Lila Lederman v. Cragun's Pine Beach , 247 F.3d 812 ( 2001 )


Menu:
  •                    United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ___________
    No. 00-1754
    ___________
    Lila Lederman,                          *
    *
    Appellant,                *
    * Appeal from the United States
    v.                                * District Court for the
    * District of Minnesota.
    Cragun's Pine Beach Resort; Cragun      *
    Corporation; Cragun Enterprises, Inc.; *
    Cragun Golf Management, Inc.; Cragun *
    Properties, Inc.; Cragun Shoreline      *
    Corporation; Brad Clark, doing business *
    as Clark Excavating,                    *
    *
    Appellees.                *
    ___________
    Submitted: December 14, 2000
    Filed: April 23, 2001
    ___________
    Before LOKEN and MAGILL, Circuit Judges, and BATTEY,1 District Judge.
    ___________
    MAGILL, Circuit Judge.
    1
    THE HONORABLE RICHARD H. BATTEY, United States District Judge for
    the District of South Dakota, sitting by designation.
    On August 23, 1995, a pathway at Cragun's Pine Beach Resort collapsed beneath
    Lila Lederman, causing her to fall into a trench and break her ankle. On June 4, 1998,
    Lederman sued the various owners and operators of Cragun's Pine Beach Resort
    (together, "Cragun's"), as well as Brad Clark, the contractor who dug the trench,
    claiming that Clark negligently excavated the trench and Cragun's negligently failed to
    protect Lederman from harm. The district court2 granted the summary judgment
    motions of Clark and Cragun's, holding that a Minnesota statute of limitations bars
    Lederman's claim. Lederman appeals, but we affirm.
    I.
    Cragun's Pine Beach Resort is a vacation resort near Brainerd, Minnesota. In
    the summer of 1995, Cragun's began the Shoreline Suites construction project, which
    involved the destruction of an existing building and the erection of a four-story complex
    consisting of suites and conference rooms. As part of the project, Cragun's hired Brad
    Clark to dig a trench so that U.S. West workers could lower existing communications
    cable that served other Cragun's buildings, and relay the cable to serve the Shoreline
    Suites as well. The communications cable had to be lowered to make room for the
    construction of the Shoreline Suites. The trench was about four and one-half feet deep,
    eight to ten feet wide, and thirty to forty feet long.
    About thirty minutes after Clark left the trench area, Lederman walked along a
    pathway adjacent to the trench. The trench caved in, causing the pathway to collapse
    underneath Lederman, who fell into the trench and broke her ankle. There
    2
    The Honorable Donald D. Alsop, United States District Judge for the District
    of Minnesota.
    -2-
    were no warnings that the pathway was unsafe. Later that day, after U.S. West
    workers completed the lowering of the communications cable, Clark refilled the trench.
    On June 4, 1998, Lederman sued Cragun's and Clark in district court under
    diversity jurisdiction, claiming that Clark negligently excavated the trench and Cragun's
    negligently failed to protect Lederman from harm. The district court granted Clark's
    motion for summary judgment, holding that Minnesota's two-year statute of limitations
    for actions to recover damages for injuries arising out of an unsafe condition of an
    improvement to real property barred Lederman's claim because the trench was an
    improvement to real property. See Minn. Stat. § 541.051 (2000). Subsequently, the
    district court granted Cragun's motion for summary judgment, holding that § 541.051
    also barred Lederman's claims against Cragun's. Lederman appeals the district court's
    judgments. This court has jurisdiction pursuant to 28 U.S.C. § 1291.
    II.
    We review the district court's grant of summary judgment de novo. Clark v.
    Kellogg Co., 
    205 F.3d 1079
    , 1082 (8th Cir. 2000). Summary judgment is appropriate
    when the evidence, viewed in the light most favorable to the non-moving party,
    demonstrates that there is no genuine issue of material fact, and that the moving party
    is entitled to judgment as a matter of law. 
    Id. In this
    diversity case, we apply the
    substantive law of Minnesota. See 
    id. We review
    de novo the district court's
    application of Minnesota law, and, if Minnesota law is ambiguous, we do our best to
    predict how the Minnesota Supreme Court would resolve the issue. See 
    id. -3- A.
    In Minnesota, a six-year statute of limitations applies to most personal injury
    claims alleging negligence. Minn. Stat. § 541.05, subd. 1(5) (2000). However, a two-
    year limitations period applies to actions for injuries arising out of "improvements to
    real property":
    Except where fraud is involved, no action by any person in contract, tort
    or otherwise to recover damages . . . for bodily injury . . . arising out of
    the defective and unsafe condition of an improvement to real property . . .
    shall be brought against any person performing or furnishing the design,
    planning, supervision, materials, or observation of construction or
    construction of the improvement to real property . . . for more than two
    years after discovery of the injury.
    Minn. Stat. § 541.051, subd.1(a) (2000). The Minnesota Supreme Court defines an
    "improvement to real property" as a "permanent addition to or betterment of real
    property that enhances its capital value and that involves the expenditure of labor or
    money and is designed to make the property more useful or valuable as distinguished
    from ordinary repairs." Pacific Indem. Co. v. Thompson-Yaeger, Inc., 
    260 N.W.2d 548
    , 554 (Minn. 1977).
    The Shoreline Suites itself is an "improvement to real property" under the Pacific
    Indemnity test, as it: (1) is a permanent addition of real property; (2) enhances the value
    of the property; (3) involved the expenditure of labor and money; and (4) required work
    going well beyond mere repair. The district court reasoned that since the Shoreline
    Suites is an "improvement to real property," "it follows that excavation, which was an
    indispensable part of the process of building those suites, is an improvement to real
    property under Minn. Stat. § 541.051." We agree that the excavation was an
    "indispensable part" of building the Shoreline Suites. Construction of the Shoreline
    Suites required U.S. West workers to lower existing communications cable to make
    -4-
    room for the construction and to relay the cable to connect the Shoreline Suites;
    lowering the communications cable necessitated the trench at issue here.
    Lederman, however, argues that the district court should have focused its
    analysis exclusively on the excavation of the trench rather than on the overall
    construction process. Since the trench was temporary, Lederman asserts that it cannot
    constitute an "improvement." We disagree.
    Minnesota case law suggests that a temporary trench that is integral to a
    construction project constitutes an "improvement to real property" under § 541.051.
    In Fiveland v. Bollig & Sons, Inc., 
    436 N.W.2d 478
    (Minn. Ct. App. 1989), the
    Minnesota Court of Appeals held that § 541.051 applied to bar a claim brought by a
    plaintiff who fell into an unguarded excavation that the defendant had dug to build a
    basement. 
    Id. at 479-81.
    The Fiveland court never specifically addressed the issue of
    whether the excavation in that case was an "improvement to real property," apparently
    because the parties "conceded that the temporary excavation site was part of an
    improvement to the property." Brandt v. Hallwood Mgmt. Co., 
    560 N.W.2d 396
    , 401
    (Minn. Ct. App. 1997). However, the Fiveland court at least assumed that the
    temporary excavation constituted an "improvement to real property."
    Furthermore, the Minnesota Court of Appeals subsequently stated that the
    excavation at issue in Fiveland, "although temporary, was an integral part of the
    construction of an improvement to real property." 
    Brandt, 560 N.W.2d at 401-02
    .
    Therefore, the Brandt court accepted, at least in dicta, that a part of an improvement
    need not be permanent to be covered by § 541.051, as long as it is an "integral part of
    the construction." 
    Id. (defining the
    word "construction" in § 541.051 to mean "the act
    or process of building, or of devising and forming; fabrication, erection"). In addition,
    in an unpublished opinion, the Minnesota Court of Appeals has held that a temporary
    trench dug to install sewer and water pipes is an improvement to real property. Lutz
    v. J.R. Bruender Constr., Inc., No. C5-93-2097, 
    1994 WL 121636
    , at *2 (Minn. Ct.
    -5-
    App. Apr. 12, 1994)3; see also American Nat. Bank & Trust Co. v. Booth/Hansen
    Assocs., Ltd., 
    542 N.E.2d 925
    , 927 (Ill. Ct. App. 1989) (interpreting a statute similar
    to § 541.051 and holding that "excavation prior to construction is an 'improvement'").
    We therefore agree with the district court's decision to examine the overall
    process of constructing the Shoreline Suites to determine whether the trench constituted
    an "improvement to real property," rather than separating out the various parts of the
    construction. We find additional support for our conclusion in case law construing
    analogous statutes. The Seventh Circuit, for instance, stated:
    [T]o artificially extract each component from an improvement to real
    property and view it in isolation would be an unrealistic and impractical
    method of determining what is an improvement to real property. . . . We
    3
    Lederman notes that Lutz is an unpublished decision and that Minnesota law
    provides that "[u]npublished opinions of the court of appeals are not precedential."
    Minn. Stat. § 480A.08, subd. 3(b). Section 480A.08, subd. 3(b) is identical in all
    relevant respects to 8th Circuit Rule 28A(i), which this court, in a scholarly opinion
    authored by Judge Richard Arnold, held to be unconstitutional. Anastasoff v. United
    States, 
    223 F.3d 898
    , 905, vacated, 
    235 F.3d 1054
    , 1056 (8th Cir. 2000) (en banc).
    The en banc court vacated the panel decision as moot, simply noting that "[t]he
    constitutionality of that portion of Rule 28A(i) which says that unpublished opinions
    have no precedential effect remains an open question in this 
    Circuit." 235 F.3d at 1056
    .
    We need not address the constitutionality of Minn. Stat. § 480.08, subd. 3(b) in this
    case, because we find sufficient support for our holding in published Minnesota case
    law. Therefore, we leave for another day the constitutionality of rules prohibiting the
    use of unpublished opinions for precedential value. In the meantime, we have no doubt
    that the propriety of such rules will continue to gain the attention of the legal journals.
    See, e.g., Boyce F. Martin, Jr., In Defense of Unpublished Opinions, 60 Ohio St. L.J.
    177 (1999); Charles E. Carpenter, Jr., The No-Citation Rule for Unpublished Opinions:
    Do the Ends of Expediency for Overloaded Appellate Courts Justify the Means of
    Secrecy?, 
    50 S.C. L
    . Rev. 235 (1998).
    -6-
    find that if a component is an essential or integral part of the improvement
    to which it belongs, then it is itself an improvement to real property.
    Hilliard v. Lummus Co., 
    834 F.2d 1352
    , 1356 (7th Cir. 1987); see also Travelers Ins.
    Co. v. Guardian Alarm Co., 
    586 N.W.2d 760
    , 762 (Mich. Ct. App. 1998) (holding that
    if a component of an improvement is an integral part of the improvement to which it
    belongs, then the component is an improvement to real property). Accordingly,
    because the trench at issue here was an integral part of building the Shoreline Suites,
    we hold that the trench, although merely temporary, was an "improvement to real
    property" under Minnesota law.
    Lederman also contends that the Minnesota courts draw a distinction between
    construction activity, which is covered by § 541.051, and "demolition-like activity,"
    which purportedly is not. Lederman's contention relies primarily on Brandt, where the
    plaintiff brought suit after a live electrical line injured him during a renovation of office
    
    space. 560 N.W.2d at 398
    . The Brandt court held that § 541.051 did not apply to bar
    the plaintiff's claim because the defendant had been hired only to remove existing light
    fixtures and to de-energize some electrical lines. 
    Id. at 400.
    According to the court,
    the plaintiffs presented "no evidence that [the defendants] 'constructed,' 'built,' or added
    anything new. . . ." 
    Id. The court
    thus held that the defendants were not engaged in
    "construction" within the meaning of § 541.051 and that the two-year statute of
    limitations did not apply to bar the plaintiff's claim. 
    Id. Lederman analogizes
    the role of the Brandt defendant to that of Clark, who,
    Lederman says, was contracted solely for "demolition-like activity"; Clark merely
    removed dirt so that U.S. West workers could access communications cable. We doubt
    that the Minnesota Supreme Court would adopt the fine distinction proposed by
    Lederman. Presumably, such a distinction would give a plaintiff six years to bring a
    lawsuit against a contractor for damages resulting from the demolition of a wall to make
    room for an addition to a home, but a plaintiff would have to bring an action within two
    -7-
    years against a contractor who rebuilt the wall. We cannot conceive of any rational
    reason why the legislature would have made such a distinction.
    In any event, the trench at issue here was not just a "demolition-like activity."
    Instead, Clark dug the trench in part to allow U.S. West workers to relay
    communications cable to connect the Shoreline Suites. Therefore, even under the
    distinction between construction and demolition proposed by Lederman, the activities
    surrounding the digging of the trench are sufficiently "construction-like" that we believe
    § 541.051 should apply.
    Thus, the district court correctly held that the trench dug by Clark constitutes
    an "improvement to real property" under § 541.051. Accordingly, because Lederman
    did not file this suit within two years of her injury, her claim against Clark is time-
    barred.
    B.
    Even if the trench is an "improvement to real property" under § 541.051, as we
    hold it is, Lederman argues that the district court erred in granting summary judgment
    to Cragun's because the two-year statute of limitations does not apply to her "claim that
    Cragun's breached its common law duty to protect her from harm on its property."
    Instead, Lederman contends, based on § 541.051, subd. 1(c), that Minnesota's general
    six-year statute of limitations for negligence actions should apply to this case.4 Section
    4
    Additionally, Lederman notes that the pathway was not part of the construction
    of the Shoreline Suites, and thus contends that "Cragun's duty to protect guests using
    that pathway continued to exist independently of whether any condition of the
    'improvement' itself was defective and unsafe." However, § 541.051, subd. 1(a)
    provides that a person may not bring an action for bodily injury "arising out of the
    defective and unsafe condition of an improvement to real property." Lederman
    concedes that the caving in of the trench caused the pathway to collapse. Since we
    -8-
    541.051, subd. 1(c) provides: "Nothing in this section shall apply to actions for
    damages resulting from negligence in the maintenance, operation, or inspection of the
    real property improvement against the owner or other person in possession." Minn.
    Stat. § 541.051, subd.1(c) (2000).
    The district court held that Lederman's complaint failed to allege that she was
    injured due to Cragun's failure to maintain the pathway; instead, the district court found
    that "the only plausible reading of the facts in this case is that [Lederman] was injured
    by the construction activities." The Federal Rules of Civil Procedure provide for a
    "liberal system of 'notice pleading.'" Leatherman v. Tarrant County Narcotics
    Intelligence & Coordination Unit, 
    507 U.S. 163
    , 168 (1993). Rule 8(a)(2) requires that
    a complaint include only "a short and plain statement of the claim showing that the
    pleader is entitled to relief." Fed. R. Civ. P. 8(a)(2). Thus, the Rules merely require
    the plaintiff to provide a statement of her claim that gives "the defendant fair notice of
    what the plaintiff's claim is and the grounds upon which it rests." Conley v. Gibson,
    
    355 U.S. 41
    , 47 (1957).
    Lederman's complaint states three "CLAIMS FOR RELIEF," including one for
    negligence, which alleges that the "defendants had a duty to plaintiff to exercise
    reasonable care to protect plaintiff and others in the course of excavating and
    maintaining the construction pit. . . . Defendants breached their duty of care by their
    acts and omissions described above. . . ." Preceding Lederman's negligence claim is
    her statement that "[n]either the path nor the pit was blocked off, and there were no
    signs or other devices placed to warn guests at Cragun's not to use the path." Although
    Lederman's complaint is not a model of clarity, we conclude that she sufficiently
    alleged a claim that Cragun's negligently maintained the pathway.
    have held the trench to be part of an "improvement to real property," Lederman's
    injuries "ar[ose] out of" the improvement.
    -9-
    The district court, assuming that Lederman sufficiently alleged a claim of
    negligent failure to maintain the pathway, nevertheless rejected Lederman's claim,
    noting that the Minnesota Supreme Court has stated that negligence in maintaining,
    operating, or inspecting real property "generally occur[s] after an improvement has
    been built." Ocel v. City of Eagan, 
    402 N.W.2d 531
    , 534 (Minn. 1987). By contrast,
    injuries resulting from negligence in constructing a real property improvement are
    governed by the two-year statute of limitations. See 
    id. (holding that
    claims for
    damages in constructing the improvement "are expressly covered by the 2-year
    limitations period"); see also Fisher v. County of Rock, 
    580 N.W.2d 510
    , 511 (Minn.
    Ct. App. 1998) ("[T]he application of Minn. Stat. § 541.051, subd. 1(c), depends on
    whether the [conduct] is classified as making an improvement to real property or as
    maintaining real property.") (emphasis added), rev'd on other grounds, 
    596 N.W.2d 646
    (Minn. 1999).
    In this case, the construction of the Shoreline Suites, not maintenance work,
    injured Lederman. Lederman notes, however, that Ocel holds that actions for negligent
    maintenance, operation, or inspection of an improvement to real property "generally
    occur after an improvement has been 
    built." 402 N.W.2d at 534
    (emphasis added).
    This case is an exception to the general rule, Lederman contends, because guests were
    at Cragun's while the construction took place.
    However, Lederman does not cite, nor have we found, any Minnesota decision
    that applies § 541.051, subd. 1(c) to actions against an owner for injuries incurred
    during construction. Indeed, the statutory language cautions against such a reading.
    Section 541.051, subd. 1(c)'s reference to actions alleging negligence in the
    "maintenance, operation or inspection" of an improvement to real property suggests an
    improvement that already has been completed, but that must be kept in a state of repair.
    For instance, Black's Law Dictionary defines "maintenance" as "[t]he upkeep or
    preservation of condition of property, including cost of ordinary repairs necessary and
    proper from time to time for that purpose." Black's Law Dictionary 953 (6th ed. 1990);
    -10-
    see also Gorton v. Mashburn, 
    995 P.2d 1114
    , 1116 (Okla. 1999) ("Maintenance is best
    characterized as after-care or upkeep."); Webster's Third New International Dictionary
    1170, 1581 (1960) (defining "inspection" as "an examination . . . of an installation" and
    "operation" as "the quality or state of being functional or operative"). In this case,
    constructing the Shoreline Suites constituted more than mere repair, the improvement
    as it existed at the time of Lederman's injury could not be called an "installation," and
    the Suites were not "functional or operative."
    Lederman's assertion that § 541.051, subd. 1(c) should apply to this case because
    guests were at Cragun's while the construction took place is an interesting policy
    argument. But this court is the wrong forum for Lederman's argument; the Minnesota
    legislature weighs such arguments, and, as currently written, § 541.051 provides no
    exception for injuries incurred when an owner of real property has stayed open for
    business during construction of an improvement. In any event, § 541.051, subd. 1(a)
    does not prohibit injured parties from initiating lawsuits alleging injury due to defective
    and unsafe improvements to real property. Rather, the statute merely requires a litigant
    to bring her suit within two years of injury.
    Nor is Sullivan v. Farmers & Merchants State Bank of New Ulm, 
    398 N.W.2d 592
    (Minn. Ct. App. 1986), to the contrary. In Sullivan, the plaintiff injured himself
    after failing to see a step as he exited the defendant bank, which had not posted a sign
    warning customers of the step. 
    Id. at 593.
    The plaintiff sued for negligent design,
    construction, and maintenance of the exit, as well as failure to warn persons using the
    exit of a dangerous and unsafe condition. 
    Id. at 594.
    In addressing the applicability of
    § 541.051, subd. 1(c) to the plaintiff's claim against the bank, the court stated that
    inclusion of [§ 541.051, subd. 1(c)] evinces a legislative intent to hold
    owners and possessors to the standard of care required at common law.
    The fact that the risk results from defects in the design or construction of
    the property improvement does not relieve the owner or possessor of the
    -11-
    duty to ensure the safety of persons using the premises through use of
    appropriate warnings. The legislature could not have intended to absolve
    owners and possessors of property improvements, particularly commercial
    property held open to the public, from the duty to use reasonable care to
    protect health and safety. We therefore hold that Minn. Stat. § 541.051,
    subd. 1 does not relieve the owner or possessor of a property
    improvement from the duty to warn of dangerous and unsafe conditions
    on the premises. Because appellants' complaint included an allegation of
    negligence in the failure to warn persons using the premises of a
    dangerous and unsafe condition, his claim is not barred by Minn. Stat. §
    541.051, subd. 1.
    
    Id. at 595.
    Sullivan does not apply to this case because the injury at issue in Sullivan did not
    occur during construction of the improvement. We therefore agree with the reasoning
    of the Minnesota federal district court, which stated that although
    Minnesota courts have allowed failure to warn claims to go ahead in the
    improvement to real property context, these cases involved instances
    where the defendant had taken on a continuing duty to warn after the
    improvement to real property was substantially completed. Thus, in
    those cases, the defendant's failure to warn was not controlled by [§
    541.051] because the actions on the part of the defendant occurred after
    the substantial completion of the construction and were independent of
    the actions constituting completion of the improvement.
    Henry v. Raynor Mfg. Co., 
    753 F. Supp. 278
    , 283 (D. Minn. 1990) (emphases added);
    see also Horvath v. Liquid Controls Corp., 
    455 N.W.2d 60
    , 64 (Minn. Ct. App. 1993)
    (noting that "a separate and distinct obligation to use due care exists in providing safety
    information to personnel of [the owner] involving the use of the facility and upon which
    the personnel relied after substantial completion of construction and is not governed
    by Minn. Stat. § 541.051") (emphasis added).
    -12-
    The district court also held that applying § 541.051, subd. 1(c) to this case would
    create potential equal protection problems. In Pacific Indemnity, the Minnesota
    Supreme Court examined a prior version of § 541.051, which provided:
    Except where fraud is involved, no action . . . shall be brought against any
    person performing or furnishing the design, planning, supervision, or
    observation of construction or construction of such improvement to real
    property more than two years after the discovery thereof, nor, in any event
    more than ten years after the completion of such construction. This
    limitation shall not be applied in favor of any person in actual
    possession and control as owner, tenant, or otherwise, of the
    improvement at the time the defective and unsafe conditions of such
    improvement constitutes the proximate cause of the injury for which it is
    proposed to bring an action.
    Minn. Stat. § 541.051 (1965) (emphasis added). The Pacific Indemnity court held that
    § 541.051 violated the Minnesota Constitution because its exclusion of owners from
    its protection "grant[ed] a special immunity to persons within its terms, without a
    rational basis for regarding those persons as a distinct and separate 
    class." 260 N.W.2d at 555
    .5 In doing so, the court stated that it found persuasive the reasoning of three
    opinions from other states construing similar statutes. 
    Id. (citing Skinner
    v. Anderson,
    
    231 N.E.2d 588
    (Ill. 1967); Fujioka v. Kam, 
    514 P.2d 568
    (Haw. 1973); Kallas
    Millwork Corp. v. Square D Co., 
    225 N.W.2d 454
    (Wis. 1975)).
    In Fujioka, for example, a portion of the defendant-owner's roof fell on the
    plaintiff, who then sued the 
    owner. 514 P.2d at 569
    . The owner filed a third-party
    complaint against the engineer and contractor who worked on constructing the roof.
    
    Id. The trial
    court granted the summary judgment motions of the engineer and
    5
    Although Pacific Indemnity addressed § 541.051's ten-year statute of repose
    rather than its two-year statute of limitations, nothing in the court's opinion suggests
    that its holding would not apply to the statute of limitations as well.
    -13-
    contractor because they had rendered their services more than ten years before the roof
    collapsed. 
    Id. On appeal,
    the Hawaii Supreme Court addressed the question of whether the
    grant of immunity to the engineer and contractor violated the equal protection clauses
    of the United States or Hawaii Constitutions. 
    Id. at 570.
    The court noted that the
    statute "on one hand grants immunity to the engineer and the contractor," but also
    "burdened" the owner with liability "for the reason that, under the common law rule in
    this jurisdiction, the owners are under a duty to use reasonable care for the safety of all
    persons reasonably expected to be upon the premises." 
    Id. at 571.
    The court therefore
    held that there was no "rational basis for treating the engineer and the contractor
    differently from the owners" and that the statute constituted "an invidious
    discrimination violative of the equal protection guaranty." 
    Id. at 572.
    The Minnesota legislature subsequently amended § 541.051 to place owners of
    real property within the protection of § 541.051, subd. 1(a). In Calder v. City of
    Crystal, 
    318 N.W.2d 838
    (Minn. 1982), the Minnesota Supreme Court examined the
    constitutionality of the amended statute. The plaintiffs in Calder sued the City of
    Crystal after their homes sustained property damage during heavy rainfalls. 
    Id. at 839.
    The plaintiffs claimed that the City's negligent design, installation, and maintenance of
    the water drainage system proximately caused the damage. 
    Id. The City
    impleaded the
    designers and installers of the drainage system. 
    Id. After setting
    out the amended
    statute, with "the owner" in italics, the court stated: "The statute as amended thus added
    into its coverage those individuals whom we noted in Pacific Indemnity had been
    improperly excluded. It also eliminated the prohibition against favored status of 'any
    person in actual possession and control as owner, tenant, or otherwise.'" 
    Id. at 843.
    The court then held that the "legislature did close the door to objection on equal
    protection grounds." 
    Id. -14- Although
    we refrain from deciding whether allowing Lederman to proceed with
    her claim against Cragun's would conflict with the Pacific Indemnity equal protection
    analysis, we do note that allowing Lederman's claim to proceed would "treat[] [people
    such as] the engineer and the contractor differently from . . . owners." 
    Fujioka, 514 P.2d at 572
    .6 Courts should not construe legislation to be unconstitutional "if any other
    possible construction remains available." NLRB v. Catholic Bishop of Chicago, 
    440 U.S. 490
    , 500 (1979). Not only do we think our interpretation is "possible," we
    conclude that our reading is the most reasonable construction of § 541.051. Therefore,
    we hold that § 541.051, subd. 1(c) does not apply to Lederman's claim against
    Cragun's.
    III.
    We AFFIRM the district court. The trench was part of an "improvement to real
    property" under § 541.051, thereby barring Lederman's complaint under the statute of
    limitations. Furthermore, § 541.051, subd. 1(c) does not apply to remove Cragun's
    from the protection of subd. 1(a)'s two-year limitations period.
    6
    Although we take no position on the wisdom of the Pacific Indemnity court's
    holding, we note that many courts construing analogous statutes have held that there
    is a rational basis for treating owners and contractors, for instance, differently. See,
    e.g., Carter v. Hartenstein, 
    455 S.W.2d 918
    , 920 (Ark. 1970) (stating that "owners of
    buildings or structures who are in sole control of premises after completion of the work
    are not similarly situated with [architects and contractors]. . . . Particularly is this true
    after construction is substantially completed and accepted by the owners. Part of
    acceptance is to accept some future responsibility for the condition of the premises.");
    Blaske v. Smith & Entzeroth, Inc., 
    821 S.W.2d 822
    , 830 (Mo. 1991) (en banc) ("Once
    construction is completed, the designers and builders normally cease to be connected
    with the improvement, while owners and occupiers continue in control of the
    improvement during its useful life.").
    -15-
    A true copy.
    Attest:
    CLERK, U.S. COURT OF APPEALS, EIGHTH CIRCUIT.
    -16-