Mine Act applies.5 In Air Products & Chemicals, Inc. v.
    5
    Clearly not every end user of coal is subject to the Mine Act. Here, however,
    the plain language of the statute indicates the Mine Act’s applicability to the
    substantial coal processing conducted at Thomas Hill. Simply characterizing the coal
    purchased by Associated as “marketable” is no answer to the question of whether the
    Thomas Hill coal-processing operation constitutes “preparation” within the meaning
    of the statute. To the extent that marketability affects the determination of whether
    the Mine Act applies, the fact that Associated substantially processes the coal it
    receives indicates that marketability is a relative concept. In any event, a functional
    approach must involve a deeper inquiry than the identity of the consumer and whether
    the coal has undergone some previous minimal processing.
    -17-
    Secretary of Labor, a power plant processed bituminous coal refuse and “run-of-
    mine” coal that was delivered by truck. See 15 FMSHRC 2428, 2429 (1993). The
    refuse and coal was screened, sized, crushed, and stored until it was fed into boilers
    to produce electricity and steam. See 
    id. The Commission
    held that the coal
    processing constituted the “work of preparing coal.” 
    Id. at 2431.
    The Commission also rejected the end-user theory in Secretary of Labor v.
    Westwood Energy Properties, concluding that the Mine Act applied to a culm bank
    operation, in which culm (anthracite coal mining waste) was screened and crushed to
    the specifications required by Westwood’s electric generation facility. See 11
    FMSHRC 2408, 2412-15 (1989); see also Secretary of Labor v. Pennsylvania Electric
    Co., 11 FMSHRC 1875, 1879-82 (1989) (concluding that the Mine Act applied to
    conveyor head drives used to transport coal at an electric generation facility). The
    Third Circuit affirmed this analysis in the Pennsylvania Electric case, stating that “the
    conveyor transports the coal to the coal-processing station. At the station the coal is
    broken, crushed, sized, washed, cleaned, dried, and blended in order to make a
    ‘useable coal product’ for the electric generating facility.” Pennsylvania Elec. 
    Co., 969 F.2d at 1503
    . The court concluded that “the delivery of coal from a mine to a
    processing station via a conveyor constitutes coal preparation ‘usually done by the
    operator of a coal mine.’” 
    Id. (citing 30
    U.S.C. § 802(i)).
    That the coal is extracted elsewhere is no answer to whether the Mine Act
    applies. The Third Circuit has stated that the definition of mine “is so expansively
    worded as to indicate an intention on the part of Congress to authorize the Secretary
    to assert jurisdiction over any lands integral to the process of preparing coal for its
    ultimate consumer.” RNS Servs., 
    Inc., 115 F.3d at 186
    (emphasis added). It can
    hardly be disputed that Thomas Hill is integral to the process of preparing coal for its
    ultimate use. Recognizing the absurdity of limiting MSHA jurisdiction to a
    geographical inquiry, the Third Circuit noted that “the delivery of raw coal to a coal
    processing facility is an activity within the Mine Act, but not the delivery of
    -18-
    completely processed coal to the ultimate consumer.” Pennsylvania Elec. 
    Co., 969 F.2d at 1504
    (citing Stroh v. Director, OWCP, 
    810 F.2d 63
    , 64 (3d Cir. 1987)
    (emphasis added)). Associated significantly processes the coal it purchases. Thus,
    it cannot be said that it receives completely processed coal. Accordingly, the
    applicability of the Mine Act does not cease once the coal is loaded in Wyoming, in
    transit, or even when Associated takes possession of it. The proper inquiry must
    focus on both the nature and extent of Thomas Hill’s coal-processing operation.
    Not only does the majority choose to disregard Congress’ clear mandate, it
    subjects the Thomas Hill coal-processing operation to a cursory, incomplete, and
    legally unfounded functional analysis. Instead of examining the facts in light of
    congressional definitions, the majority substitutes its own sense that the word “mine”
    must be defined narrowly for Congress’ clear direction that it be defined broadly and
    in conformity to the statutory definitions. As noted above, Associated processes
    approximately 83,000 tons of coal each week. The coal it receives has only been
    sized so that it will pass through a 2½ inch hole. No further crushing, sizing, or other
    form of preparation is done to the coal before it is shipped from the mines. Moreover,
    the coal does not pass under magnets before shipment to remove trash metal from the
    coal. Considering the relatively unprocessed form in which Associated receives the
    coal and the substantial processing it must therefore perform itself, the majority errs
    by focusing on the fact that a commercial transaction and geography separate the
    Thomas Hill coal-processing operation from the site of coal extraction. Based on the
    majority’s logic, once raw coal is extracted and shipped to an end user, the Mine Act
    would not apply to any subsequent coal processing–irrespective of the nature or
    extent of processing. This is plainly at odds with the functional analysis mandated
    by Congress.
    Finally, I agree that Congress is best suited to articulate the breadth of MSHA
    jurisdiction. Unlike the majority, however, I am unwilling to disregard Congress’
    clear mandate to resolve doubts in favor of MSHA jurisdiction and the Supreme
    -19-
    Court’s clear mandate to defer to the Secretary of Labor’s reasonable interpretation
    of a statute. Not only is the majority’s conclusion unsupported by the law, I fear that
    it will unnecessarily endanger the health and lives of coal-processing workers. For
    the reasons stated above, I respectfully dissent.
    A true copy.
    Attest:
    CLERK, U.S. COURT OF APPEALS, EIGHTH CIRCUIT.
    -20-