NW AR Conservation Authority v. Crossland Heavy Contractors ( 2022 )


Menu:
  •                   United States Court of Appeals
    For the Eighth Circuit
    ___________________________
    No. 21-2498
    ___________________________
    Northwest Arkansas Conservation Authority,
    lllllllllllllllllllllPlaintiff - Appellant,
    v.
    Crossland Heavy Contractors, Inc.; Fidelity & Deposit Company of Maryland,
    lllllllllllllllllllllDefendants - Appellees.
    ____________
    Appeal from United States District Court
    for the Western District of Arkansas - Fayetteville
    ____________
    Submitted: April 12, 2022
    Filed: August 30, 2022
    ____________
    Before COLLOTON, MELLOY, and GRUENDER, Circuit Judges.
    ____________
    COLLOTON, Circuit Judge.
    The Northwest Arkansas Conservation Authority is a public corporation
    created to handle wastewater treatment for municipalities in northwest Arkansas.
    After a series of pipeline failures, the Authority sued the pipeline contractor and its
    surety, alleging deficient construction. The Authority sued outside the time periods
    specified in the relevant statutes of limitations and repose, but asserted that the time
    did not run against its claims, because the Authority was suing as a public entity
    seeking to vindicate public rights. The district court* concluded that the rights the
    Authority sought to enforce were merely proprietary, and that its claims were
    therefore time-barred. We affirm.
    I.
    A group of municipalities formed the Northwest Arkansas Conservation
    Authority “to address the treatment and disposal of bio-solids” in Benton and
    Washington Counties. The municipalities formed the Authority pursuant to
    Arkansas’s Joint County and Municipal Solid Waste Disposal Act, 
    Ark. Code Ann. § 14-233-101
     et seq. This Act permits two or more municipalities to pool their
    resources and create a shared sanitation authority. 
    Id.
     § 14-233-104(a)(1). The Act
    then vests the newly created authority with corporate personhood, see id. § 14-233-
    107, and empowers it “to own, acquire, construct, reconstruct, extend, equip,
    improve, operate, maintain, sell, lease, contract concerning, or otherwise deal in or
    dispose of” public sanitation projects. Id. § 14-233-104(b)(1).
    In 2007, the Authority contracted with an engineering firm to design and
    oversee the construction of roughly 47,000 linear feet of sewer pipeline. After
    receiving bids, the Authority awarded the construction contract to Crossland Heavy
    Contractors, Inc. Fidelity & Deposit Company of Maryland issued a performance
    bond for the project. Crossland completed construction of the project in June 2010.
    Between early 2016 and mid-2020, the pipeline suffered repeated failures.
    These failures caused sewage overflows onto neighboring property. An inspection
    in 2018 revealed that ninety-six percent of the pipeline’s sections had deviations in
    *
    The Honorable P.K. Holmes, III, United States District Judge for the Western
    District of Arkansas.
    -2-
    diameter greater than the acceptable five percent. A consultant retained by the
    Authority issued a report attributing the failures to Crossland’s inadequate bedding
    of the pipe.
    The Authority sued Crossland and Fidelity in Arkansas state court in January
    2020, nine-and-a-half years after the completion of the pipeline. As relevant here, the
    Authority asserted claims for breach of contract, negligence, breach of express and
    implied warranties, and products liability against Crossland. The complaint also
    asserted a claim for breach of contract against Fidelity. The defendants later removed
    the case to federal court.
    Crossland and Fidelity moved to dismiss the complaint. Crossland asserted
    that the Authority’s claims against it were defeated by the five-year statute of repose
    for actions predicated on construction contracts. See 
    Ark. Code Ann. § 16-56-112
    (a).
    Fidelity similarly asserted that the Authority’s breach-of-contract claim was barred
    by the six-month statute of limitations for actions on bonds. See 
    id.
     § 18-44-508(b)
    (2020). The Authority responded that the common-law doctrine of nullum tempus
    occurrit regi—“time does not run against the king”—meant that the statutes of
    limitations and repose did not run against its claims.
    The district court granted the motions to dismiss in relevant part. The court
    reasoned that the Authority could not invoke nullum tempus, as its claims sought to
    enforce the Authority’s proprietary rights, rather than rights “in which the public in
    general has an interest.” Without the benefit of nullum tempus, the statutes of
    limitations and repose had run against the Authority’s claims. We review the district
    court’s decision de novo, accepting as true the factual allegations in the complaint.
    We apply the substantive law of Arkansas. EMC Ins. Cos. v. Entergy Ark., Inc., 
    924 F.3d 483
    , 485 (8th Cir. 2019). Where there is no Arkansas Supreme Court case on
    point, we predict how that court would rule if it were to confront the same issue. 
    Id.
    -3-
    II.
    The doctrine of nullum tempus occurrit regi provides that the sovereign is
    exempt from the running of statutes of limitations unless the statute in question
    expressly provides otherwise. Nullum tempus has its roots in early English law. As
    Blackstone explained it, the law presumed “that the king is always busied for the
    public good, and therefore has not leisure to assert his right within the times limited
    to subjects.” 1 William Blackstone, Commentaries *247. Upon achieving their
    independence, the former American colonies assumed the same prerogative. United
    States v. Thompson, 
    98 U.S. 486
    , 489-90 (1878). Many States, including Arkansas,
    have since opted to maintain the doctrine as a matter of public policy. These States
    justified the doctrine based on the need to protect public rights and property against
    losses caused by dilatory public servants. Guar. Tr. Co. of N.Y. v. United States, 
    304 U.S. 126
    , 132-33 (1938); Hill v. State, 
    23 Ark. 604
    , 610 (1861).
    Although the Arkansas Supreme Court has long recognized nullum tempus, that
    court has cabined the doctrine’s potential beneficiaries. The court has often said that
    nullum tempus applies “only to the sovereign itself, and not to public corporations or
    other such governmental agencies to whom powers are delegated.” E.g., Hart v.
    Sternberg, 
    171 S.W.2d 475
    , 478 (Ark. 1943) (internal quotation omitted). The task
    of governing the entire sovereignty “might well have excused a king from asserting
    his rights,” but it afforded “no reason” why the officers of a subordinate public entity
    should not be expected to “be reasonably diligent in the discharge of the very duties
    they were selected to execute.” City of Ft. Smith v. McKibbin, 
    41 Ark. 45
    , 49-50
    (1883).
    The Authority asserts, however, that it falls within an exception to this general
    rule. In Jensen v. Fordyce Bath House, 
    190 S.W.2d 977
     (Ark. 1945), the Arkansas
    Supreme Court reiterated that nullum tempus is generally “an attribute of sovereignty
    only, and cannot be invoked by counties or other subdivisions of the state.” 
    Id.
     at 979
    -4-
    (internal quotation omitted). But after taking stock of the development of nullum
    tempus in other jurisdictions, the court expanded the doctrine to encompass
    subordinate public entities in certain circumstances. The court explained that a
    county official could invoke nullum tempus if he was seeking to enforce a right
    “belonging to the public and pertaining purely to governmental affairs, and in respect
    to which [the county] represents the public at large or the state.” 
    Id.
     (internal
    quotation omitted). The court distinguished suits to enforce public rights from suits
    to enforce contract rights or other rights belonging to the entity “in a proprietary
    sense.” 
    Id.
     (internal quotation omitted). The court concluded that the plaintiff in
    Jensen, a county tax collector seeking to recover delinquent state taxes, could invoke
    nullum tempus, because he was seeking to enforce a “sovereign right of the state.”
    
    Id. at 978-81
    .
    The Arkansas case law interpreting this exception is limited, but some insights
    may be gleaned from looking to the treatment of nullum tempus in other jurisdictions.
    Some jurisdictions have abolished nullum tempus altogether. E.g., Shootman v. Dep’t
    of Transp., 
    926 P.2d 1200
    , 1207 (Colo. 1996). Others have preserved the doctrine,
    but declined to extend it to public entities other than the State itself. E.g., Bd. of Sch.
    Comm’rs of Mobile Cnty. v. Architects Grp., Inc., 
    752 So.2d 489
    , 491-92 (Ala. 1999).
    Still others, like Arkansas, have extended nullum tempus to subordinate public
    entities in certain situations. Of these jurisdictions, most determine whether a
    subordinate entity can invoke the doctrine by drawing some sort of public-proprietary
    distinction. See 54 C.J.S. Limitations of Actions § 45 (2022) (citing cases).
    Yet even in the latter jurisdictions, courts differ in how they decide whether
    nullum tempus applies. One group asks whether the public entity’s suit stems from
    the entity’s performance of a public function. See, e.g., Town of Littleton v. Layne
    Heavy Civil, Inc., 
    819 S.E.2d 101
    , 103-04 (N.C. Ct. App. 2018). These courts use
    various tests to determine whether the function at issue is public or proprietary. A
    court may consider, for example, whether the function “is one in which only a
    -5-
    governmental agency could engage,” 
    id.
     (internal quotation omitted), whether the
    function benefits the State as a whole or just local citizens, Hamilton Cnty. Bd. of
    Educ. v. Asbestospray Corp., 
    909 S.W.2d 783
    , 785 (Tenn. 1995), or whether the
    function is traceable to a sovereign power delegated by the State. Wash. Pub. Power
    Supply Sys. v. Gen. Elec. Co., 
    778 P.2d 1047
    , 1049 (Wash. 1989).
    Other courts focus on the rights sought to be enforced through the public
    entity’s lawsuit. Some rights-focused courts have looked broadly to the subject
    matter underlying the lawsuit. The Oklahoma Supreme Court, for example,
    concluded that a municipal improvement authority was seeking to enforce the
    public’s right to an “adequate water supply” when it sued a group of contractors for
    the negligent construction of a water main. Okla. City Mun. Improvement Auth. v.
    HTB, Inc., 
    769 P.2d 131
    , 132-36 (Okla. 1988). Others have taken a more
    circumscribed view and focused on the nature of the entity’s cause of action. See,
    e.g., City of Rochester v. Marcel A. Payeur, Inc., 
    152 A.3d 878
    , 882-83 (N.H. 2016);
    cf. Baltimore County v. RTKL Assocs., Inc., 
    846 A.2d 433
    , 444 (Md. 2004)
    (preserving the public-function test generally, but declining to “impose that
    mish-mash regime on contract actions”). On this view, nullum tempus does not apply
    to actions that sound in contract or tort, at least insofar as the rights at issue arise from
    the public entity’s voluntary arrangements. See City of Philadelphia v. Lead Indus.
    Ass’n, 
    994 F.2d 112
    , 119-20 (3d Cir. 1993) (applying Pennsylvania law); Okla. City
    Mun. Improvement Auth., 769 P.2d at 142 & n.32 (Opala, J., dissenting). These
    claims accrue to a public entity in the same manner as a private party, City of
    Philadelphia, 
    994 F.2d at 120
    , and unlike Blackstone’s “continually busied”
    sovereign, a subordinate entity is well-equipped to “vigilantly enforce” its rights.
    City of Rochester, 152 A.3d at 882.
    Against this backdrop, the Authority first urges that nullum tempus applies
    because the construction and maintenance of sewer pipelines are governmental
    functions. Even were we inclined to agree about the nature of these functions, we
    -6-
    think the Arkansas Supreme Court’s decisions are more consistent with the public-
    rights approach than with its public-function counterpart. In Jensen, the court
    explained that it was “well settled” that statutes of limitations would apply against
    public entities “where the enforcement of mere private or proprietary rights are
    involved.” 
    190 S.W.2d at 979
    . It was only where the entity was “seeking to enforce
    a right in which the public in general has an interest” that it would be exempted from
    the statute of limitations. 
    Id.
     (internal quotation omitted). In the Arkansas court’s
    most recent word on the subject, it emphasized again that an entity may invoke
    nullum tempus where “the ‘rights’ at issue belong to the public.” Ark. Dept. of Env’t
    Quality v. Brighton Corp., 
    102 S.W.3d 458
    , 469 (Ark. 2003). Whether or not the
    Authority was engaged in a public function when it contracted with Crossland to
    construct the pipeline, we think the appropriate question is whether the rights it is
    now seeking to enforce are public rights.
    The Authority argues that this public-rights approach is inconsistent with
    principles of municipal immunity. In Arkansas, a municipal corporation was
    historically entitled to immunity from tort suits for actions taken while it was engaged
    in a public function. See Kirksey v. City of Fort Smith, 
    300 S.W.2d 257
    , 259 (Ark.
    1957). The Authority points out that the Arkansas Supreme Court has held that cities
    operating waterworks and sewer systems were performing public functions. 
    Id. at 259-60
    . It asserts that nullum tempus is best understood as the sword accompanying
    immunity’s shield, and that it would be illogical to interpret one doctrine more
    narrowly than the other.
    We find this plea for symmetry unpersuasive. The Arkansas Supreme Court
    abolished common-law municipal immunity in 1968. Parish v. Pitts, 
    429 S.W.2d 45
    ,
    51 (Ark. 1968). The state legislature responded by enshrining the immunity in
    statute, see 
    Ark. Code Ann. § 21-9-301
    , but in so doing, the legislature severed
    municipal immunity from its common-law roots. The statute did away with the
    public-proprietary distinction of the common law and replaced it with a blanket
    -7-
    immunity (insofar as the entity is not covered by liability insurance). Augustine v.
    City of West Memphis, 
    662 S.W.2d 813
    , 814 (Ark. 1984); see White v. City of
    Newport, 
    933 S.W.2d 800
    , 801-03 (Ark. 1996). If, as the Authority supposes,
    municipal immunity and nullum tempus are still best understood as two sides of the
    same coin, there would be no reason for nullum tempus to adopt a public-proprietary
    distinction that has been abandoned for municipal immunity.
    Even if we consider the two doctrines as they appeared in the common law, the
    Arkansas Supreme Court did not treat them as coterminous. Before 1945, a
    municipal corporation was entitled to immunity if it was engaged in a public function,
    see City of Little Rock v. Holland, 
    42 S.W.2d 383
    , 384 (Ark. 1931), but under no
    circumstance could invoke nullum tempus. See City of Fort Smith, 
    41 Ark. at 49-50, 53
    . When the Arkansas Supreme Court eventually recognized that non-sovereign
    entities could rely on nullum tempus, the court could have imported a public-function
    analysis from its municipal-immunity jurisprudence, but it did not do so. Instead, the
    court has focused on whether an entity invoking nullum tempus seeks to enforce
    public rights. See Jensen, 
    190 S.W.2d at 979-80
    . Governmental immunity, like
    nullum tempus, is ultimately traceable to the prerogatives of the crown. But the two
    doctrines have evolved to support distinct public policies, see City of Shelbyville v.
    Shelbyville Restorium, Inc., 
    451 N.E.2d 874
    , 876-77 (Ill. 1983), and have traveled
    divergent paths in Arkansas law. The breadth of common-law municipal immunity
    thus has little bearing on the proper scope of nullum tempus.
    The Authority contends alternatively that even if nullum tempus applies only
    where an entity seeks to enforce public rights, the Authority satisfies that standard by
    its effort to ensure “proper construction of a functional sanitary sewer system,
    adequate disposal of wastewater, and the recovery of public funds.” The Authority
    adds that the pollution caused by overflowing sewage implicates rights to public
    health or to a clean environment.
    -8-
    In Jensen and Brighton, the Arkansas Supreme Court contrasted public rights
    that would support nullum tempus with contractual or other proprietary rights.
    Brighton Corp., 
    102 S.W.3d at 469
    ; Jensen, 
    190 S.W.2d at 979
    . In drawing the line
    between public and proprietary rights, the court looked to the “character” of the
    actions at issue, rather than the public actor’s broader policy objectives. Brighton
    Corp., 
    102 S.W.3d at 469
     (internal quotation omitted); Jensen, 
    190 S.W.2d at 979
    (internal quotation omitted). In each case, the actor was entitled to invoke nullum
    tempus because its lawsuit was predicated on enforcing a particular public right: in
    Brighton, the Department of Environmental Quality sued to enforce environmental
    regulations, 
    102 S.W.3d at 469
    ; the tax collector in Jensen sued to exercise the
    “sovereign right” to collect state taxes. 
    190 S.W.2d at 980
    .
    Perhaps the right to a well-functioning sewer system or to a clean environment
    can be characterized as “public” in the abstract. But these are not the rights at issue
    in the Authority’s action against Crossland and Fidelity. The Authority did not sue
    to enforce statutes or regulations, and a victory would not allow it to exercise any
    sovereign right. Instead, the Authority proceeded against Crossland and Fidelity on
    private-law theories: breach of contract, negligence, breach of warranty, and products
    liability. Each cause of action seeks to redress a broken promise to the Authority, or
    to obtain damages for harm caused by Crossland’s deficient performance in carrying
    out its promised obligations. The rights at issue are thus the Authority’s proprietary
    rights, not the rights of the public.
    These proprietary interests are not transformed into public rights just because
    the Authority spent public money to repair the pipeline. Every action by a public
    entity impacts the public fisc to some degree. But if financial implications alone were
    enough to invoke nullum tempus, then the public-rights exception would swallow the
    general rule that statutes of limitations and repose run against municipal entities. On
    this point, Jensen is again instructive. There, the court distinguished the tax
    collector’s claim for delinquent taxes from the claim at issue in Clarke v. School
    -9-
    District No. 16, 
    106 S.W. 677
     (Ark. 1907). In Clarke, a school district sued to
    recover funds wrongly paid out by the county treasurer, but the statute of limitations
    ran against the school district, because the action did not involve the exercise of a
    sovereign right. See Jensen, 
    190 S.W.2d at 979-80
    ; Clarke, 106 S.W. at 678. Here,
    as in Clarke, the damages sought would replenish the public entity’s coffers, but the
    relief would not vindicate a distinct public right. The Authority therefore cannot
    invoke nullum tempus to avoid the statutes of limitations or repose.
    *       *       *
    The judgment of the district court is affirmed.
    ______________________________
    -10-