Anthony Gantner v. Pg&e Corporation ( 2022 )


Menu:
  •                       FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    ANTHONY GANTNER,                              No. 21-15571
    Appellant,
    D.C. No.
    v.                        4:20-cv-02584-HSG
    PG&E CORPORATION;                       ORDER CERTIFYING
    PACIFIC GAS & ELECTRIC                  QUESTIONS TO THE
    COMPANY,                                SUPREME COURT OF
    Appellees.                 CALIFORNIA
    Filed February 28, 2022
    Before: Danny J. Boggs, * John B. Owens, and
    Michelle T. Friedland, Circuit Judges.
    Order
    *
    The Honorable Danny J. Boggs, United States Circuit Judge for
    the U.S. Court of Appeals for the Sixth Circuit, sitting by designation.
    2                      GANTNER V. PG&E
    SUMMARY **
    Certification of Questions to Supreme Court of
    California / Bankruptcy
    The panel withdrew the case from submission and
    certified to the Supreme Court of California the following
    two questions of state law:
    (1) Does California Public Utilities Code
    § 1759 preempt a plaintiff’s claim of
    negligence brought against a utility if the
    alleged negligent acts were not approved by
    the California Public Utilities Commission,
    but those acts foreseeably resulted in the
    utility having to take subsequent action (here,
    a Public Safety Power Shutoff), pursuant to
    CPUC guidelines, and that subsequent action
    caused the plaintiff’s alleged injury?
    (2) Does PG&E’s Electric Rule Number 14
    shield PG&E from liability for an
    interruption in its services that PG&E
    determines is necessary for the safety of the
    public at large, even if the need for that
    interruption arises from PG&E’s own
    negligence?
    **
    This summary constitutes no part of the opinion of the court. It
    has been prepared by court staff for the convenience of the reader.
    GANTNER V. PG&E                        3
    ORDER
    We respectfully ask the Supreme Court of California to
    exercise its discretion to decide the certified questions set
    forth in section II of this order.
    I. Administrative Information
    We provide the following information in accordance
    with California Rule of Court 8.548(b)(1). The caption of
    this case is:
    No. 21-15571
    ANTHONY GANTNER, Appellant,
    v.
    PG&E CORPORATION; PACIFIC GAS &
    ELECTRIC COMPANY, Appellees.
    The names and addresses of counsel for the parties are:
    For Appellant Anthony Gantner: Nicholas A.
    Carlin, Brian S. Conlon, and Leah Romm,
    Phillips Erlewine, Given & Carlin, LLP,
    39 Mesa Street, Suite 201, San Francisco, CA
    94129; Bonny E. Sweeney, Hausfeld LLP,
    44 Montgomery Street, Suite 3400, San
    Francisco, CA 94104.
    For Appellees PG&E Corporation and
    Pacific Gas & Electric Company
    (collectively, “PG&E”): Omid Nasab and
    Kevin Orsini, Cravath, Swaine & Moore,
    LLP, 825 8th Avenue, New York, NY 10019;
    4                    GANTNER V. PG&E
    Peter J. Benvenutti and Thomas B. Rupp,
    Keller Benvenutti Kim, LLP, 650 California
    Street, Suite 1900, San Francisco, CA 94108;
    Theodore Elias Tsekerides, Weil Gotshal &
    Manges, LLP, 767 5th Avenue, New York,
    NY 10153.
    We designate Anthony Gantner as the petitioner if our
    request for certification is granted. He is the appellant before
    our court.
    II. Certified Questions
    We certify to the Supreme Court of California the
    following two questions of state law:
    (1) Does California Public Utilities Code
    section 1759 preempt a plaintiff’s claim of
    negligence brought against a utility if the
    alleged negligent acts were not approved by
    the California Public Utilities Commission
    (“CPUC”), but those acts foreseeably
    resulted in the utility having to take
    subsequent action (here, a Public Safety
    Power Shutoff), pursuant to CPUC
    guidelines, and that subsequent action caused
    the plaintiff’s alleged injury?
    (2) Does PG&E’s Electric Rule Number 14
    shield PG&E from liability for an
    interruption in its services that PG&E
    determines is necessary for the safety of the
    public at large, even if the need for that
    interruption arises from PG&E’s own
    negligence?
    GANTNER V. PG&E                         5
    We certify these questions pursuant to California Rule of
    Court 8.548. The answers to these questions will determine
    the outcome of the appeal currently pending in our court.
    We will accept and follow the decision of the California
    Supreme Court on these questions. Our phrasing of the
    questions should not restrict the California Supreme Court’s
    consideration of the issues involved.
    III. Statement of Facts
    Anthony Gantner (“Plaintiff”) is a resident of St. Helena,
    California, and a PG&E customer. Plaintiff filed a Class
    Action Complaint in December 2019 in the United States
    Bankruptcy Court for the Northern District of California,
    asserting a claim under California Public Utilities Code
    section 2106 in an adversary proceeding in PG&E’s Chapter
    11 proceedings. Plaintiff alleges negligence on the part of
    PG&E, claiming that PG&E had a duty to maintain its grid
    in a safe condition but failed to do so and that “PG&E’s
    safety record is an abomination.” Specifically, Plaintiff
    alleges, among other things, that “PG&E has 113,000 miles
    of conductors, and over 60% of those conductors are and
    were highly susceptible to failure”; that “PG&E repeatedly
    delayed upgrading its oldest transmission lines”; and that,
    “[i]n an investigation covering 1994 to 1998, CPUC staff
    accused PG&E of more than 500,000 counts of violating
    state laws requiring utilities to keep trees pruned a safe
    distance from overhead electric lines.”
    Plaintiff further alleges that, because of PG&E’s
    negligence in maintaining its electrical equipment, PG&E
    was forced to implement Public Safety Power Shutoffs
    (“PSPSs”) on five occasions in the autumn of 2019 to
    decrease the chance that its equipment would cause
    wildfires. Since 2019, public electric utilities have been
    required to have a PSPS protocol in place. See Cal. Pub.
    6                      GANTNER V. PG&E
    Util. Code § 8386(c)(6). CPUC has adopted the policies that
    a utility “has the burden of demonstrating that its decision to
    shut off power is necessary to protect public safety,” Cal.
    Pub. Utils. Comm’n, Resolution ESRB-8, at 1, 4 (2018), and
    that a utility “must deploy de-energization as a measure of
    last resort and must justify why de-energization was
    deployed over other possible measures or actions,” Cal. Pub.
    Utils. Comm’n, Decision 19-05-042 app. A at A1 (2019).
    As a result of the 2019 PSPSs, Plaintiff alleges that he
    and others were without power for “many days, in some
    cases up to 17 days total and upwards of 10 days in a row.”
    Those affected by the PSPSs allegedly suffered “loss of
    habitability of their dwellings, loss of food items in their
    refrigerators, expenses for alternative means of lighting and
    power,” and other damages. Plaintiff seeks to certify a class
    that includes “[a]ll California residents and business
    owners” who had their power shut off by PG&E during the
    2019 PSPSs or any subsequent PSPS during this litigation.
    Plaintiff requests $2.5 billion in damages for the class.
    PG&E moved in bankruptcy court to dismiss the
    Complaint. PG&E argued that the court lacked subject
    matter jurisdiction to hear the claim because it was
    preempted by California Public Utilities Code section 1759.
    PG&E argued, in the alternative, that the Complaint should
    be dismissed because PG&E’s Electric Rule Number 14
    shields PG&E from liability for an interruption in service
    that PG&E believes is necessary for public safety. 1 CPUC
    filed an amicus brief in the bankruptcy court, contending that
    “litigation and adjudication of Plaintiff’s claim . . . would
    1
    PG&E also argued that the Complaint should be dismissed because
    it failed to adequately plead that PG&E’s alleged negligence caused
    Plaintiff’s damages.
    GANTNER V. PG&E                               7
    hinder and interfere with enforcement of the Commission’s
    guidelines concerning public safety power shutoffs.” The
    bankruptcy court issued a ruling in March 2020 dismissing
    the Complaint without leave to amend, holding that
    Plaintiff’s claim was preempted by section 1759, and not
    addressing PG&E’s Rule 14 argument. 2
    In April 2020, Plaintiff appealed the bankruptcy court’s
    dismissal of his Complaint to the United States District
    Court for the Northern District of California. In March 2021,
    the district court affirmed dismissal, ruling only on
    preemption grounds, and denying Plaintiff leave to amend.
    Plaintiff filed a timely notice of appeal of the district
    court’s decision. Alice Stebbins, the former Executive
    Director of CPUC, filed an amicus brief in support of
    Plaintiff, arguing that imposing liability on PG&E under
    Plaintiff’s theory would not be inconsistent with CPUC’s
    policies or its “regulatory reach.” CPUC filed an amicus
    brief, which nominally did not support either party but, like
    the brief it had filed in the Bankruptcy Court, took the
    position that section 1759 preempted Plaintiff’s claim. We
    heard oral argument on January 12, 2022.
    IV. Explanation of Certification Request
    No controlling California precedent has answered the
    certified question whether California Public Utilities Code
    section 1759 preempts a negligence claim alleging that a
    utility violated state-law duties and consequently needed to
    take an action, with the permission of CPUC, that caused the
    2
    The bankruptcy court also concluded that Plaintiff’s claim failed
    because PG&E’s alleged negligence would not have proximately caused
    Plaintiff’s damages.
    8                   GANTNER V. PG&E
    plaintiff to suffer damages. Similarly, no controlling
    California precedent has interpreted Rule 14 or has
    explained how a court should apply a utility’s tariff rule
    when the text is susceptible to two reasonable
    interpretations. These questions are dispositive in this case
    and have significant public policy implications for
    California residents and utilities.
    A.
    This case presents a novel question about the scope of
    preemption under California Public Utilities Code section
    1759. California law provides a private right of action
    against any public utility that acts unlawfully or that “omits
    to do any . . . thing required to be done.” 
    Cal. Pub. Util. Code § 2106
    . But section 1759 limits the jurisdiction of
    courts to hear any suit that could interfere with CPUC “in the
    performance of its official duties.” 
    Id.
     § 1759. To the extent
    there is conflict between sections 1759 and 2106, the
    California Supreme Court has held that section 1759
    preempts a claim brought under section 2106 if an award of
    damages would “hinder or frustrate [CPUC’s] declared
    supervisory and regulatory policies.” San Diego Gas &
    Elec. Co. v. Superior Ct. (“Covalt”), 
    920 P.2d 669
    , 673 (Cal.
    1996) (quoting Waters v. Pac. Tel. Co., 
    523 P.2d 1161
    , 1162
    (Cal. 1974)). Plaintiff alleges that, because of PG&E’s
    negligent maintenance of its grid, PG&E needed to
    implement PSPSs, which caused his injury. In his filings
    before the bankruptcy court, and throughout this litigation,
    Plaintiff has made clear that “this case is not about whether
    the shutoffs were appropriate or how PG&E handled them.”
    Rather, Plaintiff contends, “it is about why they had to be
    done in the first place.” PG&E responds that, regardless of
    how Plaintiff frames his theory, any damages PSPSs cause
    cannot be recovered in litigation because of section 1759
    GANTNER V. PG&E                         9
    preemption. This case thus presents the question whether
    adjudicating Plaintiff’s claim that PG&E negligently
    maintained its grid would hinder or frustrate CPUC’s
    regulatory authority with respect to PSPSs, when Plaintiff
    does not challenge the manner in which the PSPSs were
    executed but rather argues that they are a link in the causal
    chain that connects PG&E’s alleged negligence to his
    damages.
    When the California Supreme Court has considered
    whether a claim was preempted by section 1759, the Court
    has examined whether the allegedly tortious conduct was
    permitted by CPUC’s policies. For example, in Covalt, the
    California Supreme Court held that section 1759 preempted
    a private nuisance claim that alleged that a utility’s power
    lines emitted “high and unreasonably dangerous levels of
    electromagnetic radiation onto plaintiffs’ property.” Id.
    at 678. CPUC had previously decided that “regulated
    utilities need take no action to reduce [electromagnetic] field
    levels from existing powerlines.” Id. at 697. The Court held
    that plaintiffs’ claim was preempted because a determination
    of liability “would be inconsistent with [CPUC’s]
    conclusions” that the challenged conduct was lawful. Id. In
    Hartwell Corp. v. Superior Ct., 
    38 P.3d 1098
     (Cal. 2002),
    the California Supreme Court considered an allegation that
    public utilities provided unhealthy drinking water. 
    Id. at 1102
    . The Court held that that claim was preempted
    insofar as the water was in compliance with federal and state
    standards because “[a]n award of damages on the theory that
    the public utilities provided unhealthy water, even if the
    water met [applicable] standards, ‘would plainly undermine
    [CPUC’s] policy.’” 
    Id. at 1113
     (quoting Covalt, 920 P.2d
    at 704). But the Court also held that “damage claims based
    on the theory that the water failed to meet federal and state
    drinking water standards are not preempted by section
    10                       GANTNER V. PG&E
    1759.” Id. (emphasis added). The Court reasoned that a
    finding that “a public water utility violated [those] standards
    would not interfere with the [C]PUC regulatory policy.” Id.
    Existing California precedent does not address whether
    Plaintiff’s claim is preempted. In Covalt and Hartwell, and
    every other California Supreme Court case addressing
    section 1759 preemption, the utility’s allegedly unlawful
    conduct giving rise to the claim was the same conduct that
    directly caused the plaintiffs’ alleged injuries. Determining
    whether each claim was preempted required the Court to
    decide only whether that challenged conduct was consistent
    with CPUC’s policies. In this case, by contrast, there are two
    separate sets of conduct at issue. Plaintiff alleges that, first,
    PG&E negligently maintained its grid and, second, PG&E
    consequently had to engage in PSPSs, which caused
    Plaintiff’s damages. The challenged conduct—PG&E’s
    allegedly negligent maintenance of its grid—would
    undoubtedly contravene California law and CPUC’s policies
    if Plaintiff’s allegations about that conduct were proven
    true. 3 But the conduct that directly caused Plaintiff’s
    injury—the 2019 PSPSs—were implemented with CPUC’s
    permission. The caselaw does not answer whether section
    1759 prevents Plaintiff from suing PG&E for its initial
    negligence given that the PSPSs, which Plaintiff alleges
    3
    See, e.g., Pub. Util. § 8386(a) (“Each electrical corporation shall
    construct, maintain, and operate its electrical lines and equipment in a
    manner that will minimize the risk of catastrophic wildfire posed by
    those electrical lines and equipment.”); id. § 451 (“Every public utility
    shall furnish and maintain such adequate, efficient, just, and reasonable
    service, instrumentalities, equipment, and facilities . . . as are necesary
    [sic] to promote the safety, health, comfort, and convenience of its
    patrons, employees, and the public.”).
    GANTNER V. PG&E                          11
    were the foreseeable result of that negligence and caused his
    injuries, were allowed under CPUC’s policies.
    Cognizant of the burden that certifying a question adds
    to a state court’s caseload, we have stated that “[t]he
    certification procedure is reserved for state law questions
    that present significant issues, including those with
    important public policy ramifications, and that have not yet
    been resolved by the state courts.” Kremen v. Cohen,
    
    325 F.3d 1035
    , 1037 (9th Cir. 2003). This question meets
    that high standard for certification.        Wildfires are
    increasingly an annual occurrence throughout California,
    and at least some PSPSs may be necessary to minimize the
    number of those fires. How California allocates the costs of
    wildfires and PSPSs involves important policy
    considerations. Given the significance of the policy issues
    implicated by Plaintiff’s negligence claim, and the fact that
    no caselaw from the California Supreme Court directly
    addresses whether section 1759 preempts it, we certify that
    question to the California Supreme Court.
    B.
    We also certify a question about the interpretation of
    Rule 14, which would independently foreclose Plaintiff’s
    theory of liability if it were resolved in PG&E’s favor. Rule
    14 is a tariff rule that PG&E has filed with CPUC. California
    law requires utilities to file with the CPUC “tariff schedules
    containing rates, charges and classifications, ‘together with
    all rules, contracts, privileges, and fa[c]ilities which in any
    manner affect or relate to rates, tolls, rentals, classifications,
    or service.’” Waters, 
    523 P.2d at 1163
     (quoting Pub. Util.
    § 489(a)). A properly published and filed tariff rule “ha[s]
    the force and effect of a statute.” Dyke Water Co. v. Pub.
    Utils. Comm’n, 
    363 P.2d 326
    , 337 (Cal. 1961).
    12                   GANTNER V. PG&E
    Rule 14 provides generally that “PG&E will exercise
    reasonable diligence and care to furnish and deliver a
    continuous and sufficient supply of electric energy to the
    customer, but does not guarantee continuity or sufficiency of
    supply.” PG&E argues that the fourth paragraph of Rule 14
    absolves it from any liability for service interruptions,
    including PSPSs. That paragraph provides:
    PG&E specifically maintains the right to
    interrupt its service deliveries, without
    liability to the Customers or electric service
    providers (ESPs) affected, when, in PG&E’s
    sole opinion, such interruption is necessary
    for reasons including, but not limited to, the
    following:
    1. Safety of a customer, a PG&E employee,
    or the public at large.
    (emphasis added). Plaintiff argues, however, that a sentence
    in the first paragraph of Rule 14 contemplates that PG&E
    remains liable for interruptions in service that result from its
    own negligence. That sentence reads:
    PG&E will not be liable for interruption or
    shortage or insufficiency of supply, or any
    loss or damage of any kind of character
    occasioned thereby, if same is caused by
    inevitable accident, act of God, fire, strikes,
    riots, war, or any other cause except that
    arising from its failure to exercise reasonable
    diligence.
    (emphasis added).
    GANTNER V. PG&E                         13
    Both parties have put forward reasonable interpretations
    of Rule 14. Under PG&E’s reading, the fourth paragraph
    precludes liability for any interruption in service if, in
    PG&E’s opinion, that interruption is necessary to protect the
    public at large. Under Plaintiff’s reading, the first paragraph
    of Rule 14 limits PG&E’s disclaimer of liability in the fourth
    paragraph by stating that PG&E is still liable for an
    interruption in service—even one that, in PG&E’s opinion,
    is necessary to protect the public—if PG&E’s negligence
    caused the interruption.
    The California Supreme Court has never interpreted
    Rule 14 or issued an opinion that squarely answers which
    party’s reading is correct. The California Court of Appeal,
    adopting a canon of construction from contract law, has held
    that “if there is an ambiguity in a tariff any doubt in its
    interpretation is to be resolved in favor of the [nondrafter and
    against the utility].” Pink Dot, Inc. v. Teleport Commc’ns
    Grp., 
    107 Cal. Rptr. 2d 392
    , 397 (Ct. App. 2001) (brackets
    in original) (quoting Transmix Corp. v. S. Pac. Co., 
    9 Cal. Rptr. 714
    , 721 (Ct. App. 1960)). Because tariff rules have
    “the force and effect of a statute,” Dyke Water Co., 
    363 P.2d at 337
    , it is unclear whether this contract-law approach to
    resolving an ambiguity in Rule 14 is appropriate or whether
    California law instead would require a court to apply
    standard principles of statutory construction. The California
    Supreme Court has never adopted the canon that ambiguities
    in a tariff rule must be resolved against the utility, and we
    are not certain whether the Supreme Court would choose to
    do so. See, e.g., Waters, 
    523 P.2d at 1166
     (“[G]eneral
    principles which might govern disputes between private
    parties are not necessarily applicable to disputes with
    regulated utilities.”). Given that this question of Rule 14’s
    interpretation implicates the same public policy interests
    identified in section IV.A and likewise determines whether
    14                   GANTNER V. PG&E
    a claim such as Plaintiff’s may proceed, we respectfully
    certify this question as well.
    V. Accompanying Materials
    The clerk of this court is hereby directed to file in the
    Supreme Court of California, under official seal of the
    United States Court of Appeals for the Ninth Circuit, copies
    of all relevant briefs and excerpts of the record, and an
    original and ten copies of this order and request for
    certification, along with a certification of service on the
    parties, pursuant to California Rule of Court 8.548(c), (d).
    This case is withdrawn from submission. Further
    proceedings before us are stayed pending final action by the
    Supreme Court of California. The clerk is directed to
    administratively close this docket, pending further order
    from this court. The parties shall notify the clerk of this court
    within seven days after the Supreme Court of California
    accepts or rejects certification, and again within seven days
    if that Court accepts certification and subsequently renders
    an opinion. The panel retains jurisdiction over further
    proceedings.
    IT IS SO ORDERED.
    

Document Info

Docket Number: 21-15571

Filed Date: 2/28/2022

Precedential Status: Precedential

Modified Date: 2/28/2022